Professional Documents
Culture Documents
Guidelines of PCC Pavement
Guidelines of PCC Pavement
e. Sub-base Course.
The layer above subgrade soil is called
subbase course.
The main load bearing strata is the sub
base course.
It is mostly omitted when the surface is
rock.
Aggregates or stone soiling are
provided as subbase course.
Its function is to distribute the load
equally to the subgrade.
The maximum thickness of the subbase
course in CDLD area can be taken as 9
inches. Photo 3: Base and sub-base courses. Figure 6: Rolling load distribution.
f. Base Course.
The layer in between the surface course
and the sub-base course is called base
course.
It consists of lean concrete or coarse
aggregates.
Its thickness in CDLD area can be taken
between 4 and 6 inches.
g. Surface Course.
The outermost layer of PCC pavement is
called wearing course or surface
course.
It is rich cement concrete with a
thickness of between 3 and 4 inches.
In some cases, steel is also provided to
reinforce it against traffic load.
After placing the surface course the
edges should be made chamfered and
not kept sharp to prevent it from
distortion and deterioration.
Photo 5: Pavement surface and expansion joints. Photo 6: PCC sharp edges being chamfered.
h. Formwork.
Laying of concrete for the pavement
either it is base course or surface course
is not possible without fixing formwork.
Wooden sheets, plywood, fiber
hardboard and steel plates are mostly
used as formwork.
Formwork should be watertight so that
slurry of concrete may not waste after
placing.
Before using formwork should be free of
dust, clay and other impurities.
For placing concrete to appropriate
depth the thickness of formwork should
be from 1 to 2 inches with a length of 10
feet. Figure 8: Fixing form work.
The depth of wooden block should the
same as the slab thickness.
Afer 24 hours the formwork should be
displaced and shifted to other section
of the pavement.
Before placing the concrete water
should be sprinkled to the surface of the
ground and should be made wet
especially in summers. The formwork
should be fixed right in vertical position
ar right angle with the ground surface.
Formwork should be fixed in proper
alignment and two formworks should
not overlap each other to prevent
discontinuity and irregular edges. Photo 7: Improper placement of formwork, having Photo 8: Honey combing due to poor formwork and
negative slope. inappropriate water – cement ratio.
i. Expansion Joints.
Providing expansion joints is a very
Photo 9: Joint raised above slab
important component in PCC surface and is not extended till
pavement. pavement end.
The joint should be provided at an
interval of 24 to 30 times the thickness of
pavement.
Expansion joints should be pulled out
after the setting of concrete.
The depth of joint should be 1/3 to1/4
times of the slab thickness and minimum
thickness of the joint is 3 mm.
If the joint is not provided in regular and
equal intervals then cracks may
develop in the surface of concrete due
to unequal distribution of load. Photo 10: In larger slabs,
longitudinal as well as transverse
It must be straight and vertically inserted
joints are provided.
with a thin wooden strip.
The joint should be on the same level of
the slab and concave or convex joint
should be discouraged.
The longitudinal joint should be
provided if the width of the road is
greater than 15 ft.
All the joints should be provided
vertically at a right angle.
j. Water Curing.
This is final and the most important
activity in PCC pavement.
After finishing operation of the surface Photo 12: Water curing with
of pavement it is left to dry, The time of the help of sand banks.
concrete finishing and curing mainly
depends upon the temperature.
In summers the time is less and in winters
it is more.
Normally a field test is done for it that if
the concrete surface is scratched with
nail and white line is visible then curing
should be started.
Curing of pavement should be done for
28 days and if there is water issue then
minimum duration for curing is 14 days. Photo 11: Inadequate
water curing.
The simple method of curing of
pavement is that HDPE pipe should be
laid upon it perforated in the equal
interval and if water is left in it, it will be
sprinkled in all the direction and cured
automatically throughout the day.
Water is also flooded by making
different segments of the pavement
with the help of sand.
Figure 13: Side drain with drop structures Figure 14: Trapezoidal Drain Figure 15: Ditch with dry stone pitching
Figure 22: Full depth repair with dowel bars. Figure 23: Slab replacement