Weaving Calculations:
The process of producing a fabric by interlacing warp and weft threads is known as
weaving. The machine used for weaving is known as weaving machine or loom. Weaving
calculation is very important to produce fabric. It is also very critical task for weaving
master. Different formulas and calculation of weaving are given in this article.
Weaving process
Different Formulas of Weaving Calculation:
Reed Count
It is calculated in stock port system.No. of dents in 2 inches is called Reed Count.
EPI
Reed count = ……………………..
1 + Weft crimp percentage
Reed Width
100 + Weft crimp percentage
Reed Width = Cloth width X ………………….....................…
100
PPI
2. Weft cover factor = ……………………..
√Weft Count
Wp.C.F. X Wt.C.F.
3. Cloth cover factor = Wp.C. - F Wt.C.F + …………………………
28
Crimp % :
Crimp Percentage is defined as the mean difference between the straightened thread length
and the distance between the ends of the thread while in cloth, expressed as a percentage.
Loom:
Motor pully diameter
Loom Speed = Motor RPM X …………...…………..
Loom pully diameter
Actual Production
Loom Efficiency (%) = ………………………….. X 100
Calculated Production
Fabric Specification:
EPI X PPI
Fabric specification = …………………………. X Fabric width
Warp count X weft count
Or
Therefore, Cloth weight = Weight of warp + Weight of weft + Weight of size (All in lbs.)
Weving Calculations:
Calculating linear yards of fabric produced on a weaving machine per hour of operation can
be done using the following formula:
Linear Yards/Hour = (picks per min. / picks per in.) x (60 min. per hr. / 36 in. per yd) x
loom efficiency (%)
Linear Meters/Hour = (picks per min / picks per centimeter) x (60 min. per hr. / 100 cm
per meter) x loom efficiency (%)
Rate of Filling Insertion (Yards/Min) = Loom Speed (Picks/Min) x Loom Width (Yds.) x
Loom Efficiency (%)
Linear Yards/Hour = (picks per min. / picks per in.) x (60 min. per hr. / 36 in. per yd) x
loom efficiency (%)
Linear Yards/Hour = (650picks per min. / 58picks per in.) x (60 min. per hr. / 36 in. per
yd) x .92 loom efficiency
Answer: 17.2
Example-2:
What is the rate of filling insertion in a loom running 720 picks per minute with a width of
2.5 meters at 93% efficiency?