QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
1 Earth work.
1.1 Site clearence works: Clearing
the site with cutting grass,
levelling humps, uprootings and
clearing surface grass upto 15
cms and disposing in specified
places all complete as per
instructions of site engineer

Building area 1 2131.00 Area 2131.00


Total 2131.00 Sft.
1.2 Earthwork in excavation of
foundation in Boulder mix soil
up to size 30 cms, lead 10m and
lift 2.0 m all complete
FOUNDATIONS
F1 1 6.00 6.00 5.00 180.00
F2 2 7.00 7.00 5.00 490.00
F3 2 8.00 8.00 5.00 640.00
F4 2 9.58 9.58 5.00 917.76
STF1 1 9.00 6.00 5.00 270.00
STF2 1 12.67 6.00 5.00 380.10
STF3 1 10.75 6.00 5.00 322.50
Grid - A ( 2 - 3 ) 1 20.17 1.50 3.58 108.31
Grid - B ( 2 - 3 ) 1 19.17 1.50 3.58 102.94
Grid - C ( 2 - 3 ) 1 29.84 1.50 3.58 160.24
Grid - D ( 2 - 3 ) 1 7.42 1.50 3.58 39.85
Grid - 1 ( A - D ) 1 10.58 1.50 3.58 56.81
Grid - 2( A - D ) 1 9.92 1.50 3.58 53.27
Grid - 3 ( A - D ) 1 0.00 1.50 3.58 0.00
Grid - 4 ( A - D ) 1 16.81 1.50 3.58 90.27
Grid - 5 ( A - D ) 1 20.75 1.50 3.58 111.43
Total 3923.49 Cft.
1.3 Earth work in filling in
foundation, floors etc in 15 cms
layers and compaction by water
spray all complete

Total E/W 1 853.70


Building area filling 1 1035.00 1.50 1552.50

Estimated by: Checked by: Approved by:


2 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Total 2406.20 Cft.
1.4 Soling Works: First class brick
soling (flat) with sand
compaction in foundations,
floors etc all complete

Estimated by: Checked by: Approved by:


3 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Building area, G/F 1 1035.00 Area 1035.00
FOUNDATIONS
F1 1 6.00 6.00 36.00
F2 2 7.00 7.00 98.00
F3 2 8.00 8.00 128.00
F4 2 9.58 9.58 183.55
STF1 1 9.00 6.00 54.00
STF2 1 12.67 6.00 76.02
STF3 1 10.75 6.00 64.50
Grid - A ( 1 - 5 ) 1 20.17 1.50 30.26
Grid - B ( 1 - 5 ) 1 19.17 1.50 28.76
Grid - C ( 1 - 5) 1 29.84 1.50 44.76
Grid - D ( 1 - 5 ) 1 7.42 1.50 11.13
Grid - 1 ( A - D ) 1 10.58 1.50 15.87
Grid - 2( A - D ) 1 9.92 1.50 14.88
Grid - 3 ( A - D ) 1 0.00 1.50 0.00
Grid - 4 ( A - D ) 1 16.81 1.50 25.22
Grid - 5 ( A - D ) 1 20.75 1.50 31.13
Total 1877.06 Sft.
2 Concrete Works
2.1 PCC Works M10

Plain cement concret PCC(1:3:6)


in foundation, floors etc. with
cement, sand and crussed
aggregate of 10 mm to 38mm
gauge including mixing with
mixture machine & compaction
by vibrator, laying in line &
level with curing all type of
works complete as per
specifications & instructions

Same as Brick soling area 1 1877.06 Area 0.25 469.27


Total 469.27 Cft.
2.2 RCC Works in PCC M20

Estimated by: Checked by: Approved by:


4 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit

RCC work: RCC work in PCC


(1:1.5:3) in foundation, floors,
columns, beams, slabs etc. with
cement,sand and crussed
aggregate of 10 mm to 38mm
gauge including mixing with
mixture machine & compaction
by vibrator, laying in line &
level with curing all type of
works complete as per
specifications & instructions

FOUNDATIONS
F1 1 5.00 5.00 0.75 18.75
F2 2 6.00 6.00 0.75 54.00
F3 2 7.00 7.00 0.75 73.50
F4 2 8.58 8.58 0.75 110.42
STF1 1 9.00 6.00 1.17 63.18
STF2 1 11.67 5.00 1.17 68.27
STF3 1 9.75 5.00 1.17 57.04
FOUNDATION BEAM
Grid - A ( 1 - 5 ) 1 20.17 0.75 1.17 17.70
Grid - B ( 1 - 5 ) 1 19.17 0.75 1.17 16.82
Grid - C ( 1 - 5 ) 1 29.84 0.75 1.17 26.18
Grid - D ( 1 - 5) 1 7.42 0.75 1.17 6.51
Grid - 1 ( A - D ) 1 10.58 0.75 1.17 9.28
Grid - 2 ( A - D ) 1 9.92 0.75 1.17 8.70
Grid - 3 ( A - D ) 1 0.00 0.75 1.17 0.00
Grid - 4 ( A - D ) 1 16.81 0.75 1.17 14.75
Grid - 5( A - D ) 1 20.75 0.75 1.17 18.21
COLUMN
C-1 12 1.00 1.00 3.50 42.00
TIE BEAM
Grid - A ( 1 - 5 ) 1 20.17 0.75 1.17 17.70
Grid - B ( 1 - 5 ) 1 19.17 0.75 1.17 16.82
Grid - C ( 1 -5 ) 1 29.84 0.75 1.17 26.18
Grid - D ( 1 - 5 ) 1 7.42 0.75 1.17 6.51

Estimated by: Checked by: Approved by:


5 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Grid - 1 ( A - D ) 1 10.58 0.75 1.17 9.28
Grid - 2 ( A - D ) 1 9.92 0.75 1.17 8.70
Grid - 3 ( A - D ) 1 0.00 0.75 1.17 0.00
Grid - 4 ( A - D ) 1 16.81 0.75 1.17 14.75
Grid - 5 ( A - D ) 1 20.75 0.75 1.17 18.21
GROUND FLOOR
COLUMN
C-1 12 1.00 1.00 8.91 106.92
BEAM
Grid - A ( 1 - 5) 1 27.84 0.75 1.17 24.43
Grid - B ( 1 - 5 ) 1 31.84 0.75 1.17 27.94
Grid - C ( 1 - 5 ) 1 33.34 0.75 1.17 29.26
Grid - D ( 1 - 5 ) 1 17.92 0.75 1.17 15.72

Grid - 1 ( A - D ) 1 15.58 0.75 1.17 13.67


Grid - 2 ( A - D ) 1 14.42 0.75 1.17 12.65
Grid - 3 ( A - D ) 1 0.00 0.75 1.17 0.00
Grid - 4( A - D ) 1 29.00 0.75 1.17 25.45
Grid - 5( A - D ) 1 25.25 0.75 1.17 22.16
SLAB
Slab area 1 1035.00 Area 0.42 434.70
Less Staircase -1 11.17 7.92 0.42 -37.16
STAIRCASE
Waist slab 1 1 6.53 4.58 29.91
Waist slab 2 1 6.60 4.67 30.82
Waist slab 3 1 4.58 4.67 21.39
Landing 2 4.67 4.67 0.42 18.32
Riser / Tread 7.5 3.50 0.92 0.58 14.01
FIRST FLOOR
COLUMN
C-1 12 1.00 1.00 8.91 106.92
BEAM
Grid - A ( 1 - 5) 1 27.84 0.75 1.17 24.43
Grid - B ( 1 - 5) 1 31.84 0.75 1.17 27.94
Grid - C ( 1 - 5 ) 1 33.34 0.75 1.17 29.26

Estimated by: Checked by: Approved by:


6 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Grid - D ( 1 - 5 ) 1 17.92 0.75 1.17 15.72

Grid - 1 ( A - D ) 1 15.58 0.75 1.17 13.67


Grid - 2 ( A - D ) 1 14.42 0.75 1.17 12.65
Grid - 3 ( A - D ) 1 16.08 0.75 1.17 14.11
Grid 4- ( A - D ) 1 29.00 0.75 1.17 25.45
Grid - 5 ( A - D ) 1 25.25 0.75 1.17 22.16
SLAB
Slab area 1 1135.00 Area 0.42 476.70
Less Staircase -1 11.17 7.92 0.42 -37.16
STAIRCASE
Waist slab 1 1 6.53 4.58 29.91
Waist slab 2 1 6.60 4.67 30.82
Waist slab 3 1 4.58 4.67 21.39
Landing 2 4.67 4.67 0.42 18.32
Riser / Tread 7.5 3.50 0.92 0.58 14.01
TOP FLOOR
COLUMN
C-1 12 1.00 1.00 8.91 106.92
BEAM
Grid - A ( 1 - 5) 1 27.84 0.75 1.17 24.43
Grid - B ( 1 - 5) 1 31.84 0.75 1.17 27.94
Grid - C ( 1 - 5 ) 1 33.34 0.75 1.17 29.26
Grid - D ( 1 - 5 ) 1 17.92 0.75 1.17 15.72

Grid - 1 ( A - D ) 1 15.58 0.75 1.17 13.67


Grid - 2 ( A - D ) 1 14.42 0.75 1.17 12.65
Grid - 3 ( A - D ) 1 16.08 0.75 1.17 14.11
Grid 4- ( A - D ) 1 29.00 0.75 1.17 25.45
Grid - 5 ( A - D ) 1 25.25 0.75 1.17 22.16
SLAB
Slab area 1 939.75 Area 0.42 394.70
Total 3046.98 Cft.
3 Steel Reinforcement works

Estimated by: Checked by: Approved by:


7 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit

Tor /TMT Reinforcement work


for R.C.C work including
supply, straighting, cutting,
bending, binding and laying of
different diameter steel rod in all
types of R.C.C work as per
design ,drawing ,specification
and instruction all complete
work
8/10/12 /16 & 20 mm
Diameter
Total Kg. 8418.26 Kg
Total 8.42 Mt.
4 Formworks and scaffoldings
works
Form work for Foundation,
beams, column, slab etc. all
types of concrete with 19 mm
plyboard with steel props
centering & shuttering including
promping wedging, scafolding,
proping, stagging inclusive of
utilization till the support is
fully unyielding net as per
design ,drawing specification
and instruction
FOUNDATIONS
F1 1 24.00 0.50 12.00
F2 2 28.00 0.50 28.00
F3 2 32.00 0.50 32.00
F4 2 38.32 0.50 38.32
STF1 1 30.00 1.00 30.00
STF2 1 18.67 1.00 18.67
STF3 1 33.34 1.00 33.34
FOUNDATION BEAM
Grid - A ( 2 - 3 ) 1 20.17 1.5 30.26
Grid - B ( 2 - 3 ) 1 19.17 1.5 28.76
Grid - C ( 2 - 3 ) 1 29.84 1.5 44.76

Estimated by: Checked by: Approved by:


8 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit

Grid - D ( 2 - 3 ) 1 7.42 1.5 11.13


Grid - 1 ( A - D ) 1 10.58 1.5 15.87
Grid - 2( A - D ) 1 9.92 1.5 14.88
Grid - 3 ( A - D ) 1 0.00 1.5 0.00
Grid - 4 ( A - D ) 1 16.81 1.5 25.22
Grid - 5 ( A - D ) 1 20.75 1.5 31.13
COLUMN
C-1 12 4.00 3.50 168.00
TIE BEAM
Grid - A ( 2 - 3 ) 1 20.17 1.50 30.26
Grid - B ( 2 - 3 ) 1 19.17 1.50 28.76
Grid - C ( 2 - 3 ) 1 29.84 1.50 44.76
Grid - D ( 2 - 3 ) 1 7.42 1.50 11.13
Grid - 1 ( A - D ) 1 10.58 1.50 15.87
Grid - 2( A - D ) 1 9.92 1.50 14.88
Grid - 3 ( A - D ) 1 0.00 1.50 0.00
Grid - 4 ( A - D ) 1 16.81 1.50 25.22
Grid - 5 ( A - D ) 1 20.75 1.50 31.13
GROUND FLOOR
COLUMN
C-1 12 4.00 8.91 427.68
BEAM
Grid - A ( 1 - 5) 1 27.84 2.75 76.56
Grid - B ( 1 - 5 ) 1 31.84 2.75 87.56
Grid - C ( 1 - 5 ) 1 33.34 2.75 91.69
Grid - D ( 1 - 5 ) 1 17.92 2.75 49.28

Estimated by: Checked by: Approved by:


9 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit

Grid - 1 ( A - D ) 1 15.58
Grid - 2 ( A - D ) 1 14.42
Grid - 3 ( A - D ) 1 0.00 2.75 0.00
Grid - 4( A - D ) 1 29.00 2.75 79.75
Grid - 5( A - D ) 1 25.25 2.75 69.44
SLAB
Slab area 1 1021.22 Area 1021.22
Slab sides 1 158.00 0.42 66.36
Less Staircase -1 11.17 7.92 -88.47
STAIRCASE
West slab 1 1 6.53 4.58 29.91
West slab 2 1 6.60 4.67 30.82
West slab 3 1 4.58 4.67 21.39
West slab sides 2 17.71 2.00 70.84
Landing 2 3.50 4.25 29.75
Riser 15 3.50 0.58 30.45
FIRST FLOOR
COLUMN
C-1 12 4.00 8.91 427.68
BEAM 0.00
Grid - A ( 1 - 5) 1 27.84 2.75 76.56
Grid - B ( 1 - 5) 1 31.84 2.75 87.56
Grid - C ( 1 - 5 ) 1 33.34 2.75 91.69
Grid - D ( 1 - 5 ) 1 17.92 2.75 49.28

Grid - 1 ( A - D ) 1 15.58 2.75 42.85


Grid - 2 ( A - D ) 1 14.42 2.75 39.66
Grid - 3 ( A - D ) 1 16.08 2.75 44.22
Grid 4- ( A - D ) 1 29.00 2.75 79.75
Grid - 5 ( A - D ) 1 25.25 2.75 69.44
SLAB
Slab area 1 1021.22 Area 1021.22
Slab sides 1 158.00 0.42 66.36

Estimated by: Checked by: Approved by:


10 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Less Staircase -1 13.58 5.58 -75.78
STAIRCASE
West slab 1 1 6.53 4.58 29.91
West slab 2 1 6.60 4.67 30.82
West slab 3 1 4.58 4.67 21.39
West slab sides 2 17.71 2.00 70.84
Landing 2 4.67 4.67 43.62
Riser 15 3.50 0.58 30.45
TOP FLOOR
COLUMN
C-1 11 4.00 8.91 392.04
C-2 1 3.00 8.91 26.73
BEAM
Grid - A ( 1 - 5) 1 27.84 2.75 76.56
Grid - B ( 1 - 5) 1 31.84 2.75 87.56
Grid - C ( 1 - 5 ) 1 33.34 2.75 91.69
Grid - D ( 1 - 5 ) 1 17.92 2.75 49.28

Grid - 1 ( A - D ) 1 15.58 2.75 42.85


Grid - 2 ( A - D ) 1 14.42 2.75 39.66
Grid - 3 ( A - D ) 1 16.08 2.75 44.22
Grid 4- ( A - D ) 1 29.00 2.75 79.75
Grid - 5 ( A - D ) 1 25.25 2.75 69.44
SLAB
Slab area 1 872.34 Area 872.34
Slab sides 1 99.92 0.42 41.97
S. Total 7020.10 Sft.
5 First class local chimney made
exposed fair face brick wall
work in cement sand mortar
(1:4) superstructure in perfect
line and level including wetting
the brick, packing the joints and
curing all types of works as per
specification and instruction by
Engineer (fair faced brick work)

5.1 Brick work 9" th ( c:s 1:6 )

Estimated by: Checked by: Approved by:


11 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Below the Tie Beam
Grid - A ( 2 - 3 ) 1 20.17 0.75 3.50 52.95
Grid - B ( 2 - 3 ) 1 19.17 0.75 3.50 50.32
Grid - C ( 2 - 3 ) 1 29.84 0.75 3.50 78.33
Grid - D ( 2 - 3 ) 1 7.42 0.75 3.50 19.48

Grid - 1 ( A - D ) 1 10.58 0.75 3.50 27.77


Grid - 2( A - D ) 1 9.92 0.75 3.50 26.04
Grid - 3 ( A - D ) 1 0.00 0.75 3.50 0.00
Grid - 4 ( A - D ) 1 16.81 0.75 3.50 44.13
Grid - 5 ( A - D ) 1 20.75 0.75 3.50 54.47
GROUND FLOOR
EXTERNAL WALLS
Grid - A ( 1 - 5) 1 27.84 0.75 7.91 165.16
Less W1 -1 7.00 0.75 4.50 -23.63
Less DW1 -1 4.00 0.75 4.50 -13.50
Grid - 1 ( A - D ) 1 17.25 0.75 7.91 102.31
Grid - D ( 1 - 5 ) 1 9.58 0.75 8.91 64.02
Less W2 -1 6.00 0.75 4.50 -20.25
Grid - 5 ( A - D ) 1 25.25 0.75 7.91 149.80
Less W2 -3 4.00 0.75 4.50 -40.50
FIRST FLOOR
EXTERNAL WALLS
Grid - A ( 1 - 5) 1 27.84 0.75 7.91 165.16
Less W1 -1 7.00 0.75 4.50 -23.63
Less W4 -1 3.00 0.75 3.50 -7.88
Grid - 1 ( A - D ) 1 17.25 0.75 7.91 102.31
Grid - D ( 1 - 5 ) 1 9.58 0.75 8.91 64.02
Less W2 -3 6.00 0.75 4.50 -60.75
Grid - 5 ( A - D ) 1 25.25 0.75 7.91 149.80
Less W2 -2 4.00 0.75 4.50 -27.00
Less W3 -1 3.00 0.75 3.50 -7.88
Grid - C ( 1 - 5 ) 1 14.00 0.75 7.91 83.06
Less W1 -1 7.00 0.75 4.50 -23.63

Estimated by: Checked by: Approved by:


12 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Grid - 2( 1 - 5 ) 1 14.42 0.75 7.91 85.55
Less W1 1 7.00 0.75 4.50
LessV1 1 3.00 0.75 4.50
TOP FLOOR
EXTERNAL WALLS
Grid - A ( 1 - 5) 1 27.84 0.75 7.91 165.16
Less W2 -1 4.00 0.75 4.50 -13.50
Less W4 -1 3.00 0.75 3.50 -7.88
Grid - 1 ( A - D ) 1 17.25 0.75 7.91 102.31
Grid - D ( 1 - 5 ) 1 9.58 0.75 8.91 64.02
Less W2 -3 6.00 0.75 4.50 -60.75
Grid - 5 ( A - D ) 1 25.25 0.75 7.91 149.80
Less W2 -2 4.00 0.75 4.50 -27.00
Less W3 -1 3.00 0.75 3.50 -7.88
Grid - C ( 1 - 5 ) 1 14.00 0.75 2.00 21.00
Grid - 2 ( A - D ) 1 14.42 0.75 7.91 85.55
Less W1 -1 7.00 0.75 4.50 -23.63
TERRACE
Parapet Walls
Walls 1 167.00 0.75 1.75 219.19
S. Total 1902.41 Cft
5.2 Brick work 4" th ( c:s 1:4 )
GROUND FLOOR
INTERNAL WALLS
Bed Room
Wall 1 14.17 7.91 112.08
Wall 1 44.83 8.91 399.44
Less D1 -2 3.00 7.00 -42.00
LessW1 -1 7.00 4.50 -31.50
Kitchen
Wall 1 14.10 8.91 125.63
Less D1 -1 3.00 7.00 -21.00
W/C
Wall 1 7.00 8.91 62.37
Less D2 -1 2.50 7.00 -17.50

Estimated by: Checked by: Approved by:


13 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Bed Room
Wall 1 21.08 8.91 187.82
Less D2 -1 2.50 7.00 -17.50
FIRST FLOOR
INTERNAL WALLS
Bed Room
Wall 1 24.25 8.91 216.07
Less W1 -1 7.00 4.50 -31.50
Less w2 -1 4.00 4.50 -18.00
Less D2 -1 2.50 7.00 -17.50
Wall 1 13.50 8.91 120.29
LessD1 -1 3.00 7.00 -21.00
W/C
Wall 1 9.00 8.91 80.19
Less D2 -2 2.50 7.00 -35.00
Master Bedroom

Wall 1 24.75 8.91 220.52


Less D1 -1 3.00 7.00 -21.00
Living Room
Wall 1 21.67 8.91 193.08
Less D2 -1 2.50 7.00 -17.50
Less W2 -1 4.00 4.50 -18.00
TOP FLOOR
INTERNAL WALLS
Bed Room
Wall 1 23.00 8.91 204.93
Less D1 -1 3.00 7.00 -21.00
W/C
Wall 1 7.67 8.91 68.34
Less D2 -1 2.50 7.00 -17.50
Kitchen/Dinning/Store
Wall 1 27.25 8.91 242.80
Less D1 -1 3.00 7.00 -21.00
Less D2 -1 2.50 7.00 -17.50
Less W3 -1 4.00 4.50 -18.00

Estimated by: Checked by: Approved by:


14 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Puja Room
Wall 1 15.75 8.91 140.33
Less D2 -1 2.50 7.00 -17.50
S. Total 1952.39 Sft
6 12.5 / 20 mm thick (1:4) c/s
plaster work on floors, walls etc.
with proper curing all complete

6.1 Plaster work External ( c:s 1:4)

GROUND FLOOR
EXTERNAL WALLS
Grid - A ( 1 - 5) 1 27.84 7.91 220.21
Less W1 -1 7.00 4.50 -31.50
Less DW1 -1 4.00 4.50 -18.00
Grid - 1 ( A - D ) 1 17.25 7.91 136.41
Grid - D ( 1 - 5 ) 1 9.58 8.91 85.36
Less W2 -1 6.00 4.50 -27.00
Grid - 5 ( A - D ) 1 25.25 7.91 199.73
Less W2 -3 4.00 4.50 -54.00
FIRST FLOOR
EXTERNAL WALLS
Grid - A ( 1 - 5) 1 27.84 7.91 220.21
Less W1 -1 7.00 4.50 -31.50
Less W4 -1 3.00 3.50 -10.50
Grid - 1 ( A - D ) 1 17.25 7.91 136.41
Grid - D ( 1 - 5 ) 1 9.58 8.91 85.36
Less W2 -3 6.00 4.50 -81.00
Grid - 5 ( A - D ) 1 25.25 7.91 199.73
Less W2 -2 4.00 4.50 -36.00
Less W3 -1 3.00 3.50 -10.50
Grid - C ( 1 - 5 ) 1 14.00 7.91 110.74
Less W1 -1 7.00 4.50 -31.50
Grid - 2( 1 - 5 ) 1 14.42 7.91 114.06
Less W1 -1 7.00 4.50 -31.50
LessV1 -1 3.00 4.50 -13.50
TOP FLOOR

Estimated by: Checked by: Approved by:


15 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
EXTERNAL WALLS
Grid - A ( 1 - 5) 1 27.84 7.91 220.21
Less W2 -1 4.00 4.50 -18.00
Less W4 -1 3.00 3.50 -10.50
Grid - 1 ( A - D ) 1 17.25 7.91 136.41
Grid - D ( 1 - 5 ) 1 9.58 8.91 85.36
Less W2 -3 6.00 4.50 -81.00
Grid - 5 ( A - D ) 1 25.25 7.91 199.73
Less W2 -2 4.00 4.50 -36.00
Less W3 -1 3.00 3.50 -10.50
Grid - C ( 1 - 5 ) 1 14.00 2.00 28.00
Grid - 2 ( A - D ) 1 14.42 7.91 114.06
Less W1 -1 7.00 4.50 -31.50
TERRACE
Parapet Walls
Walls 2 167.00 2.50 835.00
S. Total 2562.99 Sft.
6.2 Plaster work Internal ( c:s 1:4)
INTERNAL WALLS
Outer wall area 2562.99
Inner wall area*2 3904.78
Plaster inner copla 500.00
S. Total 6967.76 Sft
7 Wood Works.
Sal Wood Door & Window Frame
7.1 Work
Providing & fitting in position 75 x
125mm Sal wood with all necessary
screws & fixing bolts or hold fast as
per drawing, specification &
instruction of the Consultant.

GROUND FLOOR
D1 3 19.75 0.33 0.25 4.89
D2 1 16.50 0.33 0.25 1.36
D3 1 19.75 0.33 0.25 1.63
D4 1 20.00 0.33 0.25 1.65

Estimated by: Checked by: Approved by:


16 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
FIRST FLOOR
D1 3 19.75 0.33 0.25 4.89
D2 3 16.50 0.33 0.25 4.08
TOP FLOOR
D1 2 17.00 0.33 0.25 2.81
D2 3 16.50 0.33 0.25 4.08
Total 25.39 Cft
7.2 Commercial Flush Door Shutter
Work

Providing & fitting door shutters


made of commercial solid core door
38mm thick ( Surya or equivalent )
as per design with sisum lattice and
necessary hardwares all complete as
per drawing, specification &
instruction of the Consultant.

GROUND FLOOR
D1 3 19.75 7.00 414.75
D2 1 16.50 7.00 115.50
D3 1 19.75 7.00 138.25
D4 1 20.00
FIRST FLOOR
D1 3 19.75 7.00 414.75
D2 3 16.50 7.00 346.50
TOP FLOOR
D1 2 17.00 7.00 238.00
D2 3 16.50 7.00 346.50
Total 2014.25 Sft
7.3 Supplying and fixing ready
made UPVC frame for
windows, 8mm thick single
layer glass with necessary tower
bolts, hinges, handle, screws,
locking set all compete work as
per specification and
instructions

GROUND FLOOR
Grid - A ( 1 - 5)

Estimated by: Checked by: Approved by:


17 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Less W1 1 7.00 4.50 31.50
Less DW1 1 4.00 4.50 18.00
Grid - 1 ( A - D )
Grid - D ( 1 - 5 ) 1 9.58 8.91
Less W2 1 6.00 4.50 27.00
Grid - 5 ( A - D )
Less W2 3 4.00 4.50 54.00
Grid - 3 ( A - D )
Less W2 3 4.00 4.50 54.00
FIRST FLOOR
Grid - A ( 1 - 5)
Less W1 1 7.00 4.50 31.50
Less W4 1 3.00 3.50 10.50
Grid - 1 ( A - D )
Grid - D ( 1 - 5 )
Less W2 3 6.00 4.50 81.00
Grid - 5 ( A - D )
Less W2 2 4.00 4.50 36.00
Less W3 1 3.00 3.50 10.50
Grid - C ( 1 - 5 )
Less W1 1 7.00 4.50 31.50
Grid - 2( 1 - 5 )
Less W1 1 7.00 4.50 31.50
LessV1 1 3.00 4.50 13.50

TOP FLOOR
EXTERNAL WALLS
Grid - A ( 1 - 5)
Less W2 1 4.00 4.50 18.00
Less W4 1 3.00 3.50 10.50
Grid - 1 ( A - D )
Grid - D ( 1 - 5 )
Less W2 3 6.00 4.50 81.00
Grid - 5 ( A - D )

Estimated by: Checked by: Approved by:


18 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Less W2 2 4.00 4.50 36.00
Less W3 1 3.00 3.50 10.50
Grid - C ( 1 - 5 )
Grid - 2 ( A - D ) 1 7.00 7.91 55.37
Less W1 1 7.00 4.50 31.50
S. Total 673.37 Sft
8 Flooring works.
8.1 Supplying and fixing Ceramic
glazed tiles (8"x8", 8"x6") in
floors, walls etc.on toilets 1:4 c/s
mortar all complete

GROUND FLOOR
Kitchen
Floor 1 14.83 10.50 155.72
Skarting 1 50.66 50.66
Wall 1 19.50 2.00 39.00
W/C
Floor 1 4.40 7.00 30.80
Wall 1 22.80 7.00 159.60
Less D2 -0.5 2.50 7.00 -8.75
Less V1 -0.5 3.00 4.50 -6.75
Staircase
Floor 1 10.33 13.42 138.63
Skarting 1 47.50 47.50
Passage
Floor 1 18.67 3.75 70.01
Skarting 1 22.42 22.42
FIRST FLOOR
W/C
Floor 1 4.40 7.00 30.80
Wall 1 22.80 7.00 159.60
Less D2 -0.5 2.50 7.00 -8.75
Less W3 -0.5 3.50 4.50 -7.88
Passage
Floor 1 9.00 5.17 46.53
Skarting 1 14.17 14.17

Estimated by: Checked by: Approved by:


19 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Attached Bathroom
Floor 1 7.00 4.33 30.31
wall 1 22.66 7.00 158.62
Less D2 -0.5 2.50 7.00 -8.75
Less V1 -0.5 3.00 4.50 -6.75
Balcony
Floor 1 5.50 5.58 30.69
Skarting 1 22.16 22.16
Floor 1 2.25 49.50 111.38

Estimated by: Checked by: Approved by:


20 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Skarting 1 103.50 103.50
TOP FLOOR
Kitchen
Floor 1 17.00 15.00 255.00
Skarting 1 64.00 64.00
Wall 1 19.50 2.00 39.00
W/C
Floor 1 7.67 4.58 35.13
Wall 1 24.50 7.00 171.50
Less D2 -0.5 2.50 7.00 -8.75
Less W2 -0.5 4.00 4.50 -9.00
Puja Room
Floor 1 6.58 4.75 31.26
Wall 1 22.66 5.00 113.30
Less D2 -0.5 2.50 7.00 -8.75
Less W2 -0.5 4.00 4.00 -8.00
Balcony
Floor 1 2.25 49.50 111.38
Skarting 1 103.50 103.50
Terrace
Floor 1 12.50 14.58 182.25
Skarting 1 54.16 54.16
Floor 1 856.28 area 856.28
Skarting 1 140.00 140.00
S. Total 3496.71 Sft
8.2 Supplying and fixing 13 mm
thick Granite on 20 mm thick
c/s mortar (1:4) on staircase,
steps, floors, walls etc. with
cutting, grooving, rubbing,
washing with oxalic acid and
wax polish etc. all complete

GROUND FLOOR
Kit/Din
Counter 2 6.50 2.00 26.00
" 1 9.00 2.00 18.00
Counter sides 2 16.00 32.00

Estimated by: Checked by: Approved by:


21 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Walls 2 2.00 2.50 10.00
Staircase
Landing 1 4.67 4.67 21.81
Tread 13 4.67 0.92 60.71
Riser 16 4.67 0.58 43.34
Skarting 1 18.33 18.33
FIRST FLOOR
Staircase
Landing 1 4.67 4.67 21.81
Tread 13 4.67 0.92 60.71
Riser 16 4.67 0.58 43.34
Skarting 1 18.33 18.33
TOP FLOOR
Staircase
Landing 1 4.58 4.58 20.98
Tread 13 4.58 0.92 59.54
Riser 16 4.58 0.58 42.50
Skarting 1 18.33 18.33
Kit/Din
Counter 2 6.50 2.00 26.00
" 1 9.00 2.00 18.00
Counter sides 2 16.00 32.00
Walls 2 2.00 2.50 10.00
Parapet Walls
Top 1 140.00 1.00 140.00
S. Total 741.72 Sft
8.3 IPS Flooring works.( 3mm thick
fine cement smoothening works)

GROUND FLOOR
Bed Room
Floor 1 11.00 11.50 126.50
Bed Room
Floor 11 10.50 14.17 1562.24
FIRST FLOOR
Bed Room
Floor 1 11.08 13.17 145.96

Estimated by: Checked by: Approved by:


22 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
Bed Room
Floor 1 13.50 10.25 138.38
Master Bed Room
Floor 1 13.50 11.25 151.88
Living Room
Floor 1 10.75 11.22 120.56
TOP FLOOR
Bed Room
Floor 1 12.00 11.00 132.00
S. Total 2377.52 Sft
9 Painting works.
9.1 Supplying and applying two
coats of plastic emulsion paint
with primar base with good
finishing as per instructions and
specifications all complete (inner
suface)
Plaster area ( I/S ) 1 7267.76 Area 7267.76
G/F Celing area 1 1021.22 Area 1021.22
1st F. Celing area 1 1181.15 Area 1181.15
Top F. Celing area 1 872.34 Area 872.34
S. Total 10342.47 Sft
9.2 Supplying and applying
weather proof Apex paint two
coat with astar with good
finishing as per instructions and
specifications all complete
(Exterior surfaces)

Plaster area ( O/S ) 1 2562.99 Area 2562.99


S. Total 2562.99 Sft
9.3
Supplying and applying 2mm
thick plain white putty plaster
on walls, ceilings etc. in perfect
line and level as per instructions
and specifications all complete

Plaster area ( I/S ) or ( O/S ) 1 12905.46 Area 12905.46


S. Total 12905.46 Sft

Estimated by: Checked by: Approved by:


23 of 58

QUANTITY ESTIMATE
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN
S.No. Description of works No. Length Breadth Height Quantity Unit
10
Stainless steel works: Supplying
and fixing stainless steel
staircase railing of height upto
0.9m, hand rail of 50mm dia ,
balusters 50mm dia in 2 m
distance and three line of 25mm
dia intermediate rails in between
stair steps/ floors and top rail
with painting all complete

Staircase, Railing
G/Floor 1 20.00 20.00
1st Floor 1 20.00 20.00
S. Total 40.00 Rft

Estimated by: Checked by: Approved by:


24 of 58

Remarks

Estimated by: Checked by: Approved by:


25 of 58

Remarks

Estimated by: Checked by: Approved by:


26 of 58

Remarks

Estimated by: Checked by: Approved by:


27 of 58

Remarks

Estimated by: Checked by: Approved by:


28 of 58

Remarks

Estimated by: Checked by: Approved by:


29 of 58

Remarks

Estimated by: Checked by: Approved by:


30 of 58

Remarks

Estimated by: Checked by: Approved by:


31 of 58

Remarks

Estimated by: Checked by: Approved by:


32 of 58

Remarks

Estimated by: Checked by: Approved by:


33 of 58

Remarks

Estimated by: Checked by: Approved by:


34 of 58

Remarks

Estimated by: Checked by: Approved by:


35 of 58

Remarks

Estimated by: Checked by: Approved by:


36 of 58

Remarks

Estimated by: Checked by: Approved by:


37 of 58

Remarks

Estimated by: Checked by: Approved by:


38 of 58

Remarks

Estimated by: Checked by: Approved by:


39 of 58

Remarks

Estimated by: Checked by: Approved by:


40 of 58

Remarks

Estimated by: Checked by: Approved by:


41 of 58

Remarks

Estimated by: Checked by: Approved by:


42 of 58

Remarks

Estimated by: Checked by: Approved by:


43 of 58

Remarks

70167.95

Estimated by: Checked by: Approved by:


44 of 58

Remarks

70167.95

Estimated by: Checked by: Approved by:


45 of 58

Remarks

Estimated by: Checked by: Approved by:


46 of 58

Remarks

Estimated by: Checked by: Approved by:


47 of 58

Client :- Ram kumar shrestha


Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN

ABSTRACT OF COST-Main Building


Item Rate Amount
Description of Works Unit Quantity
No. (NPR) (NPR)
1 Earth work.
1.1 Site clearence works: Clearing the site with
cutting grass, levelling humps, uprootings
and clearing surface grass upto 15 cms and
disposing in specified places all complete as Sft 2,131.00 3.72 7,927.32
per instructions of site engineer

1.2 Earthwork in excavation of foundation in


Boulder mix soil up to size 30 cms, lead 10m Cft 3,923.49 15.57 61,088.71
and lift 2.0 m all complete
1.3 Earth work in filling in foundation, floors etc
in 15 cms layers and compaction by water Cft 2,406.20 9.50 22,858.90
spray all complete
1.4 Soling Works: First class brick soling (flat)
with sand compaction in foundations, floors Sft 1,877.06 122.32 229,602.32
etc all complete
2 Concrete Works
2.1 Plain cement concret PCC(1:3:6) in
foundation, floors etc. with cement, sand and
crussed aggregate of 10 mm to 38mm gauge
including mixing with mixture machine &
compaction by vibrator, laying in line & level Cft 469.27 324.23 152,150.02
with curing all type of works complete as per
specifications & instructions

2.2 RCC work: RCC work in PCC (1:1.5:3) in


foundation, floors, columns, beams, slabs etc.
with cement,sand and crussed aggregate of 10
mm to 38mm gauge including mixing with Cft 3,046.98 480.00 1,462,550.47
mixture machine & compaction by vibrator,
laying in line & level with curing all type of
works complete as per specifications &
instructions
3 Tor /TMT Reinforcement work for R.C.C
work including supply, straighting, cutting,
bending, binding and laying of different
diameter steel rod in all types of R.C.C work Kg 16,836.53 112.00 1,885,691.31
as per design ,drawing ,specification and
instruction all complete work
4 Form work for Foundation, beams, column,
slab etc. all types of concrete with 19 mm
plyboard with steel props centering &
shuttering including promping wedging,
scafolding, proping, stagging inclusive of Sft 7,020.10 65.00 456,306.82
utilization till the support is fully unyielding
net as per design ,drawing specification and
instruction
48 of 58
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN

ABSTRACT OF COST-Main Building


Item Rate Amount
Description of Works Unit Quantity
No. (NPR) (NPR)
5 First class local chimney made exposed fair
face brick wall work in cement sand mortar
(1:4) superstructure in perfect line and level
including wetting the brick, packing the
joints and curing all types of works as per
specification and instruction by Engineer
(fair faced brick work)

5.1 Brick work 9" th ( c:s 1:6 ) Cft 1,902.41 411.50 782,841.93
5.2 Brick work 4" th ( c:s 1:4 ) Sft 1,952.39 290.00 566,192.58
12.5 / 20 mm thick (1:4) c/s plaster work on
6 floors, walls etc. with proper curing all
complete

6.1 Plaster work External ( c:s 1:4) Sft 2,562.99 45.00 115,334.43
6.2 Plaster work Internal ( c:s 1:4) Sft 6,967.76 38.00 264,775.02
7 Wood Works.
7.1 Sal Wood Door & Window Frame Work
Providing & fitting in position 75 x 125mm
Sal wood with all necessary screws & fixing
bolts or hold fast as per drawing, specification
& instruction of the Consultant.
Cft 25.39 6,500.00 165,030.94

7.2 Commercial Flush Door Shutter Work


Providing & fitting door shutters made of
commercial solid core door 38mm thick
( Surya or equivalent ) as per design with
sisum lattice and necessary hardwares all Sft 2,014.25 325.00 654,631.25
complete as per drawing, specification &
instruction of the Consultant.

7.3 Supplying and fixing ready made UPVC


frame for windows, 8mm thick single layer
glass with necessary tower bolts, hinges, Sft 673.37 550.00 370,353.50
handle, screws, locking set all compete work
as per specification and instructions

8 Flooring works.
8.1 Supplying and fixing Ceramic glazed tiles
(8"x8", 8"x6") in floors, walls etc.on toilets 1:4 Sft 3,496.71 275.00 961,596.54
c/s mortar all complete
8.2 Supplying and fixing 13 mm thick Granite on
20 mm thick c/s mortar (1:4) on staircase,
steps, floors, walls etc. with cutting, grooving,
Sft 741.72 450.00 333,774.81
rubbing, washing with oxalic acid and wax
polish etc. all complete

8.3 IPS Flooring works.( 3mm thick fine cement


smoothening works)
Sft 2,377.52 72.58 172,560.17
49 of 58

Client :- Ram kumar shrestha


Project :- Residential Building
Location :-THANKOT MAHADEVSATHAN

ABSTRACT OF COST-Main Building


Item Rate Amount
Description of Works Unit Quantity
No. (NPR) (NPR)
9 Painting works.
9.1 Supplying and applying two coats of plastic
emulsion paint with primar base with good
finishing as per instructions and Sft 10,342.47 25.00 258,561.75
specifications all complete (inner suface)

9.2 Supplying and applying weather proof Apex


paint two coat with astar with good finishing
as per instructions and specifications all Sft 2,562.99 29.00 74,326.63
complete (Exterior surfaces)

9.3 Supplying and applying 2mm thick plain


white putty plaster on walls, ceilings etc. in
perfect line and level as per instructions and Sft 12,905.46 11.00 141,960.03
specifications all complete
10 Stainless steel works: Supplying and fixing
stainless steel staircase railing of height upto
0.9m, hand rail of 50mm dia , balusters 50mm
dia in 2 m distance and three line of 25mm Rft 40.00 1,050.00 42,000.00
dia intermediate rails in between stair steps/
floors and top rail with painting all complete

Total amount 9,182,115.46


` 550,926.93
Electrical work ( 6% civil of cost ) 550,926.93
Interior design works ( 20% civil of cost ) 1,836,423.09
Land development works ( 5% civil of cost ) 459,105.77
Total amount 12,579,498.18
VAT 13 % 1,635,334.76
Sub Total amount 14,214,832.95
50 of 58

CT OF COST-Main Building

Remarks
51 of 58

CT OF COST-Main Building

Remarks
52 of 58

CT OF COST-Main Building

Remarks
Bill of Quantity (BoQ)
Client :- Ram kumar shrestha
Project :- Residential Building
Location :-THANKOT, MAHADEVSATHAN
Item Rate Amount (NPR)
Description of Works Unit Quantity
No. (NPR) In figures
1 Earth work.
1.1 Site clearence works: Clearing the site with cutting
grass, levelling humps, uprootings and clearing
surface grass upto 15 cms and disposing in Sft 2,131.00
specified places all complete as per instructions of
site engineer
1.2 Earthwork in excavation of foundation in Boulder
mix soil up to size 30 cms, lead 10m and lift 2.0 m Cft 3,923.49
all complete
1.3 Earth work in filling in foundation, floors etc in 15
cms layers and compaction by water spray all Cft 2,406.20
complete
1.4 Soling Works: First class brick soling (flat) with
sand compaction in foundations, floors etc all Sft 1,877.06
complete
2 Concrete Works
2.1 Plain cement concret PCC(1:3:6) in foundation,
floors etc. with cement, sand and crussed aggregate
of 10 mm to 38mm gauge including mixing with
mixture machine & compaction by vibrator, laying Cft 469.27
in line & level with curing all type of works
complete as per specifications & instructions

2.2 RCC work: RCC work in PCC (1:1.5:3) in


foundation, floors, columns, beams, slabs etc. with
cement,sand and crussed aggregate of 10 mm to
38mm gauge including mixing with mixture
machine & compaction by vibrator, laying in line & Cft 3,046.98
level with curing all type of works complete as per
specifications & instructions

3 Tor /TMT Reinforcement work for R.C.C work


including supply, straighting, cutting, bending,
binding and laying of different diameter steel rod
in all types of R.C.C work as per design ,drawing Kg 16,836.53
,specification and instruction all complete work
4 Form work for Foundation, beams, column, slab
etc. all types of concrete with 19 mm plyboard with
steel props centering & shuttering including
promping wedging, scafolding, proping, stagging Sft 7,020.10
inclusive of utilization till the support is fully
unyielding net as per design ,drawing specification
and instruction

5 First class local chimney made exposed fair face


brick wall work in cement sand mortar (1:4)
superstructure in perfect line and level including
wetting the brick, packing the joints and curing
all types of works as per specification and
instruction by Engineer (fair faced brick work)

5.1 Brick work 9" th ( c:s 1:6 ) Cft 1,902.41


5.2 Brick work 4" th ( c:s 1:4 ) Sft 1,952.39
12.5 / 20 mm thick (1:4) c/s plaster work on floors,
6 walls etc. with proper curing all complete

6.1 Plaster work External ( c:s 1:4) Sft 2,562.99


6.2 Plaster work Internal ( c:s 1:4) Sft 6,967.76
7 Wood Works.
7.1 Sal Wood Door & Window Frame Work
Providing & fitting in position 75 x 125mm Sal
wood with all necessary screws & fixing bolts or
hold fast as per drawing, specification & Cft 25.39
instruction of the Consultant.
7.2 Commercial Flush Door Shutter Work
Providing & fitting door shutters made of
commercial solid core door 38mm thick ( Surya or
equivalent ) as per design with sisum lattice and
necessary hardwares all complete as per drawing, Sft 2,014.25
specification & instruction of the Consultant.

7.3 Supplying and fixing ready made UPVC frame for


windows, 8mm thick single layer glass with
necessary tower bolts, hinges, handle, screws, Sft 673.37
locking set all compete work as per specification
and instructions

8 Flooring works.
8.1 Supplying and fixing Ceramic glazed tiles (8"x8",
8"x6") in floors, walls etc.on toilets 1:4 c/s mortar Sft 3,496.71
all complete
8.2 Supplying and fixing 13 mm thick Granite on 20
mm thick c/s mortar (1:4) on staircase, steps, floors,
walls etc. with cutting, grooving, rubbing, washing Sft 741.72
with oxalic acid and wax polish etc. all complete
8.3 IPS Flooring works.( 3mm thick fine cement
Sft 2,377.52
smoothening works)
9 Painting works.
9.1 Supplying and applying two coats of plastic
emulsion paint with primar base with good
finishing as per instructions and specifications all Sft 10,342.47
complete (inner suface)
9.2 Supplying and applying weather proof Apex paint
two coat with astar with good finishing as per
instructions and specifications all complete Sft 2,562.99
(Exterior surfaces)
9.3 Supplying and applying 2mm thick plain white
putty plaster on walls, ceilings etc. in perfect line
and level as per instructions and specifications all Sft 12,905.46
complete
10 Stainless steel works: Supplying and fixing
stainless steel staircase railing of height upto 0.9m,
hand rail of 50mm dia , balusters 50mm dia in 2 m
distance and three line of 25mm dia intermediate Rft 40.00
rails in between stair steps/ floors and top rail with
painting all complete

TOTAL CONTRACT AMOUNT (without VAT and with Overhead)= Rs.


In words :
Name of Firm :-
Name of Proprietor :-
Regtd. No.
PAN No.:-
VAT Regd Date:-
Address :-
Contact No:-
Amount (NPR)
Remarks
In words
-------------------------------
Contractor's Signature