Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Achrafieh 4748 Residential Project - Revised RV2 Update Updated vs Revised Schedule of Work - 2 Week Look-Ahead (Data Date

Updated vs Revised Schedule of Work - 2 Week Look-Ahead (Data Date 30-Jun-15) 13-Jul-15 13:05
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
General 0 14-Jul-15 14-Jul-15 -184
North Tower 0 14-Jul-15 14-Jul-15 -184
General 0 14-Jul-15 14-Jul-15 -184
General 0 14-Jul-15 14-Jul-15 -184
GGENNGEN180 Complete Aluminum Works 0 0% 14-Jul-15 -184
GGENNGEN190 Complete External Facade 0 0% 14-Jul-15 -184
Procurement & Delivery
Deliv 583 09-Jun-13 A 03-Aug-15 -184
Parking 563 09-Jun-13 A 03-Aug-15 -184
General 563 09-Jun-13 A 03-Aug-15 -184
Steel Doors 120 15-Aug-14 A 03-Aug-15 -202
PGENPSTD610 Fabricate/Deliver Aluminum OH Coiling Doors 120 80% 15-Aug-14 A 03-Aug-15 -202
Signage 120 25-Aug-14 A 14-Jul-15 -172
PGENPSIG600 Fabricate/Deliver Signage System 120 90% 25-Aug-14 A 14-Jul-15 -172
Lighting & Power 100 01-Dec-14 A 29-Jul-15 -182
PGENPPWR690 Fabricate/Deliver UPS 100 80% 01-Dec-14 A 29-Jul-15 -182
Low Current 366 09-Jun-13 A 08-Jul-15 -178
PGENPLCR610 Fabricate/Deliver Telephone System 140 95% 12-Feb-14 A 08-Jul-15 -178
PGENPLCR640 Fabricate/Deliver CCTV System 140 95% 09-Jun-13 A 08-Jul-15 -191
East Tower 202 20-Aug-14 A 31-Jul-15 -184
General 202 20-Aug-14 A 31-Jul-15 -184
Metals 100 20-Aug-14 A 11-Jul-15 -176
PGENEMET630 Fabricate/Deliver Stainless Steel Sheets for Elevator Lobby 100 90% 20-Aug-14 A 11-Jul-15 -176
Architectural Wood Wo
Work 93 21-Nov-14 A 27-Jul-15 -198
PGENEAWW 610 Fabricate/Deliver Wood Cladding 70 75% 21-Nov-14 A 27-Jul-15 -199
PGENEAWW 630 Fabricate/Deliver Reception Desk 70 75% 21-Nov-14 A 27-Jul-15 -198
Signage 110 20-Aug-14 A 31-Jul-15 -185
PGENESIG600 Fabricate/Deliver Signage System 110 80% 20-Aug-14 A 31-Jul-15 -185
Lighting & Power 120 10-Dec-14 A 14-Jul-15 -174
PGENEPWR690 Fabricate/Deliver UPS 120 90% 10-Dec-14 A 14-Jul-15 -174
North Tower 202 20-Aug-14 A 31-Jul-15 -182
General 202 20-Aug-14 A 31-Jul-15 -182
Metals 100 20-Aug-14 A 11-Jul-15 -176
PGENNMET630 Fabricate/Deliver Stainless Steel Sheets for Elevator Lobby 100 90% 20-Aug-14 A 11-Jul-15 -176
Architectural Wood Wo
Work 70 20-Nov-14 A 27-Jul-15 -199
PGENNAW W610 Fabricate/Deliver Wood Cladding 70 75% 20-Nov-14 A 27-Jul-15 -199
Signage 110 20-Aug-14 A 31-Jul-15 -182
PGENNSIG600 Fabricate/Deliver Signage System 110 80% 20-Aug-14 A 31-Jul-15 -182
Lighting & Power 120 10-Dec-14 A 14-Jul-15 -174
PGENNPWR690 Fabricate/Deliver UPS 120 90% 10-Dec-14 A 14-Jul-15 -174
South Tower 160 20-Aug-14 A 31-Jul-15 -182
General 160 20-Aug-14 A 31-Jul-15 -182
Metals 100 20-Aug-14 A 11-Jul-15 -176
PGENSMET630 Fabricate/Deliver Stainless Steel Sheets for Elevator Lobby 100 90% 20-Aug-14 A 11-Jul-15 -176
Architectural Wood Wo
Work 70 21-Nov-14 A 27-Jul-15 -199
PGENSAWW 610 Fabricate/Deliver Wood Cladding 70 75% 21-Nov-14 A 27-Jul-15 -199
Signage 110 23-Aug-14 A 31-Jul-15 -182
PGENSSIG600 Fabricate/Deliver Signage System 110 80% 23-Aug-14 A 31-Jul-15 -182
Lighting & Power 120 10-Dec-14 A 14-Jul-15 -174
PGENSPWR690 Fabricate/Deliver UPS 120 90% 10-Dec-14 A 14-Jul-15 -174
Retail 180 22-Aug-14 A 29-Jul-15 -192
General 180 22-Aug-14 A 29-Jul-15 -192
Signage 80 22-Aug-14 A 29-Jul-15 -194
PGENRSIG600 Fabricate/Deliver Signage System 80 75% 22-Aug-14 A 29-Jul-15 -194
Lighting & Power 100 10-Dec-14 A 17-Jul-15 -187
PGENRPWR690 Fabricate/Deliver UPS 100 85% 10-Dec-14 A 17-Jul-15 -187
Construction 343 18-Jul-14 A 15-Sep-15 -197
Parking 81 07-May-15 A 15-Aug-15 -182
2nd Basement Floor 77 12-May-15 A 15-Aug-15 -182
Metals 4 01-Jul-15 04-Jul-15 -175
CB02PMET100 Stainless Steel Ladder to Water Tank 3 0% 01-Jul-15 03-Jul-15 -174
CB02PMET120 Galvanized Steel Grating to Gutter 4 0% 01-Jul-15 04-Jul-15 -188
Aluminum Works 30 06-Jul-15 14-Aug-15 -188
CB02PALM100 Aluminum Joint Sealant Cover 30 0% 06-Jul-15 14-Aug-15 -188
Plumbing 30 01-Jul-15 10-Aug-15 -188
CB02PPLM200 Water Treatment Plant 30 0% 01-Jul-15 10-Aug-15 -188
Low Current 17 12-May-15 A 14-Jul-15 -182
CB02PLCR290 CO Detectors 12 80% 12-May-15 A 08-Jul-15 -177
CB02PLCR360 CCTV Cameras 12 60% 18-May-15 A 14-Jul-15 -182
Electrical 30 18-May-15 A 15-Aug-15 -182
CB02PELE100 Electrical Floor Testing/Checks 30 25% 18-May-15 A 15-Aug-15 -182
1st Basement Floor 81 07-May-15 A 14-Aug-15 -182
Metals 10 23-May-15 A 03-Jul-15 -198
CB01PMET120 Galvanized Steel Grating to Gutter 10 75% 23-May-15 A 03-Jul-15 -198
Steel Doors 30 06-Jul-15 14-Aug-15 -199
CB01PSTD110 Overhead Coiling Doors 30 0% 06-Jul-15 14-Aug-15 -199
Aluminum Works 30 03-Jul-15 13-Aug-15 -198
CB01PALM100 Aluminum Joint Sealant Cover 30 0% 03-Jul-15 13-Aug-15 -198
Plumbing 10 01-Jul-15 11-Jul-15 -181
CB01PPLM300 Water Meter 10 0% 01-Jul-15 11-Jul-15 -181
Low Current 17 07-May-15 A 16-Jul-15 -184
CB01PLCR360 CCTV Cameras/Digital Recorders 17 60% 07-May-15 A 16-Jul-15 -184
Mechanical 30 13-May-15 A 13-Aug-15 -181
CB01PMEC100 Mechanical Floor Testing/Checks 30 25% 13-May-15 A 13-Aug-15 -181
East Tower 304 18-Jul-14 A 31-Jul-15 -158
2nd Basement Floor 27 08-May-15 A 16-Jul-15 -240
Mechanical 18 08-May-15 A 16-Jul-15 -240
CB02EMEC100 Mechanical Floor Testing/Checks 18 25% 08-May-15 A 16-Jul-15 -240
Electrical 18 15-May-15 A 16-Jul-15 -240
CB02EELE100 Electrical Floor Testing/Checks 18 25% 15-May-15 A 16-Jul-15 -240
Architectural 18 19-May-15 A 16-Jul-15 -240
CB02EARC100 Architectural Floor Inspection/Checks 18 25% 19-May-15 A 16-Jul-15 -240
1st Basement Floor 48 13-May-15 A 17-Jul-15 -241
Low Current 6 01-Jul-15 07-Jul-15 -241
CB01ELCR190 PABX 6 0% 01-Jul-15 07-Jul-15 -241

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 1 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
Mechanical 18 13-May-15 A 10-Jul-15 -235
CB01EMEC100 Mechanical Floor Testing/Checks 18 50% 13-May-15 A 10-Jul-15 -235
Electrical 18 14-May-15 A 17-Jul-15 -241
CB01EELE100 Electrical Floor Testing/Checks 18 50% 14-May-15 A 17-Jul-15 -241
Architectural 18 20-May-15 A 10-Jul-15 -235
CB01EARC100 Architectural Floor Inspection/Checks 18 50% 20-May-15 A 10-Jul-15 -235
Ground Floor 18 16-May-15 A 14-Jul-15 -195
Metals 14 20-May-15 A 08-Jul-15 -198
CFGNEMET100 Steel Canopy 14 50% 20-May-15 A 08-Jul-15 -198
Tiling Works 16 19-May-15 A 14-Jul-15 -217
CFGNETIL100 Ceramic Tiles for Common Area 6 20% 20-May-15 A 06-Jul-15 -211
CFGNETIL110 Ceramic Tiles for Bathroom 16 30% 19-May-15 A 14-Jul-15 -217
CFGNETIL120 Marble Tiles for Common Area 16 30% 19-May-15 A 14-Jul-15 -217
CFGNETIL130 Terrazzo Tiles for Apartments 8 30% 19-May-15 A 07-Jul-15 -216
Gypsum Works 18 16-May-15 A 10-Jul-15 -193
CFGNEGYP100 Gypsum Board False Ceiling 18 50% 16-May-15 A 10-Jul-15 -193
Ground Floor Mezzanine
Mezzan 24 01-Jun-15 A 10-Jul-15 -235
Mechanical 18 01-Jun-15 A 10-Jul-15 -235
CFGMEMEC100 Mechanical Floor Testing/Checks 18 50% 01-Jun-15 A 10-Jul-15 -235
Electrical 18 04-Jun-15 A 10-Jul-15 -235
CFGMEELE100 Electrical Floor Testing/Checks 18 50% 04-Jun-15 A 10-Jul-15 -235
Architectural 18 08-Jun-15 A 10-Jul-15 -235
CFGMEARC100 Architectural Floor Inspection/Checks 18 50% 08-Jun-15 A 10-Jul-15 -235
2nd Floor 159 14-Aug-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 14-Aug-14 A 09-Jul-15 -240
CF02EAWW 100 Wood Closets 9 75% 14-Aug-14 A 09-Jul-15 -240
Kitchen Unit 3 22-Dec-14 A 08-Jul-15 -239
CF02EKUN100 Kitchen Units 3 65% 22-Dec-14 A 08-Jul-15 -239
Paint 16 15-Jan-15 A 07-Jul-15 -254
CF02EPNT120 Acrylic Paint Final Coat 16 65% 15-Jan-15 A 07-Jul-15 -254
Plumbing 18 08-Nov-14 A 14-Jul-15 -254
CF02EPLM140 Sanitary Fixtures 18 65% 08-Nov-14 A 14-Jul-15 -254
Lighting & Power 18 19-Dec-14 A 10-Jul-15 -251
CF02EPWR140 Wiring Devices & Outlet Boxes 18 85% 19-Dec-14 A 10-Jul-15 -251
CF02EPWR150 Lighting Fixtures 18 85% 19-Dec-14 A 10-Jul-15 -251
Low Current 9 21-Jan-15 A 10-Jul-15 -252
CF02ELCR180 Fire Alarm Detectors 9 65% 21-Jan-15 A 10-Jul-15 -252
CF02ELCR190 Telephone/Data Socket Outlets 9 65% 21-Jan-15 A 10-Jul-15 -252
CF02ELCR200 Video Interphone Units 6 65% 21-Jan-15 A 09-Jul-15 -251
CF02ELCR210 TV Sockets 9 65% 21-Jan-15 A 10-Jul-15 -252
Mechanical 18 26-Jan-15 A 27-Jul-15 -254
CF02EMEC100 Mechanical Floor Testing/Checks 18 65% 26-Jan-15 A 27-Jul-15 -254
Electrical 18 26-Jan-15 A 24-Jul-15 -252
CF02EELE100 Electrical Floor Testing/Checks 18 65% 26-Jan-15 A 24-Jul-15 -252
Architectural 18 26-Jan-15 A 17-Jul-15 -240
CF02EARC100 Architectural Floor Inspection/Checks 18 65% 26-Jan-15 A 17-Jul-15 -240
3rd Floor 27 13-Dec-14 A 27-Jul-15 -244
Paint 16 13-Dec-14 A 07-Jul-15 -254
CF03EPNT120 Acrylic Paint Final Coat 16 65% 13-Dec-14 A 07-Jul-15 -254
Low Current 10 13-Dec-14 A 10-Jul-15 -252
CF03ELCR180 Fire Alarm Detectors 9 65% 13-Dec-14 A 10-Jul-15 -252
CF03ELCR190 Telephone/Data Socket Outlets 9 65% 13-Dec-14 A 10-Jul-15 -252
CF03ELCR200 Video Interphone Units 6 65% 13-Dec-14 A 09-Jul-15 -251
CF03ELCR210 TV Sockets 9 65% 13-Dec-14 A 10-Jul-15 -252
Mechanical 18 23-Dec-14 A 27-Jul-15 -254
CF03EMEC100 Mechanical Floor Testing/Checks 18 65% 23-Dec-14 A 27-Jul-15 -254
Electrical 18 24-Dec-14 A 24-Jul-15 -252
CF03EELE100 Electrical Floor Testing/Checks 18 65% 24-Dec-14 A 24-Jul-15 -252
Architectural 18 24-Dec-14 A 14-Jul-15 -238
CF03EARC100 Architectural Floor Inspection/Checks 18 65% 24-Dec-14 A 14-Jul-15 -238
4th Floor 123 13-Aug-14 A 28-Jul-15 -244
Paint 16 01-Dec-14 A 07-Jul-15 -255
CF04EPNT120 Acrylic Paint Final Coat 16 65% 01-Dec-14 A 07-Jul-15 -255
Plumbing 18 14-Oct-14 A 14-Jul-15 -254
CF04EPLM140 Sanitary Fixtures 18 65% 14-Oct-14 A 14-Jul-15 -254
Lighting & Power 18 13-Aug-14 A 14-Jul-15 -255
CF04EPWR150 Lighting Fixtures 18 65% 13-Aug-14 A 14-Jul-15 -255
Low Current 9 19-Dec-14 A 10-Jul-15 -252
CF04ELCR180 Fire Alarm Detectors 9 65% 19-Dec-14 A 10-Jul-15 -252
CF04ELCR190 Telephone/Data Socket Outlets 9 65% 19-Dec-14 A 10-Jul-15 -252
CF04ELCR200 Video Interphone Units 6 65% 19-Dec-14 A 09-Jul-15 -251
CF04ELCR210 TV Sockets 9 65% 19-Dec-14 A 10-Jul-15 -252
Mechanical 18 19-Dec-14 A 27-Jul-15 -254
CF04EMEC100 Mechanical Floor Testing/Checks 18 65% 19-Dec-14 A 27-Jul-15 -254
Electrical 18 19-Dec-14 A 28-Jul-15 -255
CF04EELE100 Electrical Floor Testing/Checks 18 65% 19-Dec-14 A 28-Jul-15 -255
Architectural 18 20-Dec-14 A 14-Jul-15 -238
CF04EARC100 Architectural Floor Inspection/Checks 18 65% 20-Dec-14 A 14-Jul-15 -238
7th Floor 117 18-Aug-14 A 25-Jul-15 -245
Architectural Wood Wo
Work 9 18-Aug-14 A 17-Jul-15 -254
CF07EAWW 100 Wood Closets 9 50% 18-Aug-14 A 17-Jul-15 -254
Aluminum Works 3 17-Dec-14 A 14-Jul-15 -240
CF07EALM100 Mirrors 3 50% 17-Dec-14 A 14-Jul-15 -240
Wood Doors/Windows 11 18-Aug-14 A 15-Jul-15 -251
CF07EWDD120 MDF Wood Doors 9 80% 19-Aug-14 A 15-Jul-15 -251
CF07EWDD150 Walnut Wood Doors 6 65% 18-Aug-14 A 15-Jul-15 -251
Kitchen Unit 3 15-Sep-14 A 14-Jul-15 -250
CF07EKUN100 Kitchen Units 3 65% 15-Sep-14 A 14-Jul-15 -250
Paint 16 20-Dec-14 A 13-Jul-15 -269
CF07EPNT120 Acrylic Paint Final Coat 16 35% 20-Dec-14 A 13-Jul-15 -269
Plumbing 18 25-Nov-14 A 25-Jul-15 -269
CF07EPLM140 Sanitary Fixtures 18 65% 25-Nov-14 A 25-Jul-15 -269
Lighting & Power 19 11-Nov-14 A 25-Jul-15 -269
CF07EPWR140 Wiring Devices & Outlet Boxes 18 65% 11-Nov-14 A 25-Jul-15 -269
CF07EPWR150 Lighting Fixtures 18 65% 12-Nov-14 A 25-Jul-15 -269
Low Current 10 17-Dec-14 A 25-Jul-15 -269
CF07ELCR180 Fire Alarm Detectors 9 30% 17-Dec-14 A 25-Jul-15 -269

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 2 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
CF07ELCR190 Telephone/Data Socket Outlets 9 30% 17-Dec-14 A 25-Jul-15 -269
CF07ELCR200 Video Interphone Units 6 30% 17-Dec-14 A 17-Jul-15 -267
CF07ELCR210 TV Sockets 9 30% 17-Dec-14 A 25-Jul-15 -269
10th Floor 126 21-Jul-14 A 28-Jul-15 -244
Architectural Wood Wo
Work 9 20-Aug-14 A 09-Jul-15 -240
CF10EAWW 100 Wood Closets 9 80% 20-Aug-14 A 09-Jul-15 -240
Plastic 3 15-Sep-14 A 02-Jul-15 -249
CF10EPLS100 Hanex Resin White Tops 3 65% 15-Sep-14 A 02-Jul-15 -249
Wood Doors/Windows 12 14-Aug-14 A 09-Jul-15 -240
CF10EWDD120 MDF Wood Doors 9 80% 16-Aug-14 A 09-Jul-15 -240
CF10EWDD150 Walnut Wood Doors 6 80% 14-Aug-14 A 08-Jul-15 -239
Paint 16 12-Dec-14 A 07-Jul-15 -258
CF10EPNT120 Acrylic Paint Final Coat 16 65% 12-Dec-14 A 07-Jul-15 -258
Plumbing 18 27-Oct-14 A 14-Jul-15 -257
CF10EPLM140 Sanitary Fixtures 18 65% 27-Oct-14 A 14-Jul-15 -257
Lighting & Power 106 21-Jul-14 A 14-Jul-15 -258
CF10EPWR140 Wiring Devices & Outlet Boxes 18 65% 18-Dec-14 A 14-Jul-15 -258
CF10EPWR150 Lighting Fixtures 18 65% 21-Jul-14 A 14-Jul-15 -258
Low Current 10 16-Dec-14 A 10-Jul-15 -255
CF10ELCR180 Fire Alarm Detectors 9 65% 16-Dec-14 A 10-Jul-15 -255
CF10ELCR190 Telephone/Data Socket Outlets 9 65% 17-Dec-14 A 10-Jul-15 -255
CF10ELCR200 Video Interphone Units 6 65% 17-Dec-14 A 09-Jul-15 -254
CF10ELCR210 TV Sockets 9 65% 17-Dec-14 A 10-Jul-15 -255
Mechanical 18 20-Dec-14 A 27-Jul-15 -257
CF10EMEC100 Mechanical Floor Testing/Checks 18 65% 20-Dec-14 A 27-Jul-15 -257
Electrical 18 22-Dec-14 A 28-Jul-15 -258
CF10EELE100 Electrical Floor Testing/Checks 18 65% 22-Dec-14 A 28-Jul-15 -258
Architectural 18 23-Dec-14 A 16-Jul-15 -240
CF10EARC100 Architectural Floor Inspection/Checks 18 65% 23-Dec-14 A 16-Jul-15 -240
11th Floor 107 23-Jan-15 A 27-Jul-15 -246
Architectural Wood Wo
Work 9 14-Apr-15 A 17-Jul-15 -252
CF11EAWW100 Wood Closets 9 65% 14-Apr-15 A 17-Jul-15 -252
Plastic 3 06-Mar-15 A 02-Jul-15 -274
CF11EPLS100 Hanex Resin White Tops 3 65% 06-Mar-15 A 02-Jul-15 -274
Aluminum Works 3 20-May-15 A 15-Jul-15 -240
CF11EALM100 Mirrors 3 65% 20-May-15 A 15-Jul-15 -240
Wood Doors/Windows 13 23-Jan-15 A 17-Jul-15 -252
CF11EWDD120 MDF Wood Doors 9 65% 27-Jan-15 A 17-Jul-15 -252
CF11EWDD150 Walnut Wood Doors 6 65% 23-Jan-15 A 16-Jul-15 -251
Kitchen Unit 3 24-Jan-15 A 14-Jul-15 -250
CF11EKUN100 Kitchen Units 3 75% 24-Jan-15 A 14-Jul-15 -250
Paint 16 20-Apr-15 A 14-Jul-15 -288
CF11EPNT120 Acrylic Paint Final Coat 16 30% 20-Apr-15 A 14-Jul-15 -288
Plumbing 18 18-Mar-15 A 27-Jul-15 -288
CF11EPLM140 Sanitary Fixtures 18 65% 18-Mar-15 A 27-Jul-15 -288
Lighting & Power 18 24-Mar-15 A 27-Jul-15 -288
CF11EPWR140 Wiring Devices & Outlet Boxes 18 65% 24-Mar-15 A 27-Jul-15 -288
CF11EPWR150 Lighting Fixtures 18 65% 25-Mar-15 A 27-Jul-15 -288
Low Current 9 14-Apr-15 A 27-Jul-15 -288
CF11ELCR180 Fire Alarm Detectors 9 35% 14-Apr-15 A 27-Jul-15 -288
CF11ELCR190 Telephone/Data Socket Outlets 9 35% 14-Apr-15 A 27-Jul-15 -288
CF11ELCR200 Video Interphone Units 6 35% 15-Apr-15 A 24-Jul-15 -286
CF11ELCR210 TV Sockets 9 35% 14-Apr-15 A 27-Jul-15 -288
12th Floor 229 12-Aug-14 A 25-Jul-15 -245
Architectural Wood Wo
Work 9 18-Aug-14 A 16-Jul-15 -252
CF12EAWW 100 Wood Closets 9 65% 18-Aug-14 A 16-Jul-15 -252
Plastic 3 10-Dec-14 A 02-Jul-15 -275
CF12EPLS100 Hanex Resin White Tops 3 65% 10-Dec-14 A 02-Jul-15 -275
Aluminum Works 3 15-May-15 A 14-Jul-15 -240
CF12EALM100 Mirrors 3 50% 15-May-15 A 14-Jul-15 -240
Wood Doors/Windows 9 12-Aug-14 A 16-Jul-15 -252
CF12EWDD120 MDF Wood Doors 9 65% 12-Aug-14 A 16-Jul-15 -252
CF12EWDD150 Walnut Wood Doors 6 65% 13-Aug-14 A 15-Jul-15 -251
Kitchen Unit 3 15-Sep-14 A 14-Jul-15 -250
CF12EKUN100 Kitchen Units 3 65% 15-Sep-14 A 14-Jul-15 -250
Paint 16 15-Jan-15 A 13-Jul-15 -288
CF12EPNT120 Acrylic Paint Final Coat 16 35% 15-Jan-15 A 13-Jul-15 -288
Plumbing 18 20-Nov-14 A 25-Jul-15 -288
CF12EPLM140 Sanitary Fixtures 18 35% 20-Nov-14 A 25-Jul-15 -288
Lighting & Power 18 18-Nov-14 A 17-Jul-15 -287
CF12EPWR150 Lighting Fixtures 18 75% 18-Nov-14 A 17-Jul-15 -287
Low Current 9 14-Jan-15 A 25-Jul-15 -288
CF12ELCR180 Fire Alarm Detectors 9 30% 14-Jan-15 A 25-Jul-15 -288
CF12ELCR190 Telephone/Data Socket Outlets 9 30% 14-Jan-15 A 25-Jul-15 -288
CF12ELCR200 Video Interphone Units 6 30% 15-Jan-15 A 17-Jul-15 -286
CF12ELCR210 TV Sockets 9 30% 14-Jan-15 A 25-Jul-15 -288
13th Floor 159 06-Aug-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 08-Aug-14 A 10-Jul-15 -241
CF13EAWW 100 Wood Closets 9 65% 08-Aug-14 A 10-Jul-15 -241
Aluminum Works 3 13-Feb-15 A 08-Jul-15 -235
CF13EALM100 Mirrors 3 65% 13-Feb-15 A 08-Jul-15 -235
Wood Doors/Windows 6 06-Aug-14 A 09-Jul-15 -240
CF13EWDD150 Walnut Wood Doors 6 65% 06-Aug-14 A 09-Jul-15 -240
Paint 16 15-Jan-15 A 07-Jul-15 -277
CF13EPNT120 Acrylic Paint Final Coat 16 65% 15-Jan-15 A 07-Jul-15 -277
Low Current 10 16-Jan-15 A 10-Jul-15 -274
CF13ELCR180 Fire Alarm Detectors 9 65% 16-Jan-15 A 10-Jul-15 -274
CF13ELCR190 Telephone/Data Socket Outlets 9 65% 16-Jan-15 A 10-Jul-15 -274
CF13ELCR200 Video Interphone Units 6 65% 16-Jan-15 A 09-Jul-15 -273
CF13ELCR210 TV Sockets 9 65% 16-Jan-15 A 10-Jul-15 -274
Mechanical 18 20-Jan-15 A 27-Jul-15 -277
CF13EMEC100 Mechanical Floor Testing/Checks 18 65% 20-Jan-15 A 27-Jul-15 -277
Electrical 18 20-Jan-15 A 24-Jul-15 -274
CF13EELE100 Electrical Floor Testing/Checks 18 65% 20-Jan-15 A 24-Jul-15 -274
Architectural 18 21-Jan-15 A 24-Jul-15 -241
CF13EARC100 Architectural Floor Inspection/Checks 18 65% 21-Jan-15 A 24-Jul-15 -241

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 3 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
14th Floor 236 04-Aug-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 13-Aug-14 A 10-Jul-15 -241
CF14EAWW 100 Wood Closets 9 65% 13-Aug-14 A 10-Jul-15 -241
Plastic 3 17-Sep-14 A 02-Jul-15 -268
CF14EPLS100 Hanex Resin White Tops 3 65% 17-Sep-14 A 02-Jul-15 -268
Aluminum Works 3 15-May-15 A 09-Jul-15 -235
CF14EALM100 Mirrors 3 50% 15-May-15 A 09-Jul-15 -235
Wood Doors/Windows 9 04-Aug-14 A 09-Jul-15 -240
CF14EWDD120 MDF Wood Doors 9 75% 04-Aug-14 A 09-Jul-15 -240
CF14EWDD150 Walnut Wood Doors 6 60% 05-Aug-14 A 09-Jul-15 -240
Paint 16 16-Jan-15 A 07-Jul-15 -277
CF14EPNT120 Acrylic Paint Final Coat 16 65% 16-Jan-15 A 07-Jul-15 -277
Low Current 10 19-Jan-15 A 10-Jul-15 -274
CF14ELCR180 Fire Alarm Detectors 9 65% 19-Jan-15 A 10-Jul-15 -274
CF14ELCR190 Telephone/Data Socket Outlets 9 65% 20-Jan-15 A 10-Jul-15 -274
CF14ELCR200 Video Interphone Units 6 65% 19-Jan-15 A 09-Jul-15 -273
CF14ELCR210 TV Sockets 9 65% 20-Jan-15 A 10-Jul-15 -274
Mechanical 18 21-Jan-15 A 27-Jul-15 -277
CF14EMEC100 Mechanical Floor Testing/Checks 18 65% 21-Jan-15 A 27-Jul-15 -277
Electrical 18 21-Jan-15 A 24-Jul-15 -274
CF14EELE100 Electrical Floor Testing/Checks 18 65% 21-Jan-15 A 24-Jul-15 -274
Architectural 18 21-Jan-15 A 24-Jul-15 -241
CF14EARC100 Architectural Floor Inspection/Checks 18 65% 21-Jan-15 A 24-Jul-15 -241
15th Floor 191 12-Sep-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 18-Apr-15 A 10-Jul-15 -241
CF15EAWW 100 Wood Closets 9 65% 18-Apr-15 A 10-Jul-15 -241
Aluminum Works 3 02-May-15 A 09-Jul-15 -236
CF15EALM100 Mirrors 3 30% 02-May-15 A 09-Jul-15 -236
Wood Doors/Windows 9 25-Oct-14 A 09-Jul-15 -240
CF15EWDD120 MDF Wood Doors 9 80% 25-Oct-14 A 09-Jul-15 -240
CF15EWDD150 Walnut Wood Doors 6 80% 25-Oct-14 A 08-Jul-15 -239
Kitchen Unit 3 12-Sep-14 A 08-Jul-15 -239
CF15EKUN100 Kitchen Units 3 65% 12-Sep-14 A 08-Jul-15 -239
Paint 16 20-Mar-15 A 07-Jul-15 -280
CF15EPNT120 Acrylic Paint Final Coat 16 65% 20-Mar-15 A 07-Jul-15 -280
Low Current 10 23-Mar-15 A 10-Jul-15 -277
CF15ELCR180 Fire Alarm Detectors 9 65% 23-Mar-15 A 10-Jul-15 -277
CF15ELCR190 Telephone/Data Socket Outlets 9 65% 23-Mar-15 A 10-Jul-15 -277
CF15ELCR200 Video Interphone Units 6 65% 24-Mar-15 A 09-Jul-15 -276
CF15ELCR210 TV Sockets 9 65% 24-Mar-15 A 10-Jul-15 -277
Mechanical 18 27-Mar-15 A 27-Jul-15 -280
CF15EMEC100 Mechanical Floor Testing/Checks 18 65% 27-Mar-15 A 27-Jul-15 -280
Electrical 18 28-Mar-15 A 24-Jul-15 -277
CF15EELE100 Electrical Floor Testing/Checks 18 65% 28-Mar-15 A 24-Jul-15 -277
Architectural 18 28-Mar-15 A 24-Jul-15 -241
CF15EARC100 Architectural Floor Inspection/Checks 18 65% 28-Mar-15 A 24-Jul-15 -241
16th Floor 221 18-Jul-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 16-Jan-15 A 09-Jul-15 -240
CF16EAWW 100 Wood Closets 9 75% 16-Jan-15 A 09-Jul-15 -240
Aluminum Works 3 16-Apr-15 A 08-Jul-15 -235
CF16EALM100 Mirrors 3 65% 16-Apr-15 A 08-Jul-15 -235
Wood Doors/Windows 9 25-Oct-14 A 09-Jul-15 -240
CF16EWDD120 MDF Wood Doors 9 80% 25-Oct-14 A 09-Jul-15 -240
CF16EWDD150 Walnut Wood Doors 6 80% 25-Oct-14 A 08-Jul-15 -239
Paint 16 15-Jan-15 A 07-Jul-15 -280
CF16EPNT120 Acrylic Paint Final Coat 16 65% 15-Jan-15 A 07-Jul-15 -280
Lighting & Power 18 18-Jul-14 A 13-Jul-15 -278
CF16EPWR150 Lighting Fixtures 18 75% 18-Jul-14 A 13-Jul-15 -278
Low Current 9 16-Jan-15 A 10-Jul-15 -277
CF16ELCR180 Fire Alarm Detectors 9 65% 16-Jan-15 A 10-Jul-15 -277
CF16ELCR190 Telephone/Data Socket Outlets 9 65% 16-Jan-15 A 10-Jul-15 -277
CF16ELCR200 Video Interphone Units 6 65% 17-Jan-15 A 09-Jul-15 -276
CF16ELCR210 TV Sockets 9 65% 16-Jan-15 A 10-Jul-15 -277
Mechanical 18 27-Jan-15 A 27-Jul-15 -280
CF16EMEC100 Mechanical Floor Testing/Checks 18 65% 27-Jan-15 A 27-Jul-15 -280
Electrical 18 27-Jan-15 A 25-Jul-15 -278
CF16EELE100 Electrical Floor Testing/Checks 18 65% 27-Jan-15 A 25-Jul-15 -278
Architectural 18 28-Jan-15 A 17-Jul-15 -240
CF16EARC100 Architectural Floor Inspection/Checks 18 65% 28-Jan-15 A 17-Jul-15 -240
17th Floor 216 21-Jul-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 15-Jan-15 A 10-Jul-15 -241
CF17EAWW 100 Wood Closets 9 65% 15-Jan-15 A 10-Jul-15 -241
Aluminum Works 3 10-Apr-15 A 08-Jul-15 -235
CF17EALM100 Mirrors 3 65% 10-Apr-15 A 08-Jul-15 -235
Wood Doors/Windows 6 25-Oct-14 A 08-Jul-15 -239
CF17EWDD150 Walnut Wood Doors 6 80% 25-Oct-14 A 08-Jul-15 -239
Paint 16 25-Jan-15 A 07-Jul-15 -280
CF17EPNT120 Acrylic Paint Final Coat 16 65% 25-Jan-15 A 07-Jul-15 -280
Lighting & Power 18 21-Jul-14 A 13-Jul-15 -278
CF17EPWR150 Lighting Fixtures 18 75% 21-Jul-14 A 13-Jul-15 -278
Low Current 9 26-Jan-15 A 10-Jul-15 -277
CF17ELCR180 Fire Alarm Detectors 9 65% 26-Jan-15 A 10-Jul-15 -277
CF17ELCR190 Telephone/Data Socket Outlets 9 65% 26-Jan-15 A 10-Jul-15 -277
CF17ELCR200 Video Interphone Units 6 65% 26-Jan-15 A 09-Jul-15 -276
CF17ELCR210 TV Sockets 9 65% 26-Jan-15 A 10-Jul-15 -277
Mechanical 18 10-Feb-15 A 27-Jul-15 -280
CF17EMEC100 Mechanical Floor Testing/Checks 18 65% 10-Feb-15 A 27-Jul-15 -280
Electrical 18 10-Feb-15 A 25-Jul-15 -278
CF17EELE100 Electrical Floor Testing/Checks 18 65% 10-Feb-15 A 25-Jul-15 -278
Architectural 18 12-Feb-15 A 24-Jul-15 -241
CF17EARC100 Architectural Floor Inspection/Checks 18 65% 12-Feb-15 A 24-Jul-15 -241
18th Floor 237 18-Jul-14 A 28-Jul-15 -244
Architectural Wood Wo
Work 9 21-Jan-15 A 10-Jul-15 -241
CF18EAWW 100 Wood Closets 9 65% 21-Jan-15 A 10-Jul-15 -241
Aluminum Works 3 05-May-15 A 09-Jul-15 -235
CF18EALM100 Mirrors 3 50% 05-May-15 A 09-Jul-15 -235
Wood Doors/Windows 6 15-Nov-14 A 08-Jul-15 -239

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 4 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
CF18EWDD150 Walnut Wood Doors 6 80% 15-Nov-14 A 08-Jul-15 -239
Paint 16 15-Jan-15 A 07-Jul-15 -280
CF18EPNT120 Acrylic Paint Final Coat 16 65% 15-Jan-15 A 07-Jul-15 -280
Lighting & Power 18 18-Jul-14 A 14-Jul-15 -280
CF18EPWR150 Lighting Fixtures 18 65% 18-Jul-14 A 14-Jul-15 -280
Low Current 11 24-Jan-15 A 10-Jul-15 -277
CF18ELCR180 Fire Alarm Detectors 9 65% 24-Jan-15 A 10-Jul-15 -277
CF18ELCR190 Telephone/Data Socket Outlets 9 65% 26-Jan-15 A 10-Jul-15 -277
CF18ELCR200 Video Interphone Units 6 65% 24-Jan-15 A 09-Jul-15 -276
CF18ELCR210 TV Sockets 9 65% 26-Jan-15 A 10-Jul-15 -277
Mechanical 18 12-Feb-15 A 27-Jul-15 -280
CF18EMEC100 Mechanical Floor Testing/Checks 18 65% 12-Feb-15 A 27-Jul-15 -280
Electrical 18 12-Feb-15 A 28-Jul-15 -280
CF18EELE100 Electrical Floor Testing/Checks 18 65% 12-Feb-15 A 28-Jul-15 -280
Architectural 18 14-Feb-15 A 24-Jul-15 -241
CF18EARC100 Architectural Floor Inspection/Checks 18 65% 14-Feb-15 A 24-Jul-15 -241
19th Floor 152 15-Nov-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 25-Jan-15 A 10-Jul-15 -241
CF19EAWW 100 Wood Closets 9 65% 25-Jan-15 A 10-Jul-15 -241
Aluminum Works 3 15-May-15 A 09-Jul-15 -235
CF19EALM100 Mirrors 3 50% 15-May-15 A 09-Jul-15 -235
Wood Doors/Windows 9 15-Nov-14 A 10-Jul-15 -241
CF19EWDD120 MDF Wood Doors 9 65% 15-Nov-14 A 10-Jul-15 -241
Paint 16 20-Jan-15 A 07-Jul-15 -280
CF19EPNT120 Acrylic Paint Final Coat 16 65% 20-Jan-15 A 07-Jul-15 -280
Low Current 11 26-Jan-15 A 10-Jul-15 -277
CF19ELCR180 Fire Alarm Detectors 9 65% 27-Jan-15 A 10-Jul-15 -277
CF19ELCR190 Telephone/Data Socket Outlets 9 65% 26-Jan-15 A 10-Jul-15 -277
CF19ELCR200 Video Interphone Units 6 65% 26-Jan-15 A 09-Jul-15 -276
CF19ELCR210 TV Sockets 9 65% 27-Jan-15 A 10-Jul-15 -277
Mechanical 18 11-Feb-15 A 27-Jul-15 -280
CF19EMEC100 Mechanical Floor Testing/Checks 18 65% 11-Feb-15 A 27-Jul-15 -280
Electrical 18 12-Feb-15 A 24-Jul-15 -277
CF19EELE100 Electrical Floor Testing/Checks 18 65% 12-Feb-15 A 24-Jul-15 -277
Architectural 18 12-Feb-15 A 24-Jul-15 -241
CF19EARC100 Architectural Floor Inspection/Checks 18 65% 12-Feb-15 A 24-Jul-15 -241
20th Floor 191 23-Aug-14 A 28-Jul-15 -244
Architectural Wood Wo
Work 9 21-Jan-15 A 10-Jul-15 -241
CF20EAWW 100 Wood Closets 9 65% 21-Jan-15 A 10-Jul-15 -241
Aluminum Works 3 10-Apr-15 A 08-Jul-15 -235
CF20EALM100 Mirrors 3 65% 10-Apr-15 A 08-Jul-15 -235
Wood Doors/Windows 10 23-Oct-14 A 09-Jul-15 -240
CF20EWDD120 MDF Wood Doors 9 80% 23-Oct-14 A 09-Jul-15 -240
CF20EWDD150 Walnut Wood Doors 6 65% 23-Oct-14 A 09-Jul-15 -240
Paint 16 22-Jan-15 A 07-Jul-15 -280
CF20EPNT120 Acrylic Paint Final Coat 16 65% 22-Jan-15 A 07-Jul-15 -280
Plumbing 18 20-Oct-14 A 14-Jul-15 -280
CF20EPLM140 Sanitary Fixtures 18 65% 20-Oct-14 A 14-Jul-15 -280
Lighting & Power 18 23-Aug-14 A 14-Jul-15 -280
CF20EPWR150 Lighting Fixtures 18 65% 23-Aug-14 A 14-Jul-15 -280
Low Current 9 25-Jan-15 A 10-Jul-15 -277
CF20ELCR180 Fire Alarm Detectors 9 65% 25-Jan-15 A 10-Jul-15 -277
CF20ELCR190 Telephone/Data Socket Outlets 9 65% 25-Jan-15 A 10-Jul-15 -277
CF20ELCR200 Video Interphone Units 6 65% 25-Jan-15 A 09-Jul-15 -276
CF20ELCR210 TV Sockets 9 65% 25-Jan-15 A 10-Jul-15 -277
Mechanical 18 10-Feb-15 A 27-Jul-15 -280
CF20EMEC100 Mechanical Floor Testing/Checks 18 65% 10-Feb-15 A 27-Jul-15 -280
Electrical 18 10-Feb-15 A 28-Jul-15 -280
CF20EELE100 Electrical Floor Testing/Checks 18 65% 10-Feb-15 A 28-Jul-15 -280
Architectural 18 12-Feb-15 A 24-Jul-15 -241
CF20EARC100 Architectural Floor Inspection/Checks 18 65% 12-Feb-15 A 24-Jul-15 -241
21st Floor 200 11-Sep-14 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 17-Feb-15 A 10-Jul-15 -241
CF21EAWW 100 Wood Closets 9 65% 17-Feb-15 A 10-Jul-15 -241
Plastic 3 20-Oct-14 A 02-Jul-15 -268
CF21EPLS100 Hanex Resin White Tops 3 65% 20-Oct-14 A 02-Jul-15 -268
Aluminum Works 3 11-May-15 A 08-Jul-15 -235
CF21EALM100 Mirrors 3 65% 11-May-15 A 08-Jul-15 -235
Wood Doors/Windows 11 11-Sep-14 A 09-Jul-15 -240
CF21EWDD120 MDF Wood Doors 9 80% 12-Sep-14 A 09-Jul-15 -240
CF21EWDD150 Walnut Wood Doors 6 65% 11-Sep-14 A 09-Jul-15 -240
Kitchen Unit 3 21-Nov-14 A 08-Jul-15 -239
CF21EKUN100 Kitchen Units 3 65% 21-Nov-14 A 08-Jul-15 -239
Paint 16 27-Feb-15 A 07-Jul-15 -277
CF21EPNT120 Acrylic Paint Final Coat 16 65% 27-Feb-15 A 07-Jul-15 -277
Low Current 9 17-Feb-15 A 10-Jul-15 -273
CF21ELCR180 Fire Alarm Detectors 9 65% 17-Feb-15 A 10-Jul-15 -273
CF21ELCR190 Telephone/Data Socket Outlets 9 65% 17-Feb-15 A 10-Jul-15 -273
CF21ELCR200 Video Interphone Units 6 65% 17-Feb-15 A 09-Jul-15 -272
CF21ELCR210 TV Sockets 9 65% 17-Feb-15 A 10-Jul-15 -273
Mechanical 18 24-Feb-15 A 27-Jul-15 -277
CF21EMEC100 Mechanical Floor Testing/Checks 18 65% 24-Feb-15 A 27-Jul-15 -277
Electrical 18 24-Feb-15 A 24-Jul-15 -273
CF21EELE100 Electrical Floor Testing/Checks 18 65% 24-Feb-15 A 24-Jul-15 -273
Architectural 18 24-Feb-15 A 24-Jul-15 -241
CF21EARC100 Architectural Floor Inspection/Checks 18 65% 24-Feb-15 A 24-Jul-15 -241
25th Floor 183 23-Oct-14 A 27-Jul-15 -246
Architectural Wood Wo
Work 9 26-Jan-15 A 24-Jul-15 -254
CF25EAWW 100 Wood Closets 9 50% 26-Jan-15 A 24-Jul-15 -254
Plastic 3 23-Oct-14 A 02-Jul-15 -275
CF25EPLS100 Hanex Resin White Tops 3 65% 23-Oct-14 A 02-Jul-15 -275
Aluminum Works 3 03-May-15 A 15-Jul-15 -240
CF25EALM100 Mirrors 3 65% 03-May-15 A 15-Jul-15 -240
Wood Doors/Windows 11 27-Oct-14 A 17-Jul-15 -253
CF25EWDD120 MDF Wood Doors 9 65% 28-Oct-14 A 17-Jul-15 -253
CF25EWDD150 Walnut Wood Doors 6 65% 27-Oct-14 A 16-Jul-15 -252
Kitchen Unit 3 23-Jan-15 A 15-Jul-15 -251

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 5 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
CF25EKUN100 Kitchen Units 3 65% 23-Jan-15 A 15-Jul-15 -251
Paint 16 06-Mar-15 A 14-Jul-15 -289
CF25EPNT120 Acrylic Paint Final Coat 16 30% 06-Mar-15 A 14-Jul-15 -289
Plumbing 18 25-Oct-14 A 27-Jul-15 -289
CF25EPLM140 Sanitary Fixtures 18 60% 25-Oct-14 A 27-Jul-15 -289
Lighting & Power 19 13-Feb-15 A 27-Jul-15 -288
CF25EPWR140 Wiring Devices & Outlet Boxes 18 65% 13-Feb-15 A 27-Jul-15 -288
CF25EPWR150 Lighting Fixtures 18 65% 14-Feb-15 A 27-Jul-15 -288
Low Current 10 07-Mar-15 A 27-Jul-15 -288
CF25ELCR180 Fire Alarm Detectors 9 30% 07-Mar-15 A 27-Jul-15 -288
CF25ELCR190 Telephone/Data Socket Outlets 9 30% 07-Mar-15 A 27-Jul-15 -288
CF25ELCR200 Video Interphone Units 6 30% 07-Mar-15 A 24-Jul-15 -286
CF25ELCR210 TV Sockets 9 30% 07-Mar-15 A 27-Jul-15 -288
27th Floor 55 21-Jan-15 A 27-Jul-15 -244
Architectural Wood Wo
Work 9 21-Jan-15 A 10-Jul-15 -241
CF27EAWW 100 Wood Closets 9 65% 21-Jan-15 A 10-Jul-15 -241
Paint 16 28-Feb-15 A 07-Jul-15 -280
CF27EPNT120 Acrylic Paint Final Coat 16 65% 28-Feb-15 A 07-Jul-15 -280
Mechanical 18 05-Mar-15 A 27-Jul-15 -280
CF27EMEC100 Mechanical Floor Testing/Checks 18 65% 05-Mar-15 A 27-Jul-15 -280
Electrical 18 05-Mar-15 A 14-Jul-15 -274
CF27EELE100 Electrical Floor Testing/Checks 18 65% 05-Mar-15 A 14-Jul-15 -274
Architectural 18 05-Mar-15 A 24-Jul-15 -241
CF27EARC100 Architectural Floor Inspection/Checks 18 65% 05-Mar-15 A 24-Jul-15 -241
28th Floor 30 15-May-15 A 28-Jul-15 -245
Paint 16 15-May-15 A 04-Jul-15 -281
CF28EPNT120 Acrylic Paint Final Coat 16 75% 15-May-15 A 04-Jul-15 -281
Plumbing 18 16-May-15 A 11-Jul-15 -281
CF28EPLM140 Sanitary Fixtures 18 75% 16-May-15 A 11-Jul-15 -281
Low Current 10 26-May-15 A 10-Jul-15 -280
CF28ELCR180 Fire Alarm Detectors 9 50% 26-May-15 A 10-Jul-15 -280
CF28ELCR190 Telephone/Data Socket Outlets 9 50% 26-May-15 A 10-Jul-15 -280
CF28ELCR200 Video Interphone Units 6 50% 26-May-15 A 08-Jul-15 -278
CF28ELCR210 TV Sockets 9 50% 26-May-15 A 10-Jul-15 -280
Mechanical 18 29-May-15 A 28-Jul-15 -281
CF28EMEC100 Mechanical Floor Testing/Checks 18 50% 29-May-15 A 28-Jul-15 -281
Electrical 18 29-May-15 A 27-Jul-15 -280
CF28EELE100 Electrical Floor Testing/Checks 18 50% 29-May-15 A 27-Jul-15 -280
Architectural 18 29-May-15 A 15-Jul-15 -239
CF28EARC100 Architectural Floor Inspection/Checks 18 50% 29-May-15 A 15-Jul-15 -239
29th Floor 28 16-May-15 A 28-Jul-15 -245
Paint 16 19-May-15 A 04-Jul-15 -281
CF29EPNT120 Acrylic Paint Final Coat 16 75% 19-May-15 A 04-Jul-15 -281
Plumbing 18 16-May-15 A 11-Jul-15 -281
CF29EPLM140 Sanitary Fixtures 18 75% 16-May-15 A 11-Jul-15 -281
Low Current 12 23-May-15 A 08-Jul-15 -277
CF29ELCR180 Fire Alarm Detectors 9 75% 26-May-15 A 08-Jul-15 -277
CF29ELCR190 Telephone/Data Socket Outlets 9 75% 26-May-15 A 08-Jul-15 -277
CF29ELCR200 Video Interphone Units 6 75% 23-May-15 A 07-Jul-15 -277
CF29ELCR210 TV Sockets 9 75% 25-May-15 A 08-Jul-15 -277
Mechanical 18 28-May-15 A 28-Jul-15 -281
CF29EMEC100 Mechanical Floor Testing/Checks 18 50% 28-May-15 A 28-Jul-15 -281
Electrical 18 28-May-15 A 24-Jul-15 -277
CF29EELE100 Electrical Floor Testing/Checks 18 50% 28-May-15 A 24-Jul-15 -277
Architectural 18 28-May-15 A 15-Jul-15 -239
CF29EARC100 Architectural Floor Inspection/Checks 18 50% 28-May-15 A 15-Jul-15 -239
30th Floor 62 22-Apr-15 A 30-Jul-15 -247
Paint 16 15-May-15 A 04-Jul-15 -283
CF30EPNT120 Acrylic Paint Final Coat 16 75% 15-May-15 A 04-Jul-15 -283
Plumbing 18 22-Apr-15 A 11-Jul-15 -283
CF30EPLM140 Sanitary Fixtures 18 75% 22-Apr-15 A 11-Jul-15 -283
Low Current 9 10-Jun-15 A 10-Jul-15 -281
CF30ELCR180 Fire Alarm Detectors 9 50% 10-Jun-15 A 10-Jul-15 -281
CF30ELCR190 Telephone/Data Socket Outlets 9 50% 10-Jun-15 A 10-Jul-15 -281
CF30ELCR200 Video Interphone Units 6 50% 10-Jun-15 A 08-Jul-15 -280
CF30ELCR210 TV Sockets 9 50% 10-Jun-15 A 10-Jul-15 -281
Mechanical 18 22-Jun-15 A 30-Jul-15 -283
CF30EMEC100 Mechanical Floor Testing/Checks 18 40% 22-Jun-15 A 30-Jul-15 -283
Electrical 18 22-Jun-15 A 29-Jul-15 -281
CF30EELE100 Electrical Floor Testing/Checks 18 40% 22-Jun-15 A 29-Jul-15 -281
Architectural 18 22-Jun-15 A 17-Jul-15 -241
CF30EARC100 Architectural Floor Inspection/Checks 18 40% 22-Jun-15 A 17-Jul-15 -241
31st Floor 60 25-Apr-15 A 31-Jul-15 -248
Paint 16 15-May-15 A 04-Jul-15 -284
CF31EPNT120 Acrylic Paint Final Coat 16 75% 15-May-15 A 04-Jul-15 -284
Plumbing 18 25-Apr-15 A 11-Jul-15 -283
CF31EPLM140 Sanitary Fixtures 18 75% 25-Apr-15 A 11-Jul-15 -283
Low Current 9 10-Jun-15 A 13-Jul-15 -284
CF31ELCR180 Fire Alarm Detectors 9 25% 10-Jun-15 A 13-Jul-15 -284
CF31ELCR190 Telephone/Data Socket Outlets 9 25% 10-Jun-15 A 13-Jul-15 -284
CF31ELCR200 Video Interphone Units 6 25% 10-Jun-15 A 10-Jul-15 -281
CF31ELCR210 TV Sockets 9 25% 10-Jun-15 A 13-Jul-15 -284
Mechanical 18 22-Jun-15 A 30-Jul-15 -283
CF31EMEC100 Mechanical Floor Testing/Checks 18 40% 22-Jun-15 A 30-Jul-15 -283
Electrical 18 22-Jun-15 A 31-Jul-15 -284
CF31EELE100 Electrical Floor Testing/Checks 18 40% 22-Jun-15 A 31-Jul-15 -284
Architectural 18 22-Jun-15 A 17-Jul-15 -241
CF31EARC100 Architectural Floor Inspection/Checks 18 40% 22-Jun-15 A 17-Jul-15 -241
Floor Roof 18 11-May-15 A 06-Jul-15 -165
Mechanical 18 11-May-15 A 06-Jul-15 -267
CFRFEMEC100 Mechanical Floor Testing/Checks 18 75% 11-May-15 A 06-Jul-15 -267
Electrical 18 11-May-15 A 06-Jul-15 -267
CFRFEELE100 Electrical Floor Testing/Checks 18 75% 11-May-15 A 06-Jul-15 -267
Architectural 18 11-May-15 A 06-Jul-15 -165
CFRFEARC100 Architectural Floor Inspection/Checks 18 75% 11-May-15 A 06-Jul-15 -165
Floor Upper Roof & Top
To 80 10-Apr-15 A 16-Jul-15 -174
Metals 80 10-Apr-15 A 06-Jul-15 -171
Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 6 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
CFUREMET100 Stainless Steel Ladder to Water Tank 5 0% 01-Jul-15 06-Jul-15 -171
CFUREMET110 Galvanized Steel Structure 18 75% 10-Apr-15 A 06-Jul-15 -174
Mechanical 18 01-Jun-15 A 10-Jul-15 -169
CFUREMEC100 Mechanical Floor Testing/Checks 18 50% 01-Jun-15 A 10-Jul-15 -169
Electrical 18 04-Jun-15 A 16-Jul-15 -174
CFUREELE100 Electrical Floor Testing/Checks 18 50% 04-Jun-15 A 16-Jul-15 -174
Architectural 18 09-Jun-15 A 16-Jul-15 -174
CFUREARC100 Architectural Floor Inspection/Checks 18 50% 09-Jun-15 A 16-Jul-15 -174
Circulation, Shafts & V
Vertical Works 288 15-Aug-14 A 31-Jul-15 -176
Concrete 60 01-Apr-15 A 10-Jul-15 -223
CCIRECON100 Concrete Steps for Stairs/Smooth Finish to Stair Landings 60 85% 01-Apr-15 A 10-Jul-15 -223
Metals 13 11-Jul-15 31-Jul-15 -176
CCIREMET150 Stainless Steel Sheets to Elevator Lobbies 12 0% 13-Jul-15 31-Jul-15 -176
CCIREMET160 Stainless Steel Ladders to Elevator Pits 2 0% 11-Jul-15 13-Jul-15 -165
Paint 60 02-May-15 A 17-Jul-15 -241
CCIREPNT150 Acrylic Paint Final Coat - Stairs 60 75% 02-May-15 A 17-Jul-15 -241
Conveying System 127 15-Aug-14 A 10-Jul-15 -175
CCIRECOV100 Elevators 4, 5 & 6 Triplex - Block B 12797.64%15-Aug-14 A 10-Jul-15 -175
CCIRECOV110 Elevators 1 & 2 Duplex - Block A 12797.64%15-Aug-14 A 10-Jul-15 -175
CCIRECOV120 Elevators 3 Simplex - Block A 12797.64%15-Aug-14 A 10-Jul-15 -175
CCIRECOV130 Elevators 7 Simplex - Block B 12797.64%15-Aug-14 A 10-Jul-15 -175
Lighting & Power 12 02-Mar-15 A 03-Jul-15 -175
CCIREPWR190 MDB (Elevator Rooms) 12 75% 02-Mar-15 A 03-Jul-15 -175
Facade 102 20-Feb-15 A 08-Jul-15 -142
Plaster 30 20-Feb-15 A 03-Jul-15 -139
CFACEPLA130 Dismantle Scaffolding 30 90% 20-Feb-15 A 03-Jul-15 -139
Architectural 25 25-May-15 A 08-Jul-15 -178
CFACEARC100 Architectural Facade Inspection/Checks 25 75% 25-May-15 A 08-Jul-15 -178
North Tower 306 18-Jul-14 A 03-Aug-15 -160
2nd Basement Floor 20 13-May-15 A 16-Jul-15 -240
Mechanical 18 13-May-15 A 16-Jul-15 -240
CB02NMEC100 Mechanical Floor Testing/Checks 18 25% 13-May-15 A 16-Jul-15 -240
Electrical 18 15-May-15 A 16-Jul-15 -240
CB02NELE100 Electrical Floor Testing/Checks 18 25% 15-May-15 A 16-Jul-15 -240
Architectural 18 13-May-15 A 16-Jul-15 -240
CB02NARC100 Architectural Floor Inspection/Checks 18 25% 13-May-15 A 16-Jul-15 -240
1st Basement Floor 48 13-May-15 A 17-Jul-15 -241
Low Current 6 01-Jul-15 07-Jul-15 -241
CB01NLCR190 PABX 6 0% 01-Jul-15 07-Jul-15 -241
Mechanical 18 13-May-15 A 10-Jul-15 -235
CB01NMEC100 Mechanical Floor Testing/Checks 18 50% 13-May-15 A 10-Jul-15 -235
Electrical 18 20-May-15 A 17-Jul-15 -241
CB01NELE100 Electrical Floor Testing/Checks 18 50% 20-May-15 A 17-Jul-15 -241
Architectural 18 13-May-15 A 10-Jul-15 -235
CB01NARC100 Architectural Floor Inspection/Checks 18 50% 13-May-15 A 10-Jul-15 -235
Ground Floor 67 16-May-15 A 03-Aug-15 -208
Metals 12 20-May-15 A 07-Jul-15 -194
CFGNNMET100 Steel Canopy 12 50% 20-May-15 A 07-Jul-15 -194
Aluminum Works 6 18-May-15 A 14-Jul-15 -208
CFGNNALM110 Aluminum Doors & Windows 6 50% 18-May-15 A 14-Jul-15 -208
Tiling Works 16 16-May-15 A 15-Jul-15 -199
CFGNNTIL100 Ceramic Tiles for Common Area 6 20% 16-May-15 A 06-Jul-15 -208
CFGNNTIL110 Ceramic Tiles for Bathroom 16 20% 16-May-15 A 15-Jul-15 -199
CFGNNTIL120 Marble Tiles for Common Area 16 20% 16-May-15 A 15-Jul-15 -199
Gypsum Works 18 16-May-15 A 10-Jul-15 -193
CFGNNGYP100 Gypsum Board False Ceiling 18 50% 16-May-15 A 10-Jul-15 -193
Paint 12 14-Jul-15 03-Aug-15 -208
CFGNNPNT120 Acrylic Paint Final Coat 12 0% 14-Jul-15 03-Aug-15 -208
Ground Floor Mezzanine
Mezzan 24 01-Jun-15 A 10-Jul-15 -235
Mechanical 18 01-Jun-15 A 10-Jul-15 -235
CFGMNMEC100 Mechanical Floor Testing/Checks 18 50% 01-Jun-15 A 10-Jul-15 -235
Electrical 18 04-Jun-15 A 10-Jul-15 -235
CFGMNELE100 Electrical Floor Testing/Checks 18 50% 04-Jun-15 A 10-Jul-15 -235
Architectural 18 08-Jun-15 A 10-Jul-15 -235
CFGMNARC100 Architectural Floor Inspection/Checks 18 50% 08-Jun-15 A 10-Jul-15 -235
11th Floor 16 08-Jan-15 A 14-Jul-15 -254
Paint 16 08-Jan-15 A 14-Jul-15 -254
CF11NPNT120 Acrylic Paint Final Coat 16 25% 08-Jan-15 A 14-Jul-15 -254
12th Floor 62 27-Oct-14 A 17-Jul-15 -237
Paint 16 12-Dec-14 A 04-Jul-15 -237
CF12NPNT120 Acrylic Paint Final Coat 16 75% 12-Dec-14 A 04-Jul-15 -237
Plumbing 18 25-Nov-14 A 11-Jul-15 -237
CF12NPLM140 Sanitary Fixtures 18 75% 25-Nov-14 A 11-Jul-15 -237
Lighting & Power 41 27-Oct-14 A 10-Jul-15 -235
CF12NPWR140 Wiring Devices & Outlet Boxes 18 75% 25-Nov-14 A 10-Jul-15 -235
CF12NPWR150 Lighting Fixtures 18 75% 27-Oct-14 A 10-Jul-15 -235
Low Current 10 17-Dec-14 A 08-Jul-15 -233
CF12NLCR180 Fire Alarm Detectors 9 75% 17-Dec-14 A 08-Jul-15 -233
CF12NLCR190 Telephone/Data Socket Outlets 9 75% 17-Dec-14 A 08-Jul-15 -233
CF12NLCR200 Video Interphone Units 6 75% 17-Dec-14 A 07-Jul-15 -232
CF12NLCR210 TV Sockets 9 75% 17-Dec-14 A 08-Jul-15 -233
Mechanical 18 18-Dec-14 A 17-Jul-15 -237
CF12NMEC100 Mechanical Floor Testing/Checks 18 75% 18-Dec-14 A 17-Jul-15 -237
Electrical 18 18-Dec-14 A 15-Jul-15 -235
CF12NELE100 Electrical Floor Testing/Checks 18 75% 18-Dec-14 A 15-Jul-15 -235
Architectural 18 19-Dec-14 A 10-Jul-15 -235
CF12NARC100 Architectural Floor Inspection/Checks 18 75% 19-Dec-14 A 10-Jul-15 -235
13th Floor 155 21-Aug-14 A 17-Jul-15 -237
Architectural Wood Wo
Work 9 25-Oct-14 A 08-Jul-15 -237
CF13NAW W100 Wood Closets 9 75% 25-Oct-14 A 08-Jul-15 -237
Aluminum Works 3 15-Feb-15 A 06-Jul-15 -233
CF13NALM100 Mirrors 3 75% 15-Feb-15 A 06-Jul-15 -233
Wood Doors/Windows 9 27-Oct-14 A 08-Jul-15 -237
CF13NWDD120 MDF Wood Doors 9 75% 28-Oct-14 A 08-Jul-15 -237
CF13NWDD150 Walnut Wood Doors 6 75% 27-Oct-14 A 07-Jul-15 -236
Paint 16 13-Dec-14 A 04-Jul-15 -237
CF13NPNT120 Acrylic Paint Final Coat 16 75% 13-Dec-14 A 04-Jul-15 -237

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 7 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
Plumbing 18 25-Oct-14 A 11-Jul-15 -237
CF13NPLM140 Sanitary Fixtures 18 75% 25-Oct-14 A 11-Jul-15 -237
Lighting & Power 94 21-Aug-14 A 10-Jul-15 -235
CF13NPWR140 Wiring Devices & Outlet Boxes 18 75% 25-Nov-14 A 10-Jul-15 -235
CF13NPWR150 Lighting Fixtures 18 75% 21-Aug-14 A 10-Jul-15 -235
Low Current 10 16-Dec-14 A 08-Jul-15 -233
CF13NLCR180 Fire Alarm Detectors 9 75% 17-Dec-14 A 08-Jul-15 -233
CF13NLCR190 Telephone/Data Socket Outlets 9 75% 16-Dec-14 A 08-Jul-15 -233
CF13NLCR200 Video Interphone Units 6 75% 17-Dec-14 A 07-Jul-15 -232
CF13NLCR210 TV Sockets 9 75% 16-Dec-14 A 08-Jul-15 -233
Mechanical 18 19-Dec-14 A 17-Jul-15 -237
CF13NMEC100 Mechanical Floor Testing/Checks 18 75% 19-Dec-14 A 17-Jul-15 -237
Electrical 18 20-Dec-14 A 15-Jul-15 -235
CF13NELE100 Electrical Floor Testing/Checks 18 75% 20-Dec-14 A 15-Jul-15 -235
Architectural 18 20-Dec-14 A 13-Jul-15 -237
CF13NARC100 Architectural Floor Inspection/Checks 18 75% 20-Dec-14 A 13-Jul-15 -237
15th Floor 147 18-Jul-14 A 17-Jul-15 -240
Wood Doors/Windows 6 11-Aug-14 A 07-Jul-15 -236
CF15NWDD150 Walnut Wood Doors 6 75% 11-Aug-14 A 07-Jul-15 -236
Paint 16 13-Dec-14 A 04-Jul-15 -240
CF15NPNT120 Acrylic Paint Final Coat 16 75% 13-Dec-14 A 04-Jul-15 -240
Plumbing 18 18-Jul-14 A 11-Jul-15 -240
CF15NPLM140 Sanitary Fixtures 18 75% 18-Jul-14 A 11-Jul-15 -240
Lighting & Power 117 13-Aug-14 A 10-Jul-15 -238
CF15NPWR140 Wiring Devices & Outlet Boxes 18 75% 15-Dec-14 A 10-Jul-15 -238
CF15NPWR150 Lighting Fixtures 18 75% 13-Aug-14 A 10-Jul-15 -238
Low Current 10 24-Dec-14 A 08-Jul-15 -236
CF15NLCR180 Fire Alarm Detectors 9 75% 24-Dec-14 A 08-Jul-15 -236
CF15NLCR190 Telephone/Data Socket Outlets 9 75% 24-Dec-14 A 08-Jul-15 -236
CF15NLCR200 Video Interphone Units 6 75% 24-Dec-14 A 07-Jul-15 -235
CF15NLCR210 TV Sockets 9 75% 24-Dec-14 A 08-Jul-15 -236
Mechanical 18 29-Dec-14 A 17-Jul-15 -240
CF15NMEC100 Mechanical Floor Testing/Checks 18 75% 29-Dec-14 A 17-Jul-15 -240
Electrical 18 29-Dec-14 A 15-Jul-15 -238
CF15NELE100 Electrical Floor Testing/Checks 18 75% 29-Dec-14 A 15-Jul-15 -238
Architectural 18 30-Dec-14 A 11-Jul-15 -236
CF15NARC100 Architectural Floor Inspection/Checks 18 75% 30-Dec-14 A 11-Jul-15 -236
17th Floor 229 13-Sep-14 A 17-Jul-15 -240
Architectural Wood Wo
Work 9 28-Oct-14 A 08-Jul-15 -237
CF17NAW W100 Wood Closets 9 75% 28-Oct-14 A 08-Jul-15 -237
Wood Doors/Windows 6 16-Jan-15 A 07-Jul-15 -236
CF17NWDD150 Walnut Wood Doors 6 80% 16-Jan-15 A 07-Jul-15 -236
Paint 16 25-May-15 A 04-Jul-15 -240
CF17NPNT120 Acrylic Paint Final Coat 16 75% 25-May-15 A 04-Jul-15 -240
Plumbing 18 25-Oct-14 A 11-Jul-15 -240
CF17NPLM140 Sanitary Fixtures 18 75% 25-Oct-14 A 11-Jul-15 -240
Lighting & Power 120 13-Sep-14 A 10-Jul-15 -238
CF17NPWR140 Wiring Devices & Outlet Boxes 18 75% 20-Jan-15 A 10-Jul-15 -238
CF17NPWR150 Lighting Fixtures 18 75% 13-Sep-14 A 10-Jul-15 -238
Low Current 10 28-May-15 A 08-Jul-15 -236
CF17NLCR180 Fire Alarm Detectors 9 75% 29-May-15 A 08-Jul-15 -236
CF17NLCR190 Telephone/Data Socket Outlets 9 75% 29-May-15 A 08-Jul-15 -236
CF17NLCR200 Video Interphone Units 6 75% 29-May-15 A 07-Jul-15 -235
CF17NLCR210 TV Sockets 9 75% 28-May-15 A 08-Jul-15 -236
Mechanical 18 29-May-15 A 17-Jul-15 -240
CF17NMEC100 Mechanical Floor Testing/Checks 18 75% 29-May-15 A 17-Jul-15 -240
Electrical 18 29-May-15 A 15-Jul-15 -238
CF17NELE100 Electrical Floor Testing/Checks 18 75% 29-May-15 A 15-Jul-15 -238
Architectural 18 30-May-15 A 13-Jul-15 -237
CF17NARC100 Architectural Floor Inspection/Checks 18 75% 30-May-15 A 13-Jul-15 -237
22nd Floor 98 23-Jan-15 A 27-Jul-15 -276
Paint 16 05-May-15 A 14-Jul-15 -282
CF22NPNT120 Acrylic Paint Final Coat 16 25% 05-May-15 A 14-Jul-15 -282
Plumbing 18 23-Jan-15 A 27-Jul-15 -276
CF22NPLM140 Sanitary Fixtures 18 25% 23-Jan-15 A 27-Jul-15 -276
23rd Floor 79 21-Feb-15 A 25-Jul-15 -245
Architectural Wood Wo
Work 9 21-Mar-15 A 15-Jul-15 -248
CF23NAW W100 Wood Closets 9 50% 21-Mar-15 A 15-Jul-15 -248
Aluminum Works 3 12-May-15 A 11-Jul-15 -238
CF23NALM100 Mirrors 3 50% 12-May-15 A 11-Jul-15 -238
Wood Doors/Windows 9 13-May-15 A 15-Jul-15 -248
CF23NWDD120 MDF Wood Doors 9 50% 13-May-15 A 15-Jul-15 -248
CF23NWDD150 Walnut Wood Doors 6 50% 16-May-15 A 13-Jul-15 -246
Kitchen Unit 3 21-Feb-15 A 11-Jul-15 -245
CF23NKUN100 Kitchen Units 3 50% 21-Feb-15 A 11-Jul-15 -245
Paint 16 08-May-15 A 09-Jul-15 -273
CF23NPNT120 Acrylic Paint Final Coat 16 50% 08-May-15 A 09-Jul-15 -273
Plumbing 18 07-May-15 A 16-Jul-15 -270
CF23NPLM140 Sanitary Fixtures 18 50% 07-May-15 A 16-Jul-15 -270
Lighting & Power 18 07-May-15 A 25-Jul-15 -273
CF23NPWR140 Wiring Devices & Outlet Boxes 18 50% 07-May-15 A 25-Jul-15 -273
CF23NPWR150 Lighting Fixtures 18 50% 07-May-15 A 25-Jul-15 -273
Low Current 9 09-May-15 A 15-Jul-15 -269
CF23NLCR180 Fire Alarm Detectors 9 50% 09-May-15 A 15-Jul-15 -269
CF23NLCR190 Telephone/Data Socket Outlets 9 50% 09-May-15 A 15-Jul-15 -269
CF23NLCR200 Video Interphone Units 6 50% 09-May-15 A 13-Jul-15 -267
CF23NLCR210 TV Sockets 9 50% 09-May-15 A 15-Jul-15 -269
24th Floor 155 16-Jan-15 A 24-Jul-15 -290
Gypsum Works 30 16-Jan-15 A 03-Jul-15 -290
CF24NGYP100 Gypsum Board False Ceiling 30 90% 16-Jan-15 A 03-Jul-15 -290
Paint 16 01-Jul-15 24-Jul-15 -290
CF24NPNT120 Acrylic Paint Final Coat 16 0% 01-Jul-15 24-Jul-15 -290
25th Floor 16 20-Jun-15 A 14-Jul-15 -279
Paint 16 20-Jun-15 A 14-Jul-15 -279
CF25NPNT120 Acrylic Paint Final Coat 16 25% 20-Jun-15 A 14-Jul-15 -279
26th Floor 16 01-Jul-15 24-Jul-15 -290
Paint 16 01-Jul-15 24-Jul-15 -290
Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 8 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
CF26NPNT120 Acrylic Paint Final Coat 16 0% 01-Jul-15 24-Jul-15 -290
Floor Roof 37 11-May-15 A 06-Jul-15 -165
Mechanical 18 11-May-15 A 06-Jul-15 -252
CFRFNMEC100 Mechanical Floor Testing/Checks 18 75% 11-May-15 A 06-Jul-15 -252
Electrical 18 21-May-15 A 06-Jul-15 -252
CFRFNELE100 Electrical Floor Testing/Checks 18 75% 21-May-15 A 06-Jul-15 -252
Architectural 18 02-Jun-15 A 06-Jul-15 -165
CFRFNARC100 Architectural Floor Inspection/Checks 18 75% 02-Jun-15 A 06-Jul-15 -165
Floor Upper Roof & Top
To 31 01-Jun-15 A 13-Jul-15 -171
Metals 5 01-Jul-15 06-Jul-15 -171
CFURNMET100 Stainless Steel Ladder to Water Tank 5 0% 01-Jul-15 06-Jul-15 -171
Mechanical 18 01-Jun-15 A 10-Jul-15 -169
CFURNMEC100 Mechanical Floor Testing/Checks 18 50% 01-Jun-15 A 10-Jul-15 -169
Electrical 18 05-Jun-15 A 10-Jul-15 -169
CFURNELE100 Electrical Floor Testing/Checks 18 50% 05-Jun-15 A 10-Jul-15 -169
Architectural 18 10-Jun-15 A 13-Jul-15 -171
CFURNARC100 Architectural Floor Inspection/Checks 18 50% 10-Jun-15 A 13-Jul-15 -171
Circulation, Shafts & V
Vertical Works 288 12-Aug-14 A 31-Jul-15 -176
Concrete 60 01-Apr-15 A 10-Jul-15 -232
CCIRNCON100 Concrete Steps for Stairs/Smooth Finish to Stair Landings 60 85% 01-Apr-15 A 10-Jul-15 -232
Metals 13 11-Jul-15 31-Jul-15 -176
CCIRNMET150 Stainless Steel Sheets to Elevator Lobbies 12 0% 13-Jul-15 31-Jul-15 -176
CCIRNMET160 Stainless Steel Ladders to Elevator Pits 2 0% 11-Jul-15 13-Jul-15 -165
Paint 60 02-May-15 A 13-Jul-15 -237
CCIRNPNT150 Acrylic Paint Final Coat - Stairs 60 85% 02-May-15 A 13-Jul-15 -237
Conveying System 170 12-Aug-14 A 10-Jul-15 -175
CCIRNCOV100 Elevators 8, 9 & 10 Triplex - Block E 12796.06%01-Oct-14 A 10-Jul-15 -175
CCIRNCOV110 Elevators 12, 13, 14 Triplex - Block F 12796.06%12-Aug-14 A 10-Jul-15 -175
CCIRNCOV120 Elevators 15 Simplex - Block F 12796.06%12-Aug-14 A 10-Jul-15 -175
CCIRNCOV130 Elevators 11 Simplex - Block E 12796.06%01-Oct-14 A 10-Jul-15 -175
Lighting & Power 12 10-Apr-15 A 03-Jul-15 -175
CCIRNPWR190 MDB (Elevator Rooms) 12 75% 10-Apr-15 A 03-Jul-15 -175
Mechanical 60 02-Jan-15 A 07-Jul-15 -232
CCIRNMEC100 Mechanical Risers Testing/Checks F01 - F09 60 90% 02-Jan-15 A 07-Jul-15 -232
Electrical 60 02-Jan-15 A 07-Jul-15 -232
CCIRNELE100 Electrical Riser Testing/Checks F01 - F09 60 90% 02-Jan-15 A 07-Jul-15 -232
Facade 102 25-Feb-15 A 08-Jul-15 -142
Plaster 30 25-Feb-15 A 03-Jul-15 -139
CFACNPLA130 Dismantle Scaffolding 30 90% 25-Feb-15 A 03-Jul-15 -139
Architectural 25 23-May-15 A 08-Jul-15 -178
CFACNARC100 Architectural Facade Inspection/Checks 25 75% 23-May-15 A 08-Jul-15 -178
South Tower 289 12-Aug-14 A 01-Aug-15 -159
2nd Basement Floor 22 13-May-15 A 16-Jul-15 -240
Mechanical 18 13-May-15 A 16-Jul-15 -240
CB02SMEC100 Mechanical Floor Testing/Checks 18 25% 13-May-15 A 16-Jul-15 -240
Electrical 18 18-May-15 A 16-Jul-15 -240
CB02SELE100 Electrical Floor Testing/Checks 18 25% 18-May-15 A 16-Jul-15 -240
Architectural 18 13-May-15 A 16-Jul-15 -240
CB02SARC100 Architectural Floor Inspection/Checks 18 25% 13-May-15 A 16-Jul-15 -240
1st Basement Floor 48 13-May-15 A 17-Jul-15 -241
Low Current 6 01-Jul-15 07-Jul-15 -241
CB01SLCR190 PABX 6 0% 01-Jul-15 07-Jul-15 -241
Mechanical 18 13-May-15 A 10-Jul-15 -235
CB01SMEC100 Mechanical Floor Testing/Checks 18 50% 13-May-15 A 10-Jul-15 -235
Electrical 18 15-May-15 A 17-Jul-15 -241
CB01SELE100 Electrical Floor Testing/Checks 18 50% 15-May-15 A 17-Jul-15 -241
Architectural 18 13-May-15 A 10-Jul-15 -235
CB01SARC100 Architectural Floor Inspection/Checks 18 50% 13-May-15 A 10-Jul-15 -235
Ground Floor 19 14-May-15 A 14-Jul-15 -195
Metals 12 14-May-15 A 10-Jul-15 -197
CFGNSMET100 Steel Canopy 12 25% 14-May-15 A 10-Jul-15 -197
Tiling Works 17 14-May-15 A 14-Jul-15 -214
CFGNSTIL100 Ceramic Tiles for Common Area 6 30% 14-May-15 A 06-Jul-15 -207
CFGNSTIL110 Ceramic Tiles for Bathroom 16 30% 14-May-15 A 14-Jul-15 -214
CFGNSTIL120 Marble Tiles for Common Area 16 30% 15-May-15 A 14-Jul-15 -214
Gypsum Works 18 14-May-15 A 10-Jul-15 -193
CFGNSGYP100 Gypsum Board False Ceiling 18 50% 14-May-15 A 10-Jul-15 -193
Ground Floor Mezzanine
Mezzan 24 01-Jun-15 A 10-Jul-15 -235
Mechanical 18 01-Jun-15 A 10-Jul-15 -235
CFGMSMEC100 Mechanical Floor Testing/Checks 18 50% 01-Jun-15 A 10-Jul-15 -235
Electrical 18 14-Jun-15 A 10-Jul-15 -235
CFGMSELE100 Electrical Floor Testing/Checks 18 50% 14-Jun-15 A 10-Jul-15 -235
Architectural 18 08-Jun-15 A 10-Jul-15 -235
CFGMSARC100 Architectural Floor Inspection/Checks 18 50% 08-Jun-15 A 10-Jul-15 -235
6th Floor 16 01-Dec-14 A 14-Jul-15 -275
Paint 16 01-Dec-14 A 14-Jul-15 -275
CF06SPNT120 Acrylic Paint Final Coat 16 25% 01-Dec-14 A 14-Jul-15 -275
22nd Floor 16 16-Apr-15 A 14-Jul-15 -267
Paint 16 16-Apr-15 A 14-Jul-15 -267
CF22SPNT120 Acrylic Paint Final Coat 16 25% 16-Apr-15 A 14-Jul-15 -267
23rd Floor 55 11-Mar-15 A 29-Jul-15 -246
Wood Doors/Windows 6 11-Mar-15 A 13-Jul-15 -246
CF23SWDD150 Walnut Wood Doors 6 50% 11-Mar-15 A 13-Jul-15 -246
Paint 16 15-Apr-15 A 09-Jul-15 -263
CF23SPNT120 Acrylic Paint Final Coat 16 50% 15-Apr-15 A 09-Jul-15 -263
Low Current 10 23-Apr-15 A 15-Jul-15 -261
CF23SLCR180 Fire Alarm Detectors 9 50% 23-Apr-15 A 15-Jul-15 -261
CF23SLCR190 Telephone/Data Socket Outlets 9 50% 23-Apr-15 A 15-Jul-15 -261
CF23SLCR200 Video Interphone Units 6 50% 23-Apr-15 A 13-Jul-15 -260
CF23SLCR210 TV Sockets 9 50% 24-Apr-15 A 15-Jul-15 -261
Architectural 18 27-Apr-15 A 29-Jul-15 -246
CF23SARC100 Architectural Floor Inspection/Checks 18 50% 27-Apr-15 A 29-Jul-15 -246
24th Floor 16 01-Jul-15 24-Jul-15 -283
Paint 16 01-Jul-15 24-Jul-15 -283
CF24SPNT120 Acrylic Paint Final Coat 16 0% 01-Jul-15 24-Jul-15 -283
25th Floor 16 18-Jun-15 A 14-Jul-15 -272
Paint 16 18-Jun-15 A 14-Jul-15 -272

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 9 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
CF25SPNT120 Acrylic Paint Final Coat 16 25% 18-Jun-15 A 14-Jul-15 -272
26th Floor 16 20-Jun-15 A 14-Jul-15 -279
Paint 16 20-Jun-15 A 14-Jul-15 -279
CF26SPNT120 Acrylic Paint Final Coat 16 25% 20-Jun-15 A 14-Jul-15 -279
Floor Roof 27 15-May-15 A 06-Jul-15 -165
Mechanical 18 15-May-15 A 06-Jul-15 -244
CFRFSMEC100 Mechanical Floor Testing/Checks 18 75% 15-May-15 A 06-Jul-15 -244
Electrical 18 15-May-15 A 06-Jul-15 -244
CFRFSELE100 Electrical Floor Testing/Checks 18 75% 15-May-15 A 06-Jul-15 -244
Architectural 18 15-May-15 A 06-Jul-15 -165
CFRFSARC100 Architectural Floor Inspection/Checks 18 75% 15-May-15 A 06-Jul-15 -165
Floor Upper Roof & Top
To 31 01-Jun-15 A 10-Jul-15 -169
Metals 5 01-Jul-15 06-Jul-15 -171
CFURSMET100 Stainless Steel Ladder to Water Tank 5 0% 01-Jul-15 06-Jul-15 -171
Mechanical 18 01-Jun-15 A 10-Jul-15 -169
CFURSMEC100 Mechanical Floor Testing/Checks 18 50% 01-Jun-15 A 10-Jul-15 -169
Electrical 18 05-Jun-15 A 10-Jul-15 -169
CFURSELE100 Electrical Floor Testing/Checks 18 50% 05-Jun-15 A 10-Jul-15 -169
Architectural 18 08-Jun-15 A 10-Jul-15 -169
CFURSARC100 Architectural Floor Inspection/Checks 18 50% 08-Jun-15 A 10-Jul-15 -169
Circulation, Shafts & V
Vertical Works 289 12-Aug-14 A 01-Aug-15 -177
Concrete 60 08-Apr-15 A 10-Jul-15 -232
CCIRSCON100 Concrete Steps for Stairs/Smooth Finish to Stair Landings 60 85% 08-Apr-15 A 10-Jul-15 -232
Metals 12 13-Jul-15 01-Aug-15 -177
CCIRSMET150 Stainless Steel Sheets to Elevator Lobbies 12 0% 13-Jul-15 01-Aug-15 -177
CCIRSMET160 Stainless Steel Ladders to Elevator Pits 2 0% 13-Jul-15 15-Jul-15 -167
Paint 60 02-May-15 A 17-Jul-15 -241
CCIRSPNT150 Acrylic Paint Final Coat - Stairs 60 75% 02-May-15 A 17-Jul-15 -241
Conveying System 170 12-Aug-14 A 13-Jul-15 -177
CCIRSCOV100 Elevators 8, 9 & 10 Triplex - Block E 12796.06%01-Oct-14 A 13-Jul-15 -177
CCIRSCOV110 Elevators 12, 13, 14 Triplex - Block F 12796.06%12-Aug-14 A 13-Jul-15 -177
CCIRSCOV120 Elevators 15 Simplex - Block F 12796.06%12-Aug-14 A 13-Jul-15 -177
CCIRSCOV130 Elevators 11 Simplex - Block E 12796.06%01-Oct-14 A 13-Jul-15 -177
Lighting & Power 12 09-Apr-15 A 06-Jul-15 -177
CCIRSPWR190 MDB (Elevator Rooms) 12 60% 09-Apr-15 A 06-Jul-15 -177
Mechanical 60 08-Jan-15 A 09-Jul-15 -241
CCIRSMEC110 Mechanical Risers Testing/Checks F10 - F18 60 90% 08-Jan-15 A 09-Jul-15 -241
Electrical 60 08-Jan-15 A 09-Jul-15 -241
CCIRSELE110 Electrical Riser Testing/Checks F10 - F18 60 90% 08-Jan-15 A 09-Jul-15 -241
Facade 103 18-Feb-15 A 08-Jul-15 -142
Plaster 30 18-Feb-15 A 03-Jul-15 -139
CFACSPLA130 Dismantle Scaffolding 30 90% 18-Feb-15 A 03-Jul-15 -139
Architectural 25 23-May-15 A 08-Jul-15 -178
CFACSARC100 Architectural Facade Inspection/Checks 25 75% 23-May-15 A 08-Jul-15 -178
Retail 144 12-Feb-15 A 07-Aug-15 -176
1st Basement Floor 144 12-Feb-15 A 07-Aug-15 -176
Metals 20 12-Feb-15 A 06-Jul-15 -167
CB01RMET110 Steel Handrail 20 75% 12-Feb-15 A 06-Jul-15 -167
Paint 30 10-Apr-15 A 09-Jul-15 -189
CB01RPNT120 Acrylic Paint Final Coat 30 75% 10-Apr-15 A 09-Jul-15 -189
Low Current 43 13-Jun-15 A 07-Aug-15 -189
CB01RLCR140 Telephone/Data Socket Outlets/TDC 20 50% 13-Jun-15 A 27-Jul-15 -179
CB01RLCR160 CCTV Cameras/Digital Recorders 20 0% 09-Jul-15 07-Aug-15 -189
Mechanical 18 18-Jun-15 A 30-Jul-15 -169
CB01RMEC100 Mechanical Floor Testing/Checks 18 25% 18-Jun-15 A 30-Jul-15 -169
Ground Floor 139 14-Feb-15 A 04-Aug-15 -191
Metals 20 14-Feb-15 A 06-Jul-15 -186
CFGNRMET100 Galvanized Steel Stairs 20 75% 14-Feb-15 A 06-Jul-15 -186
Paint 20 15-Apr-15 A 06-Jul-15 -206
CFGNRPNT120 Acrylic Paint Final Coat 20 75% 15-Apr-15 A 06-Jul-15 -206
Low Current 41 12-Jun-15 A 04-Aug-15 -206
CFGNRLCR160 Telephone/Data Socket Outlets 20 50% 12-Jun-15 A 17-Jul-15 -196
CFGNRLCR180 CCTV Cameras 20 0% 07-Jul-15 04-Aug-15 -206
Architectural 20 18-Jun-15 A 29-Jul-15 -186
CFGNRARC100 Architectural Floor Inspection/Checks 20 25% 18-Jun-15 A 29-Jul-15 -186
Ground Floor Mezzanine
Mezzan 66 11-Apr-15 A 30-Jul-15 -187
Paint 15 11-Apr-15 A 09-Jul-15 -187
CFGMRPNT120 Acrylic Paint Final Coat 15 50% 11-Apr-15 A 09-Jul-15 -187
Electrical 18 19-Jun-15 A 30-Jul-15 -187
CFGMRELE100 Electrical Floor Testing/Checks 18 25% 19-Jun-15 A 30-Jul-15 -187
Architectural 18 20-Jun-15 A 30-Jul-15 -187
CFGMRARC100 Architectural Floor Inspection/Checks 18 25% 20-Jun-15 A 30-Jul-15 -187
Facade 58 07-May-15 A 17-Jul-15 -169
Aluminum Works 58 07-May-15 A 17-Jul-15 -169
CFACRALM100 Aluminum Composite Panels 58 75% 07-May-15 A 17-Jul-15 -169
Landscape 127 14-Apr-15 A 15-Sep-15 -209
External/Landscaping Works 127 14-Apr-15 A 15-Sep-15 -209
Site Works 60 14-Apr-15 A 30-Jul-15 -169
CEXTLSIT100 Concrete Curb Stone 60 66% 14-Apr-15 A 30-Jul-15 -232
CEXTLSIT120 Playing Court 60 65% 14-Apr-15 A 30-Jul-15 -169
Soft Landscaping 60 16-May-15 A 10-Aug-15 -184
CEXTLSLA110 Soft Landscaping Works 60 50% 16-May-15 A 10-Aug-15 -184
Tiling Works 61 01-Jul-15 15-Sep-15 -232
CEXTLTIL100 Stone Paving Tiles 55 0% 08-Jul-15 15-Sep-15 -232
CEXTLTIL110 Walkway Paving Tiles 55 0% 01-Jul-15 08-Sep-15 -232
CEXTLTIL120 Ceramic Tiles for Swimming Pools 30 0% 01-Jul-15 10-Aug-15 -207
CEXTLTIL130 Ceramic Tiles for Water Feature 30 0% 01-Jul-15 10-Aug-15 -207
Final Testing and Co
Commissioning 66 01-Jul-15 21-Sep-15 -202
Parking 66 01-Jul-15 21-Sep-15 -202
General 66 01-Jul-15 21-Sep-15 -202
Mechanical 60 01-Jul-15 14-Sep-15 -196
TGENPMEC100 Final Testing & Commissioning - Mechanical Systems 60 0% 01-Jul-15 14-Sep-15 -196
Electrical 60 01-Jul-15 14-Sep-15 -196
TGENPELE100 Final Testing & Commissioning - Electrical Systems 60 0% 01-Jul-15 14-Sep-15 -196
Architectural 60 08-Jul-15 21-Sep-15 -202
TGENPARC100 Final Architectural Inspection 60 0% 08-Jul-15 21-Sep-15 -202
Retail 30 04-Jul-15 13-Aug-15 -169
Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 10 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline
Activity ID Activity Name Original Act % Start Finish Total July
Comp. Float 15 22 29 06 13 20 27
Duration 181 182 183 184 185 186 187
General 30 04-Jul-15 13-Aug-15 -169
Mechanical 30 04-Jul-15 13-Aug-15 -169
TGENRMEC100 Final Testing & Commissioning - Mechanical Systems 30 0% 04-Jul-15 13-Aug-15 -169

Project Baseline Remaining Work Milestone Critical Milestone Actual Dates Page 11 of 11 A4748 C2 - 2 Week Look-Ahead
Actual Work Critical Remaining Work Milestone noncritical Milestone Baseline

You might also like