Professional Documents
Culture Documents
RonanLeroy Optxxx PDF
RonanLeroy Optxxx PDF
Material
Tremie mix concrete, 20 mm slump
Steel: 70 to 200 kg/m3
Properties
Moments: 1200 kN/m for 0,8 m wall; 4 000 kN.m for 1,5
m wall
Permeability: 10 E-7 m/s to 10 E-9 m/s
Plan View
AGS-ATS Perth Aug 2010
Le Havre : Design
PHASE 1
Preparation of working platform
Construction of Guide Walls
Installation of Well Points
PHASE 2
Construction of Diaphragm Walls
PHASE 3
Removal of the guide walls
Excavation in front of the wall during dewatering
PHASE 4
Cast capping beam and dock buffers
PHASE 5
Earthwork excavation behind wall during
dewatering
PHASE 6
Installation of sheet pile curtain
Lay lower layer of anchors
PHASE 6
Backfill to level upper anchor layer and
lay upper layer of anchors
Sea side
DWall 1,20 m
Sheet piles
Land side
PHASE 6
Backfill to formation level, construct all civil
works, install bumpers, stop dewatering,
dredging, crane rail foundations and rails.
Owner:
City Dvpt /American
International
Engineer:
Meinhardt
Main Contractor:
Dragages
Tower 1 No of floors: 70
Typical Floor GFA: 1,026 sqm
Height: 242m
Tower 2 No of floors: 63
Typical Floor GFA: 746 sqm
Height: 202m
Podium
No of floors: 7
Typical Floor Plate: 3,726 sqm
• up to 67 m deep, incl 20 m in
T Re
SPT>100
MR
3 rd
Temporary
D-W all • all toes grouted ;
The Sail
Project constraint: tight program, neighb. structures
Issue : design, execution
Ronan Le Roy
rleroy@menardbachy.com.au