Professional Documents
Culture Documents
Six Sigma Q&A PDF
Six Sigma Q&A PDF
---------------------------------------------------------------------------------------------------------------------
1. An X and R chart was prepared for an operation using twenty samples with five
pieces in each sample; X was found to be 33.6 and R was 6.20. During
production, a sample of five was taken and the pieces measured 36, 43, 37, 25,
and 38. At the time, this sample was taken:
A. Both the average and range were within control limits
B. Neither the average nor range were within control limits
C. Only the average was outside control limits
D. Only the range was outside control limits
Correct Answer: D
Justification: This question requires a calculation of the X and R control limits and a
comparison to the sample data and answers.
Equations:
Solution:
X = 35.8, R = 18. Thus, the X chart is in control but the R chart is not.
---------------------------------------------------------------------------------------------------------------------
2. Which of the following control charts are most sensitive to small but gradual drifts
in process?
I. X – R charts
II. CuSum charts
1 www.pmtutor.org Powered by POeT Solvers Limited.
III. EWMA charts
IV. Moving average charts
A. I and II only
B. I and III only
C. II and III only
D. III and IV only
Correct Answer: C
Justification: Both CUSUM and exponentially weighted moving average charts can
detect small sustained changes in a process.
If continued for some time, these small changes will be apparent on which of the
following control charts are most sensitive to small but gradual drifts in process?
If continued for some time, these small changes will be apparent on X – R charts and
moving averages as well. However, the word “most” in the question prevents their
selection.
---------------------------------------------------------------------------------------------------------------------
3. What does the parameter λ stand for when plotting a EWMA chart?
A. The variance
B. The depth of memory
C. The time that a sample is taken
D. The number of observations to be monitored
Correct Answer: B
---------------------------------------------------------------------------------------------------------------------
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
Correct Answer: A
Justification: This question requires knowledge of control chart limits and a review of
the answers.
UCLR = D4R
Answers B and C are filler. The D4 factor is a multiplier which establishes the distance
between the mean and the upper control limit of a range chart.
---------------------------------------------------------------------------------------------------------------------
Correct Answer: B
---------------------------------------------------------------------------------------------------------------------
7. An operator takes a routine sample using the pre-control method and notes that
the first piece is within specifications but not within target. What does the
operator do next?
A. Stops the process and adjusts it
B. Checks a second sample
C. Confirms that the next 5 consecutive pieces are within target
D. Continues to run
Correct Answer: B
---------------------------------------------------------------------------------------------------------------------
8. Certain Six Sigma improvement efforts have resulted in the need to replace the
existing measurement system and others have not. What could be reasons for
staying with an existing system?
I. It’s precise enough
II. No better equipment exists
III. The current measurement is based on count data
IV. The improvement has not been successful
A. I only
B. II and III only
C. I, II and IV only
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
Correct Answer: D
Justification: The p chart is the most sensitive attribute chart but the variable X bar – R
chart is the most sensitive control chart.
---------------------------------------------------------------------------------------------------------------------
Justification: The weakest selection is item III. Control chart paper was developed to
support a logical control chart sample size. Sample sizes should not be chosen to fit a
handy form. The other items have merit.
---------------------------------------------------------------------------------------------------------------------
11. You have just returned from a two-week vacation and are going over with your
QC manager, the control charts which have been maintained during your
absence. He calls your attention to the fact that one of the X bar-charts shows
the last 50 points to be very near the center line. In fact, they all seem to be
within about one sigma of the center line. What explanation would you offer him?
A. Somebody “goofed” in the original calculation of the control limits.
B. The process standard deviation has decreased during the time the last 50
samples were taken and nobody thought to recompute the control limits.
C. This is a terrible situation. I’ll get on it right away and see what the trouble is. I
hope we haven’t produced too much scrap.
D. This is fine, the closer the points are to the center line the better our control.
Correct Answer: B
---------------------------------------------------------------------------------------------------------------------
12. The most common subgrouping scheme for X – R control charts is to separate
the variation:
A. Within stream versus stream to stream
B. Within time versus time to time
C. Within piece versus piece to piece
D. Inherent process versus error of measurement
Correct Answer: B
---------------------------------------------------------------------------------------------------------------------
Correct Answer: D
Justification: The X-bar and R chart (Average – Range Chart) is the most sensitive to
changes in quality. Thus, answers A and B are false. The most sensitive attribute chart
is the p chart. Thus, answer C is false and D is true.
---------------------------------------------------------------------------------------------------------------------
14. Considering that all of the following terms have benefits, which would LEAST
likely affect product quality?
A. Muda
B. 5S
C. Lean Manufacturing
D. Total Productive Maintenance
Correct Answer: C
The lean manufacturing approach also helps quality (less handling, etc.) but it would
tend to affect items like delivery more.
---------------------------------------------------------------------------------------------------------------------
Correct Answer: A
Justification: The term Kaizen is associated with small incremental changes. Although
a “Kaizen blast” can speed things up a great deal. Kanban is a process flow control
mechanism, 5S deals with workplace organization, and Poka-yoke means to mistake
proof a process.
---------------------------------------------------------------------------------------------------------------------
16. Review the following 5S elements and identify the step that is being referenced.
Determine who has missing items
Create a name and location for everything
Use aisle and material placement markings
Use labels, tool boards and color codes
A. Sort
B. Straighten
C. Scrub
D. Systematize
Correct Answer: B
Justification: The only two logical elements (or steps) are straighten and systematize.
A close review of the statements indicates that the straighten step is being described.
---------------------------------------------------------------------------------------------------------------------
17. Given that resistors are produced in lots of 1000, and that the average number of
defective resistors per lot is 12.7, what are the upper and lower limits for the
control chart appropriate for this process?
A. LCL = 2.0 UCL = 23.4
B. LCL = 3.8 UCL = 20.2
Correct Answer: A
---------------------------------------------------------------------------------------------------------------------
18. If points on a c chart are outside of the control limits and we wish to set up a
control chart for future production:
A. More data are needed
B. Discard those points falling outside the control limits, for which you can
identify an assignable cause, and revise the limits
C. Check with production to determine the true process capability
D. Discard those points falling outside the control limits and revise the limits
Correct Answer: B
Justification: Answer A: normally twenty five data points are sufficient to establish c-
chart control limits. Answer C: production may not know the true process capability.
Answer D: we cannot discard points outside the control limits if the reason is unknown.
They may recur. Answer B is the correct option.
---------------------------------------------------------------------------------------------------------------------
Correct Answer: C
Justification: Answer A is incorrect because the control limits come from the process
data itself. Assuming that assignable causes do not occur, the control limits are not
“tight”. This level assures a very small type I error (calling the process out of control
when it is in control).
---------------------------------------------------------------------------------------------------------------------
20. What two distinct types of variation are noted in control charts?
A. Random and chance
B. Special and assignable
C. Chance and assignable
D. Normal and random
Correct Answer: C
Justification: The two varieties of variation are chance and assignable. Chance
variation is also referred to as normal or random (among others). Assignable variation is
also called special or non-normal.
---------------------------------------------------------------------------------------------------------------------
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
22. Identify the LEAST likely result of adopting standardized work procedures:
A. They tend to minimize variability
B. They are a basis for training
C. They assure marketplace success
D. They preserve know-how and expertise
Correct Answer: C
---------------------------------------------------------------------------------------------------------------------
23. When using a control chart, a point plotting within the limits on the chart is:
A. The equivalent of type I error
B. The equivalent of type II error
C. The equivalent of accepting the hypothesis that the process is in control
D. The equivalent of not rejecting the hypothesis that the process is in control
Correct Answer: D
Justification: If the points on a control chart fall within the limits, and do not form a non-
random pattern, the process is assumed to be in a state of statistical control. The null
hypothesis is never accepted, rather, there is not sufficient evidence to reject it. A plot
within limits is neither a type I nor type II error.
---------------------------------------------------------------------------------------------------------------------
24. In control chart theory, the distribution of the number of defects per unit follows
very closely the:
A. Normal distribution
Correct Answer: D
Justification: The normal distribution relates to variable (not attribute) data. The chi-
square distribution is used to make inferences regarding population variances. The
binomial distribution is the assumed distribution for defectives. The Poisson distribution
is the assumed distribution for defects.
---------------------------------------------------------------------------------------------------------------------
25. You are plotting a control chart and the last two of three points are greater than 2
sigma, four out of the last five points are beyond 1 sigma and eight successive
points are on one side of the center line; you should:
A. Stop the process immediately
B. Take more readings and continue to plot
C. Write a discrepancy notice to the supervisor
D. Investigate to determine what has changed
Correct Answer: D
Justification: Using any set of interpretation rules, there has been a significant change
in the process. If an X-bar chart or attribute chart is being plotted, there is evidence of a
shift, trend or drift in the process. If an R chart is being charted, the variability has
changed significantly.
---------------------------------------------------------------------------------------------------------------------
26. Overproduction, scrap, waiting, and excess motion are all forms of:
A. TPM
B. Muda
C. Kanban
D. CFM
Justification: The question states four of the major seven forms of Muda (waste).
Kanban, total productive maintenance, and continuous flow manufacturing have some
influence on waste areas but do not directly address them all.
---------------------------------------------------------------------------------------------------------------------
27. A number of charts have been devised to plot and control small production runs.
Which charting tool can display a number of variables on a single chart?
A. Short run charts
B. Individual/ moving range charts
C. Moving average/moving range charts
D. Pre-control charts
Correct Answer: A
---------------------------------------------------------------------------------------------------------------------
28. Compute the upper control limit for an S chart, based on a sample size of 10, if
the process is in control with a mean of 40 and a sample standard deviation of 7.
A. 12.0
B. 13.3
C. 15.7
D. 21.0
Correct Answer: A
Justification: The upper control limit for an S chart can be approximated by:
UCLS = 12.04
13 www.pmtutor.org Powered by POeT Solvers Limited.
--------------------------------------------------------------------------------------------------------------------
29. Which of the following techniques does NOT necessarily compliment the visual
factory concept?
A. Kanban
B. Tool boards
C. 5S
D. Poka-yoke
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
Correct Answer: A
Justification: The question is describing the kanban system of signals and control.
Muda (waste) and Poka-yoke (mistake proofing) are out of step with the question. The
Andon board is a lighted overhead display showing current status and problems. This is
a subset of the visual factory (relatively minor).
---------------------------------------------------------------------------------------------------------------------
31. If two-sigma limits are substituted for conventional three-sigma limits on a control
chart, which of the following occurs?
A. Decrease in alpha risk
B. Increase in beta risk
C. Increase in alpha risk
D. Increase in sample size
Justification: A type I or alpha risk is to reject a true hypothesis. In this case, we are
substituting 2.0 sigma boundaries for 3.0 sigma boundaries. There is an increased
probability of rejecting (or acting on) normal variation and calling it abnormal. There is
an increased alpha risk.
---------------------------------------------------------------------------------------------------------------------
32. There are several different varieties of median control charts. If median values
and ranges are plotted, what would be expected to be different than experienced
with an X bar – R chart for the sample size? Assume that control limits are used.
A. The middle value would be circled on the median chart
B. The range chart would have different control limits
C. The median control limits would be wider apart
D. The lower limit on the range chart could not be zero
Correct Answer: C
Justification: The median value might be circled in the data but would not be circled on
the median chart (with this type of chart). The range chart would be identical to an X Bar
– R chart of the same sample size (eliminates answers B and D). The control limit
factors for the median chart are slightly larger than for a traditional X bar charts, making
the control limits wider.
---------------------------------------------------------------------------------------------------------------------
33. A process is in control at X = 100, R = 7.3 with n = 4. If the process level shifts to
101.5, with the same range, what is the probability that the next X point will fall
outside the old control limits:
A. 0.016
B. 0.029
C. 0.122
D. 0.360
Correct Answer: A
Justification: This question requires the calculation of the upper control limit, the
treatment of this control limit as a specification limit, the determination of an upper Z
value and thus the projected failure rate after the process shifts.
15 www.pmtutor.org Powered by POeT Solvers Limited.
Equations:
Where,
The following drawing will help with the Z value failure rate calculation. Note the UCL
becomes an USL.
---------------------------------------------------------------------------------------------------------------------
A. I only
B. II and III only
C. I and III only
D. I, II and III
Correct Answer: C
Justification: Using some math magic, Bothe converts data into Z values and the
control limits into ± A2. With this plotting arrangement, traditional control chart
interpretation rules apply.
---------------------------------------------------------------------------------------------------------------------
35. An investigation of the total product or process variability indicates that the single
largest element is quite often:
A. Dependent on the process itself
B. The error of measurement
C. Time to time variation
D. Stream to stream variation
Correct Answer: A
Justification: For any given process or product, answers B, C and D could all be true.
Additionally, a lot to lot or piece to piece variation could be the major culprit. All of this
logic makes answer A the best choice.
---------------------------------------------------------------------------------------------------------------------
36. If a value of one is used for λ in a EWMA chart, what will be the outcome?
A. The chart becomes meaningless
B. Only older data would be considered
C. The variance of the EWMA statistic cannot be calculated
Correct Answer: D
Justification: λ is normally set between 0.2 and 0.3. The actual value is somewhat
arbitrary. If a value of 1.0 is selected, then only most recent measurements influences
the EWMA. That is, the plot degrades to a Shewhart chart.
---------------------------------------------------------------------------------------------------------------------
37. Which control chart is normally used when monitoring the number of
nonconformities per unit?
A. c chart
B. X bar chart
C. np chart
D. u chart
Correct Answer: D
Justification: The u chart is used to monitor the number of nonconformities per unit.
This is also considered the average number of defects/unit. There is nothing in the
question that states that the sample size is fixed.
---------------------------------------------------------------------------------------------------------------------
38. Which of the following charts does NOT require the averaging of variable data?
A. Moving average chart
B. X bar – R chart
C. mX – mR chart
D. Multi-vari chart
Correct Answer: D
Justification: Note that this question is asking for a negative response. The multi-vari
chart plots non-averaged individual values.
---------------------------------------------------------------------------------------------------------------------
39. If the specification limits are narrower than the control limits, then:
I. The process is not capable
A. I only
B. I and II only
C. II and III only
D. I, II and III
Correct Answer: A
Justification: If the specification limits are narrower than the control limits, then the
process is not capable. As a rule of thumb, the process capability, C p should be at least
1.3.
---------------------------------------------------------------------------------------------------------------------
Correct Answer: C
Justification: Note that the question is requesting a negative response. One of the
disadvantages of pre-control is the lack of a paper trail, indicating when process
adjustments were made.
---------------------------------------------------------------------------------------------------------------------
A. I and II only
19 www.pmtutor.org Powered by POeT Solvers Limited.
B. II and III only
C. I and III only
D. I, II and III
Correct Answer: D
Justification: There are many ways a control chart can exhibit an out of control
condition. The most popular rules were summarized by the Western Electric Company:
---------------------------------------------------------------------------------------------------------------------
42. Since CuSum charts are more complicated to operate than Shewhart control
charts, what is the most logical reason for using them at all?
I. They require less data
II. They can be computer generated
III. They can detect smaller shifts in the process mean
A. I only
B. II and III only
C. I and III only
D. I, II and III
Correct Answer: B
Justification: All of the statements I – III are true. However, the most important reason
for CuSum charts is item III. Since there is no answer selection for item III only, then
another answer must be considered important. The question writer suggests that the
rapid computer generation of CuSum charts is also important to their expanded use.
---------------------------------------------------------------------------------------------------------------------
Correct Answer: C
Justification: The question describes an application for the moving average chart. With
the moving average chart, the data is smoothed so that true trends can be analyzed.
---------------------------------------------------------------------------------------------------------------------
44. As with the 7 quality management tools, the Japanese concept of workplace
organization, 5S, has been Americanized. Of the five original tools, which two are
hardest to find in the American system?
A. Seiko and Seiton
B. Seiton and Seiso
C. Seiketso and Shitsuke
D. Seiko and Seiso
Correct Answer: C
---------------------------------------------------------------------------------------------------------------------
45. What charting technique is useful for looking at a process for trends after
smoothing of data has occurred?
A. X bar – R chart
B. Moving average chart
C. Multi-vari chart
D. np chart
Justification: The Multi-vari and np charts do not apply to this question. Although data
is “averaged” in an X bar – R chart, it is not intentionally smoothed as with a moving
average chart.
A moving average chart is useful for data (like the stock market) in that there is a
smoothing of short term information from an erratic process.
---------------------------------------------------------------------------------------------------------------------
46. In which one of the following is the use of an X bar and R chart liable to be most
helpful as a tool to control a process:
A. The machine capability is wider than the specification
B. The machine capability is equal to the specification
C. The machine capability is somewhat smaller than the specification
D. The machine capability is very small compared to the specification
Correct Answer: C
Justification: A control chart is not a useful tool in controlling a process if the capability
is wider than specification. An X bar – R control chart may not be necessary if the
capability (spread) is very small compared to the process. In this case, a pre-control
chart may be selected (or first and last piece inspection). Answer B is not a bad choice.
Answer C is a much better choice.
---------------------------------------------------------------------------------------------------------------------
47. In a hypothetical situation, if all within time, piece to piece, and measurement
variation were removed from a process, what would be left?
A. Nothing it would all be eliminated
B. Inherent process variation
C. Product spread
D. Time to time variation
Correct Answer: B
48. As applied to a Six Sigma environment, how would control chart variables be
selected?
I. From CTQ characteristics
II. From KPIVs
III. From KPOVs
IV. From non-critical KPIVs and KPOVs
A. I and IV only
B. I, II and III only
C. II, III and IV only
D. I, II, III and IV only
Correct Answer: B
Justification: Control chart characteristics in a Six Sigma world would be selected from
critical to quality customer characteristics as well as key process input and output
variables. There are too many non-critical items to be considered for control charting. If
variables are non-critical they probably wouldn’t be key variables in the first place.
---------------------------------------------------------------------------------------------------------------------
49. The identification of key process input and output variables can come from:
I. DOE results
II. Customer surveys
III. ANOVA methods
IV. Customer requirements
A. I and II only
B. II and III only
C. I, II and IV only
D. I, II, III and IV
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
50. If we drew a large number of samples from a controlled process, we would not be
surprised to discover:
I. Some differences among the values of the sample means
II. A distribution of sample means around some central value
III. That many sample means differ from the process average
A. I only
B. II only
C. I and III only
D. I, II and III
Correct Answer: D
Justification: Items I – III are all correct statements regarding sampling principles,
control chart theory and statistical inference.
---------------------------------------------------------------------------------------------------------------------
51. What % of product should fall between the P – C lines (green zone) on a pre-
control chart, assuming that the process is stable?
A. 60.0%
B. 68.4%
C. 86.0%
D. 95.4%
Correct Answer: C
---------------------------------------------------------------------------------------------------------------------
52. You look at a process and note that the chart for averages has been in control. If
the range suddenly and significantly increases, the mean will:
A. Usually increase
24 www.pmtutor.org Powered by POeT Solvers Limited.
B. Stay the same
C. Always decrease
D. Occasionally show out of control of either limit
Correct Answer: D
Justification: This question requires a review of the answers. If the range significantly
increases, then more spread in individual readings is occurring. The mean will not
always increase or decrease. The mean will not necessarily stay the same.
Occasionally it may exceed either control limit.
---------------------------------------------------------------------------------------------------------------------
53. Which of the following types of control charts has the largest average run length
for small shifts in the process mean?
A. X bar
B. Cumulative sum
C. EWMA
D. Dodge-Romig
Correct Answer: A
Justification: The average run length, ARL, is the average number of plotted points to
obtain a point outside the control limits. For a Shewhart chart, with 3-sigma limits, the
ARL is 370 (1/0.0027) if the process is in control. Shewhart charts are insensitive to
small shifts in the mean. Cumulative-sum charts (CuSum), and Exponentially weighted
moving average charts, (EWMA), are much better at detecting small shifts in the mean.
Since an X bar chart is a Shewhart chart, answer A is correct. Dodge – Romig is a
sampling technique.
---------------------------------------------------------------------------------------------------------------------
54. On the production floor, parts being produced measure 0.995 – 1.005. The
specification requires the parts to be 0.995 – 1.005. Which of the following
techniques would NOT be particularly useful in trying to improve and control the
process?
A. Pre-control
B. ANSI/ASQ Z1.4
C. Short run charts
Correct Answer: B
Even if all of the tools presented are not understood, a CSSBB student should
recognize that an attribute sampling plan ANSI/ASQ Z1.4 is out of place in a variable
measurement application.
---------------------------------------------------------------------------------------------------------------------
55. If six consecutive samples were taken from a process and measured precisely,
one would still expect to find differences. What type of variation would be most
difficult to determine?
A. Lot to lot variation
B. Piece to piece variation
C. Inherent process variation
D. Error of measurement
Correct Answer: A
Justification: The small sample size would make it impossible to provide a high level of
confidence in the results. However, measurement error, inherent process variation and
piece to piece variation are obtainable. Lot to lot variation would not be detectable
unless carefully planned for (which is not indicated in the question).
---------------------------------------------------------------------------------------------------------------------
56. If a process is truly in control, what is the probability of observing a run violation
of seven or more consecutive points on either side of the X bar chart centerline?
A. 1/32
B. 1/64
C. 1/128
D. 1/256
Correct Answer: B
---------------------------------------------------------------------------------------------------------------------
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
58. Which of the following control charts are more efficient than an X-bar chart at
detecting small shifts in the mean?
I. CuSum
II. EWQR
III. EWMA
A. I only
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
60. If a process is out of control, the theoretical probability that a single point on the
X bar chart will fall between plus one sigma and upper control limits is:
A. 0.2240
B. 0.1587
C. Unknown
D. 0.3413
Correct Answer: C
28 www.pmtutor.org Powered by POeT Solvers Limited.
Justification: This question can be a little tricky. The key phrase is “out of control”. If
the process were in control, a simple Z value determination would yield 0.1587 as the
correct answer. Since the process is out of control, the answer is unknown.
---------------------------------------------------------------------------------------------------------------------
61. Total productive maintenance involves coordinated group activities for greater
equipment effectiveness. Which of the following elements are also included?
I. Predictive maintenance
II. Preventative maintenance
III. Increased machine reliability
IV. Ease of maintenance
A. I and II only
B. II and III only
C. II, III and IV only
D. I, II, III and IV
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
62. About 9 months after embarking on a Six Sigma effort, a company moved from
measurement with traditional mikes and verniers to digital mikes and two piece
linear scales. Why was this action necessary?
A. They probably wanted to show prospective customers their level of
measurement precision
B. If changes were made they did not want to be caught “asleep at the switch”
C. Processes have improved and they needed finer product measurements
D. This would be required in the control phase of the DMAIC process
Correct Answer: C
Correct Answer: B
Justification: An R chart is used to monitor process variance. The range, the difference
between the largest and smallest measures in the sample, is used as an estimate of the
variance or standard deviation. The S chart is also used to monitor process variance,
except the standard deviation, S, is estimated directly, rather than using the range
method. This method is recommended when the sample size is large, n > 10, and when
the sample size is variable (The range method quickly loses accuracy as the sample
size increases).
---------------------------------------------------------------------------------------------------------------------
A. I and II only
B. III and IV only
C. II and III only
D. I and IV only
Correct Answer: C
Justification: Standardized work in Japan means that the process is being controlled
not the workers. To them, a standard defines the process methods that are safest and
easiest for the workers and the most cost-effective and productive for the company.
---------------------------------------------------------------------------------------------------------------------
Correct Answer: C
Justification: A V-mask was widely used with a CuSum chart before the advent of
computers. The chart can now be generated with or without a V-mask.
---------------------------------------------------------------------------------------------------------------------
66. When using a pre-control chart, it’s possible to have two consecutive samples
outside of the target area but inside of the specification. What is the expectation
that two consecutive samples would both fall between the target area and the
specification limit on the high side?
A. 1/7
B. 1/49
C. 1/196
D. 1/98
Correct Answer: C
Justification: In the CSSBB Primer it is stated that the chance that two parts will fall
outside either P – C line is 1/7 times 1/7, or 1/49. However, there are four ways that this
can occur, based on pure probability:
---------------------------------------------------------------------------------------------------------------------
67. What is the inherent danger in using an X bar and sigma chart with a sample size
of 25?
A. Finding appropriate control limit factors
B. Interpreting the chart properly
Correct Answer: D
---------------------------------------------------------------------------------------------------------------------
68. An X-bar chart has shown control for a long time. You see that points for the last
50 samples are all very near the center line on the chart. In fact, they are all
within one sigma of the center line. This probably indicates that:
A. It is a desirable situation
B. It is an undesirable situation
C. The process standard deviation has decreased during the time the last 50
samples were taken
D. The control limits are incorrectly computed
Correct Answer: C
Justification: Answer B is the least likely choice because the process standard
deviation (sample range) may have decreased. Answer A may be correct but it’s not
known if X-bar is the desired target. Answer D could be correct but it is unlikely if the
chart has been maintained for a long time. Answer C is the best choice.
---------------------------------------------------------------------------------------------------------------------
69. American visitors to an aluminum plant in Japan were given white gloves to wear.
What category of the 5S program was being displayed?
A. Sort
B. Scrub
C. Straighten
D. Standardize
Correct Answer: B
---------------------------------------------------------------------------------------------------------------------
70. A process is running under pre-control conditions and two consecutive pieces
have been sampled. The first piece is measured to be in the green zone. What is
the probability that the second piece will be measured to be in the red or yellow
zones?
A. Zero
B. 1/49
C. 1/98
D. 1/196
Correct Answer: A
Justification: Maybe zero is a bad choice because some idiot may always choose to
measure a sample when taken. However, if the first sample is within target the second
piece should not be measured.