This document provides project details for the rehabilitation and reconstruction of damaged paved national roads and drainage in Cebu City, Philippines. The contractor, A.T. Tan Cosntruction Corporation / J.S. Layson Co.Inc. joint venture, was awarded a contract worth 19.4 million Philippine pesos with a 120 calendar day duration to complete the work by August 19, 2017 under the supervision of DPWH personnel led by Project Engineer Rogelio Quibilan.
This document provides project details for the rehabilitation and reconstruction of damaged paved national roads and drainage in Cebu City, Philippines. The contractor, A.T. Tan Cosntruction Corporation / J.S. Layson Co.Inc. joint venture, was awarded a contract worth 19.4 million Philippine pesos with a 120 calendar day duration to complete the work by August 19, 2017 under the supervision of DPWH personnel led by Project Engineer Rogelio Quibilan.
This document provides project details for the rehabilitation and reconstruction of damaged paved national roads and drainage in Cebu City, Philippines. The contractor, A.T. Tan Cosntruction Corporation / J.S. Layson Co.Inc. joint venture, was awarded a contract worth 19.4 million Philippine pesos with a 120 calendar day duration to complete the work by August 19, 2017 under the supervision of DPWH personnel led by Project Engineer Rogelio Quibilan.
Cebu City District Engineering Office V. Sotto St., Cebu City
PROJECT ID AND NAME :16HH0089 – REHABILITATION / RECONSTRUCTION /
UPGRADING OF DAMAGED PAVED NATIONAL ROADS INCLUDING DRAINAGE BASED ON MANAGEMENT SYSTEM /HIGHWAY DEVELOPMENT AND MANAGEMENT – 4(HDM-4), SECONDARY ROADS, CEBU SOUTH COASTAL ROAD – (S0018CB) CHAINAGE 000 – CHAINAGE 427, (S00019CB) CHAINAGE 000 – CHAINAGE 324, CEBU CITY
CONTRACTOR : A.T. TAN COSNTRUCTION CORPORATION / J.S.
LAYSON CO.INC., (JOINT VENTURE)
CONTRACTUAL DATA
SOURCE OF FUND : FY 2017 GAA
DURATION : 120 C.D. CONTRACT AMOUNT : P 19,479,458.96 REVISED CONTRACT AMOUNT : EFFECTIVE DATE : MARCH 23, 2017 EXPIRY DATE : JUNE 30, 2017 APPROVED W.S.O. NO. 1 : 30 C.D. REVISED EXPIRY DATE : AUGUST 19, 2017
DPWH PERSONNEL
PROJECT ENGINEER : ROGELIO N. QUIBILAN