Man Power
For furnace F20K recoil, manpower peaked at 60 (30 + 30) for day shift and 20 (18+2) for night
shift during coil launching and welding period.
After this two major activity, manpower will be decreased to 50 (30 Maint + 20 FL) for day shift
and night shift will be cancelled due to no work front for UTOC.
We UTOC were to push all activity on day shift in meeting, as night shift will be having higher
cost due to the furnace recoil is a lump sum job.