Professional Documents
Culture Documents
PED-III - Heat Exchanger Networks - AK Golder PDF
PED-III - Heat Exchanger Networks - AK Golder PDF
PED-III - Heat Exchanger Networks - AK Golder PDF
Pre-requisites
“PINCH ANALYSIS AND PROCESS INTEGRATION: A User Guide on Process Integration for
the Efficient Use of Energy” by I.C. Kemp, Elsevier, 2007.
3
Grading Scheme
Mid semester exam : 30%
End semester exam : 30%
Quizzes / class tests : 10%
Tutorials & assisnments : 30%
Important Instructions
o Not be allowed to enter the class room after 2 minutes from the commencement of
the lecture
o Minimum attendance is 75% to write the end-semester examination
o Must carry graph paper, scale, calculator, eraser and supplementary pages to
the tutorial classes
o Mid semester and end semester quizzes may be conducted without prior
intimation
4
What is meant by
5
Classification of heat exchangers depending on the applications
Heat exchanger may have singe or two
phase flow on each side
Fixed tubesheet
Flow
Shell & tube U-tube
Double pipe
Finned tube
Finned plate
Lamella
Direct
contact-type
Heat
Exchanger Disk type
Rotary
regenerator
Fixed-matrix 6
regenerator
Fixed-tube heat exchanger Floating-head heat exchanger
7
Typical parts and connections of Heat Exchangers
1. Shell 16. Tubes (U-type)
2. Shell cover 17. Tie rods and spacers
3. Shell flange (channel end) 18. Transverse (or cross) baffles or support plates
4. Shell flange (cover end) 19. Longitudinal baffles
5. Shell nozzle or branch 20. Impingement baffles
6. Floating tube sheet 21. Floating head support
7. Floating head cover 22. Pass partition
8. Floating head flange 23. Vent connection
9. Floating head gland 24. Drain connection
10. Floating head backing ring 25. Instrument connection
11. Stationary tube sheet 26. Expansion bellows
12. Channel or stationary head 27. Support saddles
13. Channel cover 28. Lifting lugs
14. Channel nozzle or branch 29. Weir
15. Tube (straight) 30. Liquid level connection
8
Process (thermal) design procedure of Heat Exchanger
[Kern method ]
A U o ,assm . LMTD
Q
. FT
A
nt
do L
9
.
4m(n p / nt )
u
di 2
.
4 m(n p / nt )
Re 104
di
1.0
w
10
U o ,cal U o ,assm
0 30%
U o ,assm
A - Areqd
% Overdesign = 100
Areqd
11
If the tube-side pressure drop exceeds the allowable pressure drop for the process system,
decrease the number of tube passes or increase number of tubes per pass. Go back to step
#6 and repeat the calculations steps.
If the shell-side pressure drop exceeds the allowable pressure drop, go back to step #7 and
repeat the calculations steps.
12
Selection of Fluids for Tube and Shell Side
• Routing of the shell side and tube side fluids has considerable effects on the heat
exchanger design. Some general guidelines for positioning the fluids are given in
Table
• These guidelines are not ironclad rules and the optimal fluid placement depends on
many factors that are service specific
Cross
Approach
15
(R)
(P)
ln
16
17
Effect of terminal temperatures on FT
ln
20
Design value of ‘P’: P X P Pmax , 0<X P 1
21
Bowman RA. Mean Temperature Difference Correction in
Multipass Exchangers, Ind. Eng. Chem. 1936 (28) 541-544.
Value of P over NSHELLS number of 1-2 shells in series (PN-2N) can
be related to P for each 1-2 shell (P1-2) as:
23
24
Heat Exchanger Networks: Energy Targets
Reactor
Onion model
25
Prof. Bodo Linnhoff (born 1948) who developed Pinch
Analysis of Heat Exchanger Network Design
[University of Manchester Institute of Science and Technology (UMIST)]
Born in Berlin, Germany, Linnhoff studied at Technical University of Hanover,
Germany and ETH Zurich, Switzerland (MSc in Mechanical Engineering). He
taught at ETH until 1974 when he went to University of Leeds, UK, as a British
Council Scholar. There he gained a PhD in Chemical Engineering (1979). He
joined the company ICI in 1977 and moved to the University of Manchester
Institute of Science and Technology (UMIST) in 1982 where he was appointed to
a Chair in Chemical Engineering.
He joined GoMedia in 2015 and involved with GoMedia's first multi territory
launch in Europe, he is now heading up GoMedia’s European sales function based
in Brussels. 26
Temperature–enthalpy diagram
27
Composite Curves
28
Two-stream heat recovery problem
29
30
31
Flowsheet of a Manufacturing Unit
ΔH=27 MW
ΔH=-30 MW
Feed 2 230ºC
Product 2
140ºC Reactor 2
200ºC 80ºC
ΔH=32 MW
Off Gas
Feed 1 Reactor 1 40ºC
20ºC 180ºC 250ºC
ΔH=-31.5 MW
Coln
40ºC
Product 1
40ºC
200
PINCH
150
Cold composite curve
Hot composite curve
T, C
o
o
Tmin=10 C
100
50
0
0 10 20 30 40 50 60 70
H, MW
MW 10= QCmin QRecovery=51.5 QHmin =7.5 MW 33
Contd..
250
200
PINCH
150
Hot composite curve Cold composite curve
T, C
o
o
Tmin=20 C
100
50
0
0 10 20 30 40 50 60 70 80
H, MW
MW 14= QCmin QRecovery=47.5 QHmin =11.5 MW
37
37
3 forms of cross pinch heat transfer
Increase the
requirement of both
hot and cold utilities
by the same amount
i.e. utility
requirement increase
Process-process heat
is DOUBLE
transfer across the pinch
Inappropriate utility below the
pinch cause enthalpy imbalance
below the pinch
41
Threshold Problems (contd.)
43
Steam valuation estimated by convention method
Source:
https://www1.eere.energy.gov/manufacturing/tech_assistance/pdfs/tech_brief_true_cost.pdf
44
Problem Table Algorithm
45
Example Problem Table Algorithm ΔTmin=10°C
Stream no. Type TS, °C TT, °C ΔH, MW CP, MW.K-1 T*S, °C T*T, °C
1 Cold 20 180 32 0.2 25 185
2 Hot 250 40 -31.5 0.15 245 35
3 Cold 140 230 27 0.3 145 235
4 Hot 200 80 -30 0.25 195 75
Shifted temperature
intervals, *T, (°C)
245 2 250
235 240 230
195 200 190 4 200
35 30 40
25
1
Temperature interval heat balances
47
Problem Table Cascade
HOT HOT
UTILITY UTILITY
245°C 0 MW 7.5 MW
145°C -7.5 MW 0 MW
35°C 4.5 MW 12 MW
25°C 2.5 MW 10 MW
240
Utility pinch
200
Process pinch
Temperature (oC)
160
o
Tmin=180-170=10 C
120
o
Tmin=150-140=10 C
80
40
0
0 10 20 30 40 50 60 70
H, MW 50
Grand Composite Curve (GCC)
Although the composite curves can be used to set energy targets, however, the grand
composite curve (GCC) is a more appropriate tool for understanding the interface
between the process and utility system
51
Grand composite curve allows alternative utilities
Grid representation of streams
52
Heat Exchanger Networks: Number of Heat Exchange Units,
Number of Shells, Heat Exchange Area and Cost Targets
53
Heat Exchange Area Targets
Utility streams must be included with the process streams in the composite
curves to obtain the Balanced Composite Curves to calculate the network
area
250
Balanced Composite Curve
200
PINCH
150
T, C
o
o
Tmin=20 C
100
50
0
0 10 20 30 40 50 60 70 80
H, MW
54
Effect of individual stream film transfer coefficients can be
included to calculate network area
FT correction factor for each enthalpy interval depends both on the assumed
value of XP and the temperatures of each interval on composite curves. The above
55
equation can simply modify by incorporating FT in each interval for 1-2 pass
Balanced composite curve and temperature interval
200 o
o
179.57 C
180 179 C o
o
180 C
170 C
160
o
150 C
140
Temperature, C
o
120 C
o
120
o
100 90 C
o
110 C
o
80
o o 102.5 C 105oC
50 C 60 C o
80 C
60
o o
40 40 C 50 C
o
30 C
20 o o
20 C 22.5 C
0 10 20 30 40
H, MW
• Given data: Film transfer coefficients for all streams are 200 W·m−2·K−1 56
(including utility)
Target area calculation
Enthalpy intervals and stream population
Interval 1 2 3 4 5 6 7
Enthalpy (q i / hi ) k (q j / h j )k Ak (m2)
ΔTLMk (1-1 pass, FT=1.0)
interval Hot streams Cold streams
1 64.67 (ΔT1=60, ΔT2=69.571) 15,000 15,000 463.9
2 71.76 (ΔT1=69.571, ΔT2=74) 20,000 20,000 557.4
3 55.79 (ΔT1=65, ΔT2=47.5) 10,000 10,000 358.5
4 24.07 (ΔT1=47.5, ΔT2=10) 90,000 90,000 7478.2
5 10 (ΔT1=10, ΔT2=10) 45,000 45,000 9000
6 28.73 (ΔT1=30, ΔT2=27.5) 15,000 15,000 1044.2
7 23.55 (ΔT1=27.5, ΔT2=20) 5,000 5,000 424.6 57
Target area for the network, Ak = 19,327
Number of Shells Targets
Where,
NSHELLS = Total number of shells over K enthalpy intervals
58
Capital Cost Targets
Cost a single heat exchanger with surface area A can be expressed as:
Where,
a, b, c = Constants that vary according to materials of construction, pressure
rating and type of exchanger.
Where,
N = number of units or shells, whichever is appropriate
59
Heat Exchanger Networks: Pinch Method
of Network Design
Two rules:
o Process-to-process heat transfer
o Inappropriate use of utilities
i. Start at the pinch: Most constrained region of the problem.
ΔTmin exists between all hot and cold streams at the pinch. Number of feasible
matches in this region is severely restricted.
iii. CP-Table
Identification of the essential matches in the region of the pinch. CP values of the
hot and cold streams for the streams at the pinch are listed in descending order
60
iv. Tick-off heuristic
Grid diagram
61
Infeasible match Feasible match
Criteria for pinch
matches below the pinch
62
Above pinch Below pinch
Tick-off heuristic
To tick off a stream, individual units are made as large as possible i.e. the smaller of
the two heat duties on the streams being matched to keep the number of units to a
minimum
Utility demand
Network design using Pinch method
64
Utility demand
Threshold problem
Pseudo-pinch
65
Network design using Pinch method
Stream Splitting
Splitting of the cold
streams is required if the
number of hot streams at
the pinch, above the
pinch, is more than the
number of cold streams.
SH ≤ SC (above pinch)
66
SH ≥ SC (below pinch)
CP inequality criteria necessitates stream splitting
CPH ≤ CPC (above pinch)
CPH ≥ CPC (below pinch)
Above
pinch
Below
pinch
67
Algorithms for Stream Splitting
Above pinch
Below pinch
68
Network Design with Stream Splitting
EXAMPLE. Streams data of a high temperature process reveals that for ΔTmin = 20°C. The
process requires 9.2 MW of hot utility and 6.4 MW of cold utility and the pinch is located
at 520°C on hot stream. The network is designed for maximum energy recovery.
Stream type Supply Temp. Target Temp. (ºC) Heat capacity flow rate
(ºC) (MW.K-1)
Hot (#1) 720 320 0.045
Hot (#2) 520 220 0.04
Cold (#3) 300 900 0.043
Cold (#4) 200 550 0.02
Infeasible match at Stream splitting to have Design of network
pinch above pinch feasible match at pinch 69
above pinch
Stream grid diagram
70
Network design for multiple pinches
Two process pinches: Both hot and cold steams are parallel
250
CP=0.15
200
Temprature, Deg C
0
0 10 20 30 40 50
Enthalpy, kW
200
Temperature, Deg C
150
Tmin=20
100
50
Tmin=20
0
0 10 20 30 40 50
Enthalpy, kW
o The difference between the Energy Targets before placing a match and
Energy Targets of the Remaining Problem plus Energy Duty for that said
match will give the energy penalty for that match
o Similarly, the penalty of Network Area, Shells and Costs can determined
by the Remaining Problem 73
Hand on Calculation on Remaining Problem Analysis
EXAMPLE:
a. Develop a maximum energy recovery design above the pinch that comes close to the
area target in the minimum number of units.
b. Develop a maximum energy recovery design below the pinch that comes as close as
possible to the minimum number of units.
Data available:
(i) Low pressure steam is available condensing between 180 and 179°C
(ii) Cooling water between 20 and 30°C
(iii) All film transfer coefficients are 200 W·m−2·K−1 (both hot and cold streams)
(iv) ΔTmin = 10°C (pinch at 90°C on the hot streams and 80°C on the cold streams)
(v) Minimum hot and cold utility duties are 7 MW and 4 MW
Stream type Supply Temp. (ºC) Target Temp. (ºC) Heat capacity flow rate
(no.) (MW.K-1)
Hot (#1) 150 50 0.2
Hot (#2) 170 40 0.1
Cold (#3) 50 120 0.3
Cold (#4) 80 110 0.5 74
Design above the pinch
CPH ≤ CPC
SH ≤ SC
Pinch
CP
150°C 90°C
1
0.2
170°C 90°C
0.1 2
120°C 80°C
0.3 3
110°C 80°C
0.5 4
200 o
o
179.57 C
179 C o
180
o
180 C
170 C
160
o
150 C
140
Temperature, C
o
120 C
o
120
o
100 90 C
o
110 C
o o
80 102.5 C 105 C
o o
50 C 60 C o
80 C
60
o o
40 40 C 50 C
o
30 C
20 o o
20 C 22.5 C
0 10 20 30 40
H, MW
76
Target area calculation
Enthalpy intervals and stream population
Interval 1 2 3 4 5 6 7
Enthalpy (q i / hi ) k (q j / h j )k Ak (m2)
ΔTLMk (1-1 pass, FT=1.0)
interval Hot streams Cold streams
1 64.67 (ΔT1=60, ΔT2=69.571) 15,000 15,000 463.9
2 71.76 (ΔT1=69.571, ΔT2=74) 20,000 20,000 557.4
3 55.79 (ΔT1=65, ΔT2=47.5) 10,000 10,000 358.5
4 24.07 (ΔT1=47.5, ΔT2=10) 90,000 90,000 7478.2
5 10 (ΔT1=10, ΔT2=10) 45,000 45,000 9000
6 28.73 (ΔT1=30, ΔT2=27.5) 15,000 15,000 1044.2
7 23.55 (ΔT1=27.5, ΔT2=20) 5,000 5,000 424.6 77
Target area for the network, Ak = 19,327
tc 2 tc1 th1 th 2
TARGETING the number of shells (1-2 exchanger) P R
th1 tc1 tc 2 tc1
FT -- -- -- 0.916 0.888 -- --
(New ) (acceptable) (acceptable)
Final &
acceptable, 0.999 0.999 0.997 0.916 0.888 0.985 0.992
FT
K1orK2 (0.115×1) + (0.0539×2) + (0.2793×2) + (2.257×3) + (3.828×2) + (0.3899×2) +(0.3567×1)
N (S 1)
k 1
k (Nshells)above pinch = 7.5524 ≈ 8
(Nshells)below pinch = 8.7925 ≈ 9 , NSHELL (TOTAL) = 17
78
(Contd.) Xp=0.75
Values Interval Interval Interval (3) Interval Interval Interval Interval
(1) (2) (4) (5) (6) (7)
A1-1 pass, m2 463.9 557.4 358.5 7478.2 9000 1044.2 424.6
A1-2 pass, m2 464.4 557.9 359.6 8163.9 10135.1 1060.1 428
For 1-2 pass exchanger:
Atarget(above pinch)=9545.8 m2
Atarget(below pinch)=11623.3 m2
Atarget(total)=21169.1 m2
N(i)above pinch N(steam)=0.1689, N(1)=2.257, N(2)=2.5363, N(3)= 2.7052; N(4)=2.5902
K1
N (i)
i
=10.2576;
above pinch
N k =2.7052
k 1
(Nshells)above pinch = 7.5524
N (i)
i
below pinch =13.3671; N
k 1
k =4.5746
N(i) is greater for all stream except steam & cooling water and recalculated for N(steam)=1 and N(CW)=1.
(Nshells)above pinch = 8.3835 [(Nshells)above pinch=9] 79
(Nshells)below pinch = 9.0459 [(Nshells)below pinch =10]
Maximum Thermal Effectiveness of 1-2 Shell and Tube Exchanger
80
Target for the remaining problem after match between [1] and [3]:
[1-1 Shell- and -Tube Exchanger]
CP
150°C 90°C
0.2 1
170°C 90°C ∆T1 = 10, ∆T2 = 30
0.1 2
∆TLM = 18.2
A1 = 6593 m2
120°C
80°C 3
0.3
110°C 80°C 4
0.5
o o
CCC 179 C 180 C
180
HCC o
Steam (Hot utility) 170 C
160
Internal (1): ∆T1 = 83, ∆T2 = 70, ∆TLM = 76.31, A1 = 917.3 m2
Interval
Internal (2): ∆T1 =74, ∆T2=10, ∆TLM=31.98, A2=2501.56 m2
Temperature ( C)
#1
140
Interval
#2
120 H=7 Target area for the remaining problem above pinch
H=8
110 C
o (A1 + A2) = 3419 m2
Overall target exceed by = [{6593+3419) – 8859}/8859] × 100
100
o
o
90 C 96 C
80 o
= 13 %
80 C
10 12 14 16 18 20 22 24 26 28
H (MW)
120°C 80°C 3
0.3
104°C
110°C 80°C 4
0.5
o o
CCC o 179.57 C 180 C
180 179 C
HCC
Steam 170 C
o
o
Internal (1): ∆T1 = 60, ∆T2 = 69.571, ∆TLM = 64.67, A1 = 463.9 m2
162 C
Internal (2): ∆T1 = 69.571, ∆T2 = 74, ∆TLM = 71.76, A2 = 557.4 m2
Interval Interval
160 #2 #1
Interval
#3 Internal (3): ∆T1 = 65, ∆T2 = 58, ∆TLM = 61.43, A3 = 130.2 m2
Temperature ( C)
o
140
Internal (4): ∆T1 = 58, ∆T2 = 10, ∆TLM = 27.3, A4 = 2636.8 m2
120
Interval o
o
120 C Target area for the remaining problem above pinch
104 C o
100 #4 105 C
o 110 C
(A1 + A2 + A3 + A4) = 3788 m2
Overall target exceed by = [{5087+3788) – 8859}/8859] × 100 = 0.2 %
o
90 C
80 o
80 C
10 12 14 16 18 20 22 24 26 28 30
H(MW)
Balanced composite curve of the 82
Remaining Problem
Target for the remaining problem after match between [2] and [4]:
[1-1 Shell- and -Tube Exchanger]
CP
150°C 90°C
0.2 1
0.1 2
170°C 90°C ∆T1 = 10, ∆T2 = 74
∆TLM = 31.98
A1 = 2502 m2
o
179 C 179.57 C 180 C
o o
CCC
180
HCC Internal (1): ∆TLM = 64.667, A1 = 463.9 m2
160
Steam
Interval
Internal (2): ∆TLM = 71.67, A2 = 557.4 m2
o
150 C #1 Internal (3): ∆TLM = 29.47, A3 = 2443.5 m2
Temperature ( C)
Interval
Internal (4): ∆TLM = 13.61, A4 = 3526.7 m2
o
140
#2 H=3
Interval
o H=4
120 114 C
Target area for the remaining problem above pinch
#3
H=7.2 o
120 C
100
Interval
#4 o
o
110 C (A1 + A2 + A3 + A4) = 6991.5 m2
105 C
o
90 C
H=4.8 96 C
o
Overall target exceed by = [{6991.5+2502) – 8859}/8859] × 100 =
80 o
80 C 7.2 %
8 12 16 20 24 28
H (MW)
CP
90°C
0.2 150°C
1
90°C
170°C
0.1
2
80°C
0.3 120°C 106.67°C 3
H
4 MW 8 MW 80°C
110°C 104°C 4
0.5 H
3 MW 12 MW
84
Design below the pinch
o Stream Splitting Needed
Pinch
90°C 60°C 50°C
CP ∆H
1
0.2 8
90°C 40°C
2 0.1 5
80°C 50°C
8 MW
3 0.2 6
0.1 3
Pinch
90°C 60°C 50°C
CP ∆H
1
0.2 8
2
90°C 60°C 40°C
0.1 5
80°C 50°C
3 0.2 6
6 MW
85
3 MW
0.1 3
Complete network design ‘Below Pinch’
Pinch
CP ∆H
90°C 60°C 50°C
1 C 0.2 8
2 MW
90°C 60°C 40°C 0.1 5
2 C
2 MW
80°C 0.2 6
50°C 3
6 MW 0.1 3
3 MW
86
Complete Network Design
1
150°C 90°C 60°C 50°C
C
170°C 90°C 60°C 2 MW
2 C
2 MW
Utility
Exchanger Utility Process
Exchanger Exchanger
1
4
3
Utility
Utility Exchanger 87
Exchanger
Modification for 1-2 shell & tube exchanger with Xp=0.75
FT A1-1 PASS, A1-2 PASS, Area
N
Sl Match FT (Final & m2 m2 per
R W PMAX P=Xp*PMAX (No. of
no. between (Old) acceptable) Shell,
Shells)
m2
1 [1]-[4] 2.5 0.520 <0.5 0.32297 0.24223 0.913 5087 5571.6 3 1857.2
2 [2]-[3] 2.99 0.470 <0.5 0.27953 0.20964 0.921 2770 3007.2 3 1002.4
6
3 [3]- [Stm] 0.07 3.399 0.999 --- --- 0.999 606.4 607 1 6072
5
4 [4]- [Stm] 0.16 2.837 0.999 --- --- 0.999 413.9 414.4 1 414.2
7
5 [1]-[3] 1 --- <0.5 0.58579 0.43934 0.887 6000 6764.4 4 1691.2
(CP=0.2)
6 [2]-[3], 1 --- <0.5 0.58579 0.43934 0.887 3000 3382.2 4 845.5
(CP=0.1)
7 [1]-[CW] 1 --- 0.981 ---- --- 0.981 666. 7 679. 6 1 679.6
(R=1)
8 [2]-[CW] 2 0.598 0.942 --- --- 0.942 810.9 860.9 1 860.9
• Constrain of ΔTmin
can now be relaxed
89
Utility paths for the optimization of HEN
90
Multivariable optimization subject to:
91
Evolve the heat exchanger network in Figure to simplify its
structure
i. Remove the smallest heat recovery unit from the network by exploiting the degree
of freedom in a loop.
ii. Recalculate the network temperatures and identify any violations of the ΔTmin=
10°C constraint.
iii. Restore the original ΔTmin =10 °C throughout the network by exploiting a utility
path.
92
o Network with
6.5 MW of heat
shifted around
a loop
o Shows
infeasible
temperature
difference
93
10+x = 0.15(117.5-40)
94
Thank You
95