Professional Documents
Culture Documents
Operation Level Costing - Part 2: Harikrishna Anumandla
Operation Level Costing - Part 2: Harikrishna Anumandla
Harikrishna Anumandla
more by this author
PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM)
SAP EAM Work Order
share 0
share
tweet
share
like1
Unfollow RSS
Hello Everyone. This is Harikrishna Anumandla working as an EAM Consultant. This blog is a
continuation for my previous blog. For more information about my first blog, please go through the
link https://blogs.sap.com/2017/08/29/operation-level-costing-part-1/.
In this blog am going to walk through how settlement of work order can have its impact by activating
operation level costing. Typically, maintenance order costs are calculated and settled at the Header
level. By using OLC, this feature can be possible at the operation level. It means that, multiple
technical objects with different account assignments within one maintenance order now can be
settled at the operation level for each of the technical objects.
Following are the steps that are considered as prerequisites for the demonstration:
For operation 0020 with equipment 2, to view the detail cost overview, double click on line line1 and
go to the Account Assignment tab
Now let’s Review the settlement rule for equipment 2,
Note the cost center generated in the settlement rule is of equipment 2.
However, the total cost of the individual operations are summed up and can be viewed at the Header
level costs.
Alert Moderator
Be the first to leave a comment
Add Comment
Share & Follow