Professional Documents
Culture Documents
Designed For Offshore-, Petrochemical-And Power Industries: Mammoet
Designed For Offshore-, Petrochemical-And Power Industries: Mammoet
Designed For Offshore-, Petrochemical-And Power Industries: Mammoet
6 Ê- 1 , Ê , " 1 * ÜÀ`Ü`iÊëiV>ÃÌÃÊÊ i>ÛÞÊvÌ}Ê>`ÊÌÀ>ëÀÌ
DESCRIPTION
WORKWEAR
SUPER COMFORT WORKJACKET, PLENTY OF POCKETS
mammoet
WITH ZIPPER AND STORM FLAP, 3M REFLECTIVE
2006
Designed for Offshore-,
DOORGESTIKTE 100% POLYESTER
Petrochemical- È ä
5 YEAR world
and Power Industries
x x
x ä
th MAMMOE
MAMMOET SUMMER COLLECTION 2005 JUBILEE
T WORLD
COMPET
’S
{ x
ITION
{ ä
Mammoet’s staffs carry out their work in the most extreme condi- Î ä
people need to protect themselves when working in the most G erard Duffy fro
of the trivia du
m Brisbane,
Australia is th
£ x
moet World.
He wins a W
orkwear Pack x
g, go to:
the “Approved by Mammoet” seal are well guaranteed of Therefore the collection is also characterized by its com- •J avier Torrijo
s
their high quality, comfort and safety. The Mammoet pliance with the statutory multi-norms including: Flame from Madrid, £ ä
Spain
workwear 2006/2007 collection is in line with the com- retardant / Anti-static / Water proof / Chemical resistant • Gui Zheng
from Shangh
• J. Overduin ai £ x
from Hendrik
nds
CAVE 107 BL
ACK/GREY/R Ó x
www.mammoetworkwear.com
ED
DESCRIPTION
Footwear Î ä
x ä
Supplies Workwear
An extensive line of water- and dust proof bags. Indestructible Workwear line in compliance with the multi-norms. Optimal comfort
material that guarantees longer lifespan, even during the most due to the ergonomic design. Mammoet Workwear is manufactured È ä
extreme conditions. with 3 layers-system to ensure safety and comfort in every situation.
WORKJACKET
È x
Ç x
body. Mammoet workwear is developed based on this vision. set higher safety requirements for working attire. Mammoet 2006/
Clothes with rounded shapes which follows the contours of your body 2007 collection is in compliance with the required multi-norms includ- n x
perfectly. With extra room around the knees, elbows, underarms and ing: Flame retardant / Anti-static / Water proof / Chemical resistant
lower back, rounded forms provide extra freedom when bending for- ä
by Mammoet
Phone +31 182 589 898 Fax +44 191 2639 333 • Mammoet Romstar Sdn Bhd
Mammoet Nederland B.V. Fax +31 182 589 899 Phone +60 6799 3200 USA Mammoet Canada Western Ltd.
Phone +31 10 204 2424 Russia Fax +60 6799 3220 Mammoet USA Inc. • Calgary AB
Fax +31 10 204 2442 Belgium Mammoet Russia LLC • U.E.S. Sarawak Sdn Bhd Rosharon Phone +1 403 252 0551
• Branche Gent Phone +7 495 956 0838 Phone +60 6799 3200 Phone +1 281 3692 200 Fax +1 403 258 3846
• Branch Geleen Phone +32 9 3459 891 Fax +7 495 956 0738 Fax +60 6799 3220 Fax +1 281 3692 178 • Edmonton AB
Phone +31 46 477 1802 Fax +32 9 3455 376 Phone +1 780 4490 552 page 8
Fax +31 46 476 8405 • Branche Antwerp Southern Africa Singapore • Mammoet USA Inc. Fax +1 780 4179 623
• Branch Pernis Phone +32 3 5401 284 • Mammoet Southern Africa Pty Ltd. Mammoet (S) Pte Ltd. Mammoet Western Inc. • Ft. McMurray AB
Colophon
Photography
Chris Pennarts, Ruud van Leeuwen,
Design & Layout
Graphic Invention B.V., De Meern
Copyright
Texts and photos can only be reproduced
Transformer transformed page 18
Mammoet Employees and others after permission from the editor
! !! ! !! ! !
the helm Patrick, Jan Junior and myself. Together with Siem warning sign – symbolizing We Care!, Keep a strong and striking lay-out.
!
Kranenburg, we are Mammoet’s management team. We want Safety has top priority crew, and every office worker too, employees. Jan van Seumeren: Thinking! and Look Out! Management also believes the campaign
Mammoet to grow further and become even more professional, Continued investment in state-of-the- must promote transparent service ‘They transfer experience and must be a long-term undertaking. The safety
building on what we have achieved in the past 40 years. art technology and equipment is levels, knowledge and safety best practices to their teams The concept will be rolled out using several messages will be repeated over and over again,
We might have grown in size, but the world in which we operate extremely important but in the final awareness. ‘Only such an integrated because taking real decisions channels and will be integrated into the regular but each time using a different theme and in
is changing faster than ever before and making new demands analysis it’s the people who work approach to safety makes you less on-site requires more than just training and learning programs and into the a different form to fit the target group best.
on the way we work. with those investments who make prone to accidents,’ Roderik theoretical know-how.’ toolbox that supports safety awareness on
EMD put a lot of practical experience and know- Like Rotterdam, the port of Antwerp ranks among the busiest the center of the port area. The current facilities include dry regional maintenance operations and carries out specialized
how into the upgrade. It reviewed the existing and largest ports in the world. It is home to many of Mammoet’s docks, crane capacity, weighing stations, platform trailers and jobs for customers as well as for itself. Mammoet shares the
configuration and redesigned the components well-known customers, including those in the petrochemical much more support equipment. The site can accommodate the site in partnership with Antwerp Ship Repair. Together the two
to make the MSG a better machine. sector, power industry and general port business. assembly of modules, ship conversions and the dressing of companies are preparing for a very demanding engagement
MSG Upgrade Since February 2006, Mammoet has been able to provide these columns and vessels, while also providing capacity for that will commence later this year. Mammoet will perform lifting
customers with an even better service from an office right in temporary storage. From here, Mammoet supports local and and transport services for the construction of a large bridge.
When specifying a crane’s lifting power, 1,000 950 the world’s largest mobile cranes. employees and the Mammoet company itself. road haulers.
the numbers usually specify the maximum
950
capacity based on the minimum lift radius Ideas triggered by customer needs
which is limited by the sheaves in the hook 900 Other striking additions to the Mammoet fleet include another 170 axle lines
block or the boom head. However, at more and the containerized winch concept for a winch with a capacity of 650
practically usable radius, the capacity
850
800
tonnes. This concept has been designed especially for very high-end jobs, Black Empowerment for Mammoet South Africa
depends on the counterweight system, the such as lifting operations in nuclear power plants. The current plans involve
boom/jib configuration and other parameters. 750 two of these winches, which will first be used on a job in the US.
700
The idea itself was triggered by customers. economic inequalities and underdevelopment that arose Southern Africa (Pty) Ltd to Tlou Heavy Lift Solutions,
When examining various crane profiles, during the apartheid era. The ultimate objective is to achieve a company owned by James Ngobeni, Phumelele Siphayi and
650
it turns out that a “lighter” crane may The same is also true of innovations such as the crawler system for a substantial increase in the participation of black people in Noor Hendricks. The sale of the shares has also resulted in
outperform a “stronger” crane at a larger 600 the Platform Twin Ring and PTC, and the flat racks added to Mammoet’s the economy and the business community. changes in the organization of Mammoet Southern Africa (Pty)
radius. To provide more transparency in its container concept. The development of 20 strand jacks of 900 tonnes to Ltd. The Board of Directors has been expanded from the former
550
technical communications, Mammoet now elevate pontoons rock-steady and thus create a very stable metal island in Black Economic Empowerment is quantified using a scorecard three directors to six, and in addition to the three partners
uses the ‘tonne-meter’ number to work out 500 the Caspian Sea was also inspired by customer needs. The entrance channel of seven items and a maximum score of 100. Companies mentioned above now includes Roderik van Seumeren, Siem
which crane is the best for the job. This 450 to the Caspian Sea is too small to transport a prefab oilrig, so customers achieving a score of at least 40 are entitled to refer to them- Kranenburg and Martijn Kuipers. Martijn Kuipers (Managing
allows customers to compare competitive need a clever solution that can be constructed quickly and at a modest price. selves as Black Empowered, a qualification that is necessary Director) and Noor Hendricks (Director Operations) are
400
quotes. The tonne-meter figure is based on to be eligible for orders from the Government or organizations responsible for the day-to-day management of the company.
the weight of the lift and the operating 350 Each one of these innovations illustrates Mammoet’s ambitions to be market such as power companies and petrochemical companies.
radius, which is dictated by the crane’s 300 leader: to continue providing the safest and best solutions, in part through Since the end of apartheid in 1994 the Government of South About 90 representatives from our clients and the Government,
position. The crane’s performance can continuous innovation based on practical experience, technical know-how Africa has taken a number of steps to achieve a greater diffusion Compliance guaranteed including South Africa’s Minister of Transport, Mr. Jeff Radebe,
10 15 20 25 30 35 40 45 50 55 60 65 70
be read from a graph showing the lift and feedback from customers. of economic power within the black community. This legislation, To ensure compliance with the Black Economic Empowerment attended the official announcement of the share sale and the
Radius (m)
capacity at increasing radius. Black Economic Empowerment, is intended to overcome the legislation Mammoet has sold 50% of its stake in Mammoet signing of a Letter of Intent by all partners in Johannesburg.
Petrochemical
Job Installing heavy units using four six axle line SPMTs and a CC 2800 crawler crane
Challenge Extreme weather conditions
c
by ship and were carried to the site using SMPTs. tires were fitted with spikes. Alertness and good
Crane ballet for low cost, smart & safe solution Mammoet used a Demag CC 2800/1 and a 24 axle equipment kept disruptions and delays to a minimum.
line Scheuerle 2004 at the site.
mammoet Location Cleves, Germany, and Schiedam, the Netherlands
europe Job Transporting reactors weighing 420 and 683 tonnes
Challenge Offering the client the most economical solution through
the judicious use of equipment
Highlight:
The client, one of Europe’s largest refineries, client, Mammoet began the preparations,
had already worked with Mammoet and this time such as the crane configuration plans, several
asked us to carry out transport and lifting work months before the project began. In total some
during the simultaneous shutdown of nine plants. 30 main cranes were involved, together with
The scale of the job, the changeable crews and some 10 cranes for sundry jobs, 15 tractors and
equipment required during the project (which 20 trailers with a range of capacities and lengths.
also changed during the day, at night and in the The work began and ended with a 20-strong Efficient crane mobilization
weekend) and the limited space for the logistics crew but in the peak period (during the vacation
necessary for such a substantial project required season) 90 people were working on the job. Location Dartmouth, Nova Scotia, Canada
meticulous planning. In collaboration with our Job Carrying out various heavy lifts using a CC 4800 crawler crane
Challenge Multi-deployability of equipment over large distances
“Personal excellence
makes the difference in
Made-to-measure efficiency Highlight:
what we achieve”
In 2005, a refinery in Dartmouth, Nova
Location Porvoo, Finland Scotia, Canada, contracted Mammoet
Job Transporting and installing four reactors at an oil refinery for the replacement of a catalytic cracker
Challenge Offering the most effective solution in minimal space head, for which a CC 4800 was used.
Mammoet then won an additional
contract to install a new diesel hydro
treating reactor that was required to
Highlight: comply with new Canadian low-sulfur
An oil refinery in Finland had to expand to increase its production capacity, primarily for oil limits in accordance with the Kyoto
originating from Russia. Mammoet won the contract to transport and install four reactors with protocol. The CC 4800 was on stand-by
Tim Sittler
lengths of 52 meters and diameters of five meters – and weights of no less than 1,254 tonnes! rental for two months until it was used CEO,
to erect and install the ULSD reactor. Mammoet Canada
The client had been smart enough to place the reactors at just nine meters distance from each
other. Mammoet took advantage of this by offering a solution that minimized the conversion An interesting aspect of the job was
time. The solution entailed installing the reactors using a lifting portal stabilized with guys and that the crane was mobilized entirely by
two MSG lifting towers, connected by two 10-meter beams. The preparations consisted of railway from another recently completed
converting the single 15-meter beam unit into two 10-meter beams to connect the two MSG project in Indiana, an overland distance
towers, carried out at Schiedam. The work at the site was a challenge for even experienced of 3,000 kilometers. This logistical
operators: the reactors had to be moved over hilly terrain, lifted using a portal stabilized with simplicity produced a considerable
guys and tailed with minimal space for the SPMTs and the tailing frame. saving for the client.
Highlight: Mammoet crew traveled back and forth between Highlight; was erected “in the air”. A temporary therefore first had to issue a special 8%
This job began in the Port of Windsor, located directly the Port of Windsor and the Suncor site as they In the third quarter of 2005, Mammoet structure was constructed to position the overload permit. In the standard procedure
across the Detroit River from the city of Detroit, where performed the load-outs, sea-fastenings, load-ins, brought its third Platform Twin Ring entire boom and back mast horizontally that was carried out, critical parts of the
a geared vessel delivered 44 process modules for the and site transport services. Containerized crane (PTC III) into operation. over a live pipe rack. Large mobile cranes structure were analyzed and the configuration
Suncor Refinery in Ontario, 100 kilometers further up. After the customary tests in the Netherlands, then lifted the boom/luffing jib and back mast was recalculated. Only when the manu
With two 12 axle line SPMTs, Mammoet unloaded the The offloading operations were a special challenge. the PTC III was immediately disassembled into the air in a truly spectacular manner. facturer had determined that the excess
modules from the ship and put them in temporary storage The narrow dock facilities extend out into the fast-flowing and transported to Brazil for its maiden weight would not cause any technical
at the port. Since it is not feasible to transport large St. Clair River and have few suitable mooring bollards. project. At the refinery in Cubatao, the crane The PTC III was used to replace the 654- malfunctions and safety was guaranteed
modules by road over long distances in Ontario, Mammoet To moor the barge rock-steady, Mammoet designed a and crew had to overcome another challenge tonne reactor head of the UFCC unit at the could written permission be given.
loaded them onto a 76-meter-long and 22-meter-wide complex system with on-shore mooring points. before tackling the first real job. Because Petrobras refinery. The additional weight of Replacing the reactor head took six weeks
barge 10 to 12 at a time. The dock’s 10% grade could have been an extra there was not enough space in the live refinery the rigging, block, spreader, etc. required for in total. The PTC was then also dismantled in
complication if not for the fact that SPMTs are ideally to erect the boom/luffing jib and back mast the lift meant the load eventually weighed the air.
SMPTs conquer ten percent slope suited to climbing such grades due to their superior from the ground upwards, part of the PTC 722 tonnes. The PTC’s manufacturer
The 44 modules reached their destination in four traction abilities. The modules were therefore offloaded
consecutive barge shipments while the tireless in a very expedient and professional manner.
c
Integrated logistical transport solutions
Coke drums moved by Mammoet mammoet
asia Location Sakhalin Island, off Russia’s eastern coast and north of Japan
Job Participating in preparations to construct a refinery from a local Mammoet base
Location Fort McKay, Alberta, Canada Challenge Difficult job in remote area
Job Transporting four 413-tonne coke drums using an 800-tonne gantry system and two 150-tonne climbing jacks
Challenge Preventing delays for the client through meticulous and thorough preparation of the transport schedule
The total convoy was over 200 meters long, almost 12 meters high and more than 10 meters
wide, so a significant part of the job was to scout and prepare the road. Several utility companies
were involved – all coordinated by Mammoet – to lift power lines, turn traffic lights, remove street
furniture and control traffic.
Supervising converging cargo flows
Once outside the city, the two trucks covered the route at two-day intervals in order to limit the
impact on highway traffic. Traveling at 30 km/h, a one-way trip took five days. Some passes over Location Gove, Australia
bridges were very close to the structures’ design limits. Once on site, the jacking crew took over Job Enlarging a bauxite refinery
Challenge Moving vertical 350-tonne tanks over a site with
and the empty vehicles returned to Edmonton to collect the next two drums. After insulation, the
slopes of up to 6%
drums have been lifted onto their foundations by Mammoet’s PTC crane, completing the
factory-to-foundation service.
Although many industry experts thought the transport schedule far too ambitious, Mammoet
lived up to its promises, to the clients benefit. Only one drum incurred a delay of one day when
the ambient temperature dropped below –35° Celsius, which was too cold for safe operations.
At such extremely low temperatures, hydraulic systems do not work properly, despite the use
of arctic hydraulic oil, and steel can become brittle.
Civil
Job Heaviest lift ever using a land crane
Challenge A Mammoet Sliding Gantry especially modified for this job
Highlight:
The North Gas Field was discovered on the
northeast coast of Qatar in 1971. Since the Experience in multi-modal transport by road, rail and water together with Mammoet’s thoroughness in a field that extends from handling heavy
1990s, the emirate has been developing all facilities for lifting, skidding and jacking heavy loads ensure Mammoet’s prefabricated elements such as concrete girders and steel structures
the industries involved in worldwide gas position as a full-service provider in the civil market. Mammoet crews that are assembled on site to constructing, relocating or dismantling
exports. This has had a major impact on manage all cargo handling from factory to foundation, with a combination buildings and industrial facilities.
Qatar’s economy and is creating many jobs of skill, professionalism and state-of-the-art equipment. The cases reflect
c
for Mammoet in this tiny state. It is working
chiefly on plants that liquefy LNG (Liquid
Natural Gas) before it is shipped. One of the
mammoet
projects being carried out here is the Oryx
project, a second generation LNG plant europe
that will become the world’s largest.
boom, a 15.4-meter jib and 2,600 tonnes thanks to its compact design, the location set up a temporary manufacturing facility.
Location Ras Laffan, Qatar of counterweight. Four 900-tonne strand in the middle of the plant posed no problem. Many prefab constructions are thus produced
Job Lifting heavy installations for various gas producers jacks (160 strands each) were attached to Other operations at the site could continue at yards and have to be transported. This final the traffic on this major highway in the west of northern end – was jacked up to the required
Challenge Smart use of state-of-the-art equipment the boom head and another four 600-tonne as usual. phase includes not only the transport but also the country as little as possible, the work was height for installation on the abutments.
strand jacks (144 strands) were fitted to the assembly and/or positioning of the carried out at night. The road was closed to all With the sun about to rise on the Sunday
the back mast. During the lifts a tailing construction. It inevitably has an impact on traffic at 9.30 p.m. and the first phase of the morning, the Mammoet crew lowered the
frame supported the base of the reactor traffic flows. To minimize the inconvenience, transport began. It consisted of the Mammoet curvaceous structure safely and precisely onto
as the stack moved into position along customers draw on Mammoet’s experience crew driving the bridge transversely from the its foundations. The client was satisfied and
and turnkey solutions for engineering, construction site along the A12 onto the highway. treated everyone to champagne as the first
logistics, route surveys, negotiations with local At about 1.00 a.m. the engines of the 40 axle cars once again raced past Zoetermeer and its
and political authorities and documentation. line SPMT were started and the 1,000-tonne new landmark: an elegant white construction
colossus slowly began to move. The wheels of designed by architect Edwin Megens.
Typical SPMT job the SPMTs then rotated longitudinally to the Mammoet’s nighttime activities were photo-
In Zoetermeer in the Netherlands, for example, road and the bridge was slowly moved to its graphed and recorded by hundreds, perhaps
Mammoet was engaged to place a complete, final destination. The procession passed a even thousands of spectators and the cameras
almost 140-meter-long cyclist and pedestrian railroad gantry, after which the bridge – of several TV stations and press photographers.
High in the sky bridge over the busy A12 highway. To disrupt with an additional 12 axle line SPMT at the
c
position in many
mammoet
markets, illustrates
americas we’re doing the right
thing”
Jan Kleyn
Managing Director,
Bone chilling Mammoet USA
Highlight: This work was carried out by a local contractor with the neces-
Move a complete steel processing plant (DRI plant) from sary expertise in dealing with these types of soil conditions.
Louisiana, USA, to Trinidad. That was the challenge that was After the permits were granted, the utilities relocated, and the
presented for Mammoet USA. Execution of this project started railroad crossing completed, loads of up to 1,100 tonnes could
with the preparation of a plan to split up the plant into modules. be moved down the heavy haul road, over the levee bridge,
This plan formed the basis for the transport plan and the choice to the seagoing barges.
of equipment for the relocation.
The Mississippi River posed another challenge. The varying water
Delivering 80 beer tanks in Seville The greatest challenge was the construction of a temporary levels restricted the opportunities to transport heavy loads onto
bridge over Highway 44 and the Mississippi River Levee, a lifeline the levee and the surrounding areas. Every ‘i’ had to be dotted
Location Seville, Spain in Louisiana’s complex infrastructure in the Mississippi delta. and every ‘t’ crossed if the seagoing barges were to be loaded
Job Transporting and installing 80 beer storage tanks ranging from 17 to 35 tonnes In addition, major utility lines had to be relocated and a busy rail- out in these narrow windows of opportunity. In close cooperation
Challenge Compensating for the very high center of gravity with special equipment road line had to be crossed. Mammoet was given responsibility with the client and all the other involved parties, the dismantling
for engineering and developing a plan that would be acceptable and shipping phase was successfully completed and was imme-
to all the relevant agencies and the local community. After several diately followed by a new phase: reassembly in Trinidad.
design changes, the solution that was finally agreed was of a Here, too, another challenge was waiting for Mammoet because
Highlight: magnitude never attempted before in the state. the ground conditions in Trinidad were very similar to those in
In Seville, Spain, Mammoet transported and installed Louisiana. A sizeable amount of site work was required before
eighty 17-35 tonne beer tanks of various diameters Unstable ground, restricting water level any equipment could be mobilized. The relocation of the DRI
and heights for a newly built brewery. There is virtually no stable ground in the Mississippi delta. plant required 2 XCC 2800, 72 axle lines SPMT, as well as jacking
The challenge in this project was formed by the tanks’ Ground surveys also found that transportation would only and sliding equipment. Overall, the entire project, including the
exceptionally high centre of gravity. For a secure and be possible if several layers of existing topsoil were first removed Trinidad operations, has been successfully completed.
safe operation, the six axle lines of SPMT that we and replaced with a specially-designed compactable fill.
used for the execution was fitted with a special frame
supplied by the client. They then drove underneath the
tank and chains were fixed to it to secure it on the
trailers. To lower the center of gravity on the transport
combination the trailers also carried about 25 tonnes
of steel ballast. Nevertheless, the tilt margins were very
small. The SPMTs therefore had to be maneuvered
very carefully when it was driven into the factory.
The tank was then positioned above the foundation
plates and installed just as carefully. The experienced
“You comply with crew successfully repeated the sequence of picking
up a tank, driving it to the factory, installing it on the
safety issues not foundations and driving the SPMTs out again about
eight times a day.
because the
management wants it,
but because you
Sliding a container crane
personally believe it is
Location Montreal, Quebec, Canada
mandatory to do” Job Relocating a container crane
Challenge Skidding operation on the edge of a quay
Bryan Cronie
Corporate QSE Director,
Mammoet Holding
Highlight:
Mammoet was contracted to relocate a container crane at the Port of Montreal. The crane had
recently been constructed to increase the handling capacity at the Termont Container Terminal.
The client had built the 900-tonne crane away from the quayside so that the construction work
would not disrupt the operation of the other cranes on the site. On completion, the crane had
to be moved a distance of about 100 meters to its final position on the quayside.
A 1,000-tonne skidding system was the best solution but an inspection of the jobsite found
there was not enough space between the edge of the quay and the crane to perform the
necessary jacking work. This challenge was solved by using a steel working platform that the
client had built in consultation with Mammoet. The relocation of the crane was then completed
very quickly and efficiently. Mobilization, equipment assembly, crane skidding and
demobilization back to the Cambridge yard were all accomplished well within one week.
Offshore
Lifting a 500-tonne jacket and placing it on a 1,500-tonne platform
Job
Challenge Combination of late award and reduced time window
then it is useless to
convince others.”
Mammoet’s activities in the offshore industry include the accurate and safe platforms almost to the point of completion just before their final position- Darren Adams
Managing Director,
c
execution of transport solutions, load-ins and load-outs, and the assembly ing at sea. The cases show how the offshore industry benefits in all kinds of
Mammoet UK
of very large and heavy items. The services Mammoet offers seamlessly ways from Mammoet’s special services and its ability to move and lift large
match the industry’s desire to assemble oil and natural gas production and heavy items at the yard.
mammoet
europe
c
The hinge point for the upending was on the edge of the Mammoet’s Heavy Lift Terminal in Schiedam,
floating GBS. To keep the base level end at the correct The Netherlands. With the help of a 650-tonnes crane
height despite tidal movements throughout the operation, and a 500-tonnes crane a crane was placed on the
mammoet
Mammoet’s computer controlled Ballasting System was upper deck of the “de Ruyter”.
installed on the GBS. Since the tidal range in Flushing americas
c
Location Amelia, Louisiana, USA
Job Loading out several modules of between 3,800 and 5,600 tonnes
Location Pasir Gudang, Malaysia
Challenge Bridging the height difference between the storage location and
the barge
mammoet Job Loading out a 2,500-tonne jacket
Highlight:
Mammoet loaded out a series of modules last year. Highlight: around midnight. The tide was much
The last three modules were part of the Atlantis semi The Geographe and Thylacine gas fields lower than predicted in the tide table
submersible. Ready for load-out at the yard in Amelia, lie 55 and 70 kilometers respectively owing to local channels. The load-out
USA, were the production module (4,800 tonnes), offshore from Port Campbell, Australia, began as planned but the strand jacks
the generation module (3,800 tonnes) and the compres- in the Otway Basin. The Otway jacket could not pull at full speed on account
sion module (5,600 tonnes). Mammoet used 192 lines was designed especially for these gas of the tidal variation. Furthermore,
of SPMT and Goldhofers at the site. fields. It weighs some 2,500 tonnes alternatively pulling and waiting for
and is over 100 meters long, nearly ballasting made the process a long and
A particular challenge was the modules’ location almost 30 meters high and 30 meters wide. tedious one. The crossover stage could
three meters above the ground but still 50 centimeters not start until about five o’clock the
lower than their position on the barge. The Mammoet The contract to load out this jacket, next morning. The Mammoet team
engineering department in Rosharon designed a load one of the biggest and heaviest in worked relentlessly throughout the
spreading arrangement on the trailers that would accom- the project, was awarded to Mammoet operation. Men in red overalls were
modate the height, the jacking and the different beam Singapore, which used two of popping up from under and over the
spacing under each module. This solution worked Mammoet’s 900-tonne strand jacks jacket, here and there on the barge,
excellently: the first module was loaded out one day for the operation. Ballasting services making sure that no detail was over-
ahead of schedule. The load spreading was reconfigured, were provided by a subcontractor with looked. In the end it was one of the
and the second module was jacked up and moved to the a team of Mammoet engineers monitor- smoothest load-outs ever. The client
bulkhead all in one day! The third module went equally ing and coordinating the process. was very impressed and satisfied,
fast. For the client, this meant the job was completed After the briefing, the load-out began as was the Mammoet team.
three days ahead of schedule.
Power
Highlight:
Mammoet was awarded the contract to
transport a 61-meter, 2,300-tonne jacket from
the jetty to an ocean-going barge. Mammoet
deployed two 900-tonne strand jacks with
two x 18 120-meter strands to carry out the
load-out in a two-phase skidding operation. Modules for power plants are highly specialized facilities that are manufac- tion, so that’s what Mammoet offers. These cases highlight several aspects
In the first phase, the jacket was pulled fifteen tured by just a few firms. In many cases, the heavy and outsized modules of Mammoet’s strong reputation in the power industry and its wealth of
meters to a location five meters from the edge need complex transportation to reach their destinations, be it by road, rail or experience in all segments, from fossil fuel and nuclear power plants to
of the quay; in the second phase, the jacket sea. For such demanding jobs, customers prefer an end-to-end, safe solu- facilities using sustainable energy sources such as wind.
was pulled from the quay onto the barge.
Loading the jacket onto the barge took about
c
six hours. The jacket had to be loaded while
the tide was rising, and for this reason the 500 km journey to the middle of a Scottish mountain
load-out began early in the morning. modules weighing between 220 and 350
The calculation of the necessary ballast in tonnes, the largest being 91 x 7 x 9 meters mammoet
europe Newcastle, United Kingdom; Cruachan, Scotland
Location
anticipation of the operation and the monitor- in size. These modules were transported from Job Transporting and installing two 115-tonne transformers
ing of the ballasting during the operation the construction site to the jetty and loaded Challenge The power station’s location demanded a unique design and transport solution
were also part of Mammoet’s job. The work onto two barges using 24 axle lines of SPMT.
also involved transporting three smaller
Highlight:
Scottish Power commissioned two 115-tonne transformers from
Nijmegen, the Netherlands. They were first carried by boat to
Mammoet’s Heavy Lift Terminal in Schiedam, where they were
transferred to a seagoing boat for the journey to Newcastle, UK.
14,000 tonnes on 32 skid shoes Upon arrival, the transformers were unloaded onto two 9 axle line
trailers and prepared for a 500-kilometer journey across the Scottish
Location Pasir Gudang, Malaysia Highlands, a rugged and unspoiled mountainous region.
Job Assisting in building a spar
Challenge Tried and tested skills prove themselves again The trip to their final destination, the Cruachan Power station, took two
days. Then came the most exceptional part of this job, the installation
of the transformers into a hydroelectric power station in the middle of
a mountain that could be accessed only via a specially-constructed
Highlight: one-kilometer tunnel.
At Pasir Gudang in southern Malaysia, Mammoet is helping to build a 14,000-tonne
spar as part of the Kikeh Spar project. The structure is similar to one Mammoet Impressive professionalism
Dubai loaded-out at Jebel Ali a year or two ago. The plan of the contractor and Mammoet devised to solve this
exceptional challenge was worked out in every detail. Preparations
Building the spar is the first assignment for the Kikeh Spar project. Mammoet is began after the design phase had been completed, two and a half years
supplying 32 skid shoes and the crew occasionally moves one of the spar sections before the actual transport operation. A 100% exact copy was made of
to the next location on the skid track. Beside the skid system Mammoet is supplying the transformers designed especially for this location in order to test the
craneage to assemble the spar segments. The towers are used to place the top installation process. Only when the test with this dummy was successfully
sections on the bottom sections. completed the design was approved and work could begin on building
the transformers themselves.
The yard operater, another manufacturer of offshore structures, is also located in
Pasir Gudang. Mammoet is providing craneage here for the assembly of the modules. On arrival at the power station the transformers were reloaded precisely
according to plan onto a Mammoet girder bed combination, which ferried
the cargo through the narrow tunnel. At the end of the tunnel the trailer’s
hydraulics were applied to place the transformers on a turntable. After
rotating the table 90 degrees, the transformers were skidded 50 meters
along a passageway. They were then turned again, skidded alongside
the foundations and jacked down into position.
Both transformers were installed in just five days.
c
A clearance of just five millimeters
mammoet Location Jebel Ali Port, Dubai
Highlight:
Mammoet was asked to replace a transformer at a
nuclear facility in Taft, Louisiana, west of New Orleans.
It was an exceptional challenge because, apart from
meeting the usual extremely strict requirements on
safety, personnel training/instruction/admission and
adherence to drawings and procedures for a nuclear
plant, the job had to be done during an outage.
This demanded meticulous planning and coordination.
Furthermore, the new transformer was slightly wider
than the old one so that the clearance when installing
it was just one inch on each side. What’s more,
the 286-tonne monster was delivered on the wrong
side of the Mississippi!
Car factory applies wind energy
Highlight: and an additional 4-bed-6 combination and a The transformer arrived at the Port of New Orleans on
Location Sunderland, United Kingdom A new rail connection being built in Rotterdam, 2-bed-4 combination on the first and second night the East Bank of the Mississippi River and Mammoet
Job Transporting and erecting six 55-meter-high wind turbines the Netherlands, will run partly underground respectively to carry the taller sections. Some had mobilized its Schnabel car for a direct discharge
Challenge Preparatory consultancy and execution in close association with the client through twin 6.5-meter-diameter single-track street furniture along the route had to be removed from the ship. After tie-down, the load broke all records
tunnels with a length of 2.4 kilometers. temporarily to create sufficient space for the on this rail/road bridge and gaining the clearances
This tunnel, which will be some 25 to 30 meters seven-meter-wide loads, and the roads were required to cross the river here cost the Mammoet rail Between moving the old transformer and placing
below ground level, is the first to be bored in temporarily closed to other traffic. The transports crew a great deal of negotiation and hard work. the new one, the Mammoet crew helped the customer
Highlight: an urban region. were accompanied by two exceptional convoy and another subcontractor install cooler panels and
A car manufacturer in Sunderland, UK, purchased vehicles with further assistance being provided by Helping the customer out associated steelwork. These parts are located behind
six 55-meter-high wind turbines for installation on-site The drill used to bore the tunnel was made in the police. The whole operation enjoyed a great Upon arrival, the transformer was skidded off the railcar the transformer and can only be reached when it is
to supply electricity directly to its factory. Mammoet Schwanau, Germany. From there, it was shipped deal of interest from the newspapers and national onto a double 10 axle line SPMT and then offloaded removed. It turned out that the contractor that was
UK was contacted to find the optimal solution for in sections to the Mammoet Heavy Lift Terminal in and regional TV stations. onto load spreading mats placed directly on the facility’s supposed to do the job did not have all the right
transporting the turbine parts from the storage area Schiedam, the Netherlands, where a PHB harbor parking lot. paperwork and people. The customer didn’t find that out
and erecting them at their locations. The client had crane loaded the sections onto trailers before they After an uneventful trip the sections, including the until it was just about to start work. To avoid losing time,
allocated specific time slots for the delivery of parts were transported in twelve special road convoys cutter head, cutter wheel, centre shield and trailing The actual exchange was performed a few months later. Mammoet helped out by using the crane intended for
and new cars. Erecting the wind turbines was not to the construction site in the Rotterdam area. shield, arrived at the site. There, a 500-tonne Due to very strict ground bearing limitations, a lot of the gantry setup and some additional rigging. This was
allowed to interrupt these slots and roads could not crane and Mammoet’s crew were waiting to steel had to be installed under the skid tracks. Since the a smaller job than those Mammoet’s crews normally
be closed during shift periods, so the Mammoet crew The transport took place during two consecutive unload the trailers. It then took two months entrance road was only wide enough for a double-wide carry out and very detailed in nature. All in all, it was a
had to work to a very tight schedule. nights, with three, four and five axle line trailers to assemble the drill. SPMT, the Mammoet crew loaded and offloaded the pretty complex job completed safely and on time.
transformers using their 450-tonne capacity gantry.
Before starting the work, Mammoet carefully studied
the locations and advised the client about what
would have to be done to erect the wind turbines.
The preparations, in combination with precise meas-
urements to ensure that none of the cranes’ outriggers
would be above the underground services, ensured
that the entire operation went ahead smoothly.
mammoet
americas
c Seven different clients on one site!
Location Becancour, Quebec, Canada Cold Boxes for a Cold City
Job Transporting and installing all a power plant’s heavy equipment
Location Sudbury, Ontario, Canada
Challenge Eight contracts for seven clients required outstanding coordination
Job Delivering, erecting, and installing the six largest items for cold boxes
at a new oxygen plant
Challenge Complex transport route by road and water, with several restrictions
Highlight: equipment operated on the site included a 450-tonne
At the Becancour industrial park approximately one hour Lift-n-Lock gantry system, a 500-tonne skidding system,
north east of Montreal a new 500 MW combined cycle a 400-tonne jacking tower, a Western Star prime mover Highlight: end of the 750-kilometer journey across
power plant is currently under construction. Mammoet and, during one peak busy period, an additional self- A major nickel mine in Sudbury, Ontario, built several lakes was no more than a rocky
is taking care of the transport and installation of all propelled conventional 12 axle line Scheuerle Intercombi a new oxygen plant. Oxygen plants typically beach with limited access. For the final
the plant’s heavy equipment. This comprises two transporter. One of the challenges was to skid the four require the installation of a “cold box”, stage, from Killarney to the site by road
combustion turbines, three large generators weighing HRSG stacks underneath a low pipe rack that bridged a large tower that separates air into its through a very rugged area, a structural
approximately 250 tonnes each, one steam turbine, the only road exiting the port facility. Mammoet relocat- two main gases: nitrogen and oxygen. consultant had to be engaged to analyze
sixteen heat recovery (HRSG) modules, four large HRSG ed each stack section under the pipe rack at a rate of the many bridges along the route.
stack sections, two auxiliary boilers, two steam drums, one per day. Mammoet delivered, erected, and installed Furthermore, the route could not accommo-
three large transformers, and a few miscellaneous items. the six largest items for this project. date more than three heavy-haul vehicles
To do so it had to overcome many logistical at the same time due to traffic congestion.
Unusually, construction of the plant was divided into challenges. The first was that the items came The six items were carried over these
several mechanical installation contracts: one for the from two different fabricator’s shops and two 100 kilometers three at a time in two
combustion turbines, one for the steam turbine, one for load-out quays. This meant they had to be separate trips by three transporters.
the heat recovery boilers, one for the auxiliary boilers, carried from the two locations several hun-
etc. Each contract had its own heavy equipment dred kilometers apart over the road from At the final destination Mammoet used a
transportation and lifting requirements. Mammoet bid the shops to the quays. Three items were CC 2500 crane to erect and position the
for all nine of these subcontracts, and was honored loaded onto a medium-sized barge at the equipment. Fitted with 72 meters of main
to be awarded no fewer than eight of them! first quay and three others at the second boom and 200 tonnes of superlift, the crane
Working on eight contracts for seven different clients quay. Owing to the size of the barge, it was a erected and positioned all six items in the
required outstanding coordination, if only because for very tight squeeze to fit all six items on it. course of one week. The total project took
most of the time just one 12 axle line SPMT was used to A larger barge, however, could not be used approximately one month.
transport most of the 33 heaviest items. Other interesting because the offloading site in Killarney at the
c
common sense. Highboy conquers the road to Kaeng Khoi
mammoet
You need it, just
asia Location Kaeng Khoi, Thailand
Transporting and installing turbines, generators, transformers and condensers for a 1,400 MW power plant
like daily food and Job
Challenge Transporting a 5.4-meter-high turbine over 77 bridges and through passages with 5.5-meter clearances
drinks.”
c
also one of Mammoet’s global clients. The most recent It may sound like a routine job but in the world of Challenge A number of height restrictions
contract to be won is to replace a steam turbine Mammoet each operation is designed, engineered and
generator in Wilmington, Delaware. To lift and transport checked individually. On this job, the TITAN tower was
the 165-tonne generator, Mammoet mobilized a TITAN the most economical solution for the client. The only mammoet
tower, four 100-tonne strand jacks, a skidding system, other viable solution to replace the generator was to middle east
12 axle lines of SPMT and a 450-tonne gantry system. cut a hole in the roof and then lift out the old generator
In the short course of three and a half weeks, the with a very big crane. It would take a crane such as
equipment was assembled, the old stator removed a PTC to accomplish this.
Highlight:
For the construction of the Dewa transformer station in Bukadra, Dubai,
Mammoet was awarded the contract to transport and install a total of four
transformers, each weighing 280 tonnes – and all within a 12-day period.
In addition, Mammoet was asked to transport two 55-tonne reactors during
the same timeframe.
Highlight:
A large power plant constructed in Shelburne, Ontario, has adorned the rural landscape
with 45 new wind turbines. These wind turbines, the first phase in the Melancthon Grey Wind
project, will produce 67.5 MW of electricity to power 50,000 homes. To erect the wind
turbines, Mammoet’s Cambridge office was contracted to dispatch a CC 2600 and a CC Turbo transport for turbine
2800. Mammoet also provided five hydraulic cranes, crane mats, and specialized rigging,
most of which was custom-designed and built specifically for this project. Jebel Ali, Dubai, UAE
Location
An interesting aspect of this project is the considerable cost saving for the client, which was Transporting and installing three 185-tonne turbines
Job
achieved by using two self-propelled transporters to move the cranes on the site over distances Challenge Do an afficient operation
of up to three kilometers. This strategic choice meant the road needed to be only five meters
wide in many areas. This saved costs that would otherwise have been incurred to widen the
road to 12 meters or to dismantle and reassemble the cranes in order to move them.
Mammoet has since been contracted to carry out lifting work in phase two of the Highlight:
Melancthon Grey Wind project. Starting in August, it will involve the erection of a further The Aweer power station in Dubai is being enlarged. As part of the job,
88 wind turbines. Mammoet Middle East is transporting and erecting three 185-tonne turbines .
The 66 kilometers from the Port of Jebel Ali, where the turbines arrived, to the
power station was covered in some four hours using a Cometto MX 12 lines.
At the site, the turbines were lifted from the platform trailer with the Lift-n-Lock
gantry. Since the trailer could not be positioned above the end position owing
to the height of the foundations, the suspended turbines had to be moved
sideways for 36 meters before they could be placed on the supports.
Operations at the site took just two hours. The safe and swift service here
could well count as the fastest operation ever accomplished.
Mammoet Salvage Bridge reconstruction helps New Orleans get back on its feet
Location New Orleans, Louisiana, USA
Mammoet Salvage B.V., a joint venture with various “Zeevang” was fitted with two Hitachi KH-300 crawler Job Repairing a bridge on a key highway into New Orleans
experts from the international salvage scene, is a new cranes. The tug “Groenland” accompanied the Challenge High tempo and far from ideal conditions in the wake of a hurricane
initiative to make more targeted use of Mammoet’s “Zeevang”. The steel plates were lifted with the help
comprehensive experience and expertise. It will adopt of steel plate grippers. Divers placed these grippers
an innovative, high-quality engineering approach that on the bottom of the harbour inside the sunken barge
unites Mammoet’s experience in heavy lifting and at a depth of 16 meters, where after the cranes lifted Highlight:
transport with specific salvage expertise. Operations the plates on deck of the “Zeevang”. In a week the Part of the only highway connecting New Orleans with the east and the A crew of between 10 and 15 people worked 24/7 in three day shifts
started in January 2006 and are managed by Fokko cargo was discharged from the barge. Afterwards the north is the ten-kilometer long Twin Span Bridge across Lake Pontchartrain. and two night shifts, using three pontoons, skidding and jacking equipment
Ringersma. His team members came from Wijsmuller barge itself had to be lifted, which was found to be in Hurricane Katrina had damaged the bridge so badly that it could not be and 4x10 self-propelled Goldhofer axle line. Sometimes, they were asked
Salvage, Smit Salvage and, of course, Mammoet. two pieces. On both sections, the divers installed used and New Orleans was locked in a corner. The Louisiana authorities to do the seemingly impossible but their professional attitude and knowledge
lifting chains through holes in the side of the barge. demanded that the bridge be repaired as quickly as possible. helped them do a very good job, to the great satisfaction of the governor
Mammoet Salvage has already executed their first Both sections of the barge were lifted by a floating of Louisiana and Mammoet’s client which.
contract for the removal of the inland push barge sheerleg. The sections have been placed ashore The bridge is made up of 872 prefab concrete parts, each weighing 290
“Thor” and its cargo of 340 steel plates in the Antwerp at a quay nearby. tonnes. 74 of them had to be completely replaced and 380 had to be
port area. The weight of the steel plates is nearly repositioned. Mammoet was contracted to lift and position all the parts.
3,000 tonnes (eight tonnes each) and with a dimen-
sion of 12 x 4,5 meters. Whilst waiting for the locks
in the port, the barge “Thor” developed a crack in
the hull and sank within a matter of minutes.