Strategies For Well-Insulated Airtight Buildings: CIBSE TM29: 2002

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 48

HVAC strategies for

well-insulated airtight buildings

CIBSE TM29: 2002

The Chartered Institution of Building Services Engineers


222 Balham High Road, London SW12 9BS
The rights of publication or translation are reserved.

No part of this publication may be reproduced, stored in a


retrieval system or transmitted in any form or by any means
without the prior permission of the Institution.

©January 2002 The Chartered Institution of Building Services


Engineers London

Registered charity number 278104

ISBN 1 903287 18 9

This document is based on the best knowledge available at the


time of publication. However no responsibility of any kind for
any injury, death, loss, damage or delay however caused
resulting from the use of these recommendations can be
accepted by the Chartered Institution of Building Services
Engineers, the authors or others involved in its publication. In
adopting these recommendations for use each adopter by
doing so agrees to accept full responsibility for any personal
injury, death, loss, damage or delay arising out of or in
connection with their use by or on behalf of such adopter
irrespective of the cause or reason therefore and agrees to
defend, indemnify and hold harmless the Chartered Institution
of Building Services Engineers, the authors and others
involved in their publication from any and all liability arising
out of or in connection with such use as aforesaid and
irrespective of any negligence on the part of those
indemnified.

Note from the publisher:


This publication is primarily intended to provide guidance to
those responsible for the design, installation, commissioning,
operation and maintenance of building services. It is not
intended to be exhaustive or definitive and it will be necessary
for users of the guidance given to exercise their own
professional judgement when deciding whether to abide by or
depart from it.

Layout and typesetting by Jackie Wilson

Printed in Great Britain by Page Bros. (Norwich) Ltd., Norwich,


Norfolk, NR6 6SA
Foreword
This publication reports the results of a major Partners in Innovation project that studied
the impact of high performance envelopes on the servicing strategy for office-type
buildings. The work was based on a range of detailed computer modelling techniques
supported by extensive climate chamber testing. The results suggest that there are
significant commercial benefits to be had from high performance envelopes. Equivalent
comfort conditions, significantly reduced operating and management costs and improved
space utilisation are achievable at costs no greater and possibly slightly less than
conventional air-conditioning systems. Although these ideas have not yet been fully
tested in practice, experience gained from the closest current exemplar, the Elizabeth Fry
building at the University of East Anglia, adds credibility to the conclusions presented.

Improved envelope standards will be required by the changes to Part L of the Building
regulations that come into force in 2002. This document demonstrates how such changes
to envelope standards can open up new opportunities for innovative design solutions that
are cost effective and make a major contribution to the wider sustainability agenda.

Steve Irving
Principal author

Acknowledgements
The work leading to the production of this publication was carried out as a Partners in
Innovation project co-ordinated by Oscar Faber. The funding provided by the
Department of Trade and Industry is gratefully acknowledged. The contributions of the
other project partners are also gratefully acknowledged. The project partners and their
representatives on the steering group are listed below.

Oscar Faber Group Ltd. S Irving, Q Babcock, A Wilson


Building Research Establishment Ltd F Alamdari, D Butler, A Perry
BSRIA Ltd. A Martin
Building Sciences Ltd. S Borland
CIBSE D Braham
Department of Trade and Industry G Henderson
Flomerics Ltd. M Seymour, S Somarathne
IPPEC Systems Ltd. M Namih
Klima-Therm (Distribution) Ltd. G Lovell
Pilkington plc R Wilberforce, J Bradshaw
Trox (UK) Ltd. A Green, F Tarada
SAS International Ltd. D Wisely

In addition to the members of the project partners listed above, thanks are also due to J
Lawrence (Sampson Windows Ltd.) and D Wadham (Franklin+Andrews), who provided
useful information for this publication. The measurement and analysis work that
provided the information on which this document is based was carried out by Quentin
Babcock, David Butler, Arron Perry, Mark Seymour and John Bradshaw.

The authors are also thankful to the CIBSE referees who provided a very thorough and
helpful review of the draft document.

This document is published with the consent of the Department of Trade and Industry,
but the views expressed are not necessarily accepted or endorsed by the Department.

Principal authors
S Irving (Oscar Faber)
S Borland (Building Sciences)
Contents
1 Introduction 1
1.1 Market drivers 1
1.2 Sustainability indicators 2

2 Impact of advanced envelopes on HVAC requirements 3


2.1 Applicable building types 3
2.2 The building in winter 4
2.3 The building in summer 9
2.4 Achieving the required window performance 12
2.5 Achieving the required fabric performance 14

3 HVAC systems in combination with advanced envelopes 20


3.1 Changeover strategies 21
3.2 Simplified control 22
3.3 Central plant options 23

4 Performance estimates 25
4.1 Comfort 26
4.2 Energy costs/carbon emissions 26
4.3 Building costs 27
4.4 HVAC costs 27
4.5 Maintenance costs 28
4.6 Whole-life cost 28

5 Summary and design checklist 28

References 29

Appendix A1: Modelling methods 30


1

Heating, ventilation and air conditioning


strategies for well-insulated airtight buildings

1 Introduction 1.1 Market drivers

This publication explores the potential for high performance The design strategy presented represents a significant shift
building envelopes to simplify the design and operation of from current design norms. Despite this, there are market
HVAC systems. The keys to such high performance envelopes trends that should encourage the adoption of the approach.
are windows with low U-values and good solar protection,
coupled with good structural airtightness. These features are 1.1.1 Part L of the Building Regulations
readily attainable at marginal cost through careful design and
construction. Indeed, industry will be driven in this direction The 2002 edition of Part L of the Building Regulations(1)
by changes in the 2002 edition of Part L of the Building requires designers to make significant changes to current
Regulations(1). The practical achievement of high perfor- design norms. Key features include:
mance envelopes* can deliver the following commercial
benefits: — significant improvement in envelope standards,
including provisions to control solar overheating
— Eliminate the need for perimeter heating†,
plus and to obtain reasonable standards of airtightness
enable significant reductions in the installed
capacity of heating and cooling plant. This will — minimum efficiency standards for heating systems
reduce the capital costs for HVAC plant.
— minimum efficiency standards for air conditioning
— Free up valuable perimeter space in addition to and mechanical ventilation systems based on limit-
saving some distribution and plant room space by ing the installed input power of equipment.
eliminating perimeter heating. This will add sig-
nificant commercial value to the scheme. The design approach propounded herein takes the envelope
standards a little in advance of the standards in the 2002
— Allow simplification of the controls installation
Approved Document L(1), particularly in terms of window
and strategy, again reducing costs but also improv-
standards and airtightness. This results in low heating
ing manageability and maintainability.
demands, allowing heating systems to operate at low water
— Enable HVAC systems to operate at very high temperatures, facilitating very high efficiency systems.
efficiencies, thereby resulting in low operating Through good solar protection of glazed areas, installed
energy consumption. chiller capacities will also be significantly reduced. Cooling
— Improve the investment profile: the envelope has a systems can then similarly operate at higher water temp-
longer service life than the HVAC plant, so the eratures, allowing increased coefficient of performance (CoP)
investment shifted from savings in plant to for the chiller and substantial opportunities for free-cooling.
additional cost in the envelope can be amortised This publication therefore offers an effective solution to the
over a longer period, generating further indirect design challenge presented by the 2002 Part L; indeed, it
financial benefit. enhances and ‘future-proofs’ the design against proposed
further tightening of the standards.
— Provide good comfort: climate chamber tests
coupled with detailed computer modelling work
suggest that even with significant areas of glazing, 1.1.2 Climate change levy
good year-round comfort can be maintained.
In April 2001, the climate change levy was introduced,
This publication outlines the evidence for this approach thereby increasing the energy costs for business and
based on the results from a comprehensive series of climate industry. Given the increasing concerns over climate
chamber tests and a range of detailed computer modelling change, the impact of this levy is likely to increase with
studies. Real buildings adopting all the concepts proposed time. There is, therefore, an increasing business incentive
have yet to be constructed; the closest current exemplar is the to reduce energy costs. The approach proposed here offers
Elizabeth Fry building at the University of East Anglia, substantial reductions in energy use, whilst retaining high
Norwich. The PROBE report(2) records both excellent energy standards of occupant comfort. These benefits are achieved
and occupant satisfaction ratings for this building, giving at costs no greater, and potentially somewhat less, than
added confidence to the conclusions presented here. current norms. It also facilitates the use of low capacity but
high efficiency equipment; equipment that may well
qualify for enhanced capital allowances.
* As detailed in later sections, the achievement of high performance
envelopes requires attention to design details and construction practice.
Without such careful attention at all stages of construction, the simpler 1.1.3 Lower cost but improved quality
systems proposed will not deliver the required performance.
† This is only practical for sealed buildings with winter mechanical A major challenge facing the industry is to reduce
ventilation; natural ventilation/mixed mode may be possible in warmer construction costs by 30% whilst improving service to
weather, but any openable window needs to seal well on closure for this clients. The design concepts outlined in this document
to work effectively in winter. should make a significant contribution to achieving this
2 HVAC strategies for well-insulated airtight buildings

goal. Initial construction costs may well be reduced, but for truly sustainable buildings (5). Sustainability has a
another important aspect is that the cost distributions will number of interlinking themes, and it is believed that the
change. More money will go into the elements with the proposed design concept scores highly in all areas.
greater service life (i.e. the fabric), and less into the elements
that need more frequent replacement (either as a result of
normal wear and tear, or through a new fit-out following a 1.2.1 Environmental
change in occupier requirements). The approach, therefore,
offers a more robust and enduring investment strategy. 1.2.1.1 Carbon emissions

The strategy offers substantial whole-life cost benefits (see Concern over climate change is a significant policy driver,
section 1.2) and so will benefit from the increasing interest and so operating carbon emissions* are a significant design
in whole life costs (3). Indeed, it is now a requirement of issue. For office-type buildings, the ECON 19 (6) data set
public sector purchasers that they move to whole-life cost gives valuable bench marks for ‘typical’ and ‘good practice’
based procurement (4). As detailed later, the degree of standards†. It is always difficult to compare design predic-
comfort and operating cost delivered through this approach tions with actual operating performance but so as to give an
will also add to the quality of the building. indication of the expected level of performance, Figure 1.1
shows a comparison between the ECON 19 data and the
performance which it is expected can be achievable through
1.1.4 Flexibility and adaptability high performance envelopes. The ‘A/C’ buildings are
comfort cooled while the ‘nat vent’ are naturally ventilated.
Flexibility and adaptability are essential elements of a The strategy presented in this publication provides comfort
building that is to be capable of meeting varying needs over cooling, giving comfort performance equivalent to the ‘A/C’
its design life. High performance envelope design reduces type but with carbon emissions reduced by 40% or more
perimeter loads for heating and cooling, such that different from good ‘A/C’ standards.
zones have comparable loadings and servicing needs.
1.2.1.2 Use of materials
1.1.5 Integrated approach
Sustainability is also about efficient use of materials and
The benefits of an integrated approach to design and resources. High performance envelopes help also in this
construction are recognised by many. The technical respect. Investment is transferred from (relatively) short-
concepts presented here are dependent on the realisation of lived plant into longer life fabric measures; measures that
such integration. The success of the HVAC strategy relies on also need little maintenance. It is important to realise that
the effectiveness of the envelope in terms of insulation, although HVAC plant has an expected service life of say 15–20
airtightness and solar protection. These issues are often at years, plant (especially terminal equipment) is often removed
the boundaries between the members of the design team and scrapped as part of a new fit-out well before the end of its
and the contractor. It is therefore essential that responsibil- useful life. A high performance envelope is much more likely
ity for these issues is clearly identified, with all the team to fulfil its service life than is the M&E equipment.
working together to deliver the required objective. The
client has a particular responsibility to ensure testing of the Another aspect of the use of materials is that of embodied
envelope as part of the total commissioning process — the energy. At the current state of knowledge, this is difficult to
envelope performance is as much part of the HVAC strategy quantify. However, in terms of the main areas of enhanced
as the boiler or the chiller plant. envelope design, significant overall performance improve-
ments can be obtained with few additional materials. For
example:
1.2 Sustainability indicators — The improvement in window U-values can largely
be achieved through the use of selective glass
In order to assess the proposed design concepts, it is coatings. Research into the application of such
necessary to benchmark performance against a reference coatings to housing has demonstrated that the
building typical of current good practice. The strategy is lifetime CO2 and energy savings are several hundred
offered as a potentially significant contributor to the drive times larger than the extra embodied CO2 /energy (7).
— Improved airtightness is achieved more through
TM29 strategy
careful design details and construction practice than
through the use of substantial additional materials.
Nat.vent. (good)
1.2.2 Economic
Nat.vent. (typical)
Economic indicators are extremely important to the con-
struction industry. Traditionally, designs have been driven
A/C (good)

* The data presented here are given in terms of emissions of carbon, rather
A/C (typical) than carbon dioxide, since the former is the preferred unit for the
government’s climate change programme.
0 10 20 30 40
† ECON 19 gives the CO2 emissions in terms of carbon equivalent to be
Carbon emission / (kg/m2) per annum
consistent with the units used by the government’s climate change
Figure 1.1 Relative operating carbon emissions programme (1 kg CO2 emissions is equivalent to 0.273 kg carbon).
Impact of advanced envelopes on HVAC requirements 3

by considerations of first cost, but there is increasing 2 Impact of advanced


emphasis on whole-life costs and ‘soft issues’ such as the effect
of thermal comfort on productivity. The design approach envelopes on HVAC
proposed here is likely to outperform conventional designs requirements
on all fronts, as detailed in the following subsections.
This section details the way that the use of advanced
building envelopes change the basis on which HVAC systems
1.2.2.1 Initial cost and value
need to be designed. Additional guidance on the design of
ventilation and air conditioning systems can be found in
As detailed elsewhere, initial costs are likely to be lower, CIBSE Guide B2 (8).
with the cost distribution also being shifted from the plant
to the longer service life envelope. Further, value is added to
the building through increased usable space and improved 2.1 Applicable building types
space flexibility. The elimination of the perimeter heating
may well save installation time, and perhaps thereby This publication concentrates on issues concerning the
accelerate the contract programme. interaction between the envelope and the HVAC system. It
therefore relates to the design of the perimeter zone
(typically to a depth 6 m from the façade). The approach
1.2.2.2 Operating and maintenance costs described can be used for both shallow or deep plan
buildings, since the servicing of internal zones is relatively
Energy consumption is substantially lower than a traditional straightforward (gains are much more constant with both
fan coil system for an equivalent level of comfort (see section time and orientation) and can therefore be considered
1.2.1.1). This is likely to cut £3–£4/m2 per annum from fuel independently.
costs relative to ECON 19 type 3 good practice (with perhaps
double that from typical practice performance). The main issue that needs to be considered is the level of heat
gains into the perimeter zone. If the building is too shallow
in plan, the perimeter zone may be less than 6 m and the solar
Further, the adoption of simpler concepts and a reduction in gain through the windows will have to be averaged over a
the number and complexity of the electromechanical narrower depth. This will increase the solar cooling load per
controls will ease the demand on facilities management. The unit floor area such that control of summer overheating
elimination of conflict between heating and cooling systems becomes more difficult. Similarly, if the perimeter is very
and the reduction in diversity should lead to reduced wear narrow, local occupant density may be less than in a more
and tear and consequent plant maintenance requirements. conventional space, thereby limiting the free heat gains
required to offset the heat losses in winter.
Reconfiguring of internal partitions as a result of space
reorganisation should also be simplified, since there is no It should be noted that eliminating perimeter heating
need to ensure integration with the perimeter heating system. would not be possible if ventilation is provided by openable
windows or ventilators in winter. In warmer weather, it
may be possible to use natural ventilation as part of a
1.2.3 Occupant satisfaction and productivity mixed-mode strategy, but this would require windows that
seal well on closure to keep infiltration losses and draughts
The analysis presented later (see sections 2.2–2.3) illustrates within acceptable limits.
that the design concept can provide average comfort condi-
tions on a par with a 4-pipe fan coil air conditioning system. The following analyses focus on the situation in a typical
The careful detailing and construction of a high performance perimeter zone. Designers should always check the applicability
envelope will deliver additional benefits in terms of reduced of the following data to their own project details.
local discomfort associated with drafts or cold bridging. The
approach eliminates the compromise between comfort and 2.1.1 Reference data
carbon emissions that has been the subject of much debate in
recent years. For example, naturally ventilated buildings can The design analysis presented herein took as its reference
deliver significant reductions in summertime energy use, but envelope specification the U-values given in Table 2.1. For
the strategy can be fragile and may result in periods of sub- comparison, the standards defined in the 2002 Approved
optimal comfort at extreme weather conditions. Fully air Document to Part L are also shown.
conditioned buildings can deliver year-round comfort, but
the cost and carbon impact can be high. The approach It can be seen that the wall and window U-values are in
proposed here offers optimal thermal comfort and very low advance of the standards for the 2002 changes to Part L, but
energy use, summer and winter. The impact of high
standards of thermal comfort and the general quality of the
building on staff morale and productivity should not be Table 2.1 Comparison of U-values
underestimated, especially when the annual cost of
Element U-values (W/m2·K)
occupants’ salaries is compared with other operating costs. Reference envelope 2002 Part L standards
Walls 0.3 0.35
Radiant panels combined with displacement ventilation
are an appropriate HVAC system for buildings with high per- Windows 1.0–2.0 2.0–2.2
formance envelopes. The low-noise and good air quality Roof 0.3 0.25
characteristics of such systems can provide added user Floor 0.3 0.25
benefit.
Impact of advanced envelopes on HVAC requirements 3

by considerations of first cost, but there is increasing 2 Impact of advanced


emphasis on whole-life costs and ‘soft issues’ such as the effect
of thermal comfort on productivity. The design approach envelopes on HVAC
proposed here is likely to outperform conventional designs requirements
on all fronts, as detailed in the following subsections.
This section details the way that the use of advanced
building envelopes change the basis on which HVAC systems
1.2.2.1 Initial cost and value
need to be designed. Additional guidance on the design of
ventilation and air conditioning systems can be found in
As detailed elsewhere, initial costs are likely to be lower, CIBSE Guide B2 (8).
with the cost distribution also being shifted from the plant
to the longer service life envelope. Further, value is added to
the building through increased usable space and improved 2.1 Applicable building types
space flexibility. The elimination of the perimeter heating
may well save installation time, and perhaps thereby This publication concentrates on issues concerning the
accelerate the contract programme. interaction between the envelope and the HVAC system. It
therefore relates to the design of the perimeter zone
(typically to a depth 6 m from the façade). The approach
1.2.2.2 Operating and maintenance costs described can be used for both shallow or deep plan
buildings, since the servicing of internal zones is relatively
Energy consumption is substantially lower than a traditional straightforward (gains are much more constant with both
fan coil system for an equivalent level of comfort (see section time and orientation) and can therefore be considered
1.2.1.1). This is likely to cut £3–£4/m2 per annum from fuel independently.
costs relative to ECON 19 type 3 good practice (with perhaps
double that from typical practice performance). The main issue that needs to be considered is the level of heat
gains into the perimeter zone. If the building is too shallow
in plan, the perimeter zone may be less than 6 m and the solar
Further, the adoption of simpler concepts and a reduction in gain through the windows will have to be averaged over a
the number and complexity of the electromechanical narrower depth. This will increase the solar cooling load per
controls will ease the demand on facilities management. The unit floor area such that control of summer overheating
elimination of conflict between heating and cooling systems becomes more difficult. Similarly, if the perimeter is very
and the reduction in diversity should lead to reduced wear narrow, local occupant density may be less than in a more
and tear and consequent plant maintenance requirements. conventional space, thereby limiting the free heat gains
required to offset the heat losses in winter.
Reconfiguring of internal partitions as a result of space
reorganisation should also be simplified, since there is no It should be noted that eliminating perimeter heating
need to ensure integration with the perimeter heating system. would not be possible if ventilation is provided by openable
windows or ventilators in winter. In warmer weather, it
may be possible to use natural ventilation as part of a
1.2.3 Occupant satisfaction and productivity mixed-mode strategy, but this would require windows that
seal well on closure to keep infiltration losses and draughts
The analysis presented later (see sections 2.2–2.3) illustrates within acceptable limits.
that the design concept can provide average comfort condi-
tions on a par with a 4-pipe fan coil air conditioning system. The following analyses focus on the situation in a typical
The careful detailing and construction of a high performance perimeter zone. Designers should always check the applicability
envelope will deliver additional benefits in terms of reduced of the following data to their own project details.
local discomfort associated with drafts or cold bridging. The
approach eliminates the compromise between comfort and 2.1.1 Reference data
carbon emissions that has been the subject of much debate in
recent years. For example, naturally ventilated buildings can The design analysis presented herein took as its reference
deliver significant reductions in summertime energy use, but envelope specification the U-values given in Table 2.1. For
the strategy can be fragile and may result in periods of sub- comparison, the standards defined in the 2002 Approved
optimal comfort at extreme weather conditions. Fully air Document to Part L are also shown.
conditioned buildings can deliver year-round comfort, but
the cost and carbon impact can be high. The approach It can be seen that the wall and window U-values are in
proposed here offers optimal thermal comfort and very low advance of the standards for the 2002 changes to Part L, but
energy use, summer and winter. The impact of high
standards of thermal comfort and the general quality of the
building on staff morale and productivity should not be Table 2.1 Comparison of U-values
underestimated, especially when the annual cost of
Element U-values (W/m2·K)
occupants’ salaries is compared with other operating costs. Reference envelope 2002 Part L standards
Walls 0.3 0.35
Radiant panels combined with displacement ventilation
are an appropriate HVAC system for buildings with high per- Windows 1.0–2.0 2.0–2.2
formance envelopes. The low-noise and good air quality Roof 0.3 0.25
characteristics of such systems can provide added user Floor 0.3 0.25
benefit.
4 HVAC strategies for well-insulated airtight buildings

Table 2.2 Range of internal gains examined 15


Gain Winter Summer Conventional TM29 strategy
10
10–20 m2/person 7–10 m2/person

Ventilation
Occupancy

Infiltration
Window
Lights 10 W/m2 (of which 10 W/m2 (of which 5

Wall
6.5 W/m2 was seen as a 6.5 W/m2 was seen as a

Loads / (W/m2)
gain to the space) gain to the space) 0

People

Equipment

Lights

Net
Small power 6–12 W/m2 15–25 W/m2
–5

are slightly less demanding for roofs and floors. The better –10
standards required for roofs and floors will improve the
performance of ground and top floor zones compared with –15
the results given in the following sections.
–20
An air leakage index standard of 5 (m3/h)/m2 @ 50 Pa was Figure 2.1 Winter energy balance
set, which is significantly in advance of the standard given
in the 2002 Approved Document L, but is in line with the amounts of localised heating may be required in corner
good practice recommendations of TM23 (9). rooms with more than one external surface.

The reference internal gains assumed for the space are Traditionally, perimeter heating has been installed to fulfil
considered typical of modern offices. For the winter a number of requirements. The way these requirements
analyses the loads were also varied to be on the low side of change with the use of high performance envelopes is
normal; for the summer tests the gains were varied from discussed in the following sub-sections.
typical to high for both occupancy and small power loads.
The data are summarised in Table 2.2.
2.2.1.1 Maintaining internal temperatures

2.2 The building in winter With a high performance envelope, moderate levels of inter-
nal gain are sufficient to offset perimeter losses, even during
2.2.1 Elimination of perimeter heating design weather sequences. Figure 2.1 compares the typical
balance of gains and losses in an office-type building
A key thesis of this publication is that perimeter heating is designed to standards typical of 2000 practice, and those
unnecessary in well-insulated airtight buildings (equipped proposed in this publication. The differences between the
with mechanical ventilation in winter). The elimination of specifications for the two sets of results are summarised in
perimeter heating can have significant commercial implica- Table 2.4. The last pair of bars in Figure 2.1 shows the net
tions. First, there is the direct cost saving of the terminal units gains to the space.
(equipment and installation) and the associated distribution
system. Secondly, but perhaps more significantly, it frees The conventional design shows a significant net heat loss,
valuable perimeter space and enables more flexible partition- whereas the high performance envelope shows a significant
ing arrangements. In city centre locations, where space is at a gain, even without taking any beneficial winter solar gain
premium, this can add significant value to the project. The into account. Consequently, in a building with typical
window U-value is the critical factor as far as achieving the occupancy and with a high performance envelope, the role
required insulation performance is concerned. It should be of the heating system becomes one of ensuring the building
stressed that the required window standards do not represent is up to temperature at the beginning of occupancy, not
premium products. Indeed, as indicated in Table 2.3, the target maintaining it once occupancy has started.
overall window U-values (1.5–2.0 W/m2·K) are required as
minimum standards in many European countries.
Table 2.4 Comparison between specifications for conventional and
‘TM29’ designs
It should be noted that heating is still required for pre-heat
purposes, but this can be achieved without recourse to a Parameter Conventional design TM29 design
separate, specific perimeter heating system (see section External design temperature (°C) –3 –3
3.1.1). It should also be emphasised that at design
conditions and dependent on the degree of glazing, small Internal design temperature (°C) 21 21
Wall U-value (W/m2·K) 0.45 0.30
Table 2.3 Window U-values required in European countries Window ratio in external wall (%) 50 50
Country U-value standard Window U-value (W/m2·K) 2.8 1.5
(W/m2·K)
Occupant density (m2/person) 12 12
Austria 1.9
Equipment gain (W/m2) 10 10
Denmark 1.8
Lighting gain (W/m2)* 6.5 6.5
Finland 1.4*
Infiltration (ACH) 0.5 0.15
Netherlands 1.2*
Ventilation rate (ACH) 3 3
Norway 1.6
Ventilation supply temperature (°C) 19 19
Russia 1.8
* proposed * Lighting load 10 W/m2, but 35% is removed via air-handling luminaires
Impact of advanced envelopes on HVAC requirements 5

2.2.1.2 Control of cold radiation 8

In many current buildings, perimeter heating is provided

Radiant assymetry / K
to ensure local comfort rather than to maintain overall 6
internal temperatures. Because of the relatively lower
thermal performance of the window, glass surface 4
temperatures can become quite low, creating local
discomfort problems with radiant asymmetry. CIBSE
Guide A(10) suggests that radiant asymmetry from a cool 2
wall should be limited to 10 K. Figure 2.2 shows the radiant
asymmetry for a 50% glazed façade with a window of U- 0
value 2.0 W/m2·K. This analysis (based on the work of 0 0·5 1 1·5 2 2·5
McIntyre(11)) indicates that, even quite close to the window, Distance from window / m
the radiant asymmetry is significantly less than this
limiting value. This means that, provided the building is Figure 2.2 Radiant asymmetry
up to temperature at the beginning of occupancy, heating is
not required to offset radiant asymmetry.
3·0

2.2.1.3 Control of downdraughts 2·8

downdraught / (W/m2·K)
2·6
U-value to avoid
To ensure comfort at the perimeter, heating may also be
2·4
provided to offset the effects of downdraughts. With high
performance windows, these effects can be effectively elim- 2·2
inated without the need for any perimeter heat. Figure 2.3 2·0
shows the results of a simplified analysis based on the work
of Heiselberg (12) giving the approximate glazing U-value 1·8
required to minimise the effects of downdraught. 1·6
1·4
It should be noted that, as far as downdraught is concerned, 0·8 1 1·2 1·4 1·6 1·8 2
it is the centre-pane U-value rather than the whole window Glazing height / m
U-value that is more important. This is because it requires
significant areas of unobstructed cool surface to develop the Figure 2.3 U-value to avoid downdraught
convection current, and it is the glass rather than the frame
that provides such a surface. Currently, whole window
performance is limited by the frame technology rather than shown as a function of mean room dry resultant temperature
the glass; very low-emissivity coatings (ε ~0.02) can give for many tests covering different window sizes, internal loads,
centre-pane U-values as low as 1.0 W/m2·K for a double- ventilation rates and target room temperatures. The results
glazed unit filled with argon. Thus available glazing clearly show that perception of comfort is dominated by the
technologies can minimise downdraughts, even with average dry resultant temperature of the room. The effects of
glazing approaching full height in typical office type cold radiation and downdraught from different window
accommodation. configurations result in virtually insignificant variations
around the trend line. This suggests that local effects near the
window are largely irrelevant within the range of window
2.2.2 Detailed assessment of comfort configurations tested. The ASHRAE comfort zone is defined
as less than 20% people dissatisfied, corresponding to a PMV of
In order to validate the assertions developed in section 60.85, and so it can be seen that all test conditions (with PMVs
2.2.1, a substantial amount of climate chamber testing and ranging from –0.3 to +0.25) are well within what might
modelling has been carried out (see appendix A). reasonably be desired. Indeed, thermal neutrality could be
achieved for all conditions simply by adjusting the mean
2.2.2.1 Climate chamber tests room dry resultant temperature to around 21 °C.

The testing concentrated on establishing the relationship


between window size/U-value and comfort conditions in the
absence of any heating other than that due to the internal 0·3
Predicted mean vote (PMV)

gains in the space. Four window sizes were investigated (1.2, 0·2
1.5, 1.8 and 2.8 m high) in a room with a floor to ceiling height
0·1
of 2.8 m. Traverses of temperatures (air and globe) and air
speed were concentrated in the zone within 1.1 m of the 0
window, and the ISO 7730 (13) equations used to combine –0·1
these individual measurements as a means of predicting
comfort. –0·2
–0·3
The detailed results can be distilled into Figure 2.4. This
shows the predicted mean vote (PMV) at a seated head height –0·4
19·5 20 20·5 21 21·5 22 22·5
of 1.1 m and at a point only 300 mm from the window. The Mean temperature / °C
calculations were based on normal winter clothing (i.e. 1.0 =
clo) and normal sedentary activity (i.e. 1.2 = met). The PMV is Figure 2.4 PMV as function of mean dry resultant temperature in room
6 HVAC strategies for well-insulated airtight buildings

Figure 2.5 Iso-surfaces of 0.1 m/s; 1.8 m window, U = 1.5 W/m2·K, Figure 2.7 Iso-surfaces of 0.1 m/s; full height glazing, U = 1.5 W/m2·K,
constant cold conditions outside realistic design consideration

Three primary geometries were considered — i.e. 1.2 m,


1.8 m and full-height window sizes — with each case
analysed for window U-values of 1.5 and 2.0 W/m2·K. The
results demonstrate that the downdraught does not
penetrate significantly into the occupied zone, even with
full height glazing. In fact, apart from the additional
cooling effect generated, the downdraught tends to improve
the environment by reducing vertical temperature
stratification. Figures 2.5–2.7 show iso-surfaces encapsulat-
ing regions that have velocities higher than 0.1 m/s. The
surfaces are coloured according to the temperature of the air
at the edge of the high velocity region. The temperatures
vary from simulation to simulation, since the increasing
heat loss associated with larger window areas or higher U-
values reduces the average temperature in the room for the
Figure 2.6 Iso-surfaces of 0.1 m/s; full height window, U = 1.5 W/m2·K,
same air temperature supply and heat dissipation rates in
constant cold conditions outside
the space. As can be seen from Figures 2.5 and 2.6, even for
The fact that comfort is dominated by mean room tempera- the extreme conditions of constant outdoor conditions of
ture is further confirmed by the fact that PMV does not vary –5 °C, these ‘higher’ velocities are contained within areas
significantly with distance from the window over the range close to the glazed walls, the supply air diffusers (a thin
tested (0.3–1.2 m). There is a tendency for the PMV to be layer near the floor) and the plumes from the equipment
consistently lower at ankle height than at seated head height and occupancy heat sources. Figure 2.7 shows that the
by between 0.1 and 0.2, although much of this is probably extent of the high velocity regions are similar for the more
due to the effect of the floor-mounted swirl diffusers raising typical design condition, but the temperatures are slightly
local velocities and reducing temperatures (the air supply elevated due to the lower average rate of heat loss.
temperature was 19 °C).
2.2.2.3 Temperature and thermal stratification
The overall conclusion from this work is that typical office
spaces that are sufficiently well insulated to be self-heating The use of displacement ventilation is often expected to
(i.e. average room temperatures are adequate) will not suffer produce higher vertical temperature stratification than a
from local discomfort in the absence of perimeter heating. conventional mixed environment. The addition of large
This conclusion applies only to spaces with one exposed areas of glazing normally might be expected to increase
wall, and more detailed consideration needs to be given to this, and perhaps also to produce substantial horizontal
corner rooms (see section 2.2.2.2) or rooms with exposed stratification. The simulations investigated here consider
floors or ceilings. the effect of window height and U-value on the stratifica-
tion assuming both steady conditions of a continuous
2.2.2.2 Computational fluid dynamic period of –5 °C outside and more typical time varying
analysis of corner rooms outdoor conditions.

In corner rooms, the increased area of exposed façades Section 2.2.2.2 demonstrated that the downdraught from
might be expected to produce significant downdraughts the glazed elements did not penetrate far into the room. As
and thus produce discomfort in the occupied zone, a consequence, the thermal variation in a horizontal plane
particularly near the glazed elements. This has been is small except in the proximity of the computers
investigated for both generating significant vertical plumes. Very close to the
floor, the temperature also reduces near the swirl diffusers.
— the extreme design conditions of a continuous
This latter effect is most noticeable in the more energy-
period of –5 °C outside
efficient cases with smaller glazed elements and lower U-
— more realistic conditions of time varying outdoor values. This is because the room temperature is higher and
conditions. further away from the fixed supply air temperature. Table
Impact of advanced envelopes on HVAC requirements 7

Figure 2.8 Temperature stratification; 1.8 m window, U = 1.5 W/m2·K, Figure 2.9 Temperature stratification; full-height glazing,
constant cold conditions outside U = 1.5 W/m2·K, constant cold conditions outside

2.5 shows the vertical temperature stratification in the


room from ankle height to seated (1.2 m — columns 4 and
6) and standing (1.8 m — columns 5 and 7) head heights.
The layer of cool air created by the diffusers is also thin and
may not be perceptible to occupants. Columns 4 and 5 show
the temperature stratification excluding the values
calculated within the first 150 mm above the floor. The
values in columns 6 and 7 show the stratification including
the cold air from the diffusers close to the floor.

ISO 7730(13) recommends that the temperature difference


between head and ankle be limited to 3 K. For seated
occupants, this limit is often reduced to 2 K. Table 2.5
shows that, even at design conditions, these limits are Figure 2.10 Temperature stratification; full-height glazing,
achieved, since the ankle height would be outside the cool U = 1.5 W/m2·K, realistic design conditions
boundary layer region. Figures 2.8 and 2.9 show selected
elevations of temperature for cases with constant cold
conditions of –5 °C outside. The vertical stratification is
These results demonstrate that even in extreme conditions
clear, and the figure show the minimal horizontal
where the outdoor temperature is constant at –5 °C, the
stratification.
design can maintain relatively uniform internal tem-
peratures. Clearly, for a sustained period of low outdoor
Figure 2.10 shows the considerably warmer conditions temperature, additional heating may be required to raise
when the external conditions are those of a more typical the mean temperatures in corner rooms with substantial
design day. The stratification is little changed, however. amounts of glazing.

Table 2.5 Vertical temperature stratification in a corner room


Window U-value Vertical stratification (°C) Vertical stratification (°C)
height (m) (W/m2·K) (excluding floor boundary layer) (including floor boundary layer)
To seated To standing To seated To standing
head height head height head height head height

Continuous external condition of –5 °C:


1.2 1.5 2.1 2.7 2.6 3.2
1.2 2.0 1.8 2.4 2.2 2.8
1.8 1.5 1.7 2.6 2.1 3.0
1.8 2.0 1.3 2.2 1.6 2.5
2.8 1.5 1.6 2.7 1.8 2.8
2.8 2.0 1.4 2.5 1.4 2.5

Varying external condition typical of design day:


1.2 1.5 1.4 2.3 1.8 2.7
1.2 2.0 1.9 2.5 2.3 2.8
1.8 1.5 1.8 2.6 2.1 2.9
1.8 2.0 1.5 2.3 1.8 2.5
2.8 1.5 1.6 2.4 1.7 2.5
2.8 2.0 1.3 2.2 1.4 2.2
8 HVAC strategies for well-insulated airtight buildings

Table 2.6 Mean values of PMV and PPD in a corner room


Window U-value Predicted mean vote (PMV) Predicted percentage
height (m) (W/m2·K) dissatisfied (PPD)†
To seated To standing To seated To standing
head height head height head height head height

Continuous external condition of –5 °C:


1.2 1.5 –0.49 –0.41 8.7 7.8
1.2 2.0 –0.55 –0.48 9.9 8.9
1.8 1.5 –0.63 –0.55 11.6 10.3
1.8 2.0 –0.73 –0.66 14.2 12.9
2.8 1.5 –0.89 –0.79 19.3 16.8
2.8 2.0 –1.05 –0.96 25.6 22.8

Varying external condition typical of design day:


1.2 1.5 –0.10 –0.05 5.1 5.1
1.2 2.0 –0.23 –0.18 5.6 5.4
1.8 1.5 –0.24 –0.18 5.7 5.4
1.8 2.0 –0.36 –0.30 6.7 6.3
2.8 1.5 –0.45 –0.38 8.0 7.3
2.8 2.0 –0.64 –0.57 11.7 10.6
† The ASHRAE comfort zone is defined as less than 20% PPD

2.2.2.4 Thermal comfort — window U-value (1.0, 1.5 and 2.0 W/m2·K)

Computational fluid dynamics was also used to predict — small power loads (base case = 6, but also 12 W/m2):
comfort in the corner rooms (see section 2.2.2.1). Table 2.6 the effect of delaying the onset of internal gains was
shows the mean values of PMV and predicted percentage also investigated
dissatisfied (PPD) for the seated occupancy zone and the — pre-heat strategy: most of the runs were carried out
standing occupancy zone. with a simplified optimum start control. This
resulted in some underheating following very cold
These results demonstrate that even in extreme conditions weekend shut downs due to the limited heating
where the outdoor temperature is constant at –5 °C, the capacity offered by the radiant panel system.
design can maintain relatively uniform internal tempera- Consequently, runs were also undertaken with
tures. During sustained periods of low outdoor temperature, continuous overnight trickle heating.
corner rooms with substantial areas of glazing would
require some localised heating as demonstrated by the — ventilation rate (3 and 6 ACH).
relatively high PPD values for the larger window sizes and
the higher U-values. This same trend is confirmed by the All these details cannot be summarised here, but the
dynamic thermal modelling (see section 2.2.2.5). It should significant parameters in achieving good year-round
be stressed that these conclusions relate to the corner room comfort were the glazing U-value and size, and the pre-heat
situation with its two exposed façades, where the exposure strategy. To illustrate the key points, results are shown for
is much greater than in the climate chamber tests with the worst case configurations, i.e. N-facing ground floor (one
one exposed façade typical of the majority of a building. exposed wall and an exposed floor) and NW-facing ground
floor (two adjacent exposed walls and an exposed floor).
Figure 2.11 shows a base case analysis for a room with one
2.2.2.5 Dynamic thermal modelling exposed end wall with a U = 2.0 W/m2 ·K window. Con-
ditions are maintained within limits very well with the
Climate chambers are best suited to investigating steady exception of the full-height glazing. The underheated hours
state conditions, and thermal modelling was therefore used relate to inadequacies in the optimum start algorithm, and
to check dynamic effects and to ensure that comfort can be constant overnight trickle heating completely cuts off the
maintained in the absence of heating during all occupied
hours. In the analysis described here, the heating and 60
Window height
cooling was provided by a single set of radiant panels* 2·8 m
operating in changeover mode, with the changeover timed 50
Percentage of total office
hours (0700–1900) / %

to the beginning of occupancy. Frequency plots of dry 1·8 m


resultant temperature were generated for a wide variety of 40
office modules covering the following parameters: 1·2 m
30
— orientation (N/S/E/W)
20
— configuration (one end wall or two adjacent walls,
both with and without exposed floor or roof) 10

— window height (1.2, 1.5, 1.8 and 2.8 m in a 2.8 m 0


floor-to-ceiling height room) 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Room dry resultant temperature / °C

* Other heating strategies could be used (see section 3) Figure 2.11 Base case analysis — effect of window size
Impact of advanced envelopes on HVAC requirements 9

Ramped heating from 15 to 21·5°C (Window height = 2·8 m) 2.3.1 Control of solar gain
(U-value = 1·5 W/m2·K)
Constant heating to 21·5°C (Window height = 2·8 m) Effective solar control is a subject in its own right (14). The
(U-value = 1·5 W/m2·K) principal objectives are to achieve a balance between control-
Ramped heating from 15 to 21·5°C (Window height = 1·8 m) ling solar gain, admitting sufficient daylight, providing
(U-value = 1·5 W/m2·K) occupant view and achieving an appropriate external
60
aesthetic. The difficulty is that the problem is orientation
dependent, and treatments that may work well on one façade
50
Percentage of total office

may not work well on another. Solar control is quantified by


hours (0700–1900) / %

the shading coefficient: the ratio of the instantaneous heat


40
gain at normal incidence of the window/shading system
relative to a single sheet of 4 mm thick clear glass.
30

20 It is important to recognise that solar gain takes two forms,


and that they influence cooling load and comfort in
10 different ways:
— Direct gain from short wave radiation transmitted
0
through the glass. Occupants exposed to direct gain
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
can quickly experience discomfort from overheating
Room dry resultant temperature / °C
or from glare. Those occupants shielded from the
direct effect of the sun’s rays will not experience the
Figure 2.12 Effect of pre-heat strategy on comfort in corner office
effect of the gain immediately. The short wave
radiation is absorbed by surfaces, which warm up
tail of temperatures below 20 °C (as illustrated by the and emit increasing amounts of long wave radiation.
comparison of the two pre-heat schedules in Figure 2.12). The air temperature also increases as a result of
convection from the warm surfaces. The greater the
thermal capacity of the room, the lower the peak
The problem of maintaining temperatures in the absence of cooling load.
heating is obviously more significant in corner rooms, and
Figure 2.12 shows the equivalent data for a ground floor — Indirect gain in the form of short wave radiation
room with windows facing north and west. In this case, that has been absorbed by the glazing-blind system
temperatures can be maintained provided the window U- and re-transmitted as long wave radiation into the
value is 1.5 W/m2 ·K or better, although with full-height room. Because the glazing-blind system is usually
glazing there will always be a few hours of slight under- lightweight, these surfaces heat up very quickly in
heating during extreme weather conditions. The figure response to absorbed radiation, imposing an almost
shows the temperature frequency plot for the cases with immediate cooling load. It also has an impact on
optimum start and with constant overnight trickle heating. comfort, since there can be large areas of warm glass
It is clear that the small amount of underheating has more to that significantly affect the mean radiant temperature
do with the selected pre-heat strategy than the glazing experienced by occupants close to the window. Con-
specification. It is also perhaps surprising how well average sequently, it is best to organise the solar protection
conditions are maintained, even with relatively modest such that the solar gain is rejected back to outside
equipment gains (6 W/m2). without significantly affecting the temperature of
the inner glass surface.

It is worth noting that there are a few relatively high Therefore, when specifying a glazing/shading combination,
temperatures for this module. Although the run was carried it is important to minimise both the long wave and short
out with no special solar protection measures, it does wave shading coefficients. The short wave coefficient is a
highlight the problem of large areas of glass. It is therefore measure of the amount of solar radiation that the system
recommended that, for corner rooms especially, 65% be allows through to the room. The long wave coefficient is a
considered a sensible maximum value for glazing, and even measure of the solar absorptance that is re-radiated to the
then appropriate solar control measures will need to be room.
applied. It should be noted that 65% glazing on two
orientations would require a very demanding shading
coefficient to limit the solar overheating, as detailed in 2.3.1.1 Reduced perimeter cooling loads
section 2.3.1.
In the summer months, the shading coefficient of the
glazing is a more important characteristic than the U-value.
The relative importance of the solar protection is seen from
2.3 The building in summer Figure 2.13, which shows typical office gains on a July
design day for a 50% glazed façade equipped with clear
double glazing and internal blinds. These solar loads have
The principal function of the advanced envelope in been averaged over a 6 m deep perimeter zone for three
summer is to control solar gain. The levels of insulation orientations: N, S and SW. Depending on orientation, the
applied to reduce heat loss in winter are effective in solar contribution is between 45–70% of the peak load.
limiting conduction gains from high sol-air temperatures. Reducing the solar load can therefore significantly reduce
Consequently, the main additional requirement is to limit the total required cooling capacity, and the turn down ratio
solar gain through glazing. of the control system.
10 HVAC strategies for well-insulated airtight buildings

Occupants Small power Lights Solar — A chilled ceiling system with radiant panels and
perimeter chilled beam, typical of much current
good practice. This design includes a good shading
SW
system incorporating mid-pane blinds in the
double-glazed unit giving a shading coefficient of
Orientation

0.33. This itself is a very good shading coefficient,


S better indeed than many designs typical of
conventional practice. This suggests that typical
systems may perform worse in terms of comfort
N than the results presented here.
— A chilled ceiling system using radiant cooling
0 20 40 60 80 100 120 panels only, but with enhanced shading system
Heat gain / (W/m2) providing a shading coefficient ~0.2.
Figure 2.13 Relative heat gains for an office
Climate chamber tests were carried out with internal gains
either at or above the British Council for Offices (BCO) stan-
By going from clear double glazing plus internal blind with dard specification(16) recommendations. The module selected
a shading coefficient of 0.95 to a system with external was taken as the likely worst case, i.e. a SW-facing room, with
blinds or a ‘2+1’ window with mid-unit blinds (Figure 2.14) the solar gain being taken as the average of the three peak hours.
with a shading coefficient < 0.3, the maximum solar load is The results indicated that with the perimeter beam, comfort
reduced by a factor of three, reducing the peak design load was good for all window sizes (including full-height glazing),
by a factor of two in the critical spaces (15). Based on typical although the cooling load (and hence energy cost and carbon
elemental costs, this might save up to £10/m2 on the capital emissions) increased substantially. Figure 2.15 shows the
cost of providing cooling plant. Of equal significance is that results for the higher internal loads (7 m2/person and 25 W/m2
the ratio of maximum to minimum load will reduce by 25%, small power). The PMV is the value at the seated head height of
or even more if there is significant thermal inertia in the 1.1 m averaged across a distance 1.2 m from the perimeter. One
space. This will make control much easier, as turn down of the issues identified during the testing was the sensitivity of
ratios are reduced. The smaller sized primary plant will the perimeter conditions to the exact position of the chilled
also be operating nearer its design capacity for longer beam, and the balancing of the downward convection from the
periods, generating improvements in operating efficiency. beam and the effect of the warm glass surface.

2.3.1.2 Summer comfort conditions 0·4 2700


Predicted mean vote (PMV)

0·2 2500

Cooling load / W
In order to assess the potential for advanced envelopes to d
Loa 2300
simplify the design and operation of HVAC systems in 0
summer conditions, tests were carried out to determine the P MV 2100
relative comfort conditions achieved using two different –0·2
1900
system configurations. These were as follows:
–0·4 1700
–0·6 1500
1 1·5 2 2·5 3
Window height / m

Figure 2.15 Comfort and cooling load for chilled beam solution

For the high performance envelope solution, two sets of


runs were carried out, one with the same internal loads as
described above and another with lower loads typical of the
BCO specification (10 m2/person and 15 W/m2). For these
later runs, the displacement ventilation supply rate was also
increased from 3 to 6 ACH. The PMV data are summarised in
Figure 2.16 and indicate that, at the typical loads and with
the higher air change rate, comfort conditions are good
even for the full-height glazing. At the higher gains and
lower ventilation rate, comfort begins to become compro-
mised above a window height of about 1.5 m, equivalent to
54% glazed. (A PMV of ±0.85 is equivalent to the ASHRAE
comfort zone.) The dotted line shows the anticipated curve
for the higher gains and the higher ventilation rate (albeit
based on a single test). This suggests that comfort would be
acceptable even for full-height glazing and would be good
for glazing heights less than, say, 2.2 m. Bearing in mind
that this is for the extreme summer condition for the worst
facing orientation, and that the dynamic effects of thermal
mass could reduce the effect of these solar loads, it can be
seen that equivalent comfort to the chilled beam solution
Figure 2.14 Typical ‘2+1’ window can be obtained.
Impact of advanced envelopes on HVAC requirements 11

1·8 period, with cooling via radiant panels during


1·6 2 people, 6 ACH
3 people, 3 ACH
occupied periods. This approach was modelled for
1·4 both a lightweight and a heavyweight option.
Predicted mean vote (PMV)

3 people, 6 ACH
1·2 Ventilation was via a floor displacement system.
PMV = 0·85 (limit of
1·0
acceptable comfort)
0·8
Figures 2.18 and 2.19 illustrate typical output for two corner
0·6
offices. The NW-facing manager’s office has lower gains and
0·4 PMV = 0·5 (limit of
illustrates the performance of a space most likely to suffer
0·2 'good' comfort)
problems during the heating season. The SW-facing
0
perimeter office has typical gains, and illustrates the per-
–0·2
formance of a space most likely to suffer overheating in
–0·4
summer. The results indicate that the two peaks associated
–0·6 with the heating and cooling set points for the fan coil
1 1·5 2 2·5 3
Window height / m
system have been replaced by a smoother distribution for
the advanced envelopes options. Winter temperatures tend
Figure 2.16 PMV as a function of room temperature
to be slightly warmer and summer slightly cooler. The
thermal mass has a marginal effect on comfort (consistently
2·0 cooler), although the impact on energy is much more
pronounced (see section 4.2).
Predicted mean vote (PMV)

1·5
60
Advanced envelope
1·0 (heavy)
50
Percentage of total office
hours (0900–1800) / %

Advanced envelope
0·5 (light)
40
1995 Building
Regulations
0·0 30

20
–0·5
23 24 25 26 27 28 29 30
10
Dry resultant temperature / °C

Figure 2.17 Comfort conditions for high performance envelope solution 0


16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Room dry resultant temperature / °C
As with the winter condition, comfort is totally dominated
by the dry resultant temperature that is achievable, as Figure 2.18 Annual temperature distribution for NW-facing office
Figure 2.17 illustrates. This means that the effects of
radiant temperature and air speed are only secondary and
that, within the limits of gains analysed, the primary 60
Advanced envelope
concern is to ensure that the gains are limited such as to (heavy)
50
Percentage of total office

achieve a satisfactory dry resultant temperature.


hours (0700–1900) / %

Advanced envelope
(light)
40
Once again, it should be stressed that these results apply 1995 Building
only to the case of a room with a window on the end wall. Regulations
30
Corner rooms will create additional solar gain problems. It
should be noted that the 2002 Approved Document L(1)
20
gives guidance on the control of overheating, and this will
limit the proportion of glazing in a corner room, unless
10
very effective solar control is provided.
0
2.3.2 Annual performance 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Room dry resultant temperature / °C
To assess the performance of this approach on an annual Figure 2.19 Annual temperature distribution for SW-facing office
basis, a real building was simulated. For the basis of
comparison, the same building geometry was modelled for
each of the following two cases:
— The 1995 Building Regulation standards and with a 2.4 Achieving the required
fan coil air conditioning system with perimeter window performance
heating to offset perimeter losses. Ventilation was
provided via a full fresh air system delivered into The previous sections have indicated that windows with U-
the fan coil unit values of 1.5–2.0 W/m2·K and shading coefficients of the
order of 0.2–0.3 are capable of delivering good year-round
— An advanced envelope with windows with a U- comfort conditions with very much simpler HVAC systems.
value of 1.5 W/m2·K and a shading coefficient of This section summarises the window technologies that are
0.2. Heating was available only during the pre-heat able to deliver this sort of performance.
12 HVAC strategies for well-insulated airtight buildings

2.4.1 U-values 2·4


UPVC frame Aluminium frame
2·2
It is impractical to give a comprehensive overview of Glass (centre of pane)

U-value / (W/m2·K)
window technology, but the following illustrates some of 2·0
the parameters that influence performance. The first key 1·8
point is that window U-values are as much a function of the
1·6
frame technology as they are of the glazing system. Figure
2.20 shows the way the proportion of frame influences 1·4
overall window U-value for a UPVC and an aluminium
1·2
frame window. Because frame section dimensions are fixed,
the relative significance of the U-value of the frame 1·0
decreases as window size increases, resulting in a reduction 1·2 1·5 1·8 2·8
in overall U-value. The centre-of-pane U-value of the glass Window height / m
is shown by the horizontal line. It can be seen that the Figure 2.20 Overall U-values as a function of size
achievement of good overall U-values is therefore as much
to do with careful detailing of the frame as it is about the
specification of the glazing and inter-pane cavity.

Relative U-value (centre of pane) / %


120
The above data are typical for windows that are for ‘domestic
Air-filled
style’ construction. In large, non-domestic buildings, 100
curtain walling is a common form of construction. Because Argon-filled
of the high conductivity of the framing material, low 80
overall U-values are more difficult to achieve. Even with
very high performance double glazing with a centre-pane 60
U-value of 1.0 W/m2·K, overall U-values for a typical full
height glazed curtain walling system with 10% framing is 40
only 1.94 W/m2·K. However, systems with overall U-values
of 1.5 W/m2·K are available by utilising improved thermal 20
breaks in the framing system(17).
0
Clear glass Low emissivity glass
Increasing consideration is being given to the ‘2+1’ (ε = 0·06) (ε = 0·026)
window typical of Scandinavian practice (Figure 2.14). Glass type for inner pane of double-glazed unit
This has a single outer pane thermally isolated from an Figure 2.21 Relative performance of 2+1 windows
inner double-glazed unit. As well as improving the centre-
pane U-value, this approach has an even more marked
improvement on overall window U-value, as indicated in
Table 2.7.
140
The performance of ‘2+1’ windows can be varied through Air-filled Argon-filled
120
selective mixing of surface coating, inter-pane gap and
cavity gas. Figure 2.21 shows the centre-pane U-value for a 100
Relative cost / %

window unit with different window configurations. The


inner pane of the double-glazed unit is progressively 80
improved from clear glass with successively advanced low-
emissivity coatings. In this example, the cavity width is 60
12 mm, and two alternative configurations are shown, one
with an air-filled cavity, the other filled with argon. 40

Figure 2.22 shows the relative costs of the same window 20


units. The cost data are based on information provided by a
0
window supplier (18), and illustrate that the cost to generate Clear glass Low emissivity glass
significant improvement in performance is quite modest. (ε = 0·06) (ε = 0·026)
Clearly, these data should be regarded as indicative rather Glass type for inner pane of double-glazed unit
than absolute, but they emphasise that the achievement of
very high performance windows need not involve premium Figure 2.22 Relative costs of ‘2+1’ windows

Table 2.7 Effect of window type on U-value


Window type* U-value (W/m2·K)
Centre pane Whole window
Conventional double-glazed window 2 × 6 mm glass, 16 mm air fill 2.59 2.8
Double glazed with low-emissivity (ε = 0.16) 16 mm argon fill 1.45 2.0
Double glazed with super low-emissivity (ε = 0.026) 16 mm argon fill 1.05 1.75
‘2+1’ unit with single pane outer in wood frame, cavity blinds and double glazed inner with 0.95 1.15
low-emissivity (ε = 0.16), 16 mm argon fill in aluminium frame
*Note that the quoted U-values are based on a 3 × 2.8 m window unit; whole window U-values will vary according to window size
Impact of advanced envelopes on HVAC requirements 13

costs, especially when the reduced HVAC costs are taken into Opaque blind
account. (closed)

Opaque blind
2.4.1.1 Effect of meteorological conditions (45°)

Translucent
It is also important to appreciate that the U-value is (closed)
dependent on prevailing weather conditions, especially
temperature and wind speed. U-values are normally quoted Translucent
at standard conditions of –1 °C and 7 m/s. The centre-pane (45°)
U-value for the double-glazed unit of Figure 2.21 (low-
emissivity + argon fill) increases from 1.28 to 1.40 W/m2·K None
as the temperature drops from –1 °C to –15 °C. Because
temperatures below the reference condition of –1 °C occur 0 0·2 0·4 0·6 0·8
relatively infrequently in the UK, this effect is unimportant
Shading coefficient
in energy terms, but could be significant in local comfort
terms. In that context, what is most important is the inside Figure 2.24 Shading coefficient for different blind configurations in
surface temperature. a ‘2+1’ window

Figure 2.23 shows the inside surface temperature as a — Ventilated cavity blinds (between the units of a ‘2+1’
function of the outside temperature and the diffuse window): Figure 2.24 shows the effect of different
radiation falling on a horizontal surface. It can be seen that blind arrangements (translucent and opaque in the
even modest levels of diffuse radiation can increase the 45° and closed positions). In this arrangement, the
surface temperature by 0.5 °C. Consequently, during most cavity between the single and double-glazed unit
daytime hours the surface temperatures are likely to be can be ventilated so that the solar radiation
0.5–1.0 °C warmer than the values predicted by U-value absorbed by the blind is vented to outside, reducing
calculations alone, thereby improving winter comfort. It is the long wave re-transmitted component. As well as
also worth noting that although U-values are adversely reducing the load, this will reduce the temperature
affected by increasing wind speed, the wind speed at of the inner surface of glass, thereby improving
which U-values are quoted (7 m/s) is relatively high. For comfort.
most inland areas of the UK, the hourly mean wind speed
that is exceeded on only 10% of occasions is between 8 and
9 m/s. Further, these are meteorological wind speeds, and — External blinds: this approach provides the best
wind speeds local to the building are likely to be form of solar protection, but the shading system
significantly reduced. In rural areas with scattered needs to be robust enough to withstand wind loads.
windbreaks this reduction is about 20% and in urban areas They also represent a potential site for roosting
it is greater than 50% (10). birds and therefore may require frequent cleaning.

2.4.2 Shading coefficients — Brise-soleil: different orientations need different


treatments to exclude solar gain. Figures 2.25 and
There are a range of ways of improving the shading 2.26 illustrate the relative effectiveness of overhang
coefficient. These include: and side fin on two different window orientations
for a 3 m wide full-height (i.e. 2.8 m) window.
— Internal blinds.
— Mid-pane blinds (between the panes of a double- — Surface coatings on the glass: historically these have
glazed unit). usually involved tinted glazings, but improvements
in technology mean that colour neutral systems are
now available. Table 2.8 illustrates the effect of this
22 technology for a double-glazed unit without any
Solar radiation blinds. The only change between the two window
Glass surface temperature / °C

21 200 W/m2 options is the surface coating on the glass.


20 100 W/m2
0 W/m2
19
Table 2.8 Comparison between conventional and high performance
glazing units
18
Surface coating Centre-pane Shading
17 U-value coefficient
/ (W/m2·K)
16
Conventional double-glazed unit 2.59 0.8
15 Super low-emissivity glass (ε=0.026) 1.05 0.4
–15 –10 –5 0 5 10 15 with double silver layer solar control on
External temperature / °C inner surface of outer pane of double-
glazed unit with 16 mm argon fill
Figure 2.23 Effect of different levels of incident solar radiation on inside
surface temperature of glass for window with centre-pane U-value of Note: the shading coefficient could be further improved by the addition of
1.13 W/m2.K cavity blinds (see Figure 2.24)
14 HVAC strategies for well-insulated airtight buildings

7 Figure 2.25 Effect of fixed


Overhang and side (0 m) Overhang and side (0·5 m) Overhang and side (1 m) shading; south facing
Overhang and side (1·5 m) Overhang and side (2 m) Overhang and side (2·5 m)
6
Overhang (0·5 m) Overhang (1 m) Overhang (1·5 m)
Overhang (2 m) Overhang (2·5 m)
5
Insolation / kW

0
4 8 12 16 20
GMT

7 Figure 2.26 Effect of fixed


Overhang and side (0 m) shading; east facing
Overhang and side (0·5 m)
6
Overhang and side (1 m)
Overhang and side (1·5 m)
5 Overhang and side (2 m)
Overhang and side (2·5 m)
Insolation / kW

4 Overhang (0·5 m)
Overhang (1 m)
Overhang (1·5 m)
3
Overhang (2 m)
Overhang (2·5 m)
2

0
4 8 12 16 20
GMT

2.4.3 Daylight and view 2.5 Achieving the required


fabric performance
In achieving effective solar control, it is important that light
Two primary aspects require careful consideration during
transmission and occupant view are not compromised.
the envelope design and construction phases. These are:
Good daylight is an important energy-saving strategy, and
visual communication with outside is an important element — the overall, and localised, thermal resistance of the
of occupant satisfaction. The ideal combination is a assembly
window system with high light transmission, neutral
colour rendering, low solar heat transmission and low U- — the overall, and localised, air leakage performance
value. Such glazing systems are now available. The ratio of (infiltration/exfiltration).
light transmittance to solar heat transmittance is known as
‘selectivity’. Through recent developments in glass coating In the majority of new buildings the performance of external
technology, selectivities as high as 2 are possible. Such envelope assemblies is unsatisfactory with respect to both
coatings have very low emissivities. This means, for these issues. Such buildings would not be suitable for an
example, that a double glazing unit can achieve 66% light integrated heating and cooling approach as the envelope
transmittance and 33% solar heat transmittance while performance deficiencies would in turn lead to the failure of
simultaneously having a U-value of 1.1 W/m2·K (if the the heating and cooling strategy under certain external
cavity is argon filled). environmental conditions. Achieving satisfactory envelope
Impact of advanced envelopes on HVAC requirements 15

thermal resistance and air leakage performance is crucial to


the success of an integrated approach.

2.5.1 Insulation

Insulation must be installed in a continuous layer to be


fully effective. Gaps and discontinuities will have a signifi-
cant impact in terms of overall heat losses. In many typical
building types, thermographic surveys frequently reveal
significant areas of discontinuity in the insulation. It has
been estimated that gaps between sections of insulation can
account for up to 6% of the overall envelope area in
industrial buildings and that this can lead to up to 33%
additional heat loss(19). Figure 2.27 shows an infrared
thermographic image of a typical commercial unit with a
profiled metal site-assembled roofing system. The white
arrows near the black/purple areas highlight areas of
missing or misplaced insulation where significant
Figure 2.27 Thermographic image showing missing insulation
additional heat loss is occurring.

Cold bridges are localised areas of reduced thermal


resistance. Typically, they vary from uninsulated structural
members passing through the insulation layer to construc-
tion defects such as mortar ‘snots’ building up on cavity
wall batts during construction. Figure 2.28 shows large
mortar ‘snots’ on the top edge of the full-fill cavity
insulation in a typical masonry cavity wall. These snots will
provide significant heat and moisture bridges through the
cavity. Cold bridges have a similar effect on heat losses as
gaps and discontinuities.

Achieving effective envelope insulation performance in a


completed building requires careful consideration during
the design phase with a high level of workmanship and
supervision during the building construction. Detailed
construction drawings often show ‘ideal’ insulation
placement within the envelope assemblies, which cannot be
readily achieved on site. It is essential that any such
problem areas are identified and that an adequate Figure 2.28 Thermal
alternative means of insulation placement is achieved. bridge caused by
mortar ‘snots’

The following notes outline a methodology that should be


considered at each of the stages of design and construction insulation should be traced down through the insulating
to ensure effective insulation performance. layers to establish insulation continuity and to highlight
any weaknesses such as areas of potential cold bridging.
2.5.1.1 Concept design
2.5.1.3 Construction phase
Consideration must be given early in the design process to
the type of envelope assembly which is to be used — e.g. During the construction phase, care must be taken to
high thermal mass or lightweight quick response — and ensure effective continuity of insulation. Whilst small
this will generally dictate the type and position of the cracks and gaps between sections of insulation may seem
insulation within the assembly. insignificant to site operatives, they will have a significant
impact on the overall performance of the building. Ideally,
areas of insulation which will be concealed within the
2.5.1.2 Detail design envelope construction should be subjected to an
independent inspection of the quality of installation prior
The thickness of insulation required to achieve the target to covering up.
U-values for the type of assembly chosen can be readily
established through manual calculation or specialised
computer programs. Significant attention must be paid 2.5.1.4 Quality assurance of completed assembly
during this stage to the elimination of cold bridging,
particularly at openings within the envelope assembly. The On completion of the envelope construction, it is recom-
impact of repeating thermal bridges such as wall ties and mended that an infrared thermographic survey be
framing material should not be underestimated. Specialist undertaken on the building as the final quality assurance
insulated cavity closers should be used at all openings procedure for establishing insulation continuity. The
within cavity wall construction to minimise cold bridging. survey should be undertaken when the envelope is complete
When suitably detailed sections are available, the line of the and the building heating system is operational. A
16 HVAC strategies for well-insulated airtight buildings

temperature differential of 10 °C should exist between the A further potential problem of air leakage is that warm air
inside and outside air temperatures to ensure that an leaking through a building envelope can carry significant
effective survey can be undertaken. On a heavyweight quantities of moisture into that assembly. Measurement has
masonry construction, this temperature differential should shown that air leakage can typically move up to 100 times
ideally be maintained for a minimum period of 24 hours more moisture into an envelope assembly than would occur
prior to a survey. A shorter period is acceptable in by diffusion alone. This moisture may condense within the
lightweight envelope assemblies (e.g. curtain walling and assembly, potentially leading to degradation of insulation
profiled metal cladding) that display a much more rapid performance and long-term degradation of component
response to temperature gradients. parts.

The thermographic survey must be undertaken by a


thermographer experienced in building construction Envelope air leakage has become a much more significant
methods and building physics to ensure that the survey issue in more recent years due to the construction
findings are correctly interpreted. This is particularly industry’s gradual move away from traditional building
important when establishing acceptable levels of cold methods. Traditional methods such as plastered masonry
bridging at any openings through the envelope. Further walls, continuous ceiling linings and solid floor slabs have,
guidance on infrared thermography can be found in BRE to a great extent, given way to lightweight prefabricated
Information Paper IP7/90 (20) and BSRIA guidance (21). cladding, ceiling and floor systems. These systems are not
as forgiving in terms of envelope leakage as their more
traditional counterparts.
2.5.2 Thermal capacity

Thermal capacity can be almost as significant as insulation The problem is further increased by the fact that main
levels in modulating the energy demand in intermittently contractors tend to let envelope packages to subcontractors,
occupied buildings. This issue has been documented each of which is responsible for its own specific element.
elsewhere (22), but the essence of the effective use of thermal Unfortunately, there is often no one to take responsibility
mass is to use it as a heat recovery device by: for the interfaces between these subcontractor elements,
and it is at these interfaces where problems are most likely
— storing excess heat in winter to offset heating to arise.
system requirements at other parts of the day
— absorbing heat gains in summer so that the heat can It is relatively easy to ensure that new buildings are
be rejected from the building using free-cooling constructed to be acceptably airtight. The installation of
techniques during the night when air temperatures suitable seals between the elements typically used in
are at a minimum. envelope construction will generally always ensure that an
acceptable level of leakage is achieved. However, this
The rate of heat storage is limited by the surface heat requires a shift in the current thinking of both main and
transfer characteristics and therefore the effectiveness of subcontractors to ensure adequate integration between all
thermal mass is as much to do with surface area as it is with packages/trades.
heat capacity of the materials. Consequently, the effect of
the ceiling slab is most pronounced in the thermal storage
process. This mass should be exposed to the room air, 2.5.3.1 Airtightness standards
either directly or via open cell ceilings.
Air leakage is measured as a rate of leakage per square metre
2.5.3 Airtightness of external envelope per hour at an artificial pressure
differential through the envelope of 50 Pa (expressed as
The flow of air through the building envelope is commonly (m3/h)/m2 @ 50 Pa). Two parameters are used:
known as air leakage. Air leakage can be defined as ‘the
movement of air into and out of the building which is not — Air leakage index: this includes in the normalising
for the specific and planned purpose of exhausting stale air area only those elements of the envelope that are
or bringing in fresh air’. It is estimated that the majority of exposed to the ‘external’ air (e.g. floor slabs in direct
new non-domestic buildings constructed to comply with contact with the ground are not included). It is
the current regulatory requirements typically lose 50% of particularly useful for normalising the data
the total heating loads as a result of uncontrolled air leakage between different sized buildings of the same
through the building envelope. In addition to the direct generic type.
heat loss, air leakage often leads to ingress of pollutants,
inability to heat or cool localised zones within a building — Air permeability: this includes all the external surfaces,
and occupier complaints of draughts and discomfort. and is the parameter used to define the leakage
standards in Building Regulations Part L(1).
Air leakage should never be considered as acceptable
natural ventilation. It cannot be controlled or filtered and
will not provide adequate or evenly distributed ventilation. The typical air leakage index in a standard new commercial
It is generally at its most severe during the colder, windier, building in the UK is in the region of 20 (m3/h)/m2 @ 50 Pa.
winter months and has least impact during the warmer, For an industrial unit this figure would increase to ~25–30
calmer, summer periods. This is generally the opposite of the (m3/h)/m2 @ 50 Pa. The 2002 Part L standard is an air
requirements for ventilation within buildings. Ventilation permeability of 10 (m3/h)/m2 @ 50 Pa, equivalent to an air
of a building should never rely on air leakage, but should be leakage index of nearer 15 for most office buildings. The
provided by purpose-designed systems based on the good practice envelope leakage rates for office buildings
assumption that the envelope will be relatively airtight. recommended by CIBSE TM23(9) are shown in Table 2.9.
Impact of advanced envelopes on HVAC requirements 17

Table 2.9 Envelope air leakage rates recommended in CIBSE TM23(9)


Building type Air leakage Permeability
index (m3/h)/m2 @ 50 Pa
Naturally ventilated 10.0 7.0
Low energy/air conditioned 5.0 3.5

When adopting an integrated heating, cooling and


envelope approach, the maximum envelope air leakage
index is 5 (m3/h)/m2 @ 50 Pa, which is equivalent to the
specification recommended for a low energy building.
These standards are readily achievable with normal
construction methods, providing that the necessary air
seals are considered and specified at the design stage and
care is taken during the construction phase. Figure 2.29 Lack of air barrier continuity

Low air leakage envelope construction can be achieved


only if the requirement for tightness is considered early in flow of air and so significant leakage will occur at
the design process. Experience has shown that it is not this junction.
acceptable to design and construct buildings in the normal (d) Quality assurance of the completed building: a whole
way and then to attempt to seal junctions. This often leads building pressurisation test must be carried out to
to buildings that cannot be sealed to the specification establish the overall envelope leakage (Figure 2.30).
requirements and is also generally very costly. When the This will prove compliance or otherwise with the
requirement for low air leakage assemblies is considered at detailed envelope specification. The building
the design stage, the necessary air barrier becomes an envelope should be complete at the time of the test
integral part of the envelope design and construction. All to ensure that a meaningful result is achieved. The
seals necessary to minimise envelope leakage can then be test should be undertaken in accordance with
designed to provide optimum long-term performance. CIBSE TM23: Testing buildings for air leakage(9).
If the building were to fail to achieve the required
2.5.3.2 Design and construction leakage specification, identification of the principal
leakage routes must be undertaken, utilising either
The process of designing and constructing a low air leakage tracer smoke or an infrared thermographic camera.
building should be as follows: The contractor should then undertake remedial
(a) Conceptual design: decisions on the building form, sealing with subsequent retest(s) until the required
position and types of opening etc., all affect the ease specification is achieved. It is important that the
with which a low air leakage construction can be sealing materials be selected to give appropriate
achieved. The integration of effective draught durability in order that the required airtightness is
lobbies at external door openings is essential for the maintained over the life of the building.
success of a low air leakage strategy.
(b) Detail design: all air barrier components and seals
can be identified and specified during this stage.
Consideration must be given to the buildability of
the envelope elements, along with the necessary
seals, giving due attention to the durability of those
seals and how they can be maintained. When suffi-
ciently detailed envelope sectional drawings are
available, the line of the air barrier elements should
be traced to identify continuity between all the com-
ponents within the assembly. Junctions between
these components can then be considered in detail.
(c) Construction phase: site operatives should be educated
in the reason for, and the need for, the air barrier
within the envelope construction. Supervision must
be provided during the installation of key air barrier
elements, and the continuity and effectiveness of the
air barrier system continuously reviewed. Figure Figure 2.30 Multiple fan
pressurisation equipment
2.29 shows a typical problem where insulation has
been used to fill a gap: it will provide negligible
resistance to infiltration/exfiltration and certainly 2.5.4 Fabric details
does not constitute an element in an effective air
barrier. The figure shows the junction between the The following sections give brief details of key issues in
head of a window assembly and the underside of a different types of construction. More detailed guidance is
roof deck. Glass fibre insulation has been packed available in documents being produced(23) to support the
between the head of the window and the underside insulation standards introduced with the 2002 edition of
of the roof, but the insulation will not prevent the Approved Document L.
18 HVAC strategies for well-insulated airtight buildings

2.5.4.1 Masonry walls

Masonry wall construction is commonly found in new


commercial buildings. Walls are typically either cavity con-
struction with cavity insulation (fill or partial fill) or solid
construction with external insulation.

Continuity of insulation is the crucial issue in both types of


wall assembly. It is common to find gaps between sections of
insulation boards/batts or where blown insulants are
installed within cavity wall constructions. Defects can
either be identified visually as the work proceeds or after the
completion of the construction via infrared thermographic
surveys. These apparently minor deficiencies have a
significant impact on the overall thermal performance of
the assembly and must be minimised. For example, Figure Figure 2.32 Pre-formed cavity closer
2.31 shows a failure of insulation continuity where the
flange of a steelwork column projects into the cavity in a filled and tooled to ensure effective air barrier continuity
typical masonry cavity wall construction. The rigid partial between blocks. The actual air permeability of the block
fill insulation has not been tightly fitted against the column must be checked with the manufacturer prior to
flange and a further gap exists at the butt joint between specification. For example, Figure 2.33 shows a gap at the
board sections. Even if the boards had been tightly fitted, a abutments between the inner skin and the structural steel
cold bridge would still have existed at the flange, although column on an external cavity wall. Significant air leakage
this would not have been as severe as the illustrated will occur through this discontinuity.
configuration.
Effective soft air barrier joints must be provided wherever
Similar deficiencies can occur with external insulation the blockwork abuts structural columns or the underside of
systems, but these tend to be less frequent as it is generally floor/roof slabs. These joints must be designed and installed
much easier to inspect the installed insulation prior to to permit the differential movement that will occur between
covering with external finishes. the blockwork and structural elements.

If the inner blockwork skin has a plaster internal finish, the


plaster can be utilised as the air barrier line. Proprietary
plaster stop beads can be installed at all abutments with
structural elements or window/door openings to allow
effective soft joint mastic seals to be provided between the
plaster and adjacent substrate to ensure air barrier
continuity. Problems are often encountered where walls are
plastered but the plaster is not continuous above suspended
ceiling assemblies,in which case the air barrier resorts back
to the line of the blockwork. In such a situation it is
generally easier to utilise the blockwork as the sole line of
the air barrier and to treat the plaster finish as a simple
decorative overcoat.

Seals will also be required between any window or door


Figure 2.31 Lack of frame members and the inner blockwork skin. These seals
insulation continuity can generally be simply formed in externally insulated
assemblies as the frame member and brickwork usually
Cold bridging at window and door penetrations through abut. Cavity wall assemblies will require seals to be formed
cavity wall constructions requires careful consideration to over the cavity width. These seals can be readily provided
ensure effective insulation performance is achieved.
Utilising brick or block to close the cavity at opening
positions is not acceptable. Rigid pre-formed cavity closers
should be utilised. Figure 2.32 shows a pre-formed rigid
cavity closer installed to provide air barrier continuity
between the window assembly and inner blockwork skin,
where the mastic seal is still to be installed between the
flange of the closer and the inner skin.

Cold bridging at openings in external insulated walls do


not tend to be as problematic as the external insulation can
be continued to abut or overlap the opening element.

The inner masonry skin of the cavity or externally


insulated walls must act as the air barrier line in the
construction. The blockwork used for this skin must be
impervious and all mortar beds and perpend joints fully Figure 2.33 Air leakage path
Impact of advanced envelopes on HVAC requirements 19

by ensuring that rigid proprietary cavity closures are mastic


sealed to the inner blockwork skin during installation and
that a further mastic seal is installed between the cavity
closer and window/door frame member. An identical detail
can also be adopted at the cill of window openings. As
cavity closers are generally installed to minimise cold
bridging at such details, the additional cost of providing
airtight details relate to the mastic seals, which are marginal
in overall construction terms.

Pre-formed insulated lintels should be used over window


and door openings in cavity masonry construction. It is
important that the lower flange of the lintel be continuous
to allow an effective air seal to be provided between the
window or door frame head and the lintel, which will then
provide the continuity back to the blockwork inner skin. Figure 2.34 Sealing membrane for curtain walling system
Perforated flanges will permit leakage into the cavity void
unless overplastered. by the insulation installers to ensure that no minor gaps are
left between sections of insulant and that insulation
2.5.4.2 Curtain walling/lightweight cladding continuity is achieved at details such as roof water outlets or
other roof penetrations. Insulation must be installed to all
The standard of insulation continuity typically achieved by upstand details to roof penetrations such as smoke vents,
curtain walling and lightweight cladding assemblies is access hatches, fan outlets, etc.
generally acceptable for an integrated heating and cooling
strategy. The principal areas that require further considera- The concrete deck will generally provide an exceptionally
tion are where the assemblies abut adjacent construction good air barrier line. If pre-cast concrete planks are utilised
materials such as at cill, head and jamb details. It is seals may be required at butt joints between planks to
essential that effective insulation continuity be provided to ensure effective continuity. Any expansion joints within
ensure adequate overall performance. This can be readily the roof deck should be sealed on the underside to ensure
achieved through the application of sections of rigid board effective air barrier continuity.
insulation or expanding foam insulants applied on-site.
2.5.4.4 Roof assembly: metal deck with
Achieving effective air barrier continuity at abutment details insulation and waterproof layer over
can be problematic due to the differential movement that
generally occurs between the lightweight cladding system
Where such constructions are used for ‘flat’ roofs, insulation
and the adjacent, generally masonry, structure. The most
is generally either bonded or mechanically fixed down to the
effective means of providing effective seals whilst accom-
deck and the issues surrounding continuity are identical to
modating this movement is achieved by utilising ethylene-
those outlined in section 2.5.4.3. If the profiled metal deck is
propylene-diene-terpolymer (EPDM) membranes. These can
part of a pitched roof constructed with profiled metal
either be glazed into the curtain walling assembly or bonded
cladding assembled on site, the issue of insulation continu-
to the lightweight cladding system and then bonded back to
ity must be considered in greater detail. As a result of poor
the adjacent construction. EPDM seals are typically included
workmanship, areas of missing insulation or gaps between
in curtain wall construction at such details. The only
sections of insulation are common in site-assembled metal
additional requirement is to ensure adequate bonding
cladding systems. Figure 2.35 shows gaps left between light-
between the EPDM and adjacent substrates. This has a very
weight glass wool insulation; condensation droplets can be
marginal cost implication.
seen on the underside of the profiled metal weathering skin.
In Figure 2.34 an EPDM membrane has been installed to
Training and supervision of installers must be provided to
provide a seal between the head of the curtain walling and
ensure effective insulation continuity is achieved. An infra-
the upstand to the roof deck. The membrane is glazed into
red thermographic survey should always be undertaken on
the top channel of the curtain wall assembly and fully sealed
completion of such installations. Figure 2.36 is an infrared
to the head of the concrete roof upstand.
thermographic image showing an area of missing insulation
It is important with curtain wall assemblies that the
membrane be sealed or glazed into the front face of the
assembly to prevent the possibility of the curtain wall frame
members acting as ‘air ducts’ into the building. This seal
will require to be returned into the inner blockwork skin at
masonry wall constructions to provide effective air barrier
continuity.

2.5.4.3 Roof assembly: concrete deck with


insulation and waterproof layer over

Insulation is typically either bonded or mechanically fixed


down to the concrete deck and insulation continuity over
the general roof area is rarely a problem. Care must be taken Figure 2.35 Loss of insulation continuity
20 HVAC strategies for well-insulated airtight buildings

heating is radiant asymmetry. Figure 3.1, reproduced from


CIBSE Guide A(10), shows that the percentage dissatis-
faction is more sensitive for a heated ceiling than for any
other surface. However, for the range of envelope options
investigated, and for a full radiant ceiling, surface-room
temperatures are unlikely to exceed 8–10 K, even under
extreme weather conditions. It should also be noted that,
because heating is limited to providing pre-heat, there are
no occupants to experience any adverse radiant asymmetry
or temperature gradient. The only issue that needs
consideration is the transition from heating to cooling, and
how quickly a stable stratified layer might form. Again, this
is not significant because the situation will never arise
where there is a need for a changeover from maximum pre-
heat output to maximum cooling output.

In principle, the integrated heating and cooling could be


provided in other ways:
Figure 2.36 Thermographic image of missing insulation — Two-pipe changeover fan coil system: the changeover
would be daily in winter, rather than seasonal. The
disadvantage is that higher water supply tempera-
of approximately 6 m2 in a pitched roof. The large area of
black represents the zone of missing insulation.

To ensure effective air barrier continuity, it is essential that


the profiled metal deck be fully sealed during installation. 100
80 Warm ceiling
Reliance should never be placed on the vapour barrier or
weathering membranes within the system to act as air 60
barrier lines. As experience has shown, it is difficult, if not 40
impossible, to achieve effective air barrier continuity with
Cool wall
these elements, particularly at wall/roof junctions.
20
Dissatisfied / %

Profiled metal decking can be readily sealed during


installation with the aid of proprietary pre-formed sealant 10
strips placed at all side and end laps. Additional stitcher 8 Cool ceiling Warm wall
screws or rivets should be provided at 450 mm centres to all 6
sheet side lap junctions.
4

2
3 HVAC systems in
combination with 1
0 5 10 15 20 25 30 35 40
advanced envelopes Radiant temperature asymmetry / K

This section describes how the design of HVAC systems can Figure 3.1 Radiant asymmetry and comfort
be simplified in response to the substantially reduced
demands that result from a properly designed and
constructed advanced envelope. For information on a tures would be needed to provide the required heat
range of approaches to heating and cooling, see CIBSE output, thereby reducing efficiency.
Guides B1(24) and B2(8).
— Floor systems: pipe systems embedded in the floor
A possibility opened up by the strategies being considered in are becoming increasingly popular for heating and,
this publication is the integration of heating and cooling in some European countries, floor cooling is also
functions into a single system. If heating is no longer used. The main disadvantage is that the cooling
required during the occupied period (see section 2.2.1.1), the capacity of floors is limited by comfort constraints.
heating design issue becomes solely one of pre-heat. Conse- Since the cooling demand is likely to be the over-
quently, it is possible to envisage a situation where a single riding design criterion for office type buildings,
system is used in changeover mode to provide heating prior ceiling cooling systems are more likely to be
to occupancy then switching to cooling mode once preferred.
occupancy begins. This potentially could eliminate the cost — Ventilation system: this is likely to be less efficient in
of one complete distribution network and one set of terminal terms of transport energy (unless the ventilation rate
devices. to meet the fresh air requirements is sufficient to
provide the heating and cooling without excessive
This publication concentrates on a system whereby heating supply temperatures). In this case, the system is
and cooling are provided by ceiling mounted radiant more likely to require a mixing ventilation strategy
panels, coupled with a displacement ventilation system. because heating with displacement ventilation
One possible problem with using the radiant ceiling for diffusers is unlikely to be effective in achieving
20 HVAC strategies for well-insulated airtight buildings

heating is radiant asymmetry. Figure 3.1, reproduced from


CIBSE Guide A(10), shows that the percentage dissatis-
faction is more sensitive for a heated ceiling than for any
other surface. However, for the range of envelope options
investigated, and for a full radiant ceiling, surface-room
temperatures are unlikely to exceed 8–10 K, even under
extreme weather conditions. It should also be noted that,
because heating is limited to providing pre-heat, there are
no occupants to experience any adverse radiant asymmetry
or temperature gradient. The only issue that needs
consideration is the transition from heating to cooling, and
how quickly a stable stratified layer might form. Again, this
is not significant because the situation will never arise
where there is a need for a changeover from maximum pre-
heat output to maximum cooling output.

In principle, the integrated heating and cooling could be


provided in other ways:
Figure 2.36 Thermographic image of missing insulation — Two-pipe changeover fan coil system: the changeover
would be daily in winter, rather than seasonal. The
disadvantage is that higher water supply tempera-
of approximately 6 m2 in a pitched roof. The large area of
black represents the zone of missing insulation.

To ensure effective air barrier continuity, it is essential that


the profiled metal deck be fully sealed during installation. 100
80 Warm ceiling
Reliance should never be placed on the vapour barrier or
weathering membranes within the system to act as air 60
barrier lines. As experience has shown, it is difficult, if not 40
impossible, to achieve effective air barrier continuity with
Cool wall
these elements, particularly at wall/roof junctions.
20
Dissatisfied / %

Profiled metal decking can be readily sealed during


installation with the aid of proprietary pre-formed sealant 10
strips placed at all side and end laps. Additional stitcher 8 Cool ceiling Warm wall
screws or rivets should be provided at 450 mm centres to all 6
sheet side lap junctions.
4

2
3 HVAC systems in
combination with 1
0 5 10 15 20 25 30 35 40
advanced envelopes Radiant temperature asymmetry / K

This section describes how the design of HVAC systems can Figure 3.1 Radiant asymmetry and comfort
be simplified in response to the substantially reduced
demands that result from a properly designed and
constructed advanced envelope. For information on a tures would be needed to provide the required heat
range of approaches to heating and cooling, see CIBSE output, thereby reducing efficiency.
Guides B1(24) and B2(8).
— Floor systems: pipe systems embedded in the floor
A possibility opened up by the strategies being considered in are becoming increasingly popular for heating and,
this publication is the integration of heating and cooling in some European countries, floor cooling is also
functions into a single system. If heating is no longer used. The main disadvantage is that the cooling
required during the occupied period (see section 2.2.1.1), the capacity of floors is limited by comfort constraints.
heating design issue becomes solely one of pre-heat. Conse- Since the cooling demand is likely to be the over-
quently, it is possible to envisage a situation where a single riding design criterion for office type buildings,
system is used in changeover mode to provide heating prior ceiling cooling systems are more likely to be
to occupancy then switching to cooling mode once preferred.
occupancy begins. This potentially could eliminate the cost — Ventilation system: this is likely to be less efficient in
of one complete distribution network and one set of terminal terms of transport energy (unless the ventilation rate
devices. to meet the fresh air requirements is sufficient to
provide the heating and cooling without excessive
This publication concentrates on a system whereby heating supply temperatures). In this case, the system is
and cooling are provided by ceiling mounted radiant more likely to require a mixing ventilation strategy
panels, coupled with a displacement ventilation system. because heating with displacement ventilation
One possible problem with using the radiant ceiling for diffusers is unlikely to be effective in achieving
HVAC systems in combination with advanced envelopes 21

uniform comfort distribution. In deeper plan Flow pipe (warm or chilled water
buildings, it may be viable to provide perimeter depending on changeover mode)
pre-heat by transferring heat from the core areas to
the perimeter using the ventilation system. This
heat would have been stored in the core fabric from
Return pipe (warm or
the internal heat gains arising during the previous chilled water depending
day’s occupancy, and would minimise the need for on changeover mode)
heat to be provided from boiler plant.

3.1 Changeover strategies


Radiant
panel
This section discusses the ways in which the heating and
cooling water might be provided to the ceiling panels. The
different approaches offer different benefits in terms of cost Figure 3.3 Two-pipe configuration
and controllability. In all cases, both warm and chilled
water will be supplied to the panels. Consequently, the although the need for changeover is likely to be restricted to
design should cater for the thermal stresses during the the colder months. Control flexibility is much more limited
changeover from heating to cooling. than in the 4-pipe system, but some zonal (as opposed to
local) flexibility is possible. With the zone control
approach, relatively large sections of the building (e.g. a
wing or a floor) can be switched from heating to cooling,
3.1.1 Ceiling in 4-pipe configuration
while retaining heating in other zones (or vice versa). This
would require a 4-pipe main distribution manifold, with 2-
pipe local distribution circuits being fed from it. This
In this configuration (Figure 3.2), the system is acting like a approach would provide considerable cost savings because
4-pipe fan coil unit. This provides the maximum control the total length of installed pipe run is substantially
flexibility to maintain heating in those localised areas that reduced. There are also savings in the more labour-
may be occupied later than others. It has the disadvantage intensive parts of the network, i.e. the work carried out in
that two separate flow and return distribution networks confined ceiling voids when coordinating the layout with
have to be installed. With this configuration, the only the structure and other services.
capital cost saving is on the terminal device itself, plus the
benefit of freeing perimeter space. Also, because heating and If zonal changeover is considered unnecessary, whole
cooling must be available simultaneously, the service must building changeover would allow even more capital cost
be provided by separate central plant items, i.e. a centralised savings, since there is the saving of a complete distribution
changeover heat pump is not possible (see section 3.1.3). network as well as one set of terminal devices. However care
would be required during changeover to avoid ‘slugs’ of
Warm water flow warm water entering the chiller.
and return pipes
Flow
Return Whole-building changeover does not require totally simul-
Flow taneous occupation in all parts of the building. Because the
Return
envelope is so effective, the rate of fall of temperature is
slow, even in the absence of heating on a design winter day.
To illustrate this approach, Figure 3.4 shows simulated
conditions in a N-facing room with different amounts of
Diverting valve glazing following a cold weekend. No internal gains are
Chilled water effective in the space until 1200. The building is pre-heated
flow and to 21.5 °C, and switches off at 0700. The optimum start
return pipes algorithm for the largest glazed area is also shown for
comparison. Following the end of heating, the temperature
falls under the influence of the displacement ventilation,
but picks up reasonably quickly once the gains become
Radiant Common available in the space. The graphs present the worst case; in
panel return
real buildings there will be inter-zone coupling that will
tend to distribute heat from an occupied zone to an
unoccupied one. Further, if the ventilation system were
Figure 3.2 Four-pipe configuration controlled to avoid supplying air to unoccupied zones, the
gradient of the temperature decay would be substantially
3.1.2 Ceiling in 2-pipe configuration reduced, and comfort would be maintained (as well as
saving fan energy).
With this arrangement (Figure 3.3), the ceiling panels
operate only in changeover mode, resulting in savings on Whole building changeover would also allow a changeover
distribution pipework as well as on terminal devices and heat pump to provide both heating and cooling, thereby
perimeter space. Unlike a conventional fan coil system, the saving plant room space. Another possibility would be to
changeover follows a daily rather than a seasonal cycle, provide buffer storage so that the heat being rejected by the
22 HVAC strategies for well-insulated airtight buildings

23

22

21

20

19

18

17

16

15
Ramped heating from 15 to 21·5°C Constant heating to 21·5°C
14 (Window height 2·8 m, U-value 2 W/m2·K) (Window height 2·8 m, U-value 2 W/m2·K)
13 Constant heating to 21·5°C Constant heating to 21·5°C
(Window height 1·8 m, U-value 2 W/m2·K) (Window height 1·2 m, U-value 2 W/m2·K)
12
0000 0600 1200 1800 0000 0600 1200 1800
Monday Tuesday Figure 3.4 Building changeover
Time of day / h with delayed occupancy

chiller during the day could be stored and used to provide heating and ~16 °C for cooling. Consequently, a lower loop
the pre-heat for the following night time (see section 3.1.3). temperature may be beneficial but this would depend on the
relative efficiencies of the dry cooler and the heat pumps.
Another approach worth considering would be to use the
3.1.3 Ceiling connected via reversible heat water loop as a buffer to store energy during changeover. For
pumps to a common water loop example, during pre-heat the water temperature in the loop
could be allowed to fall in order to maximise the efficiency of
This mode of operation relies on the use of distributed cooling, once this became the dominant load. Similarly at the
reversible heat pumps (Figure 3.5). This provides the same end of daytime cooling, the water loop temperature could be
level of control flexibility as the 4-pipe system. It dis- allowed to rise, providing a higher source temperature for the
tributes the heating and cooling equipment around the next pre-heat period.
building, requiring less central plant room space. Because
the building is primarily either all-heating or all-cooling,
the dimensioning of the water loop will require careful 3.2 Simplified control
consideration to avoid excessive temperature differences
along the loop length, which would adversely affect heat Problems of zoning and of simultaneous heating and
pump performance. cooling are reduced with this approach, as the building is
always either in pre-heat or in cooling, never the two
In conventional systems, the water loop is usually controlled simultaneously. Large variations in internal gain will still
to about 33 °C. In this application, it may be appropriate to require zoning for cooling purposes, with possible supple-
reduce this as the water temperature is only ~30 °C for mental cooling provision. As far as heating is concerned,
the building can be treated as one large zone as the issue is
Water loop to provide heat source/heat dump
only pre-heat, when diversity of internal gain or variations
depending on heat pump mode in solar gain are irrelevant.

Another important consequence of the low loads is that the


system flow temperatures for both heating and cooling are
relatively close to the required room temperature. As room
temperatures change, the temperature difference between
Reversible
heat pump the radiant panel and the room also changes to modulate
the convective output, so as to return the room temperature
towards the desired set-point.

One of the reasons why current designs sometimes fail to


perform to expectations is because the HVAC systems are
trying to deal with the rapid changes in thermal energy
caused by the vagaries of the UK climate and the traditional
approach to core and perimeter zones. This problem is
exacerbated by high glazing areas and thermally light-
Radiant weight buildings. Sophisticated control systems have been
panel developed to try to cater for these rapid temporal and
spatial variations, but the systems are often not designed,
commissioned or maintained as well as they might be. The
Figure 3.5 Heat pump and common water loop approach outlined in this publication is to remove the
HVAC systems in combination with advanced envelopes 23

problem rather than treat the symptoms. High perfor- the cost of the fuel to the gross thermal efficiency). Table
mance building envelopes can substantially simplify the 3.1 compares a condensing boiler and a heat pump, based
design and operation of HVAC systems. By effectively on a relatively modest heat pump CoP of 2.5 and a high
isolating the occupied space from the external climate, the efficiency heat pump (e.g. ground source). The table
internal loads become much more constant with time and illustrates that the heat pump is significantly better in
much more even between core and perimeter and between carbon emission terms and that, at off-peak electricity rates,
different orientations of perimeter zone, especially if the the costs are comparable. Because all the heating is pre-
thermal capacity is high. heat, the majority of the heating demand will be in off-peak
periods. Clearly, the cost issue is very dependent on tariff,
but the current trend is for gas prices to increase and
3.3 Central plant options electricity rates to decrease.

This section explores the options available for providing The low supply water temperature also benefits heat pump
warm and chilled water to supply to the heating and cooling performance by reducing the required temperature lift. The
systems. key design issue for a heat pump is to identify a suitable heat
source. If an air-source heat pump is used, maximum heat
3.3.1 Heating demand occurs at times of lowest ambient temperature,
thereby reducing efficiency. This is made worse in the
Two issues influence the selection of heating plant: approach discussed here because all the heating is required
during pre-heat, when ambient temperatures are at their
— the very low supply temperature required for lowest during the diurnal cycle. This suggests that a ground
ceiling radiant heating (<35 °C) source heat pump might provide the most energy efficient
— the fact that heating is only required during the solution, although clearly capital costs will be higher than
pre-heat period and never simultaneously with for an air source heat pump. Ground temperatures below
cooling. about 2 m approximate the annual average temperature,
which in the UK is typically 10–12 °C. This constant source
The first point allows very efficient heat raising plant to be temperature can enable high CoPs in the region of 4.0 (the
utilised. One obvious option is a condensing boiler, since value used for the second example in Table 3.1). Performance
this would operate with continuous low return water is best in areas with non-consolidated (sandy) sediments,
temperatures, thereby maximising the period of condens- with a high groundwater table and groundwater flow. This
ing operation and achieving seasonal gross efficiencies of eases the drilling of the boreholes, and promotes high heat
>90%. Another important issue is that, because heating transfer rates.
demands are small, the required capacity may be met with
multiple domestic-type units, with much simpler (and Ground loop systems are usually in the form of a series of
cheaper) flue arrangements. Such units can easily be wall boreholes to a depth of ~100 m. Water/glycol mixture is
hung and thereby save further plant room space. circulated around each loop, and the individual loops
manifolded together to provide the source water for the
An alternative to a condensing boiler would be a heat reversible heat pump(s). In this way, the soil acts as a heat
pump, which would operate with a low condensing storage device: during heating, the ground temperature is
temperature resulting in a high CoP, especially if the heat lowered, storing energy to be used in the next cooling cycle.
source were at a reasonably high temperature (e.g. ground Indeed, it is usually required that the net annual heat
source) such that the temperature rise was small. Since injection into the ground by the system is approximately
heating will be needed only for pre-heat, a heat pump zero to avoid altering the thermal balance of the ground
would operate for most of the time at off-peak tariffs, beyond the boundaries of the building. With the integrated
thereby ensuring low energy costs as well as attractively low approach proposed in this publication, there is a significant
emissions of carbon. The fact that heating is required only net cooling demand, and so ground temperatures will
during the pre-heat period means that reversible heat continue to rise unless some balancing measures are taken.
pumps should also be considered because they would This could include using other forms of free-cooling in
provide another level of integration, extending plant winter months (see section 3.3.2) or cooling the ground
utilisation and reducing plant space requirements. during unoccupied night hours. This can be done by the
pre-heat operation or, when pre-heat is not required,
The 2002 edition of Part L of the Building Regulations(1) passing the water from the ground loops through a dry-air
characterises the performance of a heating system in terms cooler. This takes advantage of the lower night-time
of carbon intensity (kg(carbon)/kW·h of useful heat, i.e. the temperatures to generate cooling at a very high efficiency.
ratio of the carbon emission factor for the fuel to the gross This parasitic energy loss is compensated for through the
thermal efficiency). Users would also be interested in the very high CoP (of 5 or more) when the system is providing
cost intensity (pence/kW·h of useful heat, i.e. the ratio of cooling to the building.

Table 3.1 Comparison of a condensing boiler with electric heat pumps


Efficiency/ Fuel emission factor Price Carbon intensity Cost intensity
Heating plant CoP (kg(carbon)/kW·h) (pence/kW·h) (kg(carbon)/kW·h) (pence/kW·h)
Gas condensing boiler 95% 0.053 1.15 0.056 1.21
Electric heat pump 2.5 0.113 6.5 (peak) 0.045 2.60
2.5 (off-peak) 1.00
Electric heat pump 4.0 0.113 6.5 (peak) 0.028 1.63
2.5 (off-peak) 0.63
24 HVAC strategies for well-insulated airtight buildings

The water loop from the boreholes can be integrated into 30

Maximum daily temperature / °C


the radiant panels by using the two-pipe approach (see
25
section 3.1.2) with a centralised reversible heat pump, or it
can be the circulating loop to which distributed reversible 20
heat pumps are coupled (see section 3.1.3). In either mode,
the ground is acting as the heat rejection system, 15
eliminating the need for a rooftop heat rejection plant. This Frequency exceeded
might have significant advantages in terms of the aesthetics 10
2 days/month
of a clean roofline or where planning restrictions limit total
5 15 days/month
building height.
Target
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
3.3.2 Cooling
Figure 3.7 Frequency at which maximum daily temperature is exceeded
Radiant cooling, together with many chilled beam systems,
utilise relatively high design flow water temperatures circuit, thereby simplifying the system, increasing both the
(~16 °C). As cooling loads reduce from the design value, system CoP and the operating period, and reducing capital
flow water temperatures can be raised still further. This cost. The effect of using anti-freeze mixtures will marginally
means elevated evaporating temperatures with increased increase system pump energy, but much less than that
CoPs for mechanical cooling plant. If the heat sink also needed to provide for the pressure losses of a plate heat
allows a lower condensing temperature (such as floating exchanger. It may also slightly decrease the heat transfer
head pressure control or the use of groundwater), further efficiency of the terminal cooling devices themselves,
increases in CoP can be obtained. For these reasons, very perhaps resulting in a slight increase in their cost.
good chiller CoP should be attainable in buildings with high
performance envelopes requiring year-round cooling. The importance of this free-cooling opportunity is readily
However, the greatest energy saving benefit will come from apparent from an analysis of the weather data as illustrated
the utilisation of free or high efficiency ambient cooling, e.g. in Figure 3.7. The upper curve shows the maximum daily
dry-air coolers, cooling towers and ground/lake water temperature that is exceeded on average for only two days a
sources (25). month. This indicates that for the period November to
March, the dry cooler can provide virtually all the cooling
Even if the chilled water temperature is not increased at requirements. The lower line shows the maximum
reduced cooling load, for much of the winter period water at temperature exceeded on half the days of the month. It
16 °C can be obtained using ambient energy sources, indicates that free-cooling can provide all the cooling for at
thereby enabling apparent CoPs as high as 20 or more to be least half the days for another month or more at the
obtained for significant periods. The provision of cool water beginning and end of the winter period. Comparison with
at ~16 °C requires a source whose temperature is ≤ 14 °C. Figure 3.6 suggests that the average CoP for cooling during
The 2 K difference allows for an adequate driving potential this period will be of the order of 10. This figure would
across the heat exchanger that cools the circulating chilled improve still further if the chilled water temperature were
water. One approach is to use a dry-air cooler. Figure 3.6 scheduled to increase at reduced winter cooling demand.
shows typical CoPs as a function of ambient temperature
when operating at two different chilled water flow Another approach would be to use groundwater to cool the
temperatures, 14 °C and 16 °C(26). For comparison, the CoP chilled water circuit. The ground below about 2 m depth in
of a typical conventional water chiller system is also shown. the UK provides a year-round temperature of the order of
12 °C. With this approach, the groundwater is pumped out
It is necessary to use an anti-freeze fluid in the dry-air cooler of the ground using an open loop configuration, with the
to provide frost protection. Traditionally, the anti-freeze water being re-injected into the ground via a second,
mixture is isolated from the chilled water circuit by the use remote borehole. In some UK locations, the re-injection of
of a high efficiency plate-type heat exchanger. However, the groundwater is not even required because there are
there is no practical reason why the anti-freeze solution problems of rising groundwater tables causing flooding of
should not be circulated throughout the chilled water deep basements and underground tunnels. For example,
Sainsbury’s Millennium Superstore in Greenwich uses
groundwater in this way(27), both to cool the store via
25 embedded pipes in the floor and to lower condensing tem-
Chilled water flow temperature
peratures for the low temperature refrigeration equipment.
14°C
20 After use, the water is pumped to a surface drain.
16°C
Cooling CoP

Typical chiller system If it is a requirement that the water be re-injected, the


15
implications of continued heat rejection to the aquifer need
to be understood. If necessary, the heat rejected to the
10 ground could be taken out at night using a dry-air cooler.
Night-time temperatures will typically be at least 5 K cooler
5
than the daytime values, which would significantly increase
the efficiency of the dry cooler process and extend the
length of the season for which free-cooling is available.
0 Overall system efficiencies might be improved still further
0 5 10 15 20
by using a ground-coupled heat pump system for cooling.
Ambient temperature / °C
Figure 3.6 Efficiency of dry-air cooler * From manufacturers’ data
Performance estimates 25

Cooling could be taken from the ground during the day at 25


quoted CoPs of more than 30*.

Supply temperature / °C
20

3.3.3 Ventilation 15

This section has concentrated on using radiant ceiling panels 10 Heat recovery effectiveness
as the room heating and cooling device. Conventionally, 50%
such systems are used in conjunction with displacement 5 70%
ventilation. The detailed design of such systems is covered
90%
elsewhere(28), and this section will only review how a 0
displacement ventilation system might be integrated into –10 –50 5 10 15
the overall strategy. Outside temperature / °C
Figure 3.8 The effect of heat recovery effectiveness on supply
temperature
The main issue for consideration is the air supply
temperature, which is normally scheduled at 19 °C. The
issue is that, even during winter, the building is in cooling It is always important to assess the energy costs associated
mode even though the outside air is much cooler than the with achieving heat recovery. Increased fan power and the
room supply temperature. The amount of cooling available direct costs associated with, for example, the drive motor
via the ventilation plant is significant, as can be seen from for the thermal wheel must be offset against the cost and
Figure 2.1. However, this cooling potential is limited by the carbon impact of the heat recovered. The specification of
need to heat the room air supply temperature to 19 °C. air handling units with low specific fan power (~1.5
Reducing the ventilation supply temperature to, say, 17 °C W/litre·s–1 or less) will be beneficial in this respect. Analysis
would reduce heating demand due to ventilation and shows that such specific fan powers offer reduced whole life
simultaneously double the usable cooling potential of the cost related to conventional specifications(29).
supply air. This increased cooling would be sufficient to
maintain space conditions in cold weather without the need Another important consideration with respect to use of heat
to provide cooling from the radiant panels, even allowing recovery is the sizing of the primary heat source for the
for some solar gain to the space. Indeed, if the room building. It has been conventional practice to ignore the
temperature is allowed to rise a little from the 21 °C on effect of the heat recovery when sizing the heat-raising
which Figure 2.1 is based, the free-cooling potential of the plant. The argument has been that if the building is cold,
ventilation air would increase still further. there is no heat in the building to recover and therefore the
heating plant should be capable of supplying all the
ventilation heat demand. This logic is debatable: when
The main reason for controlling the room supply tempera- bringing a building up to temperature from cold, the
ture to approx. 19 °C is to maintain comfort in the region of ventilation system would either not be running or running
the floor diffusers. A reduction in supply temperature on full recirculation. In the context of advanced envelope
would be possible if the induction ratio of the diffuser were buildings that are self heating, it would seem fully justified
increased (28). This can be achieved with user adjustable to size the heating plant based on fabric and infiltration
outlets giving a high degree of swirl. An alternative losses only, provided the heat recovery plant is sufficiently
approach to increase the cooling potential would be to efficient to handle the ventilation loss.
increase the ventilation rate, but here the savings from the
free-cooling would have to be offset against increased fan
power. It should be pointed out that free-cooling is also
available via the radiant ceiling panels (see section 3.3.2), 4 Performance estimates
and so energy benefit is not entirely lost if high induction
diffusers are impractical or unjustifiably expensive. In order to get an indication of the relative cost of the
approach proposed in this publication, a comparison
The other issue for consideration with a relatively high air exercise was undertaken for a realistic modern office
supply temperature is the energy demand for heating the building. The work was based on the three-storey office
air. To achieve good indoor air quality, displacement shown in Figure 4.1; the gross floor area was 4130 m2.
ventilation systems are usually 100% outside air. In that Three variants of this building were analysed. All were the
context, heat recovery systems may provide significant
benefit. Figure 3.8 shows the room supply temperature
achievable with different levels of device effectiveness as a
function of outside air temperature. The analysis is based
on a return air temperature of 22 °C, i.e. a room temperature
of 21 °C and a fan pickup of 1 K. In reality, the return
temperature is likely to be much greater because of
temperature stratification with displacement ventilation
and further heat pickup through the air handling
luminaires. The analysis is therefore conservative. The
graphs indicate that heat recovery is able to meet the
ventilation heating requirement under all likely condi-
tions, provided the effectiveness can approach 90%. This is
at the top end of the performance range, but thermal wheels
and regenerators are capable of sensible effectiveness of
90% or even slightly more(8). Figure 4.1 Reference building
Performance estimates 25

Cooling could be taken from the ground during the day at 25


quoted CoPs of more than 30*.

Supply temperature / °C
20

3.3.3 Ventilation 15

This section has concentrated on using radiant ceiling panels 10 Heat recovery effectiveness
as the room heating and cooling device. Conventionally, 50%
such systems are used in conjunction with displacement 5 70%
ventilation. The detailed design of such systems is covered
90%
elsewhere(28), and this section will only review how a 0
displacement ventilation system might be integrated into –10 –50 5 10 15
the overall strategy. Outside temperature / °C
Figure 3.8 The effect of heat recovery effectiveness on supply
temperature
The main issue for consideration is the air supply
temperature, which is normally scheduled at 19 °C. The
issue is that, even during winter, the building is in cooling It is always important to assess the energy costs associated
mode even though the outside air is much cooler than the with achieving heat recovery. Increased fan power and the
room supply temperature. The amount of cooling available direct costs associated with, for example, the drive motor
via the ventilation plant is significant, as can be seen from for the thermal wheel must be offset against the cost and
Figure 2.1. However, this cooling potential is limited by the carbon impact of the heat recovered. The specification of
need to heat the room air supply temperature to 19 °C. air handling units with low specific fan power (~1.5
Reducing the ventilation supply temperature to, say, 17 °C W/litre·s–1 or less) will be beneficial in this respect. Analysis
would reduce heating demand due to ventilation and shows that such specific fan powers offer reduced whole life
simultaneously double the usable cooling potential of the cost related to conventional specifications(29).
supply air. This increased cooling would be sufficient to
maintain space conditions in cold weather without the need Another important consideration with respect to use of heat
to provide cooling from the radiant panels, even allowing recovery is the sizing of the primary heat source for the
for some solar gain to the space. Indeed, if the room building. It has been conventional practice to ignore the
temperature is allowed to rise a little from the 21 °C on effect of the heat recovery when sizing the heat-raising
which Figure 2.1 is based, the free-cooling potential of the plant. The argument has been that if the building is cold,
ventilation air would increase still further. there is no heat in the building to recover and therefore the
heating plant should be capable of supplying all the
ventilation heat demand. This logic is debatable: when
The main reason for controlling the room supply tempera- bringing a building up to temperature from cold, the
ture to approx. 19 °C is to maintain comfort in the region of ventilation system would either not be running or running
the floor diffusers. A reduction in supply temperature on full recirculation. In the context of advanced envelope
would be possible if the induction ratio of the diffuser were buildings that are self heating, it would seem fully justified
increased (28). This can be achieved with user adjustable to size the heating plant based on fabric and infiltration
outlets giving a high degree of swirl. An alternative losses only, provided the heat recovery plant is sufficiently
approach to increase the cooling potential would be to efficient to handle the ventilation loss.
increase the ventilation rate, but here the savings from the
free-cooling would have to be offset against increased fan
power. It should be pointed out that free-cooling is also
available via the radiant ceiling panels (see section 3.3.2), 4 Performance estimates
and so energy benefit is not entirely lost if high induction
diffusers are impractical or unjustifiably expensive. In order to get an indication of the relative cost of the
approach proposed in this publication, a comparison
The other issue for consideration with a relatively high air exercise was undertaken for a realistic modern office
supply temperature is the energy demand for heating the building. The work was based on the three-storey office
air. To achieve good indoor air quality, displacement shown in Figure 4.1; the gross floor area was 4130 m2.
ventilation systems are usually 100% outside air. In that Three variants of this building were analysed. All were the
context, heat recovery systems may provide significant
benefit. Figure 3.8 shows the room supply temperature
achievable with different levels of device effectiveness as a
function of outside air temperature. The analysis is based
on a return air temperature of 22 °C, i.e. a room temperature
of 21 °C and a fan pickup of 1 K. In reality, the return
temperature is likely to be much greater because of
temperature stratification with displacement ventilation
and further heat pickup through the air handling
luminaires. The analysis is therefore conservative. The
graphs indicate that heat recovery is able to meet the
ventilation heating requirement under all likely condi-
tions, provided the effectiveness can approach 90%. This is
at the top end of the performance range, but thermal wheels
and regenerators are capable of sensible effectiveness of
90% or even slightly more(8). Figure 4.1 Reference building
26 HVAC strategies for well-insulated airtight buildings

same in terms of building geometry and occupancy/use; the 140


1995 Building Regulations
variations were in terms of the fabric insulation and 120
servicing strategy. The three models were as follows: Advanced envelope (light)
100
Advanced envelope (heavy)

Load / GJ
(a) Reference case: built to 1995 Part L standards, with 80
the exception of the office glazing. This was taken 60
as U = 2.7 W/m2·K, a value in advance of 1995 Part 40
L but typical of current practice. An infiltration 20
rate of 0.5 ACH was assumed. The reference design 0
had better than average solar shading with external Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
louvres on the SE and SW façades. The building
Figure 4.3 Air heating demands
was conditioned by a 4-pipe fan coil system, with
perimeter heating under the windows. Fresh air
was supplied at 3 ACH at 17 °C to all spaces. In considering the figures for the relative heating and
cooling demands for the three options, the following points
(b) Advanced envelope (lightweight) with wall U-values of can be made:
0.3 W/m2·K and windows of 1.5 W/m2·K. Infiltra-
tion was taken as 0.15 ACH, corresponding to an air — The air heating demand is lower in the reference
leakage rate of ~5 (m3/h)/m2 @ 50 Pa. The building case because of the lower room supply temperature
was conditioned by a 2-pipe changeover heated/ (Figure 4.3). For the advanced envelope design,
chilled radiant ceiling system, with heating control- this is significant because, when the ventilation
led via a night setback and optimum start schedule. system is running, the space requires cooling.
Ventilation was via a displacement ventilation Consequently, when outside temperatures are less
system, supplying air at 3 ACH at 19 °C. than the ventilation supply temperature, air is
being heated to supply a room requiring cooling.
(c) Advanced envelope (heavyweight): details as for (b), This means that a reduction in supply air
except that the building was heated continuously temperature would reduce both heating and
overnight to maintain a set point of 21 °C. cooling demands for the advanced design. The
lightweight version was re-run using the same
The following sections detail the relative performance of supply air temperature as the conventional design.
the buildings in relation to a number of key criteria. The total heating load was reduced by 13%, and the
cooling load by 9%. As discussed in section 3.3.3, a
reduced supply air temperature may be possible in a
4.1 Comfort displacement ventilation regime, if high induction
diffusers were used.
The cumulative comfort distributions shown in Figure 4.2 — As would be expected with the increased insulation
illustrate that, in general, the advanced envelope buildings standards, the room heating demands are signifi-
were a little warmer, especially in winter, than the design cantly lower in winter for the advanced envelope
based on current practice. The light and heavy variants options (Figure 4.4). What is particularly signifi-
performed almost identically. All three buildings main- cant is the further reduction in heating demand
tained conditions within the acceptable thermal comfort with the thermally massive option. This is due to
envelope at all times. the increased ability of the fabric to retain the
excess heat gains from the previous day and thereby
reduce the pre-heat demand for the next day. There
100
is a small increase in room heating demand for the
90 Design to 1995 Building
Regulations advanced envelope design relative to the reference
80 through the summer months. This is due to the
occupied hours / %
Percentage of total

70 Advanced envelope
(light) pre-heat control algorithm still heating the build-
60 ing to 21.5 °C prior to occupancy. This is almost
Advanced envelope
50
(heavy)
certainly unnecessary in summer, and refinement
40 of the pre-heat control would mean that the
30 summer heating demand would be no greater than
20 with the reference design.
10
— The room cooling loads are significantly higher for
0
18 19 20 21 22 23 24 25 26 the lightweight advanced envelope design than the
Dry resultant temperature / °C
140
Figure 4.2 Comfort comparison for the three variants 1995 Building Regulations
120
Advanced envelope (light)
100
Advanced envelope (heavy)
Load / GJ

4.2 Energy costs/carbon emissions 80


60
In order to estimate energy consumption (and hence costs 40
and carbon emissions), the performance of the HVAC system
20
was modelled in terms of estimating the load on the central
0
plant (i.e. the efficiency of all central plant items was set at Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
100%). The effect of different central plant efficiencies can
then be assessed as a second stage calculation. Figure 4.4 Room heating demands
Performance estimates 27

reference design in winter. One reason for this is pumps, heat rejection fans etc). The summer operation
the apparent free-cooling provided by the higher would not show much improvement in CoP other than those
infiltration rate in the conventional design. This is normally consequent on the use of a displacement
no argument for higher infiltration rates, since the ventilation/chilled ceiling strategy. However, the loads that
air leakage is likely to create draughts and local have to be met are reduced by the improved solar
discomfort rather than any real cooling energy protection, and so the total energy costs/carbon emissions
benefit. As discussed previously, the winter cooling are therefore lower in summer.
can be provided via a number of free-cooling
techniques and so any winter increase is relatively
insignificant. What is more important is the 4.3 Building costs
significant reduction in summer loads consequent
upon the improved solar control. Once again, the The new approach to design puts greater emphasis on the
heavyweight version outperforms the lightweight façade investment. This delivers reduced costs in HVAC
version in all seasons (Figure 4.5). plant and equipment. The following section gives some
basic data on how these costs might be distributed.
140
1995 Building Regulations
120 4.3.1 Windows
Advanced envelope (light)
100
Advanced envelope (heavy)
Load / GJ

80 The main emphasis on the fabric is in improved windows.


60 Data from a window supplier(18) suggest that the marginal
40 cost for a good quality ‘2+1’ window with high solar
protection would be about £70/m2 relative to an equivalent
20
quality standard double-glazed unit (U ~2.7 W/m2·K). The
0 guidance in 2002 Approved Document L requires ‘standard’
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
units to improve their performance to 2.2 W/m2·K or better,
Figure 4.5 Room cooling demands so the figure of £70/m2 is an overestimate of the real
marginal cost that will apply once the 2002 Part L standards
take effect.
As explained above, the data represent the demands on the
central plant, not the energy consumed in meeting those 4.3.2 Opaque fabric
demands. The advanced concepts are likely to be more
efficient in meeting the cooling demands than is the In this area, the main changes are slightly increased
conventional design but, even before those effects are thicknesses of thermal insulation, and greater attention to
accounted for, the loads can be seen to be less, as shown by thermal bridging and air barriers. None of these activities is
Figure 4.6. The only exception is the lightweight version particularly cost intensive, apart from perhaps an initial
with a supply air temperature of 19 °C. In this case, heating investment in the development of good design details and
is very slightly more and cooling 18% more. However, as the training of site operatives. The marginal cost of these
shown from the detailed figures, this additional cooling is improvements will be recouped in many ways that are not
the result of increased demand for cooling in winter, a accounted for in the analysis presented here. For example,
demand that can be met from ‘free’ sources (see section the general building quality will be improved so that there
3.3.2). Figures 3.6 and 3.7 would suggest that the average will be reduced problems with drafts or local condensation
CoP during the period October to April would be of the and mould. Also, general insulation performance will not
order of 10. This figure could be improved if the ground be compromised by air passing behind insulation layers, a
source option were used. A conventional vapour compres- phenomenon quite common in buildings with poor
sion system would be operating at around 3, after taking airtightness.
into account the ancillary consumptions (chilled water

250
4.4 HVAC costs
Heating Cooling
Clearly the savings in HVAC system cost depend on the
configuration selected (see sections 3.1.1–3.1.3) and the
200
Loads / (MW·h) per annum

particulars of each design. However, the following general


guidance indicates that the extra cost of the windows will,
150
in most cases, be more than compensated by reduced HVAC
costs.

100 The three possible changeover modes discussed in section


3.1 progressively eliminate terminal devices, LTHW distri-
bution pipework within each heating/cooling zone and all
50 LTHW pipework other than in the plantroom. Table 4.1
shows the level of cost savings associated with each of these
three levels of system simplification(30). The figures are
0 broadly in agreement with the offices cost model published
Current Advanced envelope in the Building Services Journal(31), except that the tabulated
Light Light Heavy figures are about £7/m2 cheaper in terms of the heating
(19°C) (17°C) (19°C) elements because they are based on a more common
Figure 4.6 Total heating and cooling loads radiator system rather than a trench heating system. In
28 HVAC strategies for well-insulated airtight buildings

Table 4.1 Level of cost savings associated with changeover modes


typically £30–40/m2 (32), so the enhanced solar protection
discussed in section 3.1
might generate costs savings of £5/m2 or slightly more. This
Level Description of system option Budget cost benefit could be used to reduce capital costs, or to re-invest
reduction the savings in free-cooling equipment that will significantly
1 Eliminate perimeter heating elements only £5–7/m2 reduce running costs.
(LTHW pipework connected to each bank of
radiant panels) Taken in combination, the elimination of the perimeter
2 Eliminate both the perimeter heating elements £25–30/m2 heating elements and the downsizing of boiler and chiller
and the LTHW pipework from edge of heating/ plant is likely to generate cost reductions for mechanical
cooling zone to the radiant panels plant of about £12/m2. This would finance the extra window
cost for glazing ratios of 45% and below. If elements of the
3 Eliminate perimeter heating elements and all £28–34/m2
LTHW pipework can be eliminated (levels 2 or 3), overall
LTHW distribution pipework other than in
the plant room savings of between £15–35/m2 are possible, or approxi-
mately 1.5–4% of total building cost.

addition to these direct cost savings there is the added


value associated with the extra perimeter space and the 4.5 Maintenance costs
increased space flexibility.
It is difficult to provide quantified maintenance data, but it
Figure 4.7 shows how these cost savings usually more than is probably reasonable to assume that fewer and smaller
compensate for the additional window cost of £70/m2 (see mechanical systems should lead to reduced maintenance
section 4.3.1). To aid comparison, this cost has been requirements. This trend is likely to be enhanced by the
translated to a floor area basis for the case of a building with fact that the range of loads over which the plant will operate
a floor-to-ceiling height of 2.8 m and a plan width of 15 m. will be compressed, leading to reduced low load operation.
The window area is expressed as a function of the visible
wall area looking from the inside of the room. The saving
in terminal device cost is comparable to the additional 4.6 Whole-life cost
window cost at low glazing ratios. However, if some of the
LTHW pipework is eliminated (levels 2 or 3), significant cost The simplified cost data given above suggest that the
savings of £10–25/m2 are possible, depending on glazing approach described in this document would be cheaper in
ratio. It should be noted that the marginal window cost terms of capital costs than current design approaches,
included high solar protection, and so the cost benefit of although this would always need to be checked on a case-
the improved windows is further enhanced by reduced by-case basis. Coupled to this are substantial reductions in
chiller costs as well as reduced boiler costs (see paragraph running costs and carbon emissions. All these benefits are
below), making the financial case even stronger. attained in a building that provides comfort conditions that
are at least as good as conventional designs. The approach
will also improve the overall quality of construction and the
£40 longevity of the building, thereby contributing to the wider
sustainability agenda.
Costs/savings / (£/m2)

£30

Glazing Level 2 5 Summary and design


£20
Level 1 Level 3 checklist
£10 This publication has sought to demonstrate that high
performance envelopes can deliver substantial benefits in
allowing simpler, more efficient HVAC strategies. The
£0 evidence suggests that buildings designed to the standards
20 30 40 50 60 70 80
Window area / % 180
Boiler
Figure 4.7 Marginal extra costs of windows and reduction in heating 160
Chiller
system costs 140
120
Capacity / kW

Figure 4.8 shows that the design space heating demand in


the case study is reduced by ~50%. The overall savings 100
through the reduced boiler size will be modest, because the 80
ventilation heat loss is increasingly dominant, and this
component is not being affected by the proposed design 60
strategy. It is anticipated that the savings will not amount 40
to more than £1/m2 although, depending on building size,
this might increase by utilising simpler domestic style 20
boilers. If domestic wall-hung boilers are used, there will be 0
reduced requirement for plant room space. Current Advanced envelope
Light Heavy
Similarly, Figure 4.8 shows the required chiller capacity is Figure 4.8 Calculated plant sizes (excluding ventilation and plant
reduced by 20%. Cooling costs for office buildings are margin
28 HVAC strategies for well-insulated airtight buildings

Table 4.1 Level of cost savings associated with changeover modes


typically £30–40/m2 (32), so the enhanced solar protection
discussed in section 3.1
might generate costs savings of £5/m2 or slightly more. This
Level Description of system option Budget cost benefit could be used to reduce capital costs, or to re-invest
reduction the savings in free-cooling equipment that will significantly
1 Eliminate perimeter heating elements only £5–7/m2 reduce running costs.
(LTHW pipework connected to each bank of
radiant panels) Taken in combination, the elimination of the perimeter
2 Eliminate both the perimeter heating elements £25–30/m2 heating elements and the downsizing of boiler and chiller
and the LTHW pipework from edge of heating/ plant is likely to generate cost reductions for mechanical
cooling zone to the radiant panels plant of about £12/m2. This would finance the extra window
cost for glazing ratios of 45% and below. If elements of the
3 Eliminate perimeter heating elements and all £28–34/m2
LTHW pipework can be eliminated (levels 2 or 3), overall
LTHW distribution pipework other than in
the plant room savings of between £15–35/m2 are possible, or approxi-
mately 1.5–4% of total building cost.

addition to these direct cost savings there is the added


value associated with the extra perimeter space and the 4.5 Maintenance costs
increased space flexibility.
It is difficult to provide quantified maintenance data, but it
Figure 4.7 shows how these cost savings usually more than is probably reasonable to assume that fewer and smaller
compensate for the additional window cost of £70/m2 (see mechanical systems should lead to reduced maintenance
section 4.3.1). To aid comparison, this cost has been requirements. This trend is likely to be enhanced by the
translated to a floor area basis for the case of a building with fact that the range of loads over which the plant will operate
a floor-to-ceiling height of 2.8 m and a plan width of 15 m. will be compressed, leading to reduced low load operation.
The window area is expressed as a function of the visible
wall area looking from the inside of the room. The saving
in terminal device cost is comparable to the additional 4.6 Whole-life cost
window cost at low glazing ratios. However, if some of the
LTHW pipework is eliminated (levels 2 or 3), significant cost The simplified cost data given above suggest that the
savings of £10–25/m2 are possible, depending on glazing approach described in this document would be cheaper in
ratio. It should be noted that the marginal window cost terms of capital costs than current design approaches,
included high solar protection, and so the cost benefit of although this would always need to be checked on a case-
the improved windows is further enhanced by reduced by-case basis. Coupled to this are substantial reductions in
chiller costs as well as reduced boiler costs (see paragraph running costs and carbon emissions. All these benefits are
below), making the financial case even stronger. attained in a building that provides comfort conditions that
are at least as good as conventional designs. The approach
will also improve the overall quality of construction and the
£40 longevity of the building, thereby contributing to the wider
sustainability agenda.
Costs/savings / (£/m2)

£30

Glazing Level 2 5 Summary and design


£20
Level 1 Level 3 checklist
£10 This publication has sought to demonstrate that high
performance envelopes can deliver substantial benefits in
allowing simpler, more efficient HVAC strategies. The
£0 evidence suggests that buildings designed to the standards
20 30 40 50 60 70 80
Window area / % 180
Boiler
Figure 4.7 Marginal extra costs of windows and reduction in heating 160
Chiller
system costs 140
120
Capacity / kW

Figure 4.8 shows that the design space heating demand in


the case study is reduced by ~50%. The overall savings 100
through the reduced boiler size will be modest, because the 80
ventilation heat loss is increasingly dominant, and this
component is not being affected by the proposed design 60
strategy. It is anticipated that the savings will not amount 40
to more than £1/m2 although, depending on building size,
this might increase by utilising simpler domestic style 20
boilers. If domestic wall-hung boilers are used, there will be 0
reduced requirement for plant room space. Current Advanced envelope
Light Heavy
Similarly, Figure 4.8 shows the required chiller capacity is Figure 4.8 Calculated plant sizes (excluding ventilation and plant
reduced by 20%. Cooling costs for office buildings are margin
References 29

outlined here should be more economic to construct, allow 7 Weir G and Muneer T Low emissivity coatings in high-
better use of space and provide good comfort conditions. performance double-glazed windows: energy, monetary and
However, the achievement of these desirable objectives environmental costs Building Services Engineering Research &
Technology 18 (2) 125–127 (1997)
does require careful thought to both design and con-
struction to ensure the necessary standards are met. The 8 Ventilation and air conditioning CIBSE Guide B2 (London:
following checklist summarises the key points that need to Chartered Institution of Building Services Engineers) (2001)
be achieved. 9 Testing buildings for air leakage CIBSE Technical Memoranda
— Good window U-values, of the order of 2.0 W/m2·K TM23 (London: Chartered Institution of Building Services
or better, depending on the glazing ratio. The frame Engineers) (2000)
design is as important as the glazing specification 10 Environmental criteria for design Section 1 in Environmental design
when seeking such U-value standards. CIBSE Guide A (London: Chartered Institution of Building
Services Engineers) (1999)
— Good solar protection, offering shading coefficients
of 0.3 or better. 11 McIntyre D A Radiation draughts Building Services Engineer 43
136–139 (October 1975)
— Good envelope airtightness — an air leakage index
of 5 (m3/h)/m2 at 50 Pa. This requires careful detail- 12 Heiselberg P Draught risk from cold vertical surfaces Building
and Environment 29 (3) 297–301 (1994)
ing of the air barrier, and a pressure test of the
completed assembly to ensure the standard is 13 ISO 7730: Moderate thermal environments - determination of PMV
achieved in practice. and PPD indices and specifications of the conditions for thermal comfort
(Geneva: International Standards Organisation) (1994)
— Care over the detailing of the envelope to minimise
the effects of cold bridging. Similar care over instal- 14 Littlefair P J Solar shading of buildings BRE Report BR364
lation is needed to ensure the insulation is con- (Garston: Building Services Establishment) (1999)
tinuous. Thermographic surveys of the construc- 15 Thermal response and plant sizing Section 5 in Environmental design
tion are a useful tool to ensure the required CIBSE Guide A (London: Chartered Institution of Building
standards are achieved in practice. Services Engineers) (1999)

— Special consideration given to areas of increased 16 Best practice in the specification of offices (London: British Council
exposure to external conditions — e.g. corner rooms, for Offices) (2000)
spaces with exposed floors (such as those above 17 Borland S Private communication
underground car parks) etc. In such cases, provision
may be needed for local supplementary heating. 18 Sampson Windows Private communication

19 . Haughey D The right way for industrial buildings Architects


— Consideration of the benefits of increased thermal
Journal (9th June 1993)
mass to provide passive heat (and ‘coolth’) recovery.
This will also facilitate the use of overnight trickle 20 An introduction to infrared thermography for building surveys
heating as a means of ensuring optimum comfort BRE Information Paper IP7/90 (Garston: Building Research
during cold weather. Establishment) (1990)

— Use of displacement diffusers with a high induction 21 Guidance to the standard specification for thermal imaging of non-
electrical building services installations BSRIA Facilities
ratio to maximise the free-cooling potential of the
Management Specification FMS 6/2000 (Bracknell: Building
ventilation air. Services Research and Information Association) (2000)
— Configuring the heat rejection system pipework 22 Braham D, Barnard N and Jaunzens D Thermal mass in office
such that free-cooling can be used for much of the buildings, Part 1 An introduction, Part 2 design criteria BRE Digest
year to generate the chilled water supplied to the 454 (Garston: Building Research Establishment) (2001)
radiant panels.
23 Limiting thermal bridging and air leakage: robust construction details
— Careful consideration of the likely pattern of inter- for dwellings and similar buildings (Garston: Building Research
nal gain through the space, so that an appropriate Establishment) (in press)
balance can be struck between cost and the degree 24 Heating CIBSE Guide B1: (London: Chartered Institution of
of flexibility to heat and cool simultaneously. Building Services Engineers) (1986)

25 Butler D J G and Alamdari F Chilled ceilings and beams -


opportunities for free-cooling Proc. Institute of Refrigeration 1998-
References 1999 94–103
1 Conservation of fuel and power in buildings other than dwellings,
26 Lovell G Private communication,
Approved Document L2 2002 edition (London: Stationery
Office) (2001) 27 Going to ground Building Services 21 (10) 15–17 (October 1998)
2 PROBE 14 — Elizabeth Fry building Building Services 20 (4) 28 Displacement ventilation in non-industrial premises REHVA
37–42 (April 1998) Guidebook No. 1 (Leusden, Netherlands: European Federation
of Heating and Air Conditioning Associations) (2002)
3 Whole life costing: a client’s guide (London: Construction Clients
Forum) (2000) 29 Improved life cycle performance of ventilation systems PII Project
Report (St Albans: Oscar Faber) (2001)
4 Whole life costs Construction Procurement Guidance No 7
(London: Office of Government Commerce) ( 2000) 30 Franklin and Andrews Private communication (2001)
5 Building a better quality of life (London: Department of 31 Out of town commercial offices cost model Building Services 21
Environment, Transport and Regions) (2000) (4) 15–17 (1999)
6 Energy use in offices Energy Efficience Best Practice Programme 32 Spon’s Mechanical and Electrical Services Price Book 2002
ECON 19 (Garston: BRECSU) (1998) (London: Spon Press) (2001)
References 29

outlined here should be more economic to construct, allow 7 Weir G and Muneer T Low emissivity coatings in high-
better use of space and provide good comfort conditions. performance double-glazed windows: energy, monetary and
However, the achievement of these desirable objectives environmental costs Building Services Engineering Research &
Technology 18 (2) 125–127 (1997)
does require careful thought to both design and con-
struction to ensure the necessary standards are met. The 8 Ventilation and air conditioning CIBSE Guide B2 (London:
following checklist summarises the key points that need to Chartered Institution of Building Services Engineers) (2001)
be achieved. 9 Testing buildings for air leakage CIBSE Technical Memoranda
— Good window U-values, of the order of 2.0 W/m2·K TM23 (London: Chartered Institution of Building Services
or better, depending on the glazing ratio. The frame Engineers) (2000)
design is as important as the glazing specification 10 Environmental criteria for design Section 1 in Environmental design
when seeking such U-value standards. CIBSE Guide A (London: Chartered Institution of Building
Services Engineers) (1999)
— Good solar protection, offering shading coefficients
of 0.3 or better. 11 McIntyre D A Radiation draughts Building Services Engineer 43
136–139 (October 1975)
— Good envelope airtightness — an air leakage index
of 5 (m3/h)/m2 at 50 Pa. This requires careful detail- 12 Heiselberg P Draught risk from cold vertical surfaces Building
and Environment 29 (3) 297–301 (1994)
ing of the air barrier, and a pressure test of the
completed assembly to ensure the standard is 13 ISO 7730: Moderate thermal environments - determination of PMV
achieved in practice. and PPD indices and specifications of the conditions for thermal comfort
(Geneva: International Standards Organisation) (1994)
— Care over the detailing of the envelope to minimise
the effects of cold bridging. Similar care over instal- 14 Littlefair P J Solar shading of buildings BRE Report BR364
lation is needed to ensure the insulation is con- (Garston: Building Services Establishment) (1999)
tinuous. Thermographic surveys of the construc- 15 Thermal response and plant sizing Section 5 in Environmental design
tion are a useful tool to ensure the required CIBSE Guide A (London: Chartered Institution of Building
standards are achieved in practice. Services Engineers) (1999)

— Special consideration given to areas of increased 16 Best practice in the specification of offices (London: British Council
exposure to external conditions — e.g. corner rooms, for Offices) (2000)
spaces with exposed floors (such as those above 17 Borland S Private communication
underground car parks) etc. In such cases, provision
may be needed for local supplementary heating. 18 Sampson Windows Private communication

19 . Haughey D The right way for industrial buildings Architects


— Consideration of the benefits of increased thermal
Journal (9th June 1993)
mass to provide passive heat (and ‘coolth’) recovery.
This will also facilitate the use of overnight trickle 20 An introduction to infrared thermography for building surveys
heating as a means of ensuring optimum comfort BRE Information Paper IP7/90 (Garston: Building Research
during cold weather. Establishment) (1990)

— Use of displacement diffusers with a high induction 21 Guidance to the standard specification for thermal imaging of non-
electrical building services installations BSRIA Facilities
ratio to maximise the free-cooling potential of the
Management Specification FMS 6/2000 (Bracknell: Building
ventilation air. Services Research and Information Association) (2000)
— Configuring the heat rejection system pipework 22 Braham D, Barnard N and Jaunzens D Thermal mass in office
such that free-cooling can be used for much of the buildings, Part 1 An introduction, Part 2 design criteria BRE Digest
year to generate the chilled water supplied to the 454 (Garston: Building Research Establishment) (2001)
radiant panels.
23 Limiting thermal bridging and air leakage: robust construction details
— Careful consideration of the likely pattern of inter- for dwellings and similar buildings (Garston: Building Research
nal gain through the space, so that an appropriate Establishment) (in press)
balance can be struck between cost and the degree 24 Heating CIBSE Guide B1: (London: Chartered Institution of
of flexibility to heat and cool simultaneously. Building Services Engineers) (1986)

25 Butler D J G and Alamdari F Chilled ceilings and beams -


opportunities for free-cooling Proc. Institute of Refrigeration 1998-
References 1999 94–103
1 Conservation of fuel and power in buildings other than dwellings,
26 Lovell G Private communication,
Approved Document L2 2002 edition (London: Stationery
Office) (2001) 27 Going to ground Building Services 21 (10) 15–17 (October 1998)
2 PROBE 14 — Elizabeth Fry building Building Services 20 (4) 28 Displacement ventilation in non-industrial premises REHVA
37–42 (April 1998) Guidebook No. 1 (Leusden, Netherlands: European Federation
of Heating and Air Conditioning Associations) (2002)
3 Whole life costing: a client’s guide (London: Construction Clients
Forum) (2000) 29 Improved life cycle performance of ventilation systems PII Project
Report (St Albans: Oscar Faber) (2001)
4 Whole life costs Construction Procurement Guidance No 7
(London: Office of Government Commerce) ( 2000) 30 Franklin and Andrews Private communication (2001)
5 Building a better quality of life (London: Department of 31 Out of town commercial offices cost model Building Services 21
Environment, Transport and Regions) (2000) (4) 15–17 (1999)
6 Energy use in offices Energy Efficience Best Practice Programme 32 Spon’s Mechanical and Electrical Services Price Book 2002
ECON 19 (Garston: BRECSU) (1998) (London: Spon Press) (2001)
30 HVAC strategies for well-insulated airtight buildings

Appendix A1: Modelling methods 22 °C). At this condition, perimeter losses exactly matched
internal gains, representing the most extreme condition for
In order to prove the concepts outlined above, a comprehen- a system without perimeter heating. The measured glass
sive series of modelling (physical and computational) were surface temperature at these conditions can be used to
carried out. These are described in the following sections. predict the required glazing performance for any outside
and inside design conditions. Detailed measurements of
the comfort parameters were taken in the zone immediately
adjacent to the window.
A1.1 Climate chamber tests
For the summer tests, the purpose was to compare the
Climate chamber testing of realistic room mock-ups with performance of the proposed system with a system more
fully functioning HVAC systems is perhaps the most typical of current good practice. The reference case was a
credible way to demonstrate accurately the performance of radiant ceiling panel system, with an additional passive
HVAC systems and their interaction with the building fabric
chilled beam to cope with the perimeter load. Some solar
and indoor climate. A 6.5 m deep by 3.2 m wide office control was provided via external brise-soleil. The test
module was therefore simulated in a climate chamber system just incorporated the radiant ceiling panels, but
(Figure A1.1). with a higher performance envelope.
Tests were run for both summer and winter conditions.
Internal gains representing people, lights and computers A1.2 Dynamic thermal modelling
were placed in the chamber. The effect of a window in the
end-wall of the chamber was simulated by passing chilled In operational terms, the performance of the concept over
(winter) or warm (summer) water through coils embedded the whole year is perhaps more important than performance
in the wall. The size of the window was varied by blanking at the design condition, which by definition will occur less
off sections of the end wall with insulation board, such that than 2.5% of the time. Detailed thermal simulations were
the surface temperature of the ‘wall’ was equivalent to that carried out to assess the distribution of comfort conditions
to be expected for a wall U-value of ~0.3 W/m2·K. Detailed through a typical year.
traverses of air and globe temperatures and air speed were
made so that detailed assessments of comfort could be Figure A1.2 shows a sample output, comparing the
determined. temperature distributions for two versions of the advanced
concept (one lightweight, the other heavy) against a
For the winter tests, the main purpose was to assess comfort reference design built to current practice standards.
in the situation where there was no perimeter heating. Detailed investigations were also made of typical design
Consequently, no active heating or cooling was provided, weeks of hot and cold weather, to better understand the
other than the effect of the displacement ventilation dynamics of the building response. As well as modelling the
system. The surface temperature of the ‘window’ was building fabric, the performance of the HVAC system and
progressively lowered until thermal balance was achieved controls was simulated. This enabled the effect of the
at two pre-defined internal dry-bulb temperatures (20 and changeover control strategy to be assessed, as well as
determining the likely impact of the approach in reducing
energy consumption and carbon emissions.

Initial modelling was based on examining a number of


typical office modules. In this way, a wide range of
parameters was investigated, including orientation, win-
dow size and U-value, thermal capacity, pre-heat strategies,
and heating to cooling changeover modes. The new design
concept was compared with a reference building construct-
ed to 1995 Part L standards, with the exception of the
glazing, which was to an improved standard, typical of
current practice (i.e. double glazing with a U-value of 2.7

60
Advanced envelope
(heavy)
50
Percentage of total office
hours (0900–1800) / %

Advanced envelope
(light)
40
1995 Building
Regulations
30

20

10

0
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Room dry resultant temperature / °C
Figure A1.1 BRE climate chamber during tests Figure A1.2 Typical temperature frequency plot
Appendix A1: Modelling methods 31

rather than 3.3 W/m2·K ). The final round of modelling was The performance of the units was assessed for both winter
based on a complete real building in order to enable and summer performance in terms of U-value, internal
estimates of energy/CO2 performance to be made. To that surface temperatures and shading coefficient. Particular
end the reference building was conditioned with a 4-pipe attention was given to the performance of units with very
fan coil system, with perimeter heating scheduled to low-emissivity coatings (ε = 0.02–0.06, rather than the
outside conditions. more common ε = 0.16, such as the Pilkington K-glass).

A1.3 Finite element modelling A1.4 Computational fluid dynamics

Two-dimensional finite element modelling was used Computational fluid dynamics (CFD) was undertaken to
(Figure A1.3) to predict the distribution of window surface understand better the detail of the comfort conditions
temperatures (glazing and frame), and how this would vary throughout a typical office module (Figure A1.4). The work
as a function of meteorological wind-speed, incident solar was carried out in two stages; first, to compare predictions
radiation etc. The work highlights the importance of the against the climate chamber measurements, and then to
frame in achieving good overall window U-values, since simulate situations that would be impractical to model in
centre-pane U-values are usually better than whole-window the climate chamber (e.g. a corner room with cold glazing
values. Analyses were carried out for a range of window on two adjoining walls).
types typical of modern practice:
The degree of correlation between climate chamber and
— a thermally broken aluminium framed window CFD predictions was encouraging, enabling the modelling
typical of smaller non-domestic buildings of the more complex configurations to proceed with
confidence. Key parameters in the modelling were the
— a curtain walling construction more commonly proper representation of the floor mounted swirl diffusers
used in large scale commercial projects and the need to model the detailed radiation exchanges,
since these are crucial to the perception of comfort. One
— a ‘2+1’ window (double-glazed inner unit plus interesting point to emerge from the comparison of test
single glazed outer unit). chamber and CFD was the impact of the heat gain from
computers. These were initially modelled as convective
heat sources, resulting in a fairly strong buoyant plume that
dominated the flow field. In reality, the majority of the heat
from the computer is ejected via the cooling fan in the
computer case, resulting in a much higher degree of
horizontal entrainment and general mixing.

Figure A1.3 Finite element modelling of window Figure A1.4 Typical CFD output
Foreword
This publication reports the results of a major Partners in Innovation project that studied
the impact of high performance envelopes on the servicing strategy for office-type
buildings. The work was based on a range of detailed computer modelling techniques
supported by extensive climate chamber testing. The results suggest that there are
significant commercial benefits to be had from high performance envelopes. Equivalent
comfort conditions, significantly reduced operating and management costs and improved
space utilisation are achievable at costs no greater and possibly slightly less than
conventional air-conditioning systems. Although these ideas have not yet been fully
tested in practice, experience gained from the closest current exemplar, the Elizabeth Fry
building at the University of East Anglia, adds credibility to the conclusions presented.

Improved envelope standards will be required by the changes to Part L of the Building
regulations that come into force in 2002. This document demonstrates how such changes
to envelope standards can open up new opportunities for innovative design solutions that
are cost effective and make a major contribution to the wider sustainability agenda.

Steve Irving
Principal author

Acknowledgements
The work leading to the production of this publication was carried out as a Partners in
Innovation project co-ordinated by Oscar Faber. The funding provided by the
Department of Trade and Industry is gratefully acknowledged. The contributions of the
other project partners are also gratefully acknowledged. The project partners and their
representatives on the steering group are listed below.

Oscar Faber Group Ltd. S Irving, Q Babcock, A Wilson


Building Research Establishment Ltd F Alamdari, D Butler, A Perry
BSRIA Ltd. A Martin
Building Sciences Ltd. S Borland
CIBSE D Braham
Department of Trade and Industry G Henderson
Flomerics Ltd. M Seymour, S Somarathne
IPPEC Systems Ltd. M Namih
Klima-Therm (Distribution) Ltd. G Lovell
Pilkington plc R Wilberforce, J Bradshaw
Trox (UK) Ltd. A Green, F Tarada
SAS International Ltd. D Wisely

In addition to the members of the project partners listed above, thanks are also due to J
Lawrence (Sampson Windows Ltd.) and D Wadham (Franklin+Andrews), who provided
useful information for this publication. The measurement and analysis work that
provided the information on which this document is based was carried out by Quentin
Babcock, David Butler, Arron Perry, Mark Seymour and John Bradshaw.

The authors are also thankful to the CIBSE referees who provided a very thorough and
helpful review of the draft document.

This document is published with the consent of the Department of Trade and Industry,
but the views expressed are not necessarily accepted or endorsed by the Department.

Principal authors
S Irving (Oscar Faber)
S Borland (Building Sciences)
Editor
Jackie Wilson

CIBSE Editorial Manager


Ken Butcher

CIBSE Research Manager


Hywel Davies

CIBSE Publishing Manager


Jacqueline Balian

Note from the publisher


This publication is primarily intended to provide guidance to those responsible for the
design, installation, commissioning, operation and maintenance of building services. It is
not intended to be exhaustive or definitive and it will be necessary for users of the guidance
given to exercise their own professional judgement when deciding whether to abide by or
depart from it.
INDEX

Index Terms Links

Advanced envelopes 20–25


Air leakage 16–17
Air leakage index 4 16–17
permeability 16
Airtightness 2 16–17

Blinds 13–14
Building
costs 27
fabric 18–20
orientation 8 9 11
types suitable 13
Building Regulations Part L
2002 edition 1 3 4 17
23 27
1995 edition 11 26 30

Carbon intensity 23
Carbon emissions 2 26
Carbon dioxide emissions 2 26
Cavity walls 18–19
Ceiling panels 21–22
Central plant 23–25
Changeover strategies 21–22
2-pipe 20 21
4-pipe 21
reversible heat pumps 22
whole-building 21
zoned 21
Cladding 19–20
Climate change levy 1
Climate chamber tests 5–6 10 29
Cold bridging 15 18
This page has been reformatted by Knovel to provide easier navigation.
Index Terms Links

Cold radiation 5
Comfort
occupant 3 5–9 10–11 20–26
occupant, assessment of 5–9
summer 10–11
thermal 8
Computational fluid dynamic analysis 6 30–31
Condensing boiler 23
Construction 14–20
Construction costs 1
Cooling 24
chilled beam system 10 24
ground source 24
systems 10–11
Corner rooms 6 8–9 11
Costs
building 27
construction 1
energy 1 25–28
fabric 27
maintenance 28
HVAC 27
initial 3
operating 3
maintenance 3
whole life 2 28
windows 27
Curtain walling 19–20

Daylight 14
Design and construction 15–16 17
Displacement ventilation 6 10 20 25
Downdraughts 5 6
Dynamic thermal modelling 8–9 30

Economic indicators 2
Embodied energy 2
Energy costs 1 26–27 28
Envelope design 14–20
Environmental indicators 2
This page has been reformatted by Knovel to provide easier navigation.
Index Terms Links

Fabric (of building) 18–20


cavity walls 18–19
cladding 19–20
costs 27
curtain walling 19–20
masonry walls 18–19
performance 14–20
roof assembly 19–20
Facade, orientation 8 9 11
Finite element modelling 31
Free cooling 1 16 24 25
26

Glazing 5 10 12
Ground loop systems 23

Heat gains, level of 3 4


Heat pumps 21–22 23–24
air-source 23
ground source 23
Heating/cooling systems
2-pipe 20 21
4-pipe 21
floor 20
ventilation 20
HVAC systems
costs 27–28
impact on 3–20
with advanced envelopes 20–25

Indicators
economic 2
environmental 2
sustainability 2
Insulation 15–16 18 19
Integrated healing and cooling systems 20–23

This page has been reformatted by Knovel to provide easier navigation.


Index Terms Links

Internal temperatures, maintaining 4


Internal gains 3 4 5
Iso-surfaces 6

Light transmission 14

Maintenance costs 3 28
Market drivers 1
Masonry walls 18–19
Materials 2
Meteorological effects 13
Modelling methods 5–6 30–31

Occupant
comfort 3 5–9 10–11 20–26
productivity 3
Operating costs 3

Performance
annual 11
estimates 25–28
fabric 14–20
window 12–14
Perimeter
cooling loads 9–10
heating, elimination of 1 4–5 6
zone 3
Plant
cooling 24
heating 23–24
options 23–25
PMV 5 8 10–11
PPD 8 20
Pre–heating 4 20 23
Predicted percentage dissatisfied 8 20
Predicted mean vote 5 8 10–11
Productivity, occupant 3
This page has been reformatted by Knovel to provide easier navigation.
Index Terms Links

Quality assurance 16

Radiant panels 3 8 10 20
Radiant asymmetry 3 5 18 20
Radiation, cold 5
Roof assembly 19–20
Room, corner 6 8–9 11

Selectivity 14
Shading coefficient 9 13–14
Solar control 9 14
Solar gain 9 10 13 14
Stratification, temperature 6–8
Summer, building in 9
Summer, comfort conditions 10–11
Surface temperature 13
Sustainability indicators 2

Temperature
internal 4 13
dry resultant 5 11
stratification 6–8
surface 13
Thermal
capacity 16
comfort 8
mass 16
stratification 6–8

U-values 5 12–13
improvement in 2
standards 4

This page has been reformatted by Knovel to provide easier navigation.


Index Terms Links

Ventilation 25
and air leakage 16
displacement 6 10 20

Water loop 22 23
Whole life costs 2
Wind speed, effect of 13
Window
costs 27
performance 12–14
size 5–6
type 12
Winter, building in 4–9

This page has been reformatted by Knovel to provide easier navigation.

You might also like