Professional Documents
Culture Documents
Strategies For Well-Insulated Airtight Buildings: CIBSE TM29: 2002
Strategies For Well-Insulated Airtight Buildings: CIBSE TM29: 2002
Strategies For Well-Insulated Airtight Buildings: CIBSE TM29: 2002
ISBN 1 903287 18 9
Improved envelope standards will be required by the changes to Part L of the Building
regulations that come into force in 2002. This document demonstrates how such changes
to envelope standards can open up new opportunities for innovative design solutions that
are cost effective and make a major contribution to the wider sustainability agenda.
Steve Irving
Principal author
Acknowledgements
The work leading to the production of this publication was carried out as a Partners in
Innovation project co-ordinated by Oscar Faber. The funding provided by the
Department of Trade and Industry is gratefully acknowledged. The contributions of the
other project partners are also gratefully acknowledged. The project partners and their
representatives on the steering group are listed below.
In addition to the members of the project partners listed above, thanks are also due to J
Lawrence (Sampson Windows Ltd.) and D Wadham (Franklin+Andrews), who provided
useful information for this publication. The measurement and analysis work that
provided the information on which this document is based was carried out by Quentin
Babcock, David Butler, Arron Perry, Mark Seymour and John Bradshaw.
The authors are also thankful to the CIBSE referees who provided a very thorough and
helpful review of the draft document.
This document is published with the consent of the Department of Trade and Industry,
but the views expressed are not necessarily accepted or endorsed by the Department.
Principal authors
S Irving (Oscar Faber)
S Borland (Building Sciences)
Contents
1 Introduction 1
1.1 Market drivers 1
1.2 Sustainability indicators 2
4 Performance estimates 25
4.1 Comfort 26
4.2 Energy costs/carbon emissions 26
4.3 Building costs 27
4.4 HVAC costs 27
4.5 Maintenance costs 28
4.6 Whole-life cost 28
References 29
This publication explores the potential for high performance The design strategy presented represents a significant shift
building envelopes to simplify the design and operation of from current design norms. Despite this, there are market
HVAC systems. The keys to such high performance envelopes trends that should encourage the adoption of the approach.
are windows with low U-values and good solar protection,
coupled with good structural airtightness. These features are 1.1.1 Part L of the Building Regulations
readily attainable at marginal cost through careful design and
construction. Indeed, industry will be driven in this direction The 2002 edition of Part L of the Building Regulations(1)
by changes in the 2002 edition of Part L of the Building requires designers to make significant changes to current
Regulations(1). The practical achievement of high perfor- design norms. Key features include:
mance envelopes* can deliver the following commercial
benefits: — significant improvement in envelope standards,
including provisions to control solar overheating
— Eliminate the need for perimeter heating†,
plus and to obtain reasonable standards of airtightness
enable significant reductions in the installed
capacity of heating and cooling plant. This will — minimum efficiency standards for heating systems
reduce the capital costs for HVAC plant.
— minimum efficiency standards for air conditioning
— Free up valuable perimeter space in addition to and mechanical ventilation systems based on limit-
saving some distribution and plant room space by ing the installed input power of equipment.
eliminating perimeter heating. This will add sig-
nificant commercial value to the scheme. The design approach propounded herein takes the envelope
standards a little in advance of the standards in the 2002
— Allow simplification of the controls installation
Approved Document L(1), particularly in terms of window
and strategy, again reducing costs but also improv-
standards and airtightness. This results in low heating
ing manageability and maintainability.
demands, allowing heating systems to operate at low water
— Enable HVAC systems to operate at very high temperatures, facilitating very high efficiency systems.
efficiencies, thereby resulting in low operating Through good solar protection of glazed areas, installed
energy consumption. chiller capacities will also be significantly reduced. Cooling
— Improve the investment profile: the envelope has a systems can then similarly operate at higher water temp-
longer service life than the HVAC plant, so the eratures, allowing increased coefficient of performance (CoP)
investment shifted from savings in plant to for the chiller and substantial opportunities for free-cooling.
additional cost in the envelope can be amortised This publication therefore offers an effective solution to the
over a longer period, generating further indirect design challenge presented by the 2002 Part L; indeed, it
financial benefit. enhances and ‘future-proofs’ the design against proposed
further tightening of the standards.
— Provide good comfort: climate chamber tests
coupled with detailed computer modelling work
suggest that even with significant areas of glazing, 1.1.2 Climate change levy
good year-round comfort can be maintained.
In April 2001, the climate change levy was introduced,
This publication outlines the evidence for this approach thereby increasing the energy costs for business and
based on the results from a comprehensive series of climate industry. Given the increasing concerns over climate
chamber tests and a range of detailed computer modelling change, the impact of this levy is likely to increase with
studies. Real buildings adopting all the concepts proposed time. There is, therefore, an increasing business incentive
have yet to be constructed; the closest current exemplar is the to reduce energy costs. The approach proposed here offers
Elizabeth Fry building at the University of East Anglia, substantial reductions in energy use, whilst retaining high
Norwich. The PROBE report(2) records both excellent energy standards of occupant comfort. These benefits are achieved
and occupant satisfaction ratings for this building, giving at costs no greater, and potentially somewhat less, than
added confidence to the conclusions presented here. current norms. It also facilitates the use of low capacity but
high efficiency equipment; equipment that may well
qualify for enhanced capital allowances.
* As detailed in later sections, the achievement of high performance
envelopes requires attention to design details and construction practice.
Without such careful attention at all stages of construction, the simpler 1.1.3 Lower cost but improved quality
systems proposed will not deliver the required performance.
† This is only practical for sealed buildings with winter mechanical A major challenge facing the industry is to reduce
ventilation; natural ventilation/mixed mode may be possible in warmer construction costs by 30% whilst improving service to
weather, but any openable window needs to seal well on closure for this clients. The design concepts outlined in this document
to work effectively in winter. should make a significant contribution to achieving this
2 HVAC strategies for well-insulated airtight buildings
goal. Initial construction costs may well be reduced, but for truly sustainable buildings (5). Sustainability has a
another important aspect is that the cost distributions will number of interlinking themes, and it is believed that the
change. More money will go into the elements with the proposed design concept scores highly in all areas.
greater service life (i.e. the fabric), and less into the elements
that need more frequent replacement (either as a result of
normal wear and tear, or through a new fit-out following a 1.2.1 Environmental
change in occupier requirements). The approach, therefore,
offers a more robust and enduring investment strategy. 1.2.1.1 Carbon emissions
The strategy offers substantial whole-life cost benefits (see Concern over climate change is a significant policy driver,
section 1.2) and so will benefit from the increasing interest and so operating carbon emissions* are a significant design
in whole life costs (3). Indeed, it is now a requirement of issue. For office-type buildings, the ECON 19 (6) data set
public sector purchasers that they move to whole-life cost gives valuable bench marks for ‘typical’ and ‘good practice’
based procurement (4). As detailed later, the degree of standards†. It is always difficult to compare design predic-
comfort and operating cost delivered through this approach tions with actual operating performance but so as to give an
will also add to the quality of the building. indication of the expected level of performance, Figure 1.1
shows a comparison between the ECON 19 data and the
performance which it is expected can be achievable through
1.1.4 Flexibility and adaptability high performance envelopes. The ‘A/C’ buildings are
comfort cooled while the ‘nat vent’ are naturally ventilated.
Flexibility and adaptability are essential elements of a The strategy presented in this publication provides comfort
building that is to be capable of meeting varying needs over cooling, giving comfort performance equivalent to the ‘A/C’
its design life. High performance envelope design reduces type but with carbon emissions reduced by 40% or more
perimeter loads for heating and cooling, such that different from good ‘A/C’ standards.
zones have comparable loadings and servicing needs.
1.2.1.2 Use of materials
1.1.5 Integrated approach
Sustainability is also about efficient use of materials and
The benefits of an integrated approach to design and resources. High performance envelopes help also in this
construction are recognised by many. The technical respect. Investment is transferred from (relatively) short-
concepts presented here are dependent on the realisation of lived plant into longer life fabric measures; measures that
such integration. The success of the HVAC strategy relies on also need little maintenance. It is important to realise that
the effectiveness of the envelope in terms of insulation, although HVAC plant has an expected service life of say 15–20
airtightness and solar protection. These issues are often at years, plant (especially terminal equipment) is often removed
the boundaries between the members of the design team and scrapped as part of a new fit-out well before the end of its
and the contractor. It is therefore essential that responsibil- useful life. A high performance envelope is much more likely
ity for these issues is clearly identified, with all the team to fulfil its service life than is the M&E equipment.
working together to deliver the required objective. The
client has a particular responsibility to ensure testing of the Another aspect of the use of materials is that of embodied
envelope as part of the total commissioning process — the energy. At the current state of knowledge, this is difficult to
envelope performance is as much part of the HVAC strategy quantify. However, in terms of the main areas of enhanced
as the boiler or the chiller plant. envelope design, significant overall performance improve-
ments can be obtained with few additional materials. For
example:
1.2 Sustainability indicators — The improvement in window U-values can largely
be achieved through the use of selective glass
In order to assess the proposed design concepts, it is coatings. Research into the application of such
necessary to benchmark performance against a reference coatings to housing has demonstrated that the
building typical of current good practice. The strategy is lifetime CO2 and energy savings are several hundred
offered as a potentially significant contributor to the drive times larger than the extra embodied CO2 /energy (7).
— Improved airtightness is achieved more through
TM29 strategy
careful design details and construction practice than
through the use of substantial additional materials.
Nat.vent. (good)
1.2.2 Economic
Nat.vent. (typical)
Economic indicators are extremely important to the con-
struction industry. Traditionally, designs have been driven
A/C (good)
* The data presented here are given in terms of emissions of carbon, rather
A/C (typical) than carbon dioxide, since the former is the preferred unit for the
government’s climate change programme.
0 10 20 30 40
† ECON 19 gives the CO2 emissions in terms of carbon equivalent to be
Carbon emission / (kg/m2) per annum
consistent with the units used by the government’s climate change
Figure 1.1 Relative operating carbon emissions programme (1 kg CO2 emissions is equivalent to 0.273 kg carbon).
Impact of advanced envelopes on HVAC requirements 3
Ventilation
Occupancy
Infiltration
Window
Lights 10 W/m2 (of which 10 W/m2 (of which 5
Wall
6.5 W/m2 was seen as a 6.5 W/m2 was seen as a
Loads / (W/m2)
gain to the space) gain to the space) 0
People
Equipment
Lights
Net
Small power 6–12 W/m2 15–25 W/m2
–5
are slightly less demanding for roofs and floors. The better –10
standards required for roofs and floors will improve the
performance of ground and top floor zones compared with –15
the results given in the following sections.
–20
An air leakage index standard of 5 (m3/h)/m2 @ 50 Pa was Figure 2.1 Winter energy balance
set, which is significantly in advance of the standard given
in the 2002 Approved Document L, but is in line with the amounts of localised heating may be required in corner
good practice recommendations of TM23 (9). rooms with more than one external surface.
The reference internal gains assumed for the space are Traditionally, perimeter heating has been installed to fulfil
considered typical of modern offices. For the winter a number of requirements. The way these requirements
analyses the loads were also varied to be on the low side of change with the use of high performance envelopes is
normal; for the summer tests the gains were varied from discussed in the following sub-sections.
typical to high for both occupancy and small power loads.
The data are summarised in Table 2.2.
2.2.1.1 Maintaining internal temperatures
2.2 The building in winter With a high performance envelope, moderate levels of inter-
nal gain are sufficient to offset perimeter losses, even during
2.2.1 Elimination of perimeter heating design weather sequences. Figure 2.1 compares the typical
balance of gains and losses in an office-type building
A key thesis of this publication is that perimeter heating is designed to standards typical of 2000 practice, and those
unnecessary in well-insulated airtight buildings (equipped proposed in this publication. The differences between the
with mechanical ventilation in winter). The elimination of specifications for the two sets of results are summarised in
perimeter heating can have significant commercial implica- Table 2.4. The last pair of bars in Figure 2.1 shows the net
tions. First, there is the direct cost saving of the terminal units gains to the space.
(equipment and installation) and the associated distribution
system. Secondly, but perhaps more significantly, it frees The conventional design shows a significant net heat loss,
valuable perimeter space and enables more flexible partition- whereas the high performance envelope shows a significant
ing arrangements. In city centre locations, where space is at a gain, even without taking any beneficial winter solar gain
premium, this can add significant value to the project. The into account. Consequently, in a building with typical
window U-value is the critical factor as far as achieving the occupancy and with a high performance envelope, the role
required insulation performance is concerned. It should be of the heating system becomes one of ensuring the building
stressed that the required window standards do not represent is up to temperature at the beginning of occupancy, not
premium products. Indeed, as indicated in Table 2.3, the target maintaining it once occupancy has started.
overall window U-values (1.5–2.0 W/m2·K) are required as
minimum standards in many European countries.
Table 2.4 Comparison between specifications for conventional and
‘TM29’ designs
It should be noted that heating is still required for pre-heat
purposes, but this can be achieved without recourse to a Parameter Conventional design TM29 design
separate, specific perimeter heating system (see section External design temperature (°C) –3 –3
3.1.1). It should also be emphasised that at design
conditions and dependent on the degree of glazing, small Internal design temperature (°C) 21 21
Wall U-value (W/m2·K) 0.45 0.30
Table 2.3 Window U-values required in European countries Window ratio in external wall (%) 50 50
Country U-value standard Window U-value (W/m2·K) 2.8 1.5
(W/m2·K)
Occupant density (m2/person) 12 12
Austria 1.9
Equipment gain (W/m2) 10 10
Denmark 1.8
Lighting gain (W/m2)* 6.5 6.5
Finland 1.4*
Infiltration (ACH) 0.5 0.15
Netherlands 1.2*
Ventilation rate (ACH) 3 3
Norway 1.6
Ventilation supply temperature (°C) 19 19
Russia 1.8
* proposed * Lighting load 10 W/m2, but 35% is removed via air-handling luminaires
Impact of advanced envelopes on HVAC requirements 5
Radiant assymetry / K
to ensure local comfort rather than to maintain overall 6
internal temperatures. Because of the relatively lower
thermal performance of the window, glass surface 4
temperatures can become quite low, creating local
discomfort problems with radiant asymmetry. CIBSE
Guide A(10) suggests that radiant asymmetry from a cool 2
wall should be limited to 10 K. Figure 2.2 shows the radiant
asymmetry for a 50% glazed façade with a window of U- 0
value 2.0 W/m2·K. This analysis (based on the work of 0 0·5 1 1·5 2 2·5
McIntyre(11)) indicates that, even quite close to the window, Distance from window / m
the radiant asymmetry is significantly less than this
limiting value. This means that, provided the building is Figure 2.2 Radiant asymmetry
up to temperature at the beginning of occupancy, heating is
not required to offset radiant asymmetry.
3·0
downdraught / (W/m2·K)
2·6
U-value to avoid
To ensure comfort at the perimeter, heating may also be
2·4
provided to offset the effects of downdraughts. With high
performance windows, these effects can be effectively elim- 2·2
inated without the need for any perimeter heat. Figure 2.3 2·0
shows the results of a simplified analysis based on the work
of Heiselberg (12) giving the approximate glazing U-value 1·8
required to minimise the effects of downdraught. 1·6
1·4
It should be noted that, as far as downdraught is concerned, 0·8 1 1·2 1·4 1·6 1·8 2
it is the centre-pane U-value rather than the whole window Glazing height / m
U-value that is more important. This is because it requires
significant areas of unobstructed cool surface to develop the Figure 2.3 U-value to avoid downdraught
convection current, and it is the glass rather than the frame
that provides such a surface. Currently, whole window
performance is limited by the frame technology rather than shown as a function of mean room dry resultant temperature
the glass; very low-emissivity coatings (ε ~0.02) can give for many tests covering different window sizes, internal loads,
centre-pane U-values as low as 1.0 W/m2·K for a double- ventilation rates and target room temperatures. The results
glazed unit filled with argon. Thus available glazing clearly show that perception of comfort is dominated by the
technologies can minimise downdraughts, even with average dry resultant temperature of the room. The effects of
glazing approaching full height in typical office type cold radiation and downdraught from different window
accommodation. configurations result in virtually insignificant variations
around the trend line. This suggests that local effects near the
window are largely irrelevant within the range of window
2.2.2 Detailed assessment of comfort configurations tested. The ASHRAE comfort zone is defined
as less than 20% people dissatisfied, corresponding to a PMV of
In order to validate the assertions developed in section 60.85, and so it can be seen that all test conditions (with PMVs
2.2.1, a substantial amount of climate chamber testing and ranging from –0.3 to +0.25) are well within what might
modelling has been carried out (see appendix A). reasonably be desired. Indeed, thermal neutrality could be
achieved for all conditions simply by adjusting the mean
2.2.2.1 Climate chamber tests room dry resultant temperature to around 21 °C.
gains in the space. Four window sizes were investigated (1.2, 0·2
1.5, 1.8 and 2.8 m high) in a room with a floor to ceiling height
0·1
of 2.8 m. Traverses of temperatures (air and globe) and air
speed were concentrated in the zone within 1.1 m of the 0
window, and the ISO 7730 (13) equations used to combine –0·1
these individual measurements as a means of predicting
comfort. –0·2
–0·3
The detailed results can be distilled into Figure 2.4. This
shows the predicted mean vote (PMV) at a seated head height –0·4
19·5 20 20·5 21 21·5 22 22·5
of 1.1 m and at a point only 300 mm from the window. The Mean temperature / °C
calculations were based on normal winter clothing (i.e. 1.0 =
clo) and normal sedentary activity (i.e. 1.2 = met). The PMV is Figure 2.4 PMV as function of mean dry resultant temperature in room
6 HVAC strategies for well-insulated airtight buildings
Figure 2.5 Iso-surfaces of 0.1 m/s; 1.8 m window, U = 1.5 W/m2·K, Figure 2.7 Iso-surfaces of 0.1 m/s; full height glazing, U = 1.5 W/m2·K,
constant cold conditions outside realistic design consideration
In corner rooms, the increased area of exposed façades Section 2.2.2.2 demonstrated that the downdraught from
might be expected to produce significant downdraughts the glazed elements did not penetrate far into the room. As
and thus produce discomfort in the occupied zone, a consequence, the thermal variation in a horizontal plane
particularly near the glazed elements. This has been is small except in the proximity of the computers
investigated for both generating significant vertical plumes. Very close to the
floor, the temperature also reduces near the swirl diffusers.
— the extreme design conditions of a continuous
This latter effect is most noticeable in the more energy-
period of –5 °C outside
efficient cases with smaller glazed elements and lower U-
— more realistic conditions of time varying outdoor values. This is because the room temperature is higher and
conditions. further away from the fixed supply air temperature. Table
Impact of advanced envelopes on HVAC requirements 7
Figure 2.8 Temperature stratification; 1.8 m window, U = 1.5 W/m2·K, Figure 2.9 Temperature stratification; full-height glazing,
constant cold conditions outside U = 1.5 W/m2·K, constant cold conditions outside
2.2.2.4 Thermal comfort — window U-value (1.0, 1.5 and 2.0 W/m2·K)
Computational fluid dynamics was also used to predict — small power loads (base case = 6, but also 12 W/m2):
comfort in the corner rooms (see section 2.2.2.1). Table 2.6 the effect of delaying the onset of internal gains was
shows the mean values of PMV and predicted percentage also investigated
dissatisfied (PPD) for the seated occupancy zone and the — pre-heat strategy: most of the runs were carried out
standing occupancy zone. with a simplified optimum start control. This
resulted in some underheating following very cold
These results demonstrate that even in extreme conditions weekend shut downs due to the limited heating
where the outdoor temperature is constant at –5 °C, the capacity offered by the radiant panel system.
design can maintain relatively uniform internal tempera- Consequently, runs were also undertaken with
tures. During sustained periods of low outdoor temperature, continuous overnight trickle heating.
corner rooms with substantial areas of glazing would
require some localised heating as demonstrated by the — ventilation rate (3 and 6 ACH).
relatively high PPD values for the larger window sizes and
the higher U-values. This same trend is confirmed by the All these details cannot be summarised here, but the
dynamic thermal modelling (see section 2.2.2.5). It should significant parameters in achieving good year-round
be stressed that these conclusions relate to the corner room comfort were the glazing U-value and size, and the pre-heat
situation with its two exposed façades, where the exposure strategy. To illustrate the key points, results are shown for
is much greater than in the climate chamber tests with the worst case configurations, i.e. N-facing ground floor (one
one exposed façade typical of the majority of a building. exposed wall and an exposed floor) and NW-facing ground
floor (two adjacent exposed walls and an exposed floor).
Figure 2.11 shows a base case analysis for a room with one
2.2.2.5 Dynamic thermal modelling exposed end wall with a U = 2.0 W/m2 ·K window. Con-
ditions are maintained within limits very well with the
Climate chambers are best suited to investigating steady exception of the full-height glazing. The underheated hours
state conditions, and thermal modelling was therefore used relate to inadequacies in the optimum start algorithm, and
to check dynamic effects and to ensure that comfort can be constant overnight trickle heating completely cuts off the
maintained in the absence of heating during all occupied
hours. In the analysis described here, the heating and 60
Window height
cooling was provided by a single set of radiant panels* 2·8 m
operating in changeover mode, with the changeover timed 50
Percentage of total office
hours (0700–1900) / %
* Other heating strategies could be used (see section 3) Figure 2.11 Base case analysis — effect of window size
Impact of advanced envelopes on HVAC requirements 9
Ramped heating from 15 to 21·5°C (Window height = 2·8 m) 2.3.1 Control of solar gain
(U-value = 1·5 W/m2·K)
Constant heating to 21·5°C (Window height = 2·8 m) Effective solar control is a subject in its own right (14). The
(U-value = 1·5 W/m2·K) principal objectives are to achieve a balance between control-
Ramped heating from 15 to 21·5°C (Window height = 1·8 m) ling solar gain, admitting sufficient daylight, providing
(U-value = 1·5 W/m2·K) occupant view and achieving an appropriate external
60
aesthetic. The difficulty is that the problem is orientation
dependent, and treatments that may work well on one façade
50
Percentage of total office
It is worth noting that there are a few relatively high Therefore, when specifying a glazing/shading combination,
temperatures for this module. Although the run was carried it is important to minimise both the long wave and short
out with no special solar protection measures, it does wave shading coefficients. The short wave coefficient is a
highlight the problem of large areas of glass. It is therefore measure of the amount of solar radiation that the system
recommended that, for corner rooms especially, 65% be allows through to the room. The long wave coefficient is a
considered a sensible maximum value for glazing, and even measure of the solar absorptance that is re-radiated to the
then appropriate solar control measures will need to be room.
applied. It should be noted that 65% glazing on two
orientations would require a very demanding shading
coefficient to limit the solar overheating, as detailed in 2.3.1.1 Reduced perimeter cooling loads
section 2.3.1.
In the summer months, the shading coefficient of the
glazing is a more important characteristic than the U-value.
The relative importance of the solar protection is seen from
2.3 The building in summer Figure 2.13, which shows typical office gains on a July
design day for a 50% glazed façade equipped with clear
double glazing and internal blinds. These solar loads have
The principal function of the advanced envelope in been averaged over a 6 m deep perimeter zone for three
summer is to control solar gain. The levels of insulation orientations: N, S and SW. Depending on orientation, the
applied to reduce heat loss in winter are effective in solar contribution is between 45–70% of the peak load.
limiting conduction gains from high sol-air temperatures. Reducing the solar load can therefore significantly reduce
Consequently, the main additional requirement is to limit the total required cooling capacity, and the turn down ratio
solar gain through glazing. of the control system.
10 HVAC strategies for well-insulated airtight buildings
Occupants Small power Lights Solar — A chilled ceiling system with radiant panels and
perimeter chilled beam, typical of much current
good practice. This design includes a good shading
SW
system incorporating mid-pane blinds in the
double-glazed unit giving a shading coefficient of
Orientation
0·2 2500
Cooling load / W
In order to assess the potential for advanced envelopes to d
Loa 2300
simplify the design and operation of HVAC systems in 0
summer conditions, tests were carried out to determine the P MV 2100
relative comfort conditions achieved using two different –0·2
1900
system configurations. These were as follows:
–0·4 1700
–0·6 1500
1 1·5 2 2·5 3
Window height / m
Figure 2.15 Comfort and cooling load for chilled beam solution
3 people, 6 ACH
1·2 Ventilation was via a floor displacement system.
PMV = 0·85 (limit of
1·0
acceptable comfort)
0·8
Figures 2.18 and 2.19 illustrate typical output for two corner
0·6
offices. The NW-facing manager’s office has lower gains and
0·4 PMV = 0·5 (limit of
illustrates the performance of a space most likely to suffer
0·2 'good' comfort)
problems during the heating season. The SW-facing
0
perimeter office has typical gains, and illustrates the per-
–0·2
formance of a space most likely to suffer overheating in
–0·4
summer. The results indicate that the two peaks associated
–0·6 with the heating and cooling set points for the fan coil
1 1·5 2 2·5 3
Window height / m
system have been replaced by a smoother distribution for
the advanced envelopes options. Winter temperatures tend
Figure 2.16 PMV as a function of room temperature
to be slightly warmer and summer slightly cooler. The
thermal mass has a marginal effect on comfort (consistently
2·0 cooler), although the impact on energy is much more
pronounced (see section 4.2).
Predicted mean vote (PMV)
1·5
60
Advanced envelope
1·0 (heavy)
50
Percentage of total office
hours (0900–1800) / %
Advanced envelope
0·5 (light)
40
1995 Building
Regulations
0·0 30
20
–0·5
23 24 25 26 27 28 29 30
10
Dry resultant temperature / °C
Advanced envelope
(light)
40
Once again, it should be stressed that these results apply 1995 Building
only to the case of a room with a window on the end wall. Regulations
30
Corner rooms will create additional solar gain problems. It
should be noted that the 2002 Approved Document L(1)
20
gives guidance on the control of overheating, and this will
limit the proportion of glazing in a corner room, unless
10
very effective solar control is provided.
0
2.3.2 Annual performance 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Room dry resultant temperature / °C
To assess the performance of this approach on an annual Figure 2.19 Annual temperature distribution for SW-facing office
basis, a real building was simulated. For the basis of
comparison, the same building geometry was modelled for
each of the following two cases:
— The 1995 Building Regulation standards and with a 2.4 Achieving the required
fan coil air conditioning system with perimeter window performance
heating to offset perimeter losses. Ventilation was
provided via a full fresh air system delivered into The previous sections have indicated that windows with U-
the fan coil unit values of 1.5–2.0 W/m2·K and shading coefficients of the
order of 0.2–0.3 are capable of delivering good year-round
— An advanced envelope with windows with a U- comfort conditions with very much simpler HVAC systems.
value of 1.5 W/m2·K and a shading coefficient of This section summarises the window technologies that are
0.2. Heating was available only during the pre-heat able to deliver this sort of performance.
12 HVAC strategies for well-insulated airtight buildings
U-value / (W/m2·K)
window technology, but the following illustrates some of 2·0
the parameters that influence performance. The first key 1·8
point is that window U-values are as much a function of the
1·6
frame technology as they are of the glazing system. Figure
2.20 shows the way the proportion of frame influences 1·4
overall window U-value for a UPVC and an aluminium
1·2
frame window. Because frame section dimensions are fixed,
the relative significance of the U-value of the frame 1·0
decreases as window size increases, resulting in a reduction 1·2 1·5 1·8 2·8
in overall U-value. The centre-of-pane U-value of the glass Window height / m
is shown by the horizontal line. It can be seen that the Figure 2.20 Overall U-values as a function of size
achievement of good overall U-values is therefore as much
to do with careful detailing of the frame as it is about the
specification of the glazing and inter-pane cavity.
costs, especially when the reduced HVAC costs are taken into Opaque blind
account. (closed)
Opaque blind
2.4.1.1 Effect of meteorological conditions (45°)
Translucent
It is also important to appreciate that the U-value is (closed)
dependent on prevailing weather conditions, especially
temperature and wind speed. U-values are normally quoted Translucent
at standard conditions of –1 °C and 7 m/s. The centre-pane (45°)
U-value for the double-glazed unit of Figure 2.21 (low-
emissivity + argon fill) increases from 1.28 to 1.40 W/m2·K None
as the temperature drops from –1 °C to –15 °C. Because
temperatures below the reference condition of –1 °C occur 0 0·2 0·4 0·6 0·8
relatively infrequently in the UK, this effect is unimportant
Shading coefficient
in energy terms, but could be significant in local comfort
terms. In that context, what is most important is the inside Figure 2.24 Shading coefficient for different blind configurations in
surface temperature. a ‘2+1’ window
Figure 2.23 shows the inside surface temperature as a — Ventilated cavity blinds (between the units of a ‘2+1’
function of the outside temperature and the diffuse window): Figure 2.24 shows the effect of different
radiation falling on a horizontal surface. It can be seen that blind arrangements (translucent and opaque in the
even modest levels of diffuse radiation can increase the 45° and closed positions). In this arrangement, the
surface temperature by 0.5 °C. Consequently, during most cavity between the single and double-glazed unit
daytime hours the surface temperatures are likely to be can be ventilated so that the solar radiation
0.5–1.0 °C warmer than the values predicted by U-value absorbed by the blind is vented to outside, reducing
calculations alone, thereby improving winter comfort. It is the long wave re-transmitted component. As well as
also worth noting that although U-values are adversely reducing the load, this will reduce the temperature
affected by increasing wind speed, the wind speed at of the inner surface of glass, thereby improving
which U-values are quoted (7 m/s) is relatively high. For comfort.
most inland areas of the UK, the hourly mean wind speed
that is exceeded on only 10% of occasions is between 8 and
9 m/s. Further, these are meteorological wind speeds, and — External blinds: this approach provides the best
wind speeds local to the building are likely to be form of solar protection, but the shading system
significantly reduced. In rural areas with scattered needs to be robust enough to withstand wind loads.
windbreaks this reduction is about 20% and in urban areas They also represent a potential site for roosting
it is greater than 50% (10). birds and therefore may require frequent cleaning.
0
4 8 12 16 20
GMT
4 Overhang (0·5 m)
Overhang (1 m)
Overhang (1·5 m)
3
Overhang (2 m)
Overhang (2·5 m)
2
0
4 8 12 16 20
GMT
2.5.1 Insulation
temperature differential of 10 °C should exist between the A further potential problem of air leakage is that warm air
inside and outside air temperatures to ensure that an leaking through a building envelope can carry significant
effective survey can be undertaken. On a heavyweight quantities of moisture into that assembly. Measurement has
masonry construction, this temperature differential should shown that air leakage can typically move up to 100 times
ideally be maintained for a minimum period of 24 hours more moisture into an envelope assembly than would occur
prior to a survey. A shorter period is acceptable in by diffusion alone. This moisture may condense within the
lightweight envelope assemblies (e.g. curtain walling and assembly, potentially leading to degradation of insulation
profiled metal cladding) that display a much more rapid performance and long-term degradation of component
response to temperature gradients. parts.
Thermal capacity can be almost as significant as insulation The problem is further increased by the fact that main
levels in modulating the energy demand in intermittently contractors tend to let envelope packages to subcontractors,
occupied buildings. This issue has been documented each of which is responsible for its own specific element.
elsewhere (22), but the essence of the effective use of thermal Unfortunately, there is often no one to take responsibility
mass is to use it as a heat recovery device by: for the interfaces between these subcontractor elements,
and it is at these interfaces where problems are most likely
— storing excess heat in winter to offset heating to arise.
system requirements at other parts of the day
— absorbing heat gains in summer so that the heat can It is relatively easy to ensure that new buildings are
be rejected from the building using free-cooling constructed to be acceptably airtight. The installation of
techniques during the night when air temperatures suitable seals between the elements typically used in
are at a minimum. envelope construction will generally always ensure that an
acceptable level of leakage is achieved. However, this
The rate of heat storage is limited by the surface heat requires a shift in the current thinking of both main and
transfer characteristics and therefore the effectiveness of subcontractors to ensure adequate integration between all
thermal mass is as much to do with surface area as it is with packages/trades.
heat capacity of the materials. Consequently, the effect of
the ceiling slab is most pronounced in the thermal storage
process. This mass should be exposed to the room air, 2.5.3.1 Airtightness standards
either directly or via open cell ceilings.
Air leakage is measured as a rate of leakage per square metre
2.5.3 Airtightness of external envelope per hour at an artificial pressure
differential through the envelope of 50 Pa (expressed as
The flow of air through the building envelope is commonly (m3/h)/m2 @ 50 Pa). Two parameters are used:
known as air leakage. Air leakage can be defined as ‘the
movement of air into and out of the building which is not — Air leakage index: this includes in the normalising
for the specific and planned purpose of exhausting stale air area only those elements of the envelope that are
or bringing in fresh air’. It is estimated that the majority of exposed to the ‘external’ air (e.g. floor slabs in direct
new non-domestic buildings constructed to comply with contact with the ground are not included). It is
the current regulatory requirements typically lose 50% of particularly useful for normalising the data
the total heating loads as a result of uncontrolled air leakage between different sized buildings of the same
through the building envelope. In addition to the direct generic type.
heat loss, air leakage often leads to ingress of pollutants,
inability to heat or cool localised zones within a building — Air permeability: this includes all the external surfaces,
and occupier complaints of draughts and discomfort. and is the parameter used to define the leakage
standards in Building Regulations Part L(1).
Air leakage should never be considered as acceptable
natural ventilation. It cannot be controlled or filtered and
will not provide adequate or evenly distributed ventilation. The typical air leakage index in a standard new commercial
It is generally at its most severe during the colder, windier, building in the UK is in the region of 20 (m3/h)/m2 @ 50 Pa.
winter months and has least impact during the warmer, For an industrial unit this figure would increase to ~25–30
calmer, summer periods. This is generally the opposite of the (m3/h)/m2 @ 50 Pa. The 2002 Part L standard is an air
requirements for ventilation within buildings. Ventilation permeability of 10 (m3/h)/m2 @ 50 Pa, equivalent to an air
of a building should never rely on air leakage, but should be leakage index of nearer 15 for most office buildings. The
provided by purpose-designed systems based on the good practice envelope leakage rates for office buildings
assumption that the envelope will be relatively airtight. recommended by CIBSE TM23(9) are shown in Table 2.9.
Impact of advanced envelopes on HVAC requirements 17
2
3 HVAC systems in
combination with 1
0 5 10 15 20 25 30 35 40
advanced envelopes Radiant temperature asymmetry / K
This section describes how the design of HVAC systems can Figure 3.1 Radiant asymmetry and comfort
be simplified in response to the substantially reduced
demands that result from a properly designed and
constructed advanced envelope. For information on a tures would be needed to provide the required heat
range of approaches to heating and cooling, see CIBSE output, thereby reducing efficiency.
Guides B1(24) and B2(8).
— Floor systems: pipe systems embedded in the floor
A possibility opened up by the strategies being considered in are becoming increasingly popular for heating and,
this publication is the integration of heating and cooling in some European countries, floor cooling is also
functions into a single system. If heating is no longer used. The main disadvantage is that the cooling
required during the occupied period (see section 2.2.1.1), the capacity of floors is limited by comfort constraints.
heating design issue becomes solely one of pre-heat. Conse- Since the cooling demand is likely to be the over-
quently, it is possible to envisage a situation where a single riding design criterion for office type buildings,
system is used in changeover mode to provide heating prior ceiling cooling systems are more likely to be
to occupancy then switching to cooling mode once preferred.
occupancy begins. This potentially could eliminate the cost — Ventilation system: this is likely to be less efficient in
of one complete distribution network and one set of terminal terms of transport energy (unless the ventilation rate
devices. to meet the fresh air requirements is sufficient to
provide the heating and cooling without excessive
This publication concentrates on a system whereby heating supply temperatures). In this case, the system is
and cooling are provided by ceiling mounted radiant more likely to require a mixing ventilation strategy
panels, coupled with a displacement ventilation system. because heating with displacement ventilation
One possible problem with using the radiant ceiling for diffusers is unlikely to be effective in achieving
20 HVAC strategies for well-insulated airtight buildings
2
3 HVAC systems in
combination with 1
0 5 10 15 20 25 30 35 40
advanced envelopes Radiant temperature asymmetry / K
This section describes how the design of HVAC systems can Figure 3.1 Radiant asymmetry and comfort
be simplified in response to the substantially reduced
demands that result from a properly designed and
constructed advanced envelope. For information on a tures would be needed to provide the required heat
range of approaches to heating and cooling, see CIBSE output, thereby reducing efficiency.
Guides B1(24) and B2(8).
— Floor systems: pipe systems embedded in the floor
A possibility opened up by the strategies being considered in are becoming increasingly popular for heating and,
this publication is the integration of heating and cooling in some European countries, floor cooling is also
functions into a single system. If heating is no longer used. The main disadvantage is that the cooling
required during the occupied period (see section 2.2.1.1), the capacity of floors is limited by comfort constraints.
heating design issue becomes solely one of pre-heat. Conse- Since the cooling demand is likely to be the over-
quently, it is possible to envisage a situation where a single riding design criterion for office type buildings,
system is used in changeover mode to provide heating prior ceiling cooling systems are more likely to be
to occupancy then switching to cooling mode once preferred.
occupancy begins. This potentially could eliminate the cost — Ventilation system: this is likely to be less efficient in
of one complete distribution network and one set of terminal terms of transport energy (unless the ventilation rate
devices. to meet the fresh air requirements is sufficient to
provide the heating and cooling without excessive
This publication concentrates on a system whereby heating supply temperatures). In this case, the system is
and cooling are provided by ceiling mounted radiant more likely to require a mixing ventilation strategy
panels, coupled with a displacement ventilation system. because heating with displacement ventilation
One possible problem with using the radiant ceiling for diffusers is unlikely to be effective in achieving
HVAC systems in combination with advanced envelopes 21
uniform comfort distribution. In deeper plan Flow pipe (warm or chilled water
buildings, it may be viable to provide perimeter depending on changeover mode)
pre-heat by transferring heat from the core areas to
the perimeter using the ventilation system. This
heat would have been stored in the core fabric from
Return pipe (warm or
the internal heat gains arising during the previous chilled water depending
day’s occupancy, and would minimise the need for on changeover mode)
heat to be provided from boiler plant.
23
22
21
20
19
18
17
16
15
Ramped heating from 15 to 21·5°C Constant heating to 21·5°C
14 (Window height 2·8 m, U-value 2 W/m2·K) (Window height 2·8 m, U-value 2 W/m2·K)
13 Constant heating to 21·5°C Constant heating to 21·5°C
(Window height 1·8 m, U-value 2 W/m2·K) (Window height 1·2 m, U-value 2 W/m2·K)
12
0000 0600 1200 1800 0000 0600 1200 1800
Monday Tuesday Figure 3.4 Building changeover
Time of day / h with delayed occupancy
chiller during the day could be stored and used to provide heating and ~16 °C for cooling. Consequently, a lower loop
the pre-heat for the following night time (see section 3.1.3). temperature may be beneficial but this would depend on the
relative efficiencies of the dry cooler and the heat pumps.
Another approach worth considering would be to use the
3.1.3 Ceiling connected via reversible heat water loop as a buffer to store energy during changeover. For
pumps to a common water loop example, during pre-heat the water temperature in the loop
could be allowed to fall in order to maximise the efficiency of
This mode of operation relies on the use of distributed cooling, once this became the dominant load. Similarly at the
reversible heat pumps (Figure 3.5). This provides the same end of daytime cooling, the water loop temperature could be
level of control flexibility as the 4-pipe system. It dis- allowed to rise, providing a higher source temperature for the
tributes the heating and cooling equipment around the next pre-heat period.
building, requiring less central plant room space. Because
the building is primarily either all-heating or all-cooling,
the dimensioning of the water loop will require careful 3.2 Simplified control
consideration to avoid excessive temperature differences
along the loop length, which would adversely affect heat Problems of zoning and of simultaneous heating and
pump performance. cooling are reduced with this approach, as the building is
always either in pre-heat or in cooling, never the two
In conventional systems, the water loop is usually controlled simultaneously. Large variations in internal gain will still
to about 33 °C. In this application, it may be appropriate to require zoning for cooling purposes, with possible supple-
reduce this as the water temperature is only ~30 °C for mental cooling provision. As far as heating is concerned,
the building can be treated as one large zone as the issue is
Water loop to provide heat source/heat dump
only pre-heat, when diversity of internal gain or variations
depending on heat pump mode in solar gain are irrelevant.
problem rather than treat the symptoms. High perfor- the cost of the fuel to the gross thermal efficiency). Table
mance building envelopes can substantially simplify the 3.1 compares a condensing boiler and a heat pump, based
design and operation of HVAC systems. By effectively on a relatively modest heat pump CoP of 2.5 and a high
isolating the occupied space from the external climate, the efficiency heat pump (e.g. ground source). The table
internal loads become much more constant with time and illustrates that the heat pump is significantly better in
much more even between core and perimeter and between carbon emission terms and that, at off-peak electricity rates,
different orientations of perimeter zone, especially if the the costs are comparable. Because all the heating is pre-
thermal capacity is high. heat, the majority of the heating demand will be in off-peak
periods. Clearly, the cost issue is very dependent on tariff,
but the current trend is for gas prices to increase and
3.3 Central plant options electricity rates to decrease.
This section explores the options available for providing The low supply water temperature also benefits heat pump
warm and chilled water to supply to the heating and cooling performance by reducing the required temperature lift. The
systems. key design issue for a heat pump is to identify a suitable heat
source. If an air-source heat pump is used, maximum heat
3.3.1 Heating demand occurs at times of lowest ambient temperature,
thereby reducing efficiency. This is made worse in the
Two issues influence the selection of heating plant: approach discussed here because all the heating is required
during pre-heat, when ambient temperatures are at their
— the very low supply temperature required for lowest during the diurnal cycle. This suggests that a ground
ceiling radiant heating (<35 °C) source heat pump might provide the most energy efficient
— the fact that heating is only required during the solution, although clearly capital costs will be higher than
pre-heat period and never simultaneously with for an air source heat pump. Ground temperatures below
cooling. about 2 m approximate the annual average temperature,
which in the UK is typically 10–12 °C. This constant source
The first point allows very efficient heat raising plant to be temperature can enable high CoPs in the region of 4.0 (the
utilised. One obvious option is a condensing boiler, since value used for the second example in Table 3.1). Performance
this would operate with continuous low return water is best in areas with non-consolidated (sandy) sediments,
temperatures, thereby maximising the period of condens- with a high groundwater table and groundwater flow. This
ing operation and achieving seasonal gross efficiencies of eases the drilling of the boreholes, and promotes high heat
>90%. Another important issue is that, because heating transfer rates.
demands are small, the required capacity may be met with
multiple domestic-type units, with much simpler (and Ground loop systems are usually in the form of a series of
cheaper) flue arrangements. Such units can easily be wall boreholes to a depth of ~100 m. Water/glycol mixture is
hung and thereby save further plant room space. circulated around each loop, and the individual loops
manifolded together to provide the source water for the
An alternative to a condensing boiler would be a heat reversible heat pump(s). In this way, the soil acts as a heat
pump, which would operate with a low condensing storage device: during heating, the ground temperature is
temperature resulting in a high CoP, especially if the heat lowered, storing energy to be used in the next cooling cycle.
source were at a reasonably high temperature (e.g. ground Indeed, it is usually required that the net annual heat
source) such that the temperature rise was small. Since injection into the ground by the system is approximately
heating will be needed only for pre-heat, a heat pump zero to avoid altering the thermal balance of the ground
would operate for most of the time at off-peak tariffs, beyond the boundaries of the building. With the integrated
thereby ensuring low energy costs as well as attractively low approach proposed in this publication, there is a significant
emissions of carbon. The fact that heating is required only net cooling demand, and so ground temperatures will
during the pre-heat period means that reversible heat continue to rise unless some balancing measures are taken.
pumps should also be considered because they would This could include using other forms of free-cooling in
provide another level of integration, extending plant winter months (see section 3.3.2) or cooling the ground
utilisation and reducing plant space requirements. during unoccupied night hours. This can be done by the
pre-heat operation or, when pre-heat is not required,
The 2002 edition of Part L of the Building Regulations(1) passing the water from the ground loops through a dry-air
characterises the performance of a heating system in terms cooler. This takes advantage of the lower night-time
of carbon intensity (kg(carbon)/kW·h of useful heat, i.e. the temperatures to generate cooling at a very high efficiency.
ratio of the carbon emission factor for the fuel to the gross This parasitic energy loss is compensated for through the
thermal efficiency). Users would also be interested in the very high CoP (of 5 or more) when the system is providing
cost intensity (pence/kW·h of useful heat, i.e. the ratio of cooling to the building.
Supply temperature / °C
20
3.3.3 Ventilation 15
This section has concentrated on using radiant ceiling panels 10 Heat recovery effectiveness
as the room heating and cooling device. Conventionally, 50%
such systems are used in conjunction with displacement 5 70%
ventilation. The detailed design of such systems is covered
90%
elsewhere(28), and this section will only review how a 0
displacement ventilation system might be integrated into –10 –50 5 10 15
the overall strategy. Outside temperature / °C
Figure 3.8 The effect of heat recovery effectiveness on supply
temperature
The main issue for consideration is the air supply
temperature, which is normally scheduled at 19 °C. The
issue is that, even during winter, the building is in cooling It is always important to assess the energy costs associated
mode even though the outside air is much cooler than the with achieving heat recovery. Increased fan power and the
room supply temperature. The amount of cooling available direct costs associated with, for example, the drive motor
via the ventilation plant is significant, as can be seen from for the thermal wheel must be offset against the cost and
Figure 2.1. However, this cooling potential is limited by the carbon impact of the heat recovered. The specification of
need to heat the room air supply temperature to 19 °C. air handling units with low specific fan power (~1.5
Reducing the ventilation supply temperature to, say, 17 °C W/litre·s–1 or less) will be beneficial in this respect. Analysis
would reduce heating demand due to ventilation and shows that such specific fan powers offer reduced whole life
simultaneously double the usable cooling potential of the cost related to conventional specifications(29).
supply air. This increased cooling would be sufficient to
maintain space conditions in cold weather without the need Another important consideration with respect to use of heat
to provide cooling from the radiant panels, even allowing recovery is the sizing of the primary heat source for the
for some solar gain to the space. Indeed, if the room building. It has been conventional practice to ignore the
temperature is allowed to rise a little from the 21 °C on effect of the heat recovery when sizing the heat-raising
which Figure 2.1 is based, the free-cooling potential of the plant. The argument has been that if the building is cold,
ventilation air would increase still further. there is no heat in the building to recover and therefore the
heating plant should be capable of supplying all the
ventilation heat demand. This logic is debatable: when
The main reason for controlling the room supply tempera- bringing a building up to temperature from cold, the
ture to approx. 19 °C is to maintain comfort in the region of ventilation system would either not be running or running
the floor diffusers. A reduction in supply temperature on full recirculation. In the context of advanced envelope
would be possible if the induction ratio of the diffuser were buildings that are self heating, it would seem fully justified
increased (28). This can be achieved with user adjustable to size the heating plant based on fabric and infiltration
outlets giving a high degree of swirl. An alternative losses only, provided the heat recovery plant is sufficiently
approach to increase the cooling potential would be to efficient to handle the ventilation loss.
increase the ventilation rate, but here the savings from the
free-cooling would have to be offset against increased fan
power. It should be pointed out that free-cooling is also
available via the radiant ceiling panels (see section 3.3.2), 4 Performance estimates
and so energy benefit is not entirely lost if high induction
diffusers are impractical or unjustifiably expensive. In order to get an indication of the relative cost of the
approach proposed in this publication, a comparison
The other issue for consideration with a relatively high air exercise was undertaken for a realistic modern office
supply temperature is the energy demand for heating the building. The work was based on the three-storey office
air. To achieve good indoor air quality, displacement shown in Figure 4.1; the gross floor area was 4130 m2.
ventilation systems are usually 100% outside air. In that Three variants of this building were analysed. All were the
context, heat recovery systems may provide significant
benefit. Figure 3.8 shows the room supply temperature
achievable with different levels of device effectiveness as a
function of outside air temperature. The analysis is based
on a return air temperature of 22 °C, i.e. a room temperature
of 21 °C and a fan pickup of 1 K. In reality, the return
temperature is likely to be much greater because of
temperature stratification with displacement ventilation
and further heat pickup through the air handling
luminaires. The analysis is therefore conservative. The
graphs indicate that heat recovery is able to meet the
ventilation heating requirement under all likely condi-
tions, provided the effectiveness can approach 90%. This is
at the top end of the performance range, but thermal wheels
and regenerators are capable of sensible effectiveness of
90% or even slightly more(8). Figure 4.1 Reference building
Performance estimates 25
Supply temperature / °C
20
3.3.3 Ventilation 15
This section has concentrated on using radiant ceiling panels 10 Heat recovery effectiveness
as the room heating and cooling device. Conventionally, 50%
such systems are used in conjunction with displacement 5 70%
ventilation. The detailed design of such systems is covered
90%
elsewhere(28), and this section will only review how a 0
displacement ventilation system might be integrated into –10 –50 5 10 15
the overall strategy. Outside temperature / °C
Figure 3.8 The effect of heat recovery effectiveness on supply
temperature
The main issue for consideration is the air supply
temperature, which is normally scheduled at 19 °C. The
issue is that, even during winter, the building is in cooling It is always important to assess the energy costs associated
mode even though the outside air is much cooler than the with achieving heat recovery. Increased fan power and the
room supply temperature. The amount of cooling available direct costs associated with, for example, the drive motor
via the ventilation plant is significant, as can be seen from for the thermal wheel must be offset against the cost and
Figure 2.1. However, this cooling potential is limited by the carbon impact of the heat recovered. The specification of
need to heat the room air supply temperature to 19 °C. air handling units with low specific fan power (~1.5
Reducing the ventilation supply temperature to, say, 17 °C W/litre·s–1 or less) will be beneficial in this respect. Analysis
would reduce heating demand due to ventilation and shows that such specific fan powers offer reduced whole life
simultaneously double the usable cooling potential of the cost related to conventional specifications(29).
supply air. This increased cooling would be sufficient to
maintain space conditions in cold weather without the need Another important consideration with respect to use of heat
to provide cooling from the radiant panels, even allowing recovery is the sizing of the primary heat source for the
for some solar gain to the space. Indeed, if the room building. It has been conventional practice to ignore the
temperature is allowed to rise a little from the 21 °C on effect of the heat recovery when sizing the heat-raising
which Figure 2.1 is based, the free-cooling potential of the plant. The argument has been that if the building is cold,
ventilation air would increase still further. there is no heat in the building to recover and therefore the
heating plant should be capable of supplying all the
ventilation heat demand. This logic is debatable: when
The main reason for controlling the room supply tempera- bringing a building up to temperature from cold, the
ture to approx. 19 °C is to maintain comfort in the region of ventilation system would either not be running or running
the floor diffusers. A reduction in supply temperature on full recirculation. In the context of advanced envelope
would be possible if the induction ratio of the diffuser were buildings that are self heating, it would seem fully justified
increased (28). This can be achieved with user adjustable to size the heating plant based on fabric and infiltration
outlets giving a high degree of swirl. An alternative losses only, provided the heat recovery plant is sufficiently
approach to increase the cooling potential would be to efficient to handle the ventilation loss.
increase the ventilation rate, but here the savings from the
free-cooling would have to be offset against increased fan
power. It should be pointed out that free-cooling is also
available via the radiant ceiling panels (see section 3.3.2), 4 Performance estimates
and so energy benefit is not entirely lost if high induction
diffusers are impractical or unjustifiably expensive. In order to get an indication of the relative cost of the
approach proposed in this publication, a comparison
The other issue for consideration with a relatively high air exercise was undertaken for a realistic modern office
supply temperature is the energy demand for heating the building. The work was based on the three-storey office
air. To achieve good indoor air quality, displacement shown in Figure 4.1; the gross floor area was 4130 m2.
ventilation systems are usually 100% outside air. In that Three variants of this building were analysed. All were the
context, heat recovery systems may provide significant
benefit. Figure 3.8 shows the room supply temperature
achievable with different levels of device effectiveness as a
function of outside air temperature. The analysis is based
on a return air temperature of 22 °C, i.e. a room temperature
of 21 °C and a fan pickup of 1 K. In reality, the return
temperature is likely to be much greater because of
temperature stratification with displacement ventilation
and further heat pickup through the air handling
luminaires. The analysis is therefore conservative. The
graphs indicate that heat recovery is able to meet the
ventilation heating requirement under all likely condi-
tions, provided the effectiveness can approach 90%. This is
at the top end of the performance range, but thermal wheels
and regenerators are capable of sensible effectiveness of
90% or even slightly more(8). Figure 4.1 Reference building
26 HVAC strategies for well-insulated airtight buildings
Load / GJ
(a) Reference case: built to 1995 Part L standards, with 80
the exception of the office glazing. This was taken 60
as U = 2.7 W/m2·K, a value in advance of 1995 Part 40
L but typical of current practice. An infiltration 20
rate of 0.5 ACH was assumed. The reference design 0
had better than average solar shading with external Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
louvres on the SE and SW façades. The building
Figure 4.3 Air heating demands
was conditioned by a 4-pipe fan coil system, with
perimeter heating under the windows. Fresh air
was supplied at 3 ACH at 17 °C to all spaces. In considering the figures for the relative heating and
cooling demands for the three options, the following points
(b) Advanced envelope (lightweight) with wall U-values of can be made:
0.3 W/m2·K and windows of 1.5 W/m2·K. Infiltra-
tion was taken as 0.15 ACH, corresponding to an air — The air heating demand is lower in the reference
leakage rate of ~5 (m3/h)/m2 @ 50 Pa. The building case because of the lower room supply temperature
was conditioned by a 2-pipe changeover heated/ (Figure 4.3). For the advanced envelope design,
chilled radiant ceiling system, with heating control- this is significant because, when the ventilation
led via a night setback and optimum start schedule. system is running, the space requires cooling.
Ventilation was via a displacement ventilation Consequently, when outside temperatures are less
system, supplying air at 3 ACH at 19 °C. than the ventilation supply temperature, air is
being heated to supply a room requiring cooling.
(c) Advanced envelope (heavyweight): details as for (b), This means that a reduction in supply air
except that the building was heated continuously temperature would reduce both heating and
overnight to maintain a set point of 21 °C. cooling demands for the advanced design. The
lightweight version was re-run using the same
The following sections detail the relative performance of supply air temperature as the conventional design.
the buildings in relation to a number of key criteria. The total heating load was reduced by 13%, and the
cooling load by 9%. As discussed in section 3.3.3, a
reduced supply air temperature may be possible in a
4.1 Comfort displacement ventilation regime, if high induction
diffusers were used.
The cumulative comfort distributions shown in Figure 4.2 — As would be expected with the increased insulation
illustrate that, in general, the advanced envelope buildings standards, the room heating demands are signifi-
were a little warmer, especially in winter, than the design cantly lower in winter for the advanced envelope
based on current practice. The light and heavy variants options (Figure 4.4). What is particularly signifi-
performed almost identically. All three buildings main- cant is the further reduction in heating demand
tained conditions within the acceptable thermal comfort with the thermally massive option. This is due to
envelope at all times. the increased ability of the fabric to retain the
excess heat gains from the previous day and thereby
reduce the pre-heat demand for the next day. There
100
is a small increase in room heating demand for the
90 Design to 1995 Building
Regulations advanced envelope design relative to the reference
80 through the summer months. This is due to the
occupied hours / %
Percentage of total
70 Advanced envelope
(light) pre-heat control algorithm still heating the build-
60 ing to 21.5 °C prior to occupancy. This is almost
Advanced envelope
50
(heavy)
certainly unnecessary in summer, and refinement
40 of the pre-heat control would mean that the
30 summer heating demand would be no greater than
20 with the reference design.
10
— The room cooling loads are significantly higher for
0
18 19 20 21 22 23 24 25 26 the lightweight advanced envelope design than the
Dry resultant temperature / °C
140
Figure 4.2 Comfort comparison for the three variants 1995 Building Regulations
120
Advanced envelope (light)
100
Advanced envelope (heavy)
Load / GJ
reference design in winter. One reason for this is pumps, heat rejection fans etc). The summer operation
the apparent free-cooling provided by the higher would not show much improvement in CoP other than those
infiltration rate in the conventional design. This is normally consequent on the use of a displacement
no argument for higher infiltration rates, since the ventilation/chilled ceiling strategy. However, the loads that
air leakage is likely to create draughts and local have to be met are reduced by the improved solar
discomfort rather than any real cooling energy protection, and so the total energy costs/carbon emissions
benefit. As discussed previously, the winter cooling are therefore lower in summer.
can be provided via a number of free-cooling
techniques and so any winter increase is relatively
insignificant. What is more important is the 4.3 Building costs
significant reduction in summer loads consequent
upon the improved solar control. Once again, the The new approach to design puts greater emphasis on the
heavyweight version outperforms the lightweight façade investment. This delivers reduced costs in HVAC
version in all seasons (Figure 4.5). plant and equipment. The following section gives some
basic data on how these costs might be distributed.
140
1995 Building Regulations
120 4.3.1 Windows
Advanced envelope (light)
100
Advanced envelope (heavy)
Load / GJ
250
4.4 HVAC costs
Heating Cooling
Clearly the savings in HVAC system cost depend on the
configuration selected (see sections 3.1.1–3.1.3) and the
200
Loads / (MW·h) per annum
£30
£30
outlined here should be more economic to construct, allow 7 Weir G and Muneer T Low emissivity coatings in high-
better use of space and provide good comfort conditions. performance double-glazed windows: energy, monetary and
However, the achievement of these desirable objectives environmental costs Building Services Engineering Research &
Technology 18 (2) 125–127 (1997)
does require careful thought to both design and con-
struction to ensure the necessary standards are met. The 8 Ventilation and air conditioning CIBSE Guide B2 (London:
following checklist summarises the key points that need to Chartered Institution of Building Services Engineers) (2001)
be achieved. 9 Testing buildings for air leakage CIBSE Technical Memoranda
— Good window U-values, of the order of 2.0 W/m2·K TM23 (London: Chartered Institution of Building Services
or better, depending on the glazing ratio. The frame Engineers) (2000)
design is as important as the glazing specification 10 Environmental criteria for design Section 1 in Environmental design
when seeking such U-value standards. CIBSE Guide A (London: Chartered Institution of Building
Services Engineers) (1999)
— Good solar protection, offering shading coefficients
of 0.3 or better. 11 McIntyre D A Radiation draughts Building Services Engineer 43
136–139 (October 1975)
— Good envelope airtightness — an air leakage index
of 5 (m3/h)/m2 at 50 Pa. This requires careful detail- 12 Heiselberg P Draught risk from cold vertical surfaces Building
and Environment 29 (3) 297–301 (1994)
ing of the air barrier, and a pressure test of the
completed assembly to ensure the standard is 13 ISO 7730: Moderate thermal environments - determination of PMV
achieved in practice. and PPD indices and specifications of the conditions for thermal comfort
(Geneva: International Standards Organisation) (1994)
— Care over the detailing of the envelope to minimise
the effects of cold bridging. Similar care over instal- 14 Littlefair P J Solar shading of buildings BRE Report BR364
lation is needed to ensure the insulation is con- (Garston: Building Services Establishment) (1999)
tinuous. Thermographic surveys of the construc- 15 Thermal response and plant sizing Section 5 in Environmental design
tion are a useful tool to ensure the required CIBSE Guide A (London: Chartered Institution of Building
standards are achieved in practice. Services Engineers) (1999)
— Special consideration given to areas of increased 16 Best practice in the specification of offices (London: British Council
exposure to external conditions — e.g. corner rooms, for Offices) (2000)
spaces with exposed floors (such as those above 17 Borland S Private communication
underground car parks) etc. In such cases, provision
may be needed for local supplementary heating. 18 Sampson Windows Private communication
— Use of displacement diffusers with a high induction 21 Guidance to the standard specification for thermal imaging of non-
electrical building services installations BSRIA Facilities
ratio to maximise the free-cooling potential of the
Management Specification FMS 6/2000 (Bracknell: Building
ventilation air. Services Research and Information Association) (2000)
— Configuring the heat rejection system pipework 22 Braham D, Barnard N and Jaunzens D Thermal mass in office
such that free-cooling can be used for much of the buildings, Part 1 An introduction, Part 2 design criteria BRE Digest
year to generate the chilled water supplied to the 454 (Garston: Building Research Establishment) (2001)
radiant panels.
23 Limiting thermal bridging and air leakage: robust construction details
— Careful consideration of the likely pattern of inter- for dwellings and similar buildings (Garston: Building Research
nal gain through the space, so that an appropriate Establishment) (in press)
balance can be struck between cost and the degree 24 Heating CIBSE Guide B1: (London: Chartered Institution of
of flexibility to heat and cool simultaneously. Building Services Engineers) (1986)
outlined here should be more economic to construct, allow 7 Weir G and Muneer T Low emissivity coatings in high-
better use of space and provide good comfort conditions. performance double-glazed windows: energy, monetary and
However, the achievement of these desirable objectives environmental costs Building Services Engineering Research &
Technology 18 (2) 125–127 (1997)
does require careful thought to both design and con-
struction to ensure the necessary standards are met. The 8 Ventilation and air conditioning CIBSE Guide B2 (London:
following checklist summarises the key points that need to Chartered Institution of Building Services Engineers) (2001)
be achieved. 9 Testing buildings for air leakage CIBSE Technical Memoranda
— Good window U-values, of the order of 2.0 W/m2·K TM23 (London: Chartered Institution of Building Services
or better, depending on the glazing ratio. The frame Engineers) (2000)
design is as important as the glazing specification 10 Environmental criteria for design Section 1 in Environmental design
when seeking such U-value standards. CIBSE Guide A (London: Chartered Institution of Building
Services Engineers) (1999)
— Good solar protection, offering shading coefficients
of 0.3 or better. 11 McIntyre D A Radiation draughts Building Services Engineer 43
136–139 (October 1975)
— Good envelope airtightness — an air leakage index
of 5 (m3/h)/m2 at 50 Pa. This requires careful detail- 12 Heiselberg P Draught risk from cold vertical surfaces Building
and Environment 29 (3) 297–301 (1994)
ing of the air barrier, and a pressure test of the
completed assembly to ensure the standard is 13 ISO 7730: Moderate thermal environments - determination of PMV
achieved in practice. and PPD indices and specifications of the conditions for thermal comfort
(Geneva: International Standards Organisation) (1994)
— Care over the detailing of the envelope to minimise
the effects of cold bridging. Similar care over instal- 14 Littlefair P J Solar shading of buildings BRE Report BR364
lation is needed to ensure the insulation is con- (Garston: Building Services Establishment) (1999)
tinuous. Thermographic surveys of the construc- 15 Thermal response and plant sizing Section 5 in Environmental design
tion are a useful tool to ensure the required CIBSE Guide A (London: Chartered Institution of Building
standards are achieved in practice. Services Engineers) (1999)
— Special consideration given to areas of increased 16 Best practice in the specification of offices (London: British Council
exposure to external conditions — e.g. corner rooms, for Offices) (2000)
spaces with exposed floors (such as those above 17 Borland S Private communication
underground car parks) etc. In such cases, provision
may be needed for local supplementary heating. 18 Sampson Windows Private communication
— Use of displacement diffusers with a high induction 21 Guidance to the standard specification for thermal imaging of non-
electrical building services installations BSRIA Facilities
ratio to maximise the free-cooling potential of the
Management Specification FMS 6/2000 (Bracknell: Building
ventilation air. Services Research and Information Association) (2000)
— Configuring the heat rejection system pipework 22 Braham D, Barnard N and Jaunzens D Thermal mass in office
such that free-cooling can be used for much of the buildings, Part 1 An introduction, Part 2 design criteria BRE Digest
year to generate the chilled water supplied to the 454 (Garston: Building Research Establishment) (2001)
radiant panels.
23 Limiting thermal bridging and air leakage: robust construction details
— Careful consideration of the likely pattern of inter- for dwellings and similar buildings (Garston: Building Research
nal gain through the space, so that an appropriate Establishment) (in press)
balance can be struck between cost and the degree 24 Heating CIBSE Guide B1: (London: Chartered Institution of
of flexibility to heat and cool simultaneously. Building Services Engineers) (1986)
Appendix A1: Modelling methods 22 °C). At this condition, perimeter losses exactly matched
internal gains, representing the most extreme condition for
In order to prove the concepts outlined above, a comprehen- a system without perimeter heating. The measured glass
sive series of modelling (physical and computational) were surface temperature at these conditions can be used to
carried out. These are described in the following sections. predict the required glazing performance for any outside
and inside design conditions. Detailed measurements of
the comfort parameters were taken in the zone immediately
adjacent to the window.
A1.1 Climate chamber tests
For the summer tests, the purpose was to compare the
Climate chamber testing of realistic room mock-ups with performance of the proposed system with a system more
fully functioning HVAC systems is perhaps the most typical of current good practice. The reference case was a
credible way to demonstrate accurately the performance of radiant ceiling panel system, with an additional passive
HVAC systems and their interaction with the building fabric
chilled beam to cope with the perimeter load. Some solar
and indoor climate. A 6.5 m deep by 3.2 m wide office control was provided via external brise-soleil. The test
module was therefore simulated in a climate chamber system just incorporated the radiant ceiling panels, but
(Figure A1.1). with a higher performance envelope.
Tests were run for both summer and winter conditions.
Internal gains representing people, lights and computers A1.2 Dynamic thermal modelling
were placed in the chamber. The effect of a window in the
end-wall of the chamber was simulated by passing chilled In operational terms, the performance of the concept over
(winter) or warm (summer) water through coils embedded the whole year is perhaps more important than performance
in the wall. The size of the window was varied by blanking at the design condition, which by definition will occur less
off sections of the end wall with insulation board, such that than 2.5% of the time. Detailed thermal simulations were
the surface temperature of the ‘wall’ was equivalent to that carried out to assess the distribution of comfort conditions
to be expected for a wall U-value of ~0.3 W/m2·K. Detailed through a typical year.
traverses of air and globe temperatures and air speed were
made so that detailed assessments of comfort could be Figure A1.2 shows a sample output, comparing the
determined. temperature distributions for two versions of the advanced
concept (one lightweight, the other heavy) against a
For the winter tests, the main purpose was to assess comfort reference design built to current practice standards.
in the situation where there was no perimeter heating. Detailed investigations were also made of typical design
Consequently, no active heating or cooling was provided, weeks of hot and cold weather, to better understand the
other than the effect of the displacement ventilation dynamics of the building response. As well as modelling the
system. The surface temperature of the ‘window’ was building fabric, the performance of the HVAC system and
progressively lowered until thermal balance was achieved controls was simulated. This enabled the effect of the
at two pre-defined internal dry-bulb temperatures (20 and changeover control strategy to be assessed, as well as
determining the likely impact of the approach in reducing
energy consumption and carbon emissions.
60
Advanced envelope
(heavy)
50
Percentage of total office
hours (0900–1800) / %
Advanced envelope
(light)
40
1995 Building
Regulations
30
20
10
0
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Room dry resultant temperature / °C
Figure A1.1 BRE climate chamber during tests Figure A1.2 Typical temperature frequency plot
Appendix A1: Modelling methods 31
rather than 3.3 W/m2·K ). The final round of modelling was The performance of the units was assessed for both winter
based on a complete real building in order to enable and summer performance in terms of U-value, internal
estimates of energy/CO2 performance to be made. To that surface temperatures and shading coefficient. Particular
end the reference building was conditioned with a 4-pipe attention was given to the performance of units with very
fan coil system, with perimeter heating scheduled to low-emissivity coatings (ε = 0.02–0.06, rather than the
outside conditions. more common ε = 0.16, such as the Pilkington K-glass).
Two-dimensional finite element modelling was used Computational fluid dynamics (CFD) was undertaken to
(Figure A1.3) to predict the distribution of window surface understand better the detail of the comfort conditions
temperatures (glazing and frame), and how this would vary throughout a typical office module (Figure A1.4). The work
as a function of meteorological wind-speed, incident solar was carried out in two stages; first, to compare predictions
radiation etc. The work highlights the importance of the against the climate chamber measurements, and then to
frame in achieving good overall window U-values, since simulate situations that would be impractical to model in
centre-pane U-values are usually better than whole-window the climate chamber (e.g. a corner room with cold glazing
values. Analyses were carried out for a range of window on two adjoining walls).
types typical of modern practice:
The degree of correlation between climate chamber and
— a thermally broken aluminium framed window CFD predictions was encouraging, enabling the modelling
typical of smaller non-domestic buildings of the more complex configurations to proceed with
confidence. Key parameters in the modelling were the
— a curtain walling construction more commonly proper representation of the floor mounted swirl diffusers
used in large scale commercial projects and the need to model the detailed radiation exchanges,
since these are crucial to the perception of comfort. One
— a ‘2+1’ window (double-glazed inner unit plus interesting point to emerge from the comparison of test
single glazed outer unit). chamber and CFD was the impact of the heat gain from
computers. These were initially modelled as convective
heat sources, resulting in a fairly strong buoyant plume that
dominated the flow field. In reality, the majority of the heat
from the computer is ejected via the cooling fan in the
computer case, resulting in a much higher degree of
horizontal entrainment and general mixing.
Figure A1.3 Finite element modelling of window Figure A1.4 Typical CFD output
Foreword
This publication reports the results of a major Partners in Innovation project that studied
the impact of high performance envelopes on the servicing strategy for office-type
buildings. The work was based on a range of detailed computer modelling techniques
supported by extensive climate chamber testing. The results suggest that there are
significant commercial benefits to be had from high performance envelopes. Equivalent
comfort conditions, significantly reduced operating and management costs and improved
space utilisation are achievable at costs no greater and possibly slightly less than
conventional air-conditioning systems. Although these ideas have not yet been fully
tested in practice, experience gained from the closest current exemplar, the Elizabeth Fry
building at the University of East Anglia, adds credibility to the conclusions presented.
Improved envelope standards will be required by the changes to Part L of the Building
regulations that come into force in 2002. This document demonstrates how such changes
to envelope standards can open up new opportunities for innovative design solutions that
are cost effective and make a major contribution to the wider sustainability agenda.
Steve Irving
Principal author
Acknowledgements
The work leading to the production of this publication was carried out as a Partners in
Innovation project co-ordinated by Oscar Faber. The funding provided by the
Department of Trade and Industry is gratefully acknowledged. The contributions of the
other project partners are also gratefully acknowledged. The project partners and their
representatives on the steering group are listed below.
In addition to the members of the project partners listed above, thanks are also due to J
Lawrence (Sampson Windows Ltd.) and D Wadham (Franklin+Andrews), who provided
useful information for this publication. The measurement and analysis work that
provided the information on which this document is based was carried out by Quentin
Babcock, David Butler, Arron Perry, Mark Seymour and John Bradshaw.
The authors are also thankful to the CIBSE referees who provided a very thorough and
helpful review of the draft document.
This document is published with the consent of the Department of Trade and Industry,
but the views expressed are not necessarily accepted or endorsed by the Department.
Principal authors
S Irving (Oscar Faber)
S Borland (Building Sciences)
Editor
Jackie Wilson
Blinds 13–14
Building
costs 27
fabric 18–20
orientation 8 9 11
types suitable 13
Building Regulations Part L
2002 edition 1 3 4 17
23 27
1995 edition 11 26 30
Carbon intensity 23
Carbon emissions 2 26
Carbon dioxide emissions 2 26
Cavity walls 18–19
Ceiling panels 21–22
Central plant 23–25
Changeover strategies 21–22
2-pipe 20 21
4-pipe 21
reversible heat pumps 22
whole-building 21
zoned 21
Cladding 19–20
Climate change levy 1
Climate chamber tests 5–6 10 29
Cold bridging 15 18
This page has been reformatted by Knovel to provide easier navigation.
Index Terms Links
Cold radiation 5
Comfort
occupant 3 5–9 10–11 20–26
occupant, assessment of 5–9
summer 10–11
thermal 8
Computational fluid dynamic analysis 6 30–31
Condensing boiler 23
Construction 14–20
Construction costs 1
Cooling 24
chilled beam system 10 24
ground source 24
systems 10–11
Corner rooms 6 8–9 11
Costs
building 27
construction 1
energy 1 25–28
fabric 27
maintenance 28
HVAC 27
initial 3
operating 3
maintenance 3
whole life 2 28
windows 27
Curtain walling 19–20
Daylight 14
Design and construction 15–16 17
Displacement ventilation 6 10 20 25
Downdraughts 5 6
Dynamic thermal modelling 8–9 30
Economic indicators 2
Embodied energy 2
Energy costs 1 26–27 28
Envelope design 14–20
Environmental indicators 2
This page has been reformatted by Knovel to provide easier navigation.
Index Terms Links
Glazing 5 10 12
Ground loop systems 23
Indicators
economic 2
environmental 2
sustainability 2
Insulation 15–16 18 19
Integrated healing and cooling systems 20–23
Light transmission 14
Maintenance costs 3 28
Market drivers 1
Masonry walls 18–19
Materials 2
Meteorological effects 13
Modelling methods 5–6 30–31
Occupant
comfort 3 5–9 10–11 20–26
productivity 3
Operating costs 3
Performance
annual 11
estimates 25–28
fabric 14–20
window 12–14
Perimeter
cooling loads 9–10
heating, elimination of 1 4–5 6
zone 3
Plant
cooling 24
heating 23–24
options 23–25
PMV 5 8 10–11
PPD 8 20
Pre–heating 4 20 23
Predicted percentage dissatisfied 8 20
Predicted mean vote 5 8 10–11
Productivity, occupant 3
This page has been reformatted by Knovel to provide easier navigation.
Index Terms Links
Quality assurance 16
Radiant panels 3 8 10 20
Radiant asymmetry 3 5 18 20
Radiation, cold 5
Roof assembly 19–20
Room, corner 6 8–9 11
Selectivity 14
Shading coefficient 9 13–14
Solar control 9 14
Solar gain 9 10 13 14
Stratification, temperature 6–8
Summer, building in 9
Summer, comfort conditions 10–11
Surface temperature 13
Sustainability indicators 2
Temperature
internal 4 13
dry resultant 5 11
stratification 6–8
surface 13
Thermal
capacity 16
comfort 8
mass 16
stratification 6–8
U-values 5 12–13
improvement in 2
standards 4
Ventilation 25
and air leakage 16
displacement 6 10 20
Water loop 22 23
Whole life costs 2
Wind speed, effect of 13
Window
costs 27
performance 12–14
size 5–6
type 12
Winter, building in 4–9