Professional Documents
Culture Documents
Merging & Splitting of MRP DCP-Dolita PDF
Merging & Splitting of MRP DCP-Dolita PDF
Introduction
Splitting
- Process for the MAHs
- Timetable
Merging
- Process for the MAHs
Some key points related to
Merging & Splitting pilot phase
Introduction 3
CMDh
CMDh Meeting with
Meeting with Interested
Interested Parties
Parties on MRP/DCP
on MRP/DCP Improvements
Improvements - 23 May 2016 December
– and
16 November 7 November 2015 -
2015 2016 CMDh
Working
Document
on Merging
Publication of CMDh
and
guidance for extension of Splitting of
pilot the pilot for MRP/DCPs
procedure in splitting of
December procedures- was
2015 Dec 2017 published
further on July
2018
extended up
to Dec 2018
Splitting 5
The CMDh has started a pilot procedure in January 2016 for 10 procedures
which has been finalized in November 2016.
The outcome of the pilot was quite successful but the number of procedures
too low for being able to decide on a transfer into a general procedure.
The CMDh therefore decided to extend the pilot phase for another year until
December 31, 2017 without restriction of the number of procedures involved in
the pilot in order to learn more about this procedure and to have sufficient time
for evaluating the legal possibility for a permanent procedure.
Also in the extended pilot the number of procedures has been too low to take a
final decision on this procedure, however, the requested splitting's were
successfully finalized. Further, CMDh decided to prolong the pilot phase for a
further year until December 31 2018 & now until June 30, 2019.
Conditions for splitting 7
The initial MRP/DCP should be finalised;
Different MAHs in the different MS are a prerequisite for the splitting.
Splitting into several lines is only possible per different MAHs.
The new RMS(s) have to be CMS in the MRP/DCP before. They have to
agree to act as new RMS in the split procedure;
Splitting is allowed only once in the lifecycle of a product; splitting into
several lines (i.e. more than two RMS) is allowed.
All regulatory procedures have to be completed before the splitting
can take place;
It is not acceptable to split single strengths of a procedure to a new
RMS. Example:
XX/H/9999/001/DC: CMS = MS1, MS2, MS3, MS4
XX/H/9999/002/DC: CMS = MS1, MS2, MS3, MS4, MS5
A split of the procedure 002 alone would only be possible for splitting MS5
out and MS5 becoming the new RMS.
Procedure for Splitting 8
In case of agreement between old and new RMSs, the old RMS
introduces the splitting in CTS by using the splitting function.
The new RMS(s) will issue new procedure number(s) and inform
the old RMS, who includes it in CTS and informs the MAH and the
new CMS(s) accordingly.
For the splitting request and all communication during the
splitting procedure specific email addresses should be used that
are listed in the annex.
The RMS of the initial procedure will keep the previous procedure
number but the CMS(s) that are switched to the new procedure
will no longer be involved in the initial procedure from the CTS
product sheet. Both procedures will remain as active procedures
in CTS.
10
The current RMS provides the new RMS with the PAR in word
format, if applicable.
Variations of the newly created lines with new RMS and new
procedure number should be submitted starting with the
sequential number XX/H/nnnn/vvv /001.
11
The existing eCTD lifecycle should continue for the existing (old)
procedure number with the existing dossier UUID.
table
14
Merging 15
No need for MAHs to contact RMS, RMS will contact MAH in case
of questions
Fees are national issue. In pilot phase probably no fees are raised
but maybe afterwards in permanent handling when this causes an
increased workload.
Guidance 22
January 2019
CMDh/354/2017, Rev.5
23