Assembling and Commissioning Programme of TBM, Multi-lane Road Tunnel under the River Karnaphuli

Date
No. Task Name 2018/8/5 2018/8/25 2018/9/14 2018/10/4 2018/10/24 2018/11/13
Start Duration(d) End

1 Cutterhead assembling and welding on ground 2018/8/8 15 2018/8/13 Cutterhead assembling and welding on ground

2 Steel sleeve pedestal installation schedule 2018/8/12 9 2018/8/20 Steel sleeve pedestal installation schedule

3 Launching shaft cleaning and measurement recheck 2018/8/12 2 2018/8/13 Launching shaft cleaning and measurement recheck

4 Extending steel ring and installation &welding of A1 2018/8/14 3 2018/8/16 Extending steel ring and installation &welding of A1

5 Installation &reinforcing of A2~A6 2018/8/17 3 2018/8/19 Installation &reinforcing of A2~A6

6 Bottom part of frame support installation and sand filling into the steel sleeve 2018/8/20 1 2018/8/20 Bottom part of frame support installation and sand filling into the steel sleeve

7 TBM hoisting 2018/8/21 48 2018/10/7 TBM hoisting


8 Bottom parts of Front and middle shield installation in the LB 2018/8/21 1 2018/8/21 Bottom parts of Front and middle shield installation in the LB
9 Drive turning frame installation 2018/8/22 1 2018/8/22 Drive turning frame installation
10 Installation of R1 and R2 in the LB 2018/8/23 1 2018/8/23 Installation of R1 and R2 in the LB
11 Installation of bearing and P-ring 2018/8/24 1 2018/8/24 Installation of bearing and P-ring
12 Turing over of main drive as support 2018/8/25 1 2018/8/25 Turing over of main drive as support
13 Installation of drive motor 2018/8/26 1 2018/8/26 Installation of drive motor
14 Second turning-over of the drive 2018/8/27 1 2018/8/27 Second turning-over of the drive

15 Dismantling of left side turning frame and hositing of front TBM left blocks 2018/8/28 1 2018/8/28 Dismantling of left side turning frame and hositing of front TBM left blocks
Dismantling of right side turning frame and hositing of front TBM right blocks
16 Dismantling of right side turning frame and hositing of front TBM right blocks 2018/8/29 1 2018/8/29
Welding of front and middle TBM bottom
17 Welding of front and middle TBM bottom 2018/8/28 3 2018/8/30
Hositing of Front TBM upper blocks and middle shield H-beam
18 Hositing of Front TBM upper blocks and middle shield H-beam 2018/8/30 1 2018/8/30
Hositing of middle shield left and right blocks
19 Hositing of middle shield left and right blocks 2018/8/31 1 2018/8/31
Hositing of man silo, platform and slurry pipe
20 Hositing of man silo, platform and slurry pipe 2018/9/1 3 2018/9/3
Hositing of middle shield upper blocks
21 Hositing of middle shield upper blocks 2018/9/4 1 2018/9/4
Hositing of Cutterhead
22 Hositing of Cutterhead 2018/9/5 2 2018/9/6
Hositing of tail TBM lower parts
23 Hositing of tail TBM lower parts 2018/9/7 2 2018/9/8
Assembling machine main beam and hoisitng of revolving body
24 Assembling machine main beam and hoisitng of revolving body 2018/9/9 1 2018/9/9
Hositing of Tail TBM left and right upper blocks
25 Hositing of Tail TBM left and right upper blocks 2018/9/10 2 2018/9/11
Installation of support frame
26 Installation of support frame 2018/9/12 3 2018/9/14
27 2018/9/15 1 2018/9/15 TBM unveiling ceremony- Option A
TBM unveiling ceremony- Option A
28 TBM initial commissioning 2018/9/16 11 2018/9/27 TBM initial commissioning

29 2018/9/28 1 2018/9/28 TBM cutterhead launching ceremony-Option B


TBM cutterhead launching ceremony-Option B
30 Installation of Steel sleeve upper cover 2018/9/28 7 2018/10/4 Installation of Steel sleeve upper cover

31 Acceptance of Steel sleeve sealing 2018/10/5 3 2018/10/7 Acceptance of Steel sleeve sealing

32 Hoisitng of Rear matching trolley 2018/8/20 25 2018/9/13 Hoisitng of Rear matching trolley

33 Installation of 1# trolley (7 pieces) 2018/8/20 7 2018/8/26 Installation of 1# trolley (7 pieces)


Hositing of 1# trolley 1st level right blocks and moving horizontally
34 Hositing of 1# trolley 1st level right blocks and moving horizontally 2018/8/20 1 2018/8/20
Hositing of 1# trolley 1st level left blocks and moving horizontally
35 Hositing of 1# trolley 1st level left blocks and moving horizontally 2018/8/21 1 2018/8/21
Hositing of 1# trolley 1st level middle blocks
36 Hositing of 1# trolley 1st level middle blocks 2018/8/22 1 2018/8/22
Hositing of 1# trolley 2nd level right blocks and moving horizontally
37 Hositing of 1# trolley 2nd level right blocks and moving horizontally 2018/8/23 1 2018/8/23
Hositing of 1# trolley 2nd level left blocks and moving horizontally
38 Hositing of 1# trolley 2nd level left blocks and moving horizontally 2018/8/24 1 2018/8/24
39 Hositing of 1# trolley 2nd level middle blocks and top beam blocks 2018/8/25 1 2018/8/25 Hositing of 1# trolley 2nd level middle blocks and top beam blocks

40 Moving 1# trolley totally to 30m forward 2018/8/26 1 2018/8/26 Moving 1# trolley totally to 30m forward

41 Installation of 2# trolley (6 pieces) 2018/8/27 6 2018/9/1 Installation of 2# trolley (6 pieces)

42 Hoisting of 2# trolley 1st level right blocks and moving horizontally 2018/8/27 1 2018/8/27 Hoisting of 2# trolley 1st level right blocks and moving horizontally

43 Hoisting of 2# trolley 1st level left blocks and moving horizontally 2018/8/28 1 2018/8/28 Hoisting of 2# trolley 1st level left blocks and moving horizontally

44 Hoisting of 2# trolley 2nd level right blocks and moving horizontally 2018/8/29 1 2018/8/29 Hoisting of 2# trolley 2nd level right blocks and moving horizontally

45 Hoisting of 2# trolley 2nd level left blocks and moving horizontally 2018/8/30 1 2018/8/30 Hoisting of 2# trolley 2nd level left blocks and moving horizontally

46 Hoisting of 2# trolley 2nd level middle blocks and top beam blocks 2018/8/31 1 2018/8/31 Hoisting of 2# trolley 2nd level middle blocks and top beam blocks

47 Moving 2# trolley totally 30m forward 2018/9/1 1 2018/9/1 Moving 2# trolley totally 30m forward

48 Installation of 3# trolley (6 pieces) 2018/9/2 6 2018/9/7 Installation of 3# trolley (6 pieces)

49 Hoisting of 3# trolley 1st level right blocks being hoisted and moving horizontally 2018/9/2 1 2018/9/2 Hoisting of 3# trolley 1st level right blocks being hoisted and moving horizontally

50 Hoisting of 3# trolley 1st level left blocks being hoisted and moving horizontally 2018/9/3 1 2018/9/3 Hoisting of 3# trolley 1st level left blocks being hoisted and moving horizontally

51 Hoisting of 3# trolley 2nd level right blocks being hoisted and movinghorizontally 2018/9/4 1 2018/9/4 Hoisting of 3# trolley 2nd level right blocks being hoisted and movinghorizontally

52 Hoisting of 3# trolley 2nd level left blocks being hoisted and moving horizontally 2018/9/5 1 2018/9/5 Hoisting of 3# trolley 2nd level left blocks being hoisted and moving horizontally

53 Hoisting of 3# trolley 2nd level middle blocks and top beam blocks 2018/9/6 1 2018/9/6 Hoisting of 3# trolley 2nd level middle blocks and top beam blocks

54 Moving 3# trolley totally moved 30m forward 2018/9/7 1 2018/9/7 Moving 3# trolley totally moved 30m forward

55 Installation of 4# trolley 2018/9/8 6 2018/9/13 Installation of 4# trolley

56 Hoisting of 4# trolley front left and right platforms 2018/9/8 1 2018/9/8 Hoisting of 4# trolley front left and right platforms

57 Hoisting of 4# trolley front door-shape components 2018/9/9 1 2018/9/9 Hoisting of 4# trolley front door-shape components
58 Hoisting of 4# trolley rear left and right platforms 2018/9/10 1 2018/9/10 Hoisting of 4# trolley rear left and right platforms
59 Hoisting of Elements on 4# trolley left and right platforms 2018/9/11 1 2018/9/11 Hoisting of Elements on 4# trolley left and right platforms
60 Hoisting of 4# trolley rear upper middle platform 2018/9/12 1 2018/9/12 Hoisting of 4# trolley rear upper middle platform
61 Hoisting of 4# trolley upper middle platform elements 2018/9/13 1 2018/9/13 Hoisting of 4# trolley upper middle platform elements
62 Freezing and reinforcing 2018/9/7 51 2018/10/27 Freezing and reinforcing
63 Construction of freezing holes 2018/9/7 14 2018/9/20 Construction of freezing holes
64 Freezing and reinforcing 2018/9/21 30 2018/10/20 Freezing and reinforcing
65 Chiseling off Tunnel portal 2018/10/21 7 2018/10/27 Chiseling off Tunnel portal
66 TBM pipelines and circuits installation and commission 2018/9/14 25 2018/10/8 TBM pipelines and circuits installation and commission
67 TBM formal launching-Opion C 2018/10/28 1 2018/10/28 TBM formal launching-Opion C