DSKP Pendidikan Jasmani KSSR Tahun 5

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 6

Site Labour V205

Monday Tuesday Wednesday


Day/Date 15-Apr-19 16-Apr-19 17-Apr-19

Time: 15.00pm 50 Time: 15.00pm 62 Time: 15.00pm 66

FT 1&2: assembling work working platform 5 SGB 06 : prepare rebar column 1st lif 8 SGB 06 : fixing rebar column 1st lif 8

FT 3&4: assembling work main girder 5 SGB 07 : prepare rebar 2nd lif 8 SGB 07 : fixing rebar 2nd lif 8

LG2: Adjusting segment 10 FT 1, 2, 3, 4 : assembling work 10 SGB 01a : crosshead grouting work 10

SGB03: Housekeeping and touch up work 4 LG 2 : advancing work 10 SGB 02 - SGB 03 : Span stressing work 6

Section 1 TNE 36 : dismantle soffit formwork & install main


Sungai Besi SGB01: Dismantle blister 4 18 FT 1&2 : assembling work working platform 5
rail

TNE36: Housekeeping and touch up work 6 SGB 03 : dismantling formwork 8 FT 3&4 : assembling work main girder 5

SBG06: dismantle pilecap formwork 8 LG 2 : dismantle spreader beam 10

SGB07: dismantle column formwork 8 SGB01 : dismantle blister 4

TNE 36 : housekeeping & touch up work 6

SGB 03 : housekeeping & touch up work 4

Time: 17.00pm 15 Time 17.48am 18 Time: 22.00pm 15

SGB10: Cutting hollow section for temporary SGB 10: Fabricate link bar for pier head on
SGB11: Installing formwork for tendon opening 6 4 3
platform ground

SGB12: Installation plywood for working platform SGB11: installation rebar for monolithic pier head SGB 11: Installation rebar for monolithic pier
Section 2 5 8 7
floor MD1 (Stage 2) head MD1 (stage 2)
Technology Park

TP 03: Installation column's starter bar and


SGB13: Yard: Bending rebar for pier column SGB07 4 TP03: continue install rebar pilecap 6 5
pilecap's mould

LG 3: SWO 0

Time: 18.00pm 103 Time: 16.30pm 103 Time: 17.00pm 87

TP26/TP27 / SRN02A: Roughening construction TP26/TP27 / SRN02A: Roughening construction


5 5 TP19: erecting scaffold 9
joint / cranking rebars/ installing bottom rebar joint / cranking rebars/ installing bottom rebar
Bending Yard (Gagasan): cut and bend 6 Bending Yard (Gagasan): cut and bend 6 TP20: tightening mould 5

SRN01 S : Installing pier head rebar 6 SRN01 S : Installing pier head rebar 6 TP27: installing bottom rebars 5

SRN01N/ SRN04S: installing pier head mould up to SRN01N/ SRN04S: installing pier head mould up to
8 8 Bending Yard (Gagasan): cut and bend 5
concreting concreting

SRN02: erecting / dismantling scaffold 13 SRN02: erecting / dismantling scaffold 13 SRN01S : installing pier head mould 7

SRN03A: PS adjustment 5 SRN03A: PS adjustment 5 SRN01A: PS adjustment 4

Section 3 SRN04A: installing rebars, formwork up until


Serdang SRN04A: Installing rebars 6 SRN04A: Installing rebars 6 6
concreting

SRN11/ SRN10: loosening mould tie down and props, SRN11/ SRN10: loosening mould tie down and SRN11: installing plinth formwork and
8 8 8
bolting I beam to column props, bolting I beam to column dismantling crossbeam side-mould

SRN19: Arranging scaffolding 2 SRN19: Arranging scaffolding 2 SRN19: arranging scaffold 2

TP03: installing column starter bars and


TP03: installing rebar and formwork 6 TP03: installing rebar and formwork 6 7
concreting
TP04: installing mould 4 TP04: installing mould 4 TP06: dismantling pilecap formwork 3
TP06: dismantling pilecap formwork 6 TP06: dismantling pilecap formwork 6 TP07: installing rebars 7

TP07: arranging link bars 6 TP07: arranging link bars 6 SRN02: 3rd pair - threading work 6

SRN02: threading work 6 SRN02: threading work 6 LG1: SRN12-13: Advancing 13


LG1: SRN13-14: Dismantle spreader beam and LG1: SRN13-14: Dismantle spreader beam and
16 16
preparation for advancing preparation for advancing

Total (Day) 168 183 168


Site Labour V205
Thursday Friday Saturday Sunday
18-Apr-19 19-Apr-19 20-Apr-19 21-Apr-19

Time: 18.00pm 68 Time: 18.00pm 62 Time: 16.00am 81 Time: 17.00pm

SGB 06 : fixing rebar column 1st lif 8 SGB 06 : prepare rebar column 1st lif 8 SGB 06 : repair crack NCR 4 SGB01b :threading work

SGB 07 : fixing rebar 2nd lif 8 SGB 07 : prepare rebar 2nd lif 8 SGB 07 : prepare rebar 2nd lif 8 SGB 09 : installation sheetpile cofferdam

SGB 02 : erection xhead 2R 10 FT 1, 2, 3, 4 : assembling work 10 SGB01b : threading work 6 TNE 37 : fixing rebar & formwork in progress

FT 1&2 : assembling work working platform 5 LG 2 : advancing work 10 Span 02 - 03 : cropping tendon 4 LG 2 : erection SBG span 03-04

TNE 36 : dismantle soffit formwork & install main


FT 3&4 : assembling work main girder 5 18 SGB 09 : installation sheetpile cofferdam 3 FT 1 : installation parts on hammerhead
rail

LG 2 : checking and repair defects 10 SGB 03 : dismantling formwork 8 TNE 37 : fixing rebar & formwork in progress 10 FT 2, 3, 4 : assemble parts and jointing work

TNE 36 : dismantle soffit formwork & install TNE 36 : dismantle soffit scaffolding &
18 FT 1, 2, 3, 4 : assembling work 10
main rail housekeeping

SGB 03 : housekeeping & touch up work 4 LG 2 : advancing work 10

TNE 36 : dismantle soffit formwork & install main 18


frame

SGB 03 : dismantling formwork 8

Time: 19.00pm 25 Time: 11.00am 16 Time: 10.33am 18 Time: 11.00am

SGB 10: fabricate rebar for pier head & SGB 11: Installation tie down bar and formwork for SGB 11: joint survey and adjust mould for pier
14 7 8 No activity
preparation to install side mould monolithic pier head MD1 (stage 2) head 2nd stage

SGB 12: installation side mould for pier head 1st


SGB 13: bending rebar for column SGB 07 4 SGB 12: Installation i- beam for steel mould 5 5
stage

SGB 18: fabricate PERI working platform for 7 4 TP 03: dismantle formwork of pilecap 5
pier column TP 06 SGB 18: Fabrcate peri working platform for tp 06

Time: 16.00pm 102 Time: 18.00pm 93 Time: 17.30pm 102 Time: 15.00pm

TP20: finalising plinth rebars and LG1 cast in


TP19: installing scaffold 6 7 TP20: concreting 6 SRN02: erecting scaffold
items,aiming to cast
TP20: adjusting mould, preparing plinth bars 5 TP23: installing vertical lap bars 6 TP23: installing rebars 7 TP17: installing rebars
and cast in items

TP26 infill / TP24 1st lif column : roughening


TP26: roughening construction joint 2 2 TP24: roughening const joint 2 SRN01A: tendons ducting
construction joint / roughening construction joint

TP24 yard / SRN04A: installing j bolts on peri


TP27: installing bottom and side bars 7 TP27: adjusting rebars for PT bar pipe/sleeve 4 slabs / 3 LG1: SRN12-13: SBG Erection dan jointing
dismantling infill formwork

TP26 infill / SRN04A : cranking rebars /


TP27 infill / SRN02: installing side bars / dismantling
Bending Yard (Gagasan): cut and bend 6 3 shifing and installing blisters (preparation for 1st 5
side blisters pair)

SRN01S PH / SRN01N plinths: finalising n


concreting PH / finalising and concreting 8 Bending Yard (Gagasan): cut and bend 6 Bending Yard (Gagasan): cut and bend 6
plinths

SRN01A: installing bottom bars 7 SRN01N: dismantling PH mould 8 SRN02A: installing rebars 7

SRN04S: dismantling and shifing scaffold


SRN03: rectifying edge railing n toe board 3 SRN04S: dismantling scaffold 11 11
materials

SRN11: finalising and concreting plinths 8 SRN10: installing rebars 7 SRN10: installing rebars 8

TP06: dismantling formwork and patching 4 SRN19: arranging scaffold 2 SRN19: arranging scaffold 2
work
TP07: installing rebars 7 TP06: patching work (rectification 5 TP03: dismantling props and formwork 4
TP17: preparing rebars on ground 7 TP07: installing rebars 6 TP04: installing 2nd lif link bars 5

TP17: installing link bars and brushing mould


SRN01: segment joints patching 2 5 TP07: installing rebars 3
surface

SRN02: 3rd pair -stressing 5 SRN02: 3rd pair -cropping 5 TP17: installing rebars 6

SRN02A: tendons ducting 3 SRN02A: tendons ducting 3 SRN01: 3rd pair -joints patching work 2

SRN04S: dismantling scaffold 9 LG1 : SRN12-13: Advancing 13 SRN02A / SRN01A: tendons ducting 3
LG1 : SRN12-13: Advancing 13 SRN02 : 3rd pair -joints patching work 3
SRN03 : 2nd pair -threading work 6
LG1 : SRN12-13: Advancing & SBG erection 8/13 13
nos
195 171 201 Total (Day)
75

10

10

10

18

18

36

14
6

13

111

You might also like