Professional Documents
Culture Documents
Relief Valves PDF
Relief Valves PDF
Relief Valves PDF
EDS 2004/RV-1
Outline
Introduction
Hazard Identification
Process Model for Relieving Conditions
PRV Calculations: External Fire
PRV Calculations: Electrical Power Failure
Sizing and Selecting a Pressure Relief Device
EDS 2004/RV-2
Relief system design begins with identifying the causes of overpressure in the process
unit. Various qualitative methodologies are used to identify events that require
overpressure protection, e.g. safety checklists and HAZOP studies.
Once the relieving rates are determined, pressure relief devices are sized and selected for
each service.
Note: Relief system design only addresses those events that cause high pressure. Vessels
can fail due to over-temperature, brittle fracture, corrosion, erosion, metal fatigue, etc.
These failure events have to be managed by other means, such as depressurization,
metallurgy selection, inspection and maintenance.
EDS 2004/RV-3
Many protection layers are needed to provide effective process safety, and the
pressure relief system is only one of them.
This training session focuses on relief system design, but the student should be
aware that multiple systems are required for process safety.
Managing Process Safety
Maintenance
Inspection Procedures
Process Safety
Management
Permits Training
Managing Change
EDS 2004/RV-4
Process Safety Management extends beyond process design and construction. It has
to address and manage safety issues that develop throughout the operating life of the
process unit.
Collapsed Fractionating Column
EDS 2004/RV-5
Not all hazards are addressed with pressure relief. This incident occurred during a
repair operation. Hot metal from a welder’s torch ignited polymer that had built-up
on the trays in this fractionating column. The ensuing fire weakened the vessel wall,
and caused it to collapse under its own weight. .
Failed Pressure Test
EDS 2004/RV-6
Here is another example. A pressure test was conducted on this vessel during an
exceptionally cold winter day. The vessel failed due to brittle fracture before its
design pressure was reached.
Note: A relief valve is typically removed prior to the pressure test, and its inlet
nozzle is blanked-off. Hazards associated with pressure tests must be managed
using other safety systems, such as testing protocols.
OSHA 1910.119 Process Safety Management
EDS 2004/RV-7
Process hazard analysis (PHA) identifies the events that can cause high pressure
in a process unit. Thus, the PHA report provides a convenient source for those
overpressure events that are addressed by pressure relief protection.
Safety checklists can also be used to generate a list of high pressure events.
These lists appear in API recommended practice, Center for Chemical Process
Safety (CCPS) publications, and journal articles.
OSHA Requirements
EDS 2004/RV-8
Various techniques can be used for PHA, and the choice depends on process
complexity, the past incident history, the available personnel and other factors.
Since the PHA lists pressure relief valves as safeguards for high pressure events, it
provides information pertinent to relief system design.
The PHA team should include personnel familiar with the design and operation of
the process unit, and it should led by a person experienced in PHA methodology.
PHA recommendations must be reviewed and resolved, and action taken by the
follow-up team must be documented.
Factors Affecting PHA Methodology
EDS 2004/RV-9
EDS 2004/RV-10
Approved PHA Methods
Checklist
"What if " Analysis
Failure Modes and Effects Analysis
Hazard and Operability (HAZOP) Studies
Fault Tree Analysis
EDS 2004/RV-11
OSHA approves five PHA methodologies. The owner/operator is free to choose any
method on this list, but we will focus on HAZOP methodology..
HAZOP
Methodology
EDS 2004/RV-12
Hazard and Operability (HAZOP) Analysis is a systematic, team effort that uses
process deviations to identify hazards and operating problems.
HAZOP Objectives
EDS 2004/RV-13
The HAZOP study has five main objectives as listed above. Although OSHA
requires a process hazard analysis to be performed, the benefits of the HAZOP
study go far beyond regulatory compliance.
Note: After the HAZOP study is complete, an action plan must be developed to
address recommendations. All recommendations are reviewed, and if accepted,
they must have an implementation plan. Hazards identified but not addressed will
dramatically increase the owner’s liability.
Scope of HAZOP Analyses
EDS 2004/RV-14
The scope of the HAZOP study must be defined prior to conducting the
analysis. Otherwise, the study can easily expand beyond allocated time and
resources. A well planned study minimizes the potential for a cursory
analysis toward the end of the study due to time pressure.
Process Unit Interface
Feed(s) from Other
Feed(s) from Storage
Process Units
Utilities
Injection
Chemicals
Process Unit
Catalysts,
Absorbents
Ancillary
Systems
Design Intention
Process Deviation
Causes
Consequences
Safeguards
Risk Ranking
Recommendations
Yes
More Deviations ?
Yes
Other Nodes ?
EDS 2004/RV-16
Generally, a HAZOP team needs 1-2 hours to analyze each study node, based
on average size and complexity. The number of nodes can be used for cost
estimates, meeting planning, or as a coarse measure of study progress.
There is no “right” way to break the process unit into study nodes. Node size
depends on process complexity, team experience, company policy, and/or
personal preference. However, node size may affect team efficiency. If
nodes are defined too small, the study becomes tedious and team members
may lose interest. If nodes are defined too large, the team may get lost in
their analysis and miss important hazards.
Problem 1A: Node Break-Up
1. There is no right way to define the study nodes. Node size is a function of
the skill of the team leader, personal preference, team experience, and
process complexity.
2. There is a direct relationship between node size and the process deviations
considered in that node. As a node gets smaller, process deviations are
fewer.
3. Utilities that interface with the process unit can be added to the equipment
using that utility, or they can be defined as a separate node. If the utility is
added to the equipment node, utility system deviations are entered as
causes.
Process Deviations
EDS 2004/RV-19
Process control indicates which variables are important, and as such, it makes
a significant contribution to the deviation list. For example if pressure is
controlled, both high pressure and low pressure deviations should be analyzed
Likewise, unit operations can supplement the deviation list. For example, a
fractionating column (unit operation) distributes feed components into two or
more product streams. If the fractionating column does not function as
designed, heavy components will exit with the overhead product, or light
components will exit with the bottoms. Either way, poor fractionation should
be considered as a process deviation.
EDS 2004/RV-20
The design intent defines the safe operating envelop for a process variable,
and process deviations are defined as those falling outside that range. For
example, if a pump is designed for 50%-125% of its normal operating
capacity, the low flow deviation only considers the consequence of flow less
than 50%. Likewise, the high flow deviation only considers the consequences
of flow greater than 125%.
Problem 1B: Process Deviations
EDS 2004/RV-21
1. Only those process variables that are controlled within the study node
are listed. Likewise, only the unit operations found in the study node
are considered.
2. Process control and unit operations indicate which variables are
significant.
3. Supplement your process deviation list using commercially available
deviation lists. Refer to the deviation list provided for this problem.
4. Once the process variables are identified, deviations are constructed
using guidewords. For example if “pressure” is the process variable,
the standard guidewords are “high” and “low”. Process deviations for
“pressure”become “high pressure” and “low pressure”.
Determining the Causes for a Deviation
EDS 2004/RV-22
Once the process deviations are identified, causes for each deviation must be
determined. Only those causes originating within the node are analyzed. This
strategy focuses team effort, minimizes redundancy, and makes the HAZOP
study more efficient.
EDS 2004/RV-23
The probability that two unrelated causes will occur at the same time is very
remote, but not impossible. If the consequence of two unrelated events
occurring simultaneously is catastrophic, this low probability event is better
investigated using fault tree analysis.
Process deviations that occur upstream of the node boundary are included in
the feed node as “causes”. For example, changes in feed composition can be
listed as causes in the “As Well As Flow” deviation.
Problem 1C: Causes
Using the P&ID for the overhead condensing system, list the
causes for two deviations: “High Pressure” and “Low Pressure”.
EDS 2004/RV-24
1. For each process deviation, develop a list of causes for that deviation.
After the list is completed, the individual causes can be further analyzed,
i.e. determining consequences, identifying safeguards, etc.
2. Focus on loss of function to combine a number of causes, assuming that
each cause has similar consequences. For example, condenser duty can be
lowered by control failure, losing electric power to the fans, vapor
blanketing, etc. However, the consequences of reduced heat removal is
qualitatively the same regardless of the cause.
3. Include equipment names and item numbers in all descriptions. This
makes the HAZOP study more understandable for future users.
Consequences
Causes are limited to the study node, but consequences are not. Since
consequences (effects) are linked to a specific cause, a complete description
of the failure event must include consequences that propagate outside the
study node.
EDS 2004/RV-27
EDS 2004/RV-28
A risk ranking system must be established prior to the HAZOP study. The
size of the risk matrix should reflect HSE policy and be used consistently
throughout the company.
Level I II III IV
Description Catastrophic Severe Moderate Low
Human Impact Death Injury Minor None
Environmental Damage Major Serious Minor None
Production Loss > 6 Months 1- 6 Months 1- 4 Weeks < 1 week
Damage Value > $10M $1M - $10M $0.1M - $1M < $0.1M
M = Million
EDS 2004/RV-29
The consequence with the highest severity ranking determines the severity
level.
Likelihood Definitions
Frequent (Level 1)
– Expected to occur frequently (many times a year)
Occasional (Level 2)
– Expected to occur occasionally (once a year)
Infrequent (Level 3)
– Expected to occur under unusual circumstances
(once or twice during facility lifetime)
Unlikely (Level 4)
– Could occur; however, not likely during facility
lifetime
EDS 2004/RV-30
Severity
I II III IV
Likelihood 1 D D C B
2 D C B A
3 C A A A
4 A A A A
EDS 2004/RV-31
Note: “D” risk rankings require a design change to improve the ranking to
“C” or better. As such, they are only assigned to a consequence and its
safeguards when it is absolutely necessary.
Response to Risk Ranking
Ranking Action
EDS 2004/RV-32
Although “A” risk ratings do not require an action, the team can still make
recommendations that improve safety or operability.
EDS 2004/RV-33
Assign Priority
Implement or Reject
Recommendation
During After
HAZOP HAZOP Document Decision in
Meeting Meeting Follow-up Report
EDS 2004/RV-34
The process hazard analysis has four phases: the HAZOP meeting itself, an
engineering review of all recommendations, implementation of those that are
valid, and issuing a close-out report. The PHA is not finished until all four
phases are complete.
Rationale For
Allocating Resources
HAZOP
Study Results
Operator Training
Documentation
Required by OSHA
EDS 2004/RV-35
Documentation for the HAZOP study not only meets OSHA requirements,
but also provides information for operator training, and a rationale for
allocating resources for process safety.
Fire-Heated Boiler
EDS 2004/RV-36
EDS 2004/RV-37
Heat and mass balances are constructed at relief conditions to determine the amount of
material that needs to be relieved to limit overpressure .
The process model for relief conditions incorporates assumptions that can significantly
affect the relieving rate obtained, and API recommendations regarding those
assumptions are closely followed.
A process model is constructed for each overpressure case identified in the safety
checklist or HAZOP study. Once the relieving rates are determined for the overpressure
cases, the maximum rate is used to size and select the pressure relief device.
Heat and Mass Balances
In = Out
EDS 2004/RV-38
Steady state balances are used for process design, but unsteady state balances
are required for relief calculations. Although only two terms are added to the
unsteady state equation, multiple, non-linear differential equations result, and
complicate the analysis immensely.
However for most problems, a time interval can be carefully selected, and
quasi-unsteady state balances constructed. This reduces the problem to one
that can be solved algebraically. The difficulty with this approach is
selecting the “right” time interval.
Blocked Outlet Transient
RS 31.4-R00-4
EDS 2004/RV-39
For a blocked liquid outlet, flow through the relief valve will increase very
rapidly once the vessel becomes liquid full. The time interval chosen to
construct the heat and weight balance occurs after the surge drum liquid fills.
Upstream Control Valve Fails Open
RS 31.4-R00-5
EDS 2004/RV-40
When the upstream control valve fails open, liquid from the HP separator
flows into the LP Flash drum. Once the liquid level in the HP separator is
lost, reactor vapor breaks through, and the reactor circuit depressurizes into
the LP Flash Drum, causing its pressure to rise rapidly. The pressure relief
valve on the LP Flash Drum will open and relieve the excess flow. As
pressure in the reactor circuit decreases, less mass will flow into the the flash
drum, and the relieving rate will tail off.
The time interval selected to construct the relieving heat and mass balance.
occurs relatively soon after the failure event, when HP reactor circuit
pressure is at its maximum.
Relief Model Development
EDS 2004/RV-41
If a HAZOP study was conducted, the sequence of events can be extracted from
the HAZOP report. If a safety checklist was used to identify the causes of
overpressure, the sequence of events will have to be constructed. As the failure
event progresses, additional failures may occur, and the relief model has to take
the worsening situation into account.
API recommended practice does not allow credit for a beneficial instrumentation
response during the relief event. However, if the normal instrumentation
response increases the relief load, it is assumed to function as designed.
Codes and Practices
EDS 2004/RV-42
EDS 2004/RV-43
RS 31.4-R00-7
EDS 2004/RV-44
We can take credit for the valve’s normal position when calculating the
relieving requirement.
Instrumentation Response
RS 31.4-R00-8
EDS 2004/RV-45
The maximum required relieving rate is the maximum expected inlet flow
based on this diagram.
Operator Response
EDS 2004/RV-46
EDS 2004/RV-47
The following section will concentrate on the relief valve calculation for an external
fire.
EDS 2004/RV-48
I don’t know where this picture came from, but I thought it provided a sobering
introduction to external fires.
Feed Surge Drum
LLC
RS 31.5-R00-9a
EDS 2004/RV-49
A feed surge drum system will be examined in this section to determine the
relieving rate during an external fire. Feed is normally pumped to the drum,
and liquid is pressured out of the surge drum to a fractionating column.
Fire Case Model
Qfire RS 31.5-R00-9c
EDS 2004/RV-50
For the fire case model, it is assumed that the system is isolated, i.e. there is
no liquid input and no liquid output.
Heat Input Due to External Fire
Q = 2100FA0.82
EDS 2004/RV-51
The heat input equation is based on API Recommended Practice 521. This
equation assumes that English units of measurement are used.
Environmental Factor
EDS 2004/RV-52
The environmental factor (F) can be less than 1.0 if credit is taken for fire
proof insulation. API RP 520 lists environmental factors for various
insulation thickness. UOP recommends that a minimum environmental factor
0.075, regardless of insulation thickness.
25 ft.
Elev.
RS 31.5-R00-10
EDS 2004/RV-53
If the actual liquid level is lower than 25 ft from grade, we use the actual
liquid height to calculate the wetted surface area of the vessel. If the liquid
level is higher than 25 ft, then the wetted surface area of the vessel should be
calculated based on 25 ft.
For trayed vessels, assume 2 to 3 inch liquid hold-up on each tray. The total
liquid height of a trayed vessel includes the bottom liquid inventory plus the
sum of the liquid holdup on all the trays. Then apply the 25 ft effective fire
height for wetted surface area.
For packed columns, the total liquid height is the bottom liquid inventory plus
5% of the packing volume.
Vaporization Rate
Q
Wfire =
∆Hv
EDS 2004/RV-54
The liquid vaporization rate inside the vessel can be calculated by dividing the
total heat input by the latent heat of vaporization of the liquid. This
vaporization rate is equal to the required relieving rate through the relief
valve.
EDS 2004/RV-55
The latent heat of vaporization can be found by using the vapor pressure (i.e.
absolute relieving pressure) and molecular weight of the boiling liquid. The
chart will also provide the relieving temperature.
EDS 2004/RV-56
Using the data given in the problem, calculate the vapor relieving rate. Use
Figure D-3 in API RP 520 to estimate the latent heat of vaporization and the
relieving temperature.
Liquid Filled Vessel: Initial Conditions
Qfire Qfire
EDS 2004/RV-57
After the initial thermal relieving stage, vapor will form at the top of the
vessel, and the relieving material will be two phase because there is no vapor-
liquid disengaging space available.
Liquid Filled Vessel: Later Conditions
Qfire Qfire
EDS 2004/RV-58
The above diagram shown that sufficient space is available for vapor-liquid
disengagement, and all vapor flows out the relief valve.
UOP Design Practice for Liquid Full Vessels
EDS 2004/RV-59
Auto-chilling minimum temperatures will affect the design of the material for
the relief valve and the relief header.
PSV Calculations:
Debutanizer
EDS 2004/RV-60
The Debutanizer relief valves calculations are covered in the following section.
Debutanizer
EDS 2004/RV-61
1. The normal heat and weight balance is modified to construct the HWB at
relieving conditions. If everything balances at normal conditions, proceed
with the relief analysis. If heat and mass do not balance for both envelopes,
correct your mistake before proceeding with the relief analysis.
2. Two envelopes are used to construct the heat and weight balances because
this format makes the relief analysis somewhat easier.
Summary of Overpressure Events
for the Debutanizer
EDS 2004/RV-63
These are the main overpressure events considered in this training session.
The overpressure events could have been taken from a safety checklist, or
they could have been extracted from the HAZOP report.
There are other overpressure cases not listed here, e.g. higher than normal
reboiler duty, but these cases usually do not govern PRV sizing, nor does they
impact the flare design. However, the designer should use engineering
judgment regarding pertinent overpressure cases for a specific design.
Refinery-Wide Electrical Power Failure
EDS 2004/RV-64
Although not shown, the feed is pumped to the debutanizer, When electrical
power is lost, the motor driven feed pump stops. If the feed is pressured into
the column, feed may/may not continue depending on upstream control, and
system hydraulics during the relief event.
API recommended practice allows a 20-30% residual duty credit for air-
cooled exchangers. UOP conservatively uses 20%.
If the receiver level control functions as designed, it would close the reflux
valve. Since losing reflux tends to increase the relieving rate, API
recommends that reflex be stopped.
If the pressure controller functions as designed, it would open the net vapor
product valve. Since this would reduce the relieving rate, API recommends
that the pressure control valve be “frozen”in its normal position.
Debutanizer
(Electrical Power Failure Model)
Condenser Duty
(natural convection)
HWB 1 HWB II
Reboiler Duty
(radiation from refractory)
EDS 2004/RV-65
Analysis of the power failure model requires two steps. First, construct a heat
and material balance around the column (HWB I) to determine the quantity of
bottoms material that has to be vaporized to maintain heat balance. Second,
construct a heat and mass balance on the overhead system to determine the
relieving rate required during the power failure.
Power Failure HWB I
Mass Heat
Total 0 0
EDS 2004/RV-66
Note: In order to balance heat and mass during relief conditions, bottoms
liquid is vaporized (depleted). The vaporized bottoms material then leaves
the envelope and removes the excess enthalpy.
HWB I: Power Failure Case
(Working Equations)
QREB
WB =
∆H V
EDS 2004/RV-67
If the reboiler duty during relieving conditions is known, then the amount of
material that is vaporized can be directly calculated if the latent heat of
vaporization of the material is known.
Qcond
Wcond =
∆H v
EDS 2004/RV-68
The air condenser will still have partial condensing duty based on natural air
convection. It is acceptable to take 20% of the normal air condensing duty as
the residual condenser credit.
The latent heat of vaporization in this equation (HWB II) should be the same
as that used in HWB I.
1. Heat and weight must balance during for relief conditions. Bottoms liquid
is vaporized to obtain a heat balance, and its depletion must be accounted for.
3. Bottoms material will reach the top of the debutanizer only after the trays
dry out, and this generally takes 10-15 minutes to occur. (No fractionation
will occur once the tray liquid is gone.) A refinery-wide power failure is so
disruptive that it will take hours (not minutes) to recover. Thus, UOP
assumes that bottoms material will have plenty of time to migrate to the top of
the debutanizer.
Loss of Air-Cooled
Condenser Duty
EDS 2004/RV-70
EDS 2004/RV-71
During the casualty the PRC control valve will attempt to open wide, but API
does not allow to consider this credit. Therefore, we assume the net overhead
vapor will be the normal rate during relieving conditions.
Because the reflux stops, heavy material will migrate to the top of the column.
Debutanizer
(Model for Loss of Condenser Duty)
Condenser Duty
(natural convection)
HWB 1
HWB II
Reboiler Duty
(normal)
RS 31.6-R00-17
EDS 2004/RV-72
As in the power failure case, the analysis is a two step process, i.e. construct
HWB 1 and then HWB 2.
Condenser Failure HWB I
Mass Heat
Feed
+Wf +Wf hf
Net bottoms −Wnb −Wnbhnb
Reboiler Duty
+ Qreb
− Wno − Wnohno
Net Overhead Vapor
− WT − WThv
Vaporized Tray Liquid
+ WT + WThl
Depleted Tray Liquid
Total 0 0
EDS 2004/RV-73
The heat and mass balances should not have any accumulation, i.e. net in
must equal net out.
Vaporized Tray Liquid
(Working Equation)
EDS 2004/RV-74
RS 31.6-R00-18
EDS 2004/RV-75
The above drawing shows normal operation and when the reflux stops.
Notice the liquid inventory on the tray.
Heat Content of Net Bottoms
(Leaving the Envelop)
Before F/B exchanger After F/B exchanger
F/B exchanger
must be rated
regardless of
heat & mass
envelop
RS 31.6-R00-19
EDS 2004/RV-76
In order to close the heat balance on the fractionator, the F/B exchanger must
be analyzed at relieving conditions. This will then provide the corrected heat
content to the column.
Feed/Bottoms Exchanger Duty
Thsi
Assumes:
The corrected duty of the F/B exchanger will depend on the inlet temperatures
of the feed and bottoms at relieving conditions.
Problem 5: Construct HWB I at Relief Conditions
Using the working equation for HWB I, determine the amount
of tray material that must leave the first envelope as a vapor to
obtain a heat and mass balance during a condenser failure case
1. Heat and weight must balance during for relief conditions. Bottoms liquid
is vaporized to obtain a heat balance, and its depletion must be accounted for.
3. Bottoms material will reach the top of the debutanizer only after the trays
dry out, and this generally takes 10-15 minutes to occur. (No fractionation
will occur once the tray liquid is gone.) A refinery-wide power failure is so
disruptive that it will take hours (not minutes) to recover. Thus, UOP
assumes that bottoms material will have plenty of time to migrate to the top of
the debutanizer.
Condenser Failure HWB II
Mass Heat
Total 0 0
EDS 2004/RV-79
The air condenser will have partial condensing duty based on natural air
convection. It is acceptable to take 20% of the normal air condensing duty as
the residual condenser credit.
Loss of Condenser Duty Relieving Rate
Qcond
Wcond =
∆Hv
Relieving rate (difference between total vapor rate
leaving debutanizer and residual condensation):
Wrel =Wtotal−Wcond
EDS 2004/RV-80
The air condenser will have partial condensing duty based on natural air
convection. It is acceptable to take 20% of the normal air condensing duty as
the residual condenser credit.
The latent heat of vaporization is based on the composition of the liquid in the
overhead receiver.
In reality, for the case of reflux failure, loss of condenser, or PRC failing
closed, the required relieving capacity should not be greater than the normal
overhead vapor rate.
Receiver PRC Fails Closed
EDS 2004/RV-82
These items refer to the assumptions that are made when the net overhead
vapor control valve fails closed. Refer to Debutanizer flow sketch in Slide 2
of this section.
Since feed continues into the column in this case, use feed composition as the
heavy material to be vaporized.
Separator LLC Fails Opened
These items refer to the assumptions that are made when the separator control
valve, which is the column’s feed control valve, fails opened. Refer to
Debutanizer flow sketch in Slide 2 of this section.
Even though the PRC control valve will tend to open wide during this
casualty, credit for this cannot be taken. Assume the PRC control valve is at
its normal position.
Selecting the
Pressure Relief Device
EDS 2004/RV-84
EDS 2004/RV-85
Weighted pallet commonly used for tank vents for pressures 2 psig and lower.
Vent lines are sized by hydraulic formulas, and should contain no pockets
(free draining).
Conventional
Pressure Relief Valve
RS 31.7-R00-22
EDS 2004/RV-86
This type of valve is the most common and are not used where high
backpressures may be present.
Balanced-Bellows
Pressure Relief Valve
RS-31.7-R00-23
EDS 2004/RV-87
The principal difference between the conventional spring loaded relief valve
and the balanced-bellows spring loaded relief valve is the presence of a
bellows located between the spring and the disk.
Opening & Closing
Spring-Loaded PSV
EDS 2004/RV-88
This is a detail view of typical opening and closing of a spring loaded relief
valve. This chart plots relieving capacity versus system pressure.
As the system pressure approaches set pressure, the relief valve may start to
leak. Once set pressure is reached, the relief valve pops open, and the
relieving capacity reaches 70 - 80% of the design capacity.
If the system pressure continues to increase, then the relief valve will reach
the fully open position.
Blowdown, which is closing of the valve, follows a different path. Once the
system pressure drops to approximately 93% of the system set pressure, the
valve will close. Blowdown percentage will vary depending on whether the
valve is designed for vapor relief, liquid relief, or two-phase relief.
EDS 2004/RV-89
There is much impact on the design. There is the spread between the
operating and the set pressure. In addition inlet pressure losses must be
reviewed. Rapid opening of the valve is another design criteria.
Force Balance
Conventional Pressure Relief Valve
RS 31.7.R00- 27
EDS 2004/RV-90
For a conventional relief valve the spring force is opposed by the inlet
pressure force.
Seating Force
Spring-Loaded Pressure Relief Valve
RS 31.7.R00-26
EDS 2004/RV-91
As the operating pressure increases, the seating force decreases. When the
operating pressure approaches the set pressure, the seating force decreases to
zero. When the seating force approaches zero, the valve starts to open.
Valve Leakage
Set Pressure
Operating Pressure
EDS 2004/RV-92
To obtain a stable operation, the spread between set pressure and operating
pressure should be a minimum of 10%. The minimum spread should be
larger for liquid or two-phase applications.
Design Options for Leakage
EDS 2004/RV-93
The above slide shows the design options for leakage in relief valves.
Inlet Pressure Loss
} Blowdown Pressure
90 93
Operating Pressure
EDS 2004/RV-94
Both API and ASME limit the inlet pressure loss to 3% of the PSV set
pressure for spring loaded relief valves.
The blowdown pressure is the pressure required to reseat the valve after it has
opened during a relieving case.
Inlet Line Sizing
Pressure Drop Calculated Using
Rated Capacity of Valve
Equivalent length
includes:
Sudden contraction
Elbows
Tee
Reducer
Length of piping
RS 31.7.R00- 40
EDS 2004/RV-95
The sudden contraction means the pipe entrance (from the vessel).
The total frictional loss from the protected vessel to the inlet of the relief
valve should not exceed 3% of the valve’s set pressure.
The pressure drop is based on the valve’s “rated” capacity. For example, if
the required relieving capacity of 5000 lb/hr needs 0.25 in2 orifice area, we
have to select an “F” orifice with 0.307 in2 orifice area. Therefore, the
frictional loss should be based on 6,140 lb/hr of relieving (rated) capacity.
Design Options for Meeting 3% Inlet ∆P
EDS 2004/RV-96
RS 31.7.R00- 25
EDS 2004/RV-97
The above diagram shows the force balance in convention pressure relief
valves.
Effect of Back Pressure
RS 31.7.R00-29
EDS 2004/RV-98
When the built-up back pressure reaches 10%, there will be no flow through
the relief valve with 10% overpressure. Similarly, when the built-up back
pressure reaches 21%, there will be no flow through the relief valve with 21%
overpressure.
Force Balance
Balanced Pressure Relief Valve
RS 31.7-R00-30
EDS 2004/RV-99
The back pressure force on the disk is reduced due to the presence of the
bellows.
Effect of Back Pressure
Balanced Relief Valve
16 %
RS 31.7-.R00-31
EDS 2004/RV-100
If the built-up back pressure is less than 30% of set pressure, the relieving
capacity will not be reduced. The maximum allowable built-up back pressure
for balanced bellows relief valves is 50%.
Design Options for High Back Pressure
EDS 2004/RV-101
Increasing the diameter of the discharge piping will reduce the built-up back
pressure only. It will have no effect on the superimposed back pressure
Lowering the spring setting will offset the superimposed back pressure only.
It will have no effect on the built-up back pressure.
Summary
Spring-Loaded Pressure Relief Valves
110
Accumulated Pressure
% of Set Pressure
97 100
Set Pressure (Design Pressure)
Minimum Inlet Pressure
90 92 95
Significant Leakage
Operating Pressure
EDS 2004/RV-102
The above diagram shows the percent of set pressure for spring-loaded
pressure relief valves.
Sizing for Vapor
Spring Loaded Relief Valve
The coefficient of discharge (K) will vary depending on the valve type and
manufacturer of the valve.
The back pressure correction factor (Kb) is for balanced bellows relief valves
only. For conventional relief valves, Kb is 1.0.
Sizing for Liquid
Pressure Relief Valve with Liquid Trim
Q SpGr
RA =
38 K Pacc − Pb
EDS 2004/RV-104
The API equation includes two other terms in this equation. There are
correction factors due to back pressure and liquid viscosity. This simplified
equation assumes the correction factors are both 1.0.
The coefficient of discharge (K) will vary depending on the valve type and
manufacturer of the valve.
EDS 2004/RV-105
This approach for sizing of flashing flow is UOP design practice. API will
soon publish new methods for calculating two phase flow.
Pop-Action Pilot-Operated Valve
(Flowing Type)
RS 31.7-.R00 -34
EDS 2004/RV-106
There are actually two valves, the main relief valve and a pilot valve. The
main valve
The pilot controls the opening and closing of the main valve.
Flow Characteristic
Open and Closing
% Capacity
No Blowdown
Modulating Pilot
No Leakage
The pilot can be specified to give pop action like we saw before, or
modulating action.
RS 31.7-R00-36
EDS 2004/RV-108
One of the advantages for the PORV is that the seating force increases when
the inlet pressure increases. When it reaches the set pressure, the seat force
reaches its maximum. Therefore, there is no leakage before the valve
relieves.
Seating Force
Pilot Operated Pressure Relief Valve
RS 31.7-R00-37
EDS 2004/RV-109
Once the inlet pressure reaches the set pressure, the seating force becomes
less than inlet pressure and the valve opens.
Unique Considerations
Pilot Operated Relief Valves
Backflow Preventer
EDS 2004/RV-110
Three different types of materials can be used for seats and seals: viton
(elastomer), teflon (plastic), and metal. Each material has its own pressure
and temperature limitations. For example, elastomers are only acceptable up
to temperatures of 400-450F.
Backflow Through a PORV
RS 31.7-R00-36
EDS 2004/RV-111
In cases where the inlet pressure is low (providing very low force to keep the
valve closed), an increase in relief header pressure could cause the valve to
open, resulting in back flow.
Backflow Preventer
RS 31.7-R00-39
EDS 2004/RV-112
The backflow preventer will use the relief header back pressure to keep the
valve closed when the inlet pressure to the valve is low. For vacuum
operation a backflow preventer must be installed.
Remote Sensing
Applying the 3% Pressure Loss Constraint
EDS 2004/RV-113
If the pressure loss from the vessel to the inlet of the PORV is greater than
3%, then the required relieving area of the valve will need to be increased.
PORV Advantages
Seat Tightness
Remote Pressure Sensing
Less Sensitive to Back Pressure
Field Testing of Pilot Set Point
Remote Depressuring
Ability to Modulate Flow
EDS 2004/RV-114
Seat tightness prevents leakage at set pressure and allows for the application
of a narrow spread between set pressure and operating pressure.
Remote pressure sensing allows inlet line losses greater than 3% of set
pressure.
PORV can be used for vacuum and low pressure operation with backflow
preventer.
Ability to modulate flow will reduce loss of product to the relief header.
PORV Disadvantages
Difficult to Specify
Temperature Constraint
Elastomeric Compatibility
Limited Metallurgy Selection
Unfamiliar Technology
EDS 2004/RV-115
For small sizes, pilot operated valves can be more expensive than spring
loaded valves
PORV Applications
EDS 2004/RV-116
PORV are commonly used in specialty chemical plants so that product loss
can be reduced due to modulating action of the valve.
PORV are also used in large vapor relief services, e.g. in gas pipeline
applications.
PORV Sizing for Vapor
W TZ
RA =
CKPacc MW
EDS 2004/RV-117
Accumulated pressure can be 21% for fire case or 10% for non-fire cases.
PORV Sizing for Liquid
Q SpGr
RA =
38 K Pacc − Pb
EDS 2004/RV-118
The equation assumes the correction factor for the liquid viscosity and correction
factor due to back pressure are 1.0.
EDS 2004/RV-119
Selecting multiple valves of the same size is a UOP practice. Some refiners
use valves of different sizes in the same service.
Example
EDS 2004/RV-120
The above example shows the required area and number of valves required.
Spare Valves
EDS 2004/RV-121
If a spare valve is specified, both the spare valve and the on-line valve must
have isolation valves.
Isolating Block Valves
Design Considerations
EDS 2004/RV-122
The isolating block valve must be locked open (or car sealed open) on the
operating relief valve and locked closed (or car sealed closed) on the spare
relief valve.
Rupture Discs
Safety Head
Process Process
Pressure Pressure
RS 31.7-R00-41
EDS 2004/RV-123
The rupture disc is not recoverable, i.e. once it opens, it must be replaced.
Once the rupture disc opens, the process pressure will drop to outlet pressure,
resulting in large loss of product.
Rupture Disc Applications
EDS 2004/RV-124
RS-31.7-R00-42
EDS 2004/RV-125
The inlet pipe size may need to be increased due to the pressure loss of the
rupture disc device.
Rupture Disc Sizing
RS 31.7-R00-43
EDS 2004/RV-126
For purposes of frictional loss calculation, assume the opened rupture disc is
equivalent to 75 pipe diameters.
Critical Flow
(Critical Flow Equation for a Rupture Disc)
Qm S g T
RA =
260 Pacc
EDS 2004/RV-127
This equation is for vapor service only, and is simplified from the API critical
flow equation using a Kd value of 0.62.
Piping Systems
Atmosphere
Po
P2
Rupture Disc P1
P4
P3
From Reactor To Reactor
Section Section
P5
RS 31.7-R00-44
EDS 2004/RV-128
The above shows a rupture disc around a control valve if the control valve
fails.