Weekly Progress Report
Weekly Progress Report
M & E Services
WEATHER REPORT 29 Electrical Wiring Work 48% 40% 40%
30 Photovoltaic System 50% 0% 0%
31 Security Alarm & CCTV System 14% 0% 0%
32 Smarthome System 22% 0% 0%
33 Air Cond & Mech. Ventilation 29% 0% 0%
34 Central Vacuum System 0% 0% 0%
Heavy Rain; 35 Lift System Installation 17% 0% 0%
35.71% Clear; 35.71%
FINISHING WORK
49 Plumbing/Sanitary Fittings 68% 5% 5%
50 Sewerage piping, manhole and Rain Water S 71% 50% 50%
Slight Rain; 7.14%
56 Koi pond / Swimming Pool System Installation 33% 0% 0%
Cloudy; 21.43%
Slight Rain; 7.14%
Cloudy; 21.43%
NOTE :
- 1st floor brickworks started at Guest Room, Guest Bath, Bedroom 3, Bath 3, wet kitchen, pantry, Dry Kitchen, Dining Room
- All concreting works for structure are completed. The final concreting works done on the 11/05/2016
- External fencing work has started.
PREPARED BY : VERIFIED BY :
nt
2016
%
%
1%
2016
017
Remarks
No progress
No new progress
No new progress
No progress
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016
PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS
LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH,
DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
Front Elevation
Side Elevation
Side Elevation
Side Elevation
Heavy Rain;
35.71% Clear; 35.71%
Cloudy; 21.43%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT
46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH
PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
Manpower 5/9/2016 5/10/2016 5/11/2016 5/12/2016 5/13/2016 5/14/2016 5/16/2016
Project Coordinator
Clerk of Work 1 1 1 1 1 1 1
Site Engineer
Safety Supervisor
Supervisor 1 1 1 0 0 0 0
Surveyor
Operator
Piler
Carpenter 6 6 6 5 5 5 5
Concretor
Barbender 1 1 1
General Worker 3 3 3 2 2 2 2
Door & Window Frame Inst.
Brick Layer 5 5 5 5 0 0 0
Roofer
Roof covering
Pre-Caster
Ceiling Work Inst.
Aluminium Inst.
Electrician
Plumber
Plasterer
Skim coating
G.I.Work Inst.
M.S.Work Inst.
Floor Screeder
Tiler
Drain Layer
Painter
Fume Cupboard Installer
Gas installer
Sprinkler System Installer
Airconditioning Workers
Emergency Shower Installer
Total Manpower 17 17 17 13 8 8 8
3/30/2016 4/13/2016 4/18/2016
Scheduled Progress 17.16% 18.14%
Actual Progress 15.45% 16.39%
45.00%
40.00%
35.00%
30.00%
% Progress
25.00%
Scheduled Progress
20.00%
17.16% 18.14%
Actual Progress
15.00% 16.39%
15.45%
10.00%
5.00%
0.00%
3/30/2016 4/6/2016 4/13/2016
PROPOSED WORK PROGRAMME (Revisio
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016
Earthwork
Ground Floor
Footing/Stump
Ground Beam
* Delayed due to Changes Work
Alteration to Existing Ground Beam, Lift Pit
and underground sewerage pipe
Anti Termite
1 st Floor
1sr Floor Beam
Staircase
Second Floor
Second Floor Beam / Swimming Pool Structure
Roof
Roof Beam
Roof Column
Upper Roof Beam
Roof Truss
Building Work
Brickwall
Metal I-beam
Plastering
M&E Services
Electrical Wiring Work
Photovoltaic System
Smarthome System
Finishing Work
Install Alum. Door, Window Panel and Fix Glass
R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate
External Wall Finishes
Note: Otherwise indicated, this revised program is based on the amended Architectural Drawing
Interior Design Drawings
dated 2 Nov 15. Any amendment to the above drawings or additional items in future not sho
consideration in this program.
OGRAMME (Revision # 5) - 4th May 2016
G DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETAL
16.67% 33.33%
CHANGES ON DESIGN (FROM RC TO STEEL STRUCTURE)
chitectural Drawings dated 23 Sept 15, Engineer Drawings dated 16 Oct 15 and
50.00% 100.0%
50.00% 100.0%
50.00% 100.0%
50.00% 100.0%
50.00% 100.0%
11.11% 22.2%
16.67%
Actual
Ahead / B
No. Description May-15 Jun-15 Jul-15
1 8 18 25 1 8 15 22 29 6 13
Preliminaries
A Site Mobilization
B Site Clearing
C Site Survey
D Site Office/Store
E Signboard & Hoading
Piling & Earthwork
F Setting Out
G Piling Work
1 Site Mobilization / Building Material Order
2 Earthwork
Ground Floor
3 Footing/Stump
4 Ground Beam
* Delayed due to Changes Work
5 Alteration to Existing Ground Beam, Lift Pit
and underground sewerage pipe
6 Anti Termite
1 st Floor
12 1sr Floor Beam
15 Staircase
Second Floor
16 Second Floor Beam / Swimming Pool Structure
Roof
19 Roof Beam
21 Roof Column
23 Roof Truss
Building Work
25 Brickwall
26 Metal I-beam
28 Plastering
M&E Services
29 Electrical Wiring Work 3.7% 7.4%
30 Photovoltaic System
32 Smarthome System
Finishing Work
36 Install Alum. Door, Window Panel and Fix Glass
51 R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate
4.5%
Jul-15 Aug-15 Sep-15 Oct-15 Nov-1
20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERT
16.7% 33.3%
CHANGES ON DESIGN (FROM RC TO STEEL STRUCTURE)
11.1% 22.2%
ESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SE
80.0% 100.0%
50.0% 100.0%
50.0% 100.0%
50.0% 100.0%
50.0% 100.0%
50.0% 100.0%
eb-16 Mar-16 Apr-16 May-16 Jun-16
29 7 14 21 28 4 11 18 25 2 9 16 23 30 6
25.0% 50.0%
6.3%
31.8% 36.4% 40.9% 45.5% 50.0% 54.5% 59.1% 63.6% 68.2% 72.7% 77.3% 81.8%
eb-16 Mar-16 Apr-16 May-16 Jun-16
29 7 14 21 28 4 11 18 25 2 9 16 23 30 6
58.8% 64.7% 70.6%
33.3%
BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
66.7% 83.3% 100.0% Timber Door Frame confirmed on 14/4/16, 3 weeks required for manufacture, Alumn no confirmation yet
40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% Plastering cannot proceed due to concealed smarthome/alarm wiring not confirmed
No confirmation
No confirmation
9.1% 18.2% 27.3% 36.4% 45.5% 54.5% 63.6% 72.7% 81.8% 90.9% 100.0%
10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0%
5.9% 11.8% 17.6% 23.5% 29.4% 35.3% 41.2% 47.1% 52.9% 58.8%
12.5% 18.8% 25.0% 31.3% 37.5% 43.8% 50.0% 56.3% 62.5% 68.8%
25.0% 50.0%
75.00% 100.0%
90.9% 100.0%
100.0%
75.0% 100.0%
50.0% 100.0%
A
c
t
u
a
l
Jan-17
Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All % Propose Schedule
23 30 W
/
D
0% 0% 0% 0 0.00% o
0.00% ###
n
0% 0% 0% 0 0.00% 0.00% ###
e
0% 0% 0% 0 0.00% 0.00% ###
0% 0% 0% 0 0.00% 0.00% ###
0% 0% 0% 0 0.00% 0.00% ###
100%
100%
0%
0%
0%
0%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
0% 0% 0.00% 0.00%
30.78% 19.66%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016
( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING,
NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
Preliminaries
A Site Mobilization
B Site Clearing
C Site Survey
D Site Office/Store
E Signboard & Hoading
Piling & Earthwork
F Setting Out
G Piling Work
1 Site Mobilization / Building Material Order 100% 100% 0% 0.49% 0.49%
Ground Floor
3 Footing/Stump 100% 100% 0% 0.74% 0.74%
8 Ground Floor Column / Lift Shaft Structure / RC wall 100% 100% 0% 0.74% 0.74%
10 Sub-basement Compartment for Genset and Bal. tank 100% 100% 0% 1.23% 1.23%
11 Koi Pond, Balancing Tank & Pump Room 100% 100% 0% 0.74% 0.74%
1 st Floor
12 1sr Floor Beam 100% 100% 0% 0.99% 0.99%
14 1st Floor Column / Lift Shaft Structure 100% 100% 0% 0.74% 0.74%
Second Floor
16 Second Floor Beam / Swimming Pool Structure 100% 100% 0% 1.23% 1.23%
18 Second Floor Column / Lift Shaft Structure 100% 100% 0% 0.49% 0.49%
Roof
19 Roof Beam 100% 100% 0% 0.49% 0.49%
24 Roof Covering / Sky Light Cover 33% 33% 0% -33% 0.74% 0.00%
Building Work
25 Brickwall 100% 55% -45% 2.22% 1.22%
27 Timber Door Frame & Alumn. Frame 33% 33% 0% -33% 0.49% 0.00%
M&E Services
29 Electrical Wiring Work 48% 40% -8% 3.20% 2.66%
31 Security Alarm & CCTV System 14% 14% 0% -14% 0.49% 0.00%
33 Air Cond & Mech. Ventilation 29% 29% 0% -29% 0.49% 0.00%
Finishing Work
36 Install Alum. Door, Window Panel and Fix Glass 0% 0% 0% 0.00% 0.00%
40 Internal Skim coat, External and Internal Painting Work 0% 0% 0% 0.00% 0.00%
50 Sewage Piping, Manhole and Rain Water System 71% 50% -21% 2.96% 2.09%
51 R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate 0% 0% 0% 0.00% 0.00%
56 Koi pond / Swimming Pool System Installation 33% 0% -33% 0.74% 0.00%
33.25% 20.04%
* : Delayed items