WEEKLY PROJECT PROGRESS REPORT

FROM : 09/05/2016 - 16/05/2016 FINANCIAL STATEM


PROJECT TITLE : Contract Sum
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT Piling
46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH
Variation Order
PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
PC Sum
Revised Contract Sum
SUMMARY PHYSICAL PROGRESS REPORT
Previous Current
Description
09/05/2016 16/05/2016
Schedule Progress 30.78% 33.25%
Actual Progress 19.66% 20.04%
Ahead / Delay ( % ) -11.13% -13.21%
Ahead / Delay ( Day ) -45 -54
Date of Completion ( Contract ) 12/18/2016 12/18/2016
Estimated Date of Completion 2/1/2017 2/10/2017
MANPOWER AT SITE SITE ACTIVITY
18 17 17 17
Progress
17 Activities Scheduled Actual %
16 % Last Week This Week
15
14 1ST FLOOR
13
13 15 Staircase 100% 0% 0%
12
11
ROOF
10 19 Roof Beam 100% 100% 100%
9 8 8 8 20 RC Flat Roof Slab 100% 100% 100%
8
7 21 Roof Column 100% 100% 100%
6 22 Upper Roof Beam 100% 50% 100%
5
4
23 Roof Truss 100% 0% 0%
3 Building Work
2 25 Brickwall 100% 55% 55%
1
0 26 Metal Beam 100% 0% 0%
5/9/2016
5/10/2016
5/11/2016
5/12/2016
5/13/2016
5/14/2016
5/16/2016 27 Timber Door Frame & Alumn. Frame 33% 0% 0%

M & E Services
WEATHER REPORT 29 Electrical Wiring Work 48% 40% 40%
30 Photovoltaic System 50% 0% 0%
31 Security Alarm & CCTV System 14% 0% 0%
32 Smarthome System 22% 0% 0%
33 Air Cond & Mech. Ventilation 29% 0% 0%
34 Central Vacuum System 0% 0% 0%
Heavy Rain; 35 Lift System Installation 17% 0% 0%
35.71% Clear; 35.71%
FINISHING WORK
49 Plumbing/Sanitary Fittings 68% 5% 5%
50 Sewerage piping, manhole and Rain Water S 71% 50% 50%
Slight Rain; 7.14%
56 Koi pond / Swimming Pool System Installation 33% 0% 0%

Cloudy; 21.43%
Slight Rain; 7.14%

Cloudy; 21.43%

NOTE :
- 1st floor brickworks started at Guest Room, Guest Bath, Bedroom 3, Bath 3, wet kitchen, pantry, Dry Kitchen, Dining Room
- All concreting works for structure are completed. The final concreting works done on the 11/05/2016
- External fencing work has started.

PREPARED BY : VERIFIED BY :

ABDUL BASIT BIN ABD NASIR


CIAL STATEMENT
RM3,578,347.29

nt
2016
%
%
1%

2016
017

Remarks

No progress

removing sides fwk


removing sides fwk
removing sides fwk
removing sides fwk
No progress

1st floor on progress


No progress
No progress

Ducting & conduit


No progress
No progress
No progress
No progress
No progress
No progress

No new progress
No new progress
No progress
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016
PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS
LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH,
DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG

Front Elevation

Side Elevation

Side Elevation

Side Elevation

External Fencing: Cantilever


beams construction
WEEKLY PROJECT PROGRESS REPORT
FROM : 09/05/2016 - 16/05/2016
PROJECT TITLE :
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS
LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH,
DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG

1st Flr : Rumpus Room 1st Flr : Dry Kitchen Area

1st Flr : External Garden View


1st Flr : Guest Room

2nd Flr : Pool Side View


2nd Flr : Study Room

Roof Level : Roof Beam & Upper Roof


2nd Flr : Bedroom 2 View Beam
Weather Date
Descriptio
n 5/9/2016 5/9/2016 5/10/2016 5/10/2016 5/11/2016 5/11/2016 5/12/2016
Clear 1 1 1
Cloudy 1 1
Slight Rain 1
Heavy Rain 1

5/9/2016 5/10/2016 5/11/2016 5/12/2016 5/13/2016 5/14/2016 5/15/2016


Date
Total
5/12/2016 5/13/2016 5/13/2016 5/14/2016 5/14/2016 5/16/2016 5/16/2016
1 1 5
1 3
1
1 1 1 1 5

Heavy Rain;
35.71% Clear; 35.71%

Slight Rain; 7.14%

Cloudy; 21.43%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT
46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH
PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG
Manpower 5/9/2016 5/10/2016 5/11/2016 5/12/2016 5/13/2016 5/14/2016 5/16/2016

Project Coordinator
Clerk of Work 1 1 1 1 1 1 1
Site Engineer
Safety Supervisor
Supervisor 1 1 1 0 0 0 0
Surveyor
Operator
Piler
Carpenter 6 6 6 5 5 5 5
Concretor
Barbender 1 1 1
General Worker 3 3 3 2 2 2 2
Door & Window Frame Inst.
Brick Layer 5 5 5 5 0 0 0
Roofer
Roof covering
Pre-Caster
Ceiling Work Inst.
Aluminium Inst.
Electrician
Plumber
Plasterer
Skim coating
G.I.Work Inst.
M.S.Work Inst.
Floor Screeder
Tiler
Drain Layer
Painter
Fume Cupboard Installer
Gas installer
Sprinkler System Installer
Airconditioning Workers
Emergency Shower Installer

Total Manpower 17 17 17 13 8 8 8
3/30/2016 4/13/2016 4/18/2016
Scheduled Progress 17.16% 18.14%
Actual Progress 15.45% 16.39%

Project Performance From January 2012


50.00%

45.00%

40.00%

35.00%

30.00%
% Progress

25.00%
Scheduled Progress
20.00%
17.16% 18.14%
Actual Progress
15.00% 16.39%
15.45%
10.00%

5.00%

0.00%
3/30/2016 4/6/2016 4/13/2016
PROPOSED WORK PROGRAMME (Revisio
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016

COMMENCEMENT DATE : 16/01/2015 CO

May-15 Jun-15 Jul-15 Aug-15


Description 1 8 18 25 1 8 15 22 29 6 13 20 27 3
Preliminaries
Site Mobilization
Site Clearing
Site Survey
Site Office/Store
Signboard & Hoading
Piling & Earthwork
Setting Out
Piling Work
Site Mobilization / Building Material Order

Earthwork

Ground Floor
Footing/Stump

Ground Beam
* Delayed due to Changes Work
Alteration to Existing Ground Beam, Lift Pit
and underground sewerage pipe
Anti Termite

Ground Floor Slab

Ground Floor Column / Lift Shaft Structure / RC wall

Sub-basement Compartment for Genset and Bal. tank

Koi Pond, Balancing Tank & Pump Room

1 st Floor
1sr Floor Beam

1st Floor Slab

1st Floor Column / Lift Shaft Structure

Staircase

Second Floor
Second Floor Beam / Swimming Pool Structure

Second Floor Slab

Second Floor Column / Lift Shaft Structure

Roof
Roof Beam

RC Flat Roof Slab

Roof Column
Upper Roof Beam

Roof Truss

Roof Covering / Sky Light Cover

Building Work
Brickwall

Metal I-beam

Timber Door Frame & Alumn. Frame

Plastering

M&E Services
Electrical Wiring Work

Photovoltaic System

Security Alarm & CCTV System

Smarthome System

Air Cond & Mech. Ventilation

Central Vacuum System

Lift System Installation

Finishing Work
Install Alum. Door, Window Panel and Fix Glass

Internal Wall and Swimming Pool Finishes/Tiles/Stone/Mosaic

Internal Floor Finishes

Internal ceiling Finishes/Roof EaveTimber Ceiling

Internal Skim coat, External and Internal Painting Work

Metal Grille & Screen

Metal Handrail / Glass Handrail Railing

Metal Spiral Staircase

Timber Door Leaf

Timber Skirting and Architrave

External Wall Timber Cladding

Timber Varnishing Work and R.C Feature Coating

Timber Flooring and Staircase Finishes

Plumbing/Sanitary Fittings Installation

Sewage Piping, Manhole and Rain Water System

R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate
External Wall Finishes

External Floor Finishes and Koi Pond Finishes

Timber Decking Koi Pond and Pump Room

Lighting and Electrical Work Installation

Koi pond / Swimming Pool System Installation

Built-in Furniture and ID Works

Turfing / Lanscape Work

Touch-up and Cleaning

Testing, Commissioning and Hand Over

Note: Otherwise indicated, this revised program is based on the amended Architectural Drawing
Interior Design Drawings
dated 2 Nov 15. Any amendment to the above drawings or additional items in future not sho
consideration in this program.
OGRAMME (Revision # 5) - 4th May 2016
G DI ATAS LOT 46016 ( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETAL

/2015 COMPLETION DATE : 15/04/2016

Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16


10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25

16.67% 33.33%
CHANGES ON DESIGN (FROM RC TO STEEL STRUCTURE)
chitectural Drawings dated 23 Sept 15, Engineer Drawings dated 16 Oct 15 and

ms in future not shows on the drawings are not taking


ULOH, DAERAH PETALING, NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG

REVISED COMMENCEMENT DATE: 18/05/15 REVISED COMPLETION DATE: 10/12/16

Feb-16 Mar-16 Apr-16 May-16


1 8 15 22 29 7 14 21 28 4 11 18 25 2 9

50.0% 66.67% 83.33% 100.00%

20.00% 40.0% 60.0% 80.0% 100.0%

33.33% 66.7% 100.0%

50.00% 100.0%

50.00% 100.0%

50.00% 100.0%

50.00% 100.0%
50.00% 100.0%

25.00% 50.0% 75.0% 100.0%

11.11% 22.2%

11.11% 22.2% 33.3% 44.4% 55.6% 66.7% 77.8% 88.9% ###

20.00% 40.0% 60.0% 80.0%

16.67%

Change of skirting design and construction method


G YEW TONG

May-16 Schedule ActualAhead/(Behind)Overall week Week Lapsed Over All %


Schedule Actual
(Overall) W/Done
16 23 30

100% 100% 0% 2 2 0.49% 0.49% 0.49%

100% 100% 0% 3 3 0.74% 0.74% 0.74%

100% 100% 0% 3 3 0.74% 0.74% 0.74%

100% 100% 0% 4 9 0.99% 0.99% 0.99%

100% 100% 0% 3 2 0.74% 0.74% 0.74%

100% 100% 0% 1 1 0.25% 0.25% 0.25%

100% 100% 0% 2 3 0.49% 0.49% 0.49%

100% 100% 0% 3 3 0.74% 0.74% 0.74%

100% 100% 0% 5 5 1.23% 1.23% 1.23%

100% 100% 0% 3 3 0.74% 0.74% 0.74%

100% 100% 0% 4 4 0.99% 0.99% 0.99%

100% 100% 0% 2 3 0.49% 0.49% 0.49%

100% 100% 0% 3 2 0.74% 0.74% 0.74%

0% 0% 0% 6 0 1.48% 0.00% 0.00%

100% 100% 0% 5 6 1.23% 1.23% 1.23%

100% 100% 0% 3 4 0.74% 0.74% 0.74%

100% 100% 0% 2 2 0.49% 0.49% 0.49%

100% 90% -10% 2 4 0.49% 0.49% 0.44%

100% 90% -10% 2 2 0.49% 0.49% 0.44%

100% 50% -50% 2 1 0.49% 0.49% 0.25%


100% 50% -50% 2 1 0.49% 0.49% 0.25%

25% 0% -25% 4 0 0.99% 0.25% 0.00%

33.3% 44.4% 55.6% 0% 0% 0% 9 0 2.22% 0.00% 0.00%

70% 30% -40% 9 7 2.22% 1.55% 0.67%

### 0% 0% 0% 5 0 1.23% 0.00% 0.00%

33.3% 50.0% 66.7% 0% 0% 0% 6 0 1.48% 0.00% 0.00%

0% 0% 0% 10 0 2.46% 0.00% 0.00%

38% 38% 0% 27 11 6.65% 2.53% 2.53%

0% 0% 0% 6 0 1.48% 0.00% 0.00%

0% 0% 0% 14 0 3.45% 0.00% 0.00%

0% 0% 0% 9 0 2.22% 0.00% 0.00%

0% 0% 0% 7 0 1.72% 0.00% 0.00%

0% 0% 0% 4 0 0.99% 0.00% 0.00%

0% 0% 0% 6 0 1.48% 0.00% 0.00%

0% 0% 0% 8 0 1.97% 0.00% 0.00%

0% 0% 0% 11 0 2.71% 0.00% 0.00%

0% 0% 0% 10 0 2.46% 0.00% 0.00%

0% 0% 0% 11 0 2.71% 0.00% 0.00%

0% 0% 0% 17 0 4.19% 0.00% 0.00%

0% 0% 0% 8 0 1.97% 0.00% 0.00%

0% 0% 0% 16 0 3.94% 0.00% 0.00%

0% 0% 0% 5 0 1.23% 0.00% 0.00%

0% 0% 0% 4 0 0.99% 0.00% 0.00%

0% 0% 0% 3 0 0.74% 0.00% 0.00%

0% 0% 0% 6 0 1.48% 0.00% 0.00%

0% 0% 0% 11 0 2.71% 0.00% 0.00%

0% 0% 0% 9 0 2.22% 0.00% 0.00%

45% 5% -40% 22 1 5.42% 2.44% 0.27%

60% 50% -10% 17 7 4.19% 2.51% 2.09%

0% 0% 0% 11 0 2.71% 0.00% 0.00%


0% 0% 0% 10 0 2.46% 0.00% 0.00%

0% 0% 0% 6 0 1.48% 0.00% 0.00%

0% 0% 0% 5 0 1.23% 0.00% 0.00%

0% 0% 0% 5 0 1.23% 0.00% 0.00%

0% 0% 0% 9 0 2.22% 0.00% 0.00%

0% 0% 0% 15 0 3.69% 0.00% 0.00%

0% 0% 0% 4 0 0.99% 0.00% 0.00%

0% 0% 0% 3 0 0.74% 0.00% 0.00%

0% 0% 0% 2 0 0.49% 0.00% 0.00%

406 89 100.00% 23.07% 18.76%


Proposed

Actual

Ahead / B
No. Description May-15 Jun-15 Jul-15
1 8 18 25 1 8 15 22 29 6 13
Preliminaries
A Site Mobilization
B Site Clearing
C Site Survey
D Site Office/Store
E Signboard & Hoading
Piling & Earthwork
F Setting Out
G Piling Work
1 Site Mobilization / Building Material Order

2 Earthwork

Ground Floor
3 Footing/Stump

4 Ground Beam
* Delayed due to Changes Work
5 Alteration to Existing Ground Beam, Lift Pit
and underground sewerage pipe
6 Anti Termite

7 Ground Floor Slab

8 Ground Floor Column / Lift Shaft Structure / RC wall

10 Sub-basement Compartment for Genset and Bal. tank

11 Koi Pond, Balancing Tank & Pump Room

1 st Floor
12 1sr Floor Beam

13 1st Floor Slab

14 1st Floor Column / Lift Shaft Structure

15 Staircase

Second Floor
16 Second Floor Beam / Swimming Pool Structure

17 Second Floor Slab

18 Second Floor Column / Lift Shaft Structure

Roof
19 Roof Beam

20 RC Flat Roof Slab

21 Roof Column

22 Upper Roof Beam


No. Description May-15 Jun-15 Jul-15
1 8 18 25 1 8 15 22 29 6 13

23 Roof Truss

24 Roof Covering / Sky Light Cover

Building Work
25 Brickwall

26 Metal I-beam

27 Timber Door Frame & Alumn. Frame

28 Plastering

M&E Services
29 Electrical Wiring Work 3.7% 7.4%

30 Photovoltaic System

31 Security Alarm & CCTV System

32 Smarthome System

33 Air Cond & Mech. Ventilation

34 Central Vacuum System

35 Lift System Installation

Finishing Work
36 Install Alum. Door, Window Panel and Fix Glass

37 Internal Wall and Swimming Pool


Finishes/Tiles/Stone/Mosaic

38 Internal Floor Finishes

39 Internal ceiling Finishes/Roof EaveTimber Ceiling

40 Internal Skim coat, External and Internal Painting Work

41 Metal Grille & Screen

42 Metal Handrail / Glass Handrail Railing

43 Metal Spiral Staircase

44 Timber Door Leaf

45 Timber Skirting and Architrave

46 External Wall Timber Cladding

47 Timber Varnishing Work and R.C Feature Coating

48 Timber Flooring and Staircase Finishes

49 Plumbing/Sanitary Fittings Installation


No. Description May-15 Jun-15 Jul-15
1 8 18 25 1 8 15 22 29 6 13
50 Sewage Piping, Manhole and Rain Water System

51 R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate

52 External Wall Finishes

53 External Floor Finishes and Koi Pond Finishes

54 Timber Decking Koi Pond and Pump Room

55 Lighting and Electrical Work Installation

56 Koi pond / Swimming Pool System Installation

57 Built-in Furniture and ID Works

58 Turfing / Lanscape Work

59 Touch-up and Cleaning

60 Testing, Commissioning and Hand Over


Jul-15 Aug-15 Sep-15 Oct-15 Nov-1
20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2
Jul-15 Aug-15 Sep-15 Oct-15 Nov-1
20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2

4.5%
Jul-15 Aug-15 Sep-15 Oct-15 Nov-1
20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERT

Nov-15 Dec-15 Jan-16 Feb-16


9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22

16.7% 33.3%
CHANGES ON DESIGN (FROM RC TO STEEL STRUCTURE)

20.0% 40.0% 60.0%


Nov-15 Dec-15 Jan-16 Feb-16
9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22

11.1% 14.8% 18.5% 22.2%

Change of skirting design and constru

9.1% 13.6% 18.2% 22.7% 27.3%


Nov-15 Dec-15 Jan-16 Feb-16
9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22
5.9% 11.8% 17.6% 23.5% 29.4% 35.3% 41.2% 47.1% 52.9%

11.1% 22.2%
ESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016 (PT 32614), NO. 40, JALAN PJU 3/12 MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING NEGERI SE

WORK PROGRAM AS PER REVISED ON 18 APRIL 2016

eb-16 Mar-16 Apr-16 May-16 Jun-16


29 7 14 21 28 4 11 18 25 2 9 16 23 30 6

50.0% 66.7% 83.3% 100.0%

80.0% 100.0%

33.3% 66.7% 100.0%

50.0% 100.0%

50.0% 100.0%

50.0% 100.0%

50.0% 100.0%

50.0% 100.0%
eb-16 Mar-16 Apr-16 May-16 Jun-16
29 7 14 21 28 4 11 18 25 2 9 16 23 30 6

25.0% 50.0% 75.0% 100.0%

11.1% 22.2% 33.3% 44.4% 55.6%

11.1% 22.2% 33.3% 44.4% 55.6% 66.7% 77.8% 88.9% 100.0%

20.0% 40.0% 60.0% 80.0% 100.0%

16.7% 33.3% 50.0%

10.0% 20.0% 30.0%

25.9% 29.6% 33.3% 37.0% 40.7% 44.4% 48.1%

16.7% 33.3% 50.0%

7.1% 14.3% 21.4% 28.6%

11.1% 22.2% 33.3% 44.4% 55.6%

14.3% 28.6% 42.9% 57.1%

25.0% 50.0%

16.7% 33.3% 50.0%

6.3%

ange of skirting design and construction method

31.8% 36.4% 40.9% 45.5% 50.0% 54.5% 59.1% 63.6% 68.2% 72.7% 77.3% 81.8%
eb-16 Mar-16 Apr-16 May-16 Jun-16
29 7 14 21 28 4 11 18 25 2 9 16 23 30 6
58.8% 64.7% 70.6%

33.3%
BULOH, DAERAH PETALING NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG

Jun-16 Jul-16 Aug-16 Sep-16


13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26
Jun-16 Jul-16 Aug-16 Sep-16
13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26

66.7% 77.8% 88.9% 100.0%

66.7% 83.3% 100.0% Timber Door Frame confirmed on 14/4/16, 3 weeks required for manufacture, Alumn no confirmation yet

40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0% Plastering cannot proceed due to concealed smarthome/alarm wiring not confirmed

51.9% 55.6% 59.3% 63.0% 66.7% 70.4% 74.1% 77.8% 81.5%

No confirmation 35.7% 42.9% 50.0%

No confirmation

No confirmation

12.5% 25.0% 37.5% 50.0% 62.5% 75.0% 87.5% 100.0%

9.1% 18.2% 27.3% 36.4% 45.5% 54.5% 63.6% 72.7% 81.8% 90.9% 100.0%

10.0% 20.0% 30.0% 40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0%

9.1% 18.2% 27.3% 36.4% 45.5% 54.5% 63.6% 72.7% 81.8%

5.9% 11.8% 17.6% 23.5% 29.4% 35.3% 41.2% 47.1% 52.9% 58.8%

12.5% 25.0% 37.5% 50.0% 62.5% 75.0% 87.5%

12.5% 18.8% 25.0% 31.3% 37.5% 43.8% 50.0% 56.3% 62.5% 68.8%

20.0% 40.0% 60.0% 80.0% 100.0%

25.0% 50.0%

16.7% 33.3% 50.0% 66.7% 83.3% 100.0%

9.1% 18.2% 27.3% 36.4% 45.5% 54.5% 63.6% 72.7%

11.1% 22.2% 33.3% 44.4% 55.6%


Jun-16 Jul-16 Aug-16 Sep-16
13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26
76.5% 82.4% 88.2%

9.1% 18.2% 27.3% 36.4% 45.5% 54.5% 63.6%

10.0% 20.0% 30.0%

44.4% 55.6% 66.7%

6.7% 13.3% 20.0% 26.7% 33.3% 40.0%


Oct-16 Nov-16 Dec-16 Jan-17
3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16
Oct-16 Nov-16 Dec-16 Jan-17
3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16

wiring not confirmed

85.2% 88.9% 92.6% 96.3% 100.0%

66.7% 83.3% 100.0%

57.1% 64.3% 71.4% 78.6% 85.7% 92.9% 100.0%

66.7% 77.8% 88.9% 100.0%

71.4% 85.7% 100.0%

75.00% 100.0%

66.67% 83.3% 100.0%

90.9% 100.0%

64.7% 70.6% 76.5% 82.4% 88.2% 94.1% 100.0%

100.0%

75.0% 81.3% 87.5% 93.8% 100.0%

75.0% 100.0%

81.8% 90.9% 100.0%

66.7% 77.8% 88.9% 100.0%

86.4% 90.9% 95.5% 100.0%


Oct-16 Nov-16 Dec-16 Jan-17
3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16
94.1% 100.0%

72.7% 81.8% 90.9% 100.0%

40.0% 50.0% 60.0% 70.0% 80.0% 90.0% 100.0%

16.7% 33.3% 50.0% 66.7% 83.3% 100.0%

20.0% 40.0% 60.0% 80.0% 100.0%

20.0% 40.0% 60.0% 80.0% 100.0%

77.8% 88.9% 100.0%

46.7% 53.3% 60.0% 66.7% 73.3% 80.0% 86.7% 93.3% 100.0%

25.0% 50.0% 75.0% 100.0%

33.3% 66.7% 100.0%

50.0% 100.0%
A
c
t
u
a
l
Jan-17
Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All % Propose Schedule
23 30 W
/
D
0% 0% 0% 0 0.00% o
0.00% ###
n
0% 0% 0% 0 0.00% 0.00% ###
e
0% 0% 0% 0 0.00% 0.00% ###
0% 0% 0% 0 0.00% 0.00% ###
0% 0% 0% 0 0.00% 0.00% ###

0% 0% 0% 0 0.00% 0.00% ###


0% 0% 0% 0 0.00% 0.00% ###
100% 100% 0% 2 2 0.66% 0.66% ### 100%

100% 100% 0% 3 3 0.99% 0.99% ### 100%

100% 100% 0% 3 3 0.99% 0.99% ### 100%

100% 95% -5% 9 5 2.98% 1.66% ### 100%

100%

0% 0% 0% 1 0 0.33% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

100%

0% 0% 0% 8 0 2.65% 0.00% ### 100%

0% 0% 0% 4 0 1.32% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 1 0 0.33% 0.00% ### 100%

0% 0% 0% 5 0 1.66% 0.00% ### 100%

0% 0% 0% 3 0 0.99% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 2 0 0.66% 0.00% ### 100%


A
c
t
u
a
l
Jan-17
Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All % Propose Schedule
23 30 W
/
D
0% 0% 0% 4 0 1.32% o 75%
0.00% ###
n
e
0% 0% 0% 6 0 1.99% 0.00% ### 11%

0% 0% 0% 2 0 0.66% 0.00% ### 100%

0% 0% 0% 5 0 1.66% 0.00% ### 60%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 29 0 9.60% 0.00% ### 48%

0% 0% 0% 6 0 1.99% 0.00% ### 50%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 4 0 1.32% 0.00% ### 50%

0% 0% 0% 4 0 1.32% 0.00% ### 0%

0% 0% 0% 5 0 1.66% 0.00% ### 0%

0% 0% 0% 12 0 3.97% 0.00% ### 0%

0% 0% 0% 7 0 2.32% 0.00% ### 0%

0% 0% 0% 11 0 3.64% 0.00% ### 0%

0% 0% 0% 5 0 1.66% 0.00% ### 0%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 10 0 3.31% 0.00% ### 0%

0% 0% 0% 24 0 7.95% 0.00% ### 0%

0% 0% 0% 5 0 1.66% 0.00% ### 0%

0%

0%

0%

0% 0% 0% 3 0 0.99% 0.00% ### 0%

0% 0% 0% 15 0 4.97% 0.00% ### 64%


A
c
t
u
a
l
Jan-17
Schedule Actual Ahead/(Behind) Overall week Week Lapsed Over All % Propose Schedule
23 30 W
/
D 71%
o
n
e 0%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0%

0% 0% 0% 6 0 1.99% 0.00% ### 0%

0% 0% 0% 11 0 3.64% 0.00% ### 33%

0% 0% 0% 3 0 0.99% 0.00% ### 0%

0% 0% 0% 11 0 3.64% 0.00% ### 0%

0% 0% 0% 5 0 1.66% 0.00% ### 0%

0% 0% 0% 4 0 1.32% 0.00% ### 0%

302 13 100.00% 4.30% ###


Ahead/Be Schedule Actual
Actual
hind (Overall) W/Done

100% 0% 0.49% 0.49%

100% 0% 0.74% 0.74%

100% 0% 0.74% 0.74%

100% 0% 0.99% 0.99%

100% 0% 0.74% 0.74%

100% 0% 0.25% 0.25%

100% 0% 0.49% 0.49%

100% 0% 0.74% 0.74%

100% 0% 1.23% 1.23%

100% 0% 0.74% 0.74%

100% 0% 0.99% 0.99%

100% 0% 0.49% 0.49%

100% 0% 0.74% 0.74%

0% -100% 1.48% 0.00%

100% 0% 1.23% 1.23%

100% 0% 0.74% 0.74%

100% 0% 0.49% 0.49%

100% 0% 0.49% 0.49%

100% 0% 0.49% 0.49%

100% 0% 0.49% 0.49%

50% -50% 0.49% 0.25%


Ahead/Be Schedule Actual
Actual
hind (Overall) W/Done

0% -75% 0.74% 0.00%

0% -11% 0.25% 0.00%

55% -45% 2.22% 1.22%

0% -60% 0.74% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

38% -10% 3.20% 2.53%

0% -50% 0.74% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% -50% 0.49% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

5% -59% 3.45% 0.27%


Ahead/Be Schedule Actual
Actual
hind (Overall) W/Done

50% -21% 2.96% 2.09%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% -33% 0.74% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

0% 0% 0.00% 0.00%

30.78% 19.66%
CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016
( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING,
NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG

May-16 Schedule Ahead/ Overall Actual


Actual
No. Description 16 (Behind) Scheduled W/Done

Preliminaries
A Site Mobilization
B Site Clearing
C Site Survey
D Site Office/Store
E Signboard & Hoading
Piling & Earthwork
F Setting Out
G Piling Work
1 Site Mobilization / Building Material Order 100% 100% 0% 0.49% 0.49%

2 Earthwork 100% 100% 0% 0.74% 0.74%

Ground Floor
3 Footing/Stump 100% 100% 0% 0.74% 0.74%

4 Ground Beam 100% 100% 0% 0.99% 0.99%


* Delayed due to Changes Work
5 Alteration to Existing Ground Beam, Lift Pit 100% 100% 0% 0.74% 0.74%
and underground sewerage pipe
6 Anti Termite 100% 100% 0% 0.25% 0.25%

7 Ground Floor Slab 100% 100% 0% 0.49% 0.49%

8 Ground Floor Column / Lift Shaft Structure / RC wall 100% 100% 0% 0.74% 0.74%

10 Sub-basement Compartment for Genset and Bal. tank 100% 100% 0% 1.23% 1.23%

11 Koi Pond, Balancing Tank & Pump Room 100% 100% 0% 0.74% 0.74%

1 st Floor
12 1sr Floor Beam 100% 100% 0% 0.99% 0.99%

13 1st Floor Slab 100% 100% 0% 0.49% 0.49%

14 1st Floor Column / Lift Shaft Structure 100% 100% 0% 0.74% 0.74%

15 Staircase 100% 0% -100% 1.48% 0.00%

Second Floor
16 Second Floor Beam / Swimming Pool Structure 100% 100% 0% 1.23% 1.23%

17 Second Floor Slab 100% 100% 0% 0.74% 0.74%

18 Second Floor Column / Lift Shaft Structure 100% 100% 0% 0.49% 0.49%

Roof
19 Roof Beam 100% 100% 0% 0.49% 0.49%

20 RC Flat Roof Slab 100% 100% 0% 0.49% 0.49%

21 Roof Column 100% 100% 0% 0.49% 0.49%

22 Upper Roof Beam 100% 100% 0% 0.49% 0.49%


CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016
( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING,
NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG

May-16 Schedule Ahead/ Overall Actual


Actual
No. Description 16 (Behind) Scheduled W/Done

23 Roof Truss 100% 0% -100% 0.99% 0.00%

24 Roof Covering / Sky Light Cover 33% 33% 0% -33% 0.74% 0.00%

Building Work
25 Brickwall 100% 55% -45% 2.22% 1.22%

26 Metal I-beam 100% 100% 0% -100% 1.23% 0.00%

27 Timber Door Frame & Alumn. Frame 33% 33% 0% -33% 0.49% 0.00%

28 Plastering 0% 0% 0% 0.00% 0.00%

M&E Services
29 Electrical Wiring Work 48% 40% -8% 3.20% 2.66%

30 Photovoltaic System 0% 0% 0% 0.00% 0.00%

31 Security Alarm & CCTV System 14% 14% 0% -14% 0.49% 0.00%

32 Smarthome System 22% 22% 0% -22% 0.49% 0.00%

33 Air Cond & Mech. Ventilation 29% 29% 0% -29% 0.49% 0.00%

34 Central Vacuum System 0% 0% 0% 0.00% 0.00%

35 Lift System Installation 17% 17% 0% -17% 0.25% 0.00%

Finishing Work
36 Install Alum. Door, Window Panel and Fix Glass 0% 0% 0% 0.00% 0.00%

37 Internal Wall and Swimming Pool Finishes/Tiles/Stone/Mosaic 0% 0% 0% 0.00% 0.00%

38 Internal Floor Finishes 0% 0% 0% 0.00% 0.00%

39 Internal ceiling Finishes/Roof EaveTimber Ceiling 0% 0% 0% 0.00% 0.00%

40 Internal Skim coat, External and Internal Painting Work 0% 0% 0% 0.00% 0.00%

41 Metal Grille & Screen 0% 0% 0% 0.00% 0.00%

42 Metal Handrail / Glass Handrail Railing 0% 0% 0% 0.00% 0.00%

43 Metal Spiral Staircase 0% 0% 0% 0.00% 0.00%

44 Timber Door Leaf 0% 0% 0% 0.00% 0.00%

45 Timber Skirting and Architrave 0% 0% 0% 0.00% 0.00%

46 External Wall Timber Cladding 0% 0% 0% 0.00% 0.00%

47 Timber Varnishing Work and R.C Feature Coating 0% 0% 0% 0.00% 0.00%

48 Timber Flooring and Staircase Finishes 0% 0% 0% 0.00% 0.00%


CADANGAN MEMBINA RUMAH SESEBUAH 3 TINGKAT BERSERTA KOLAM RENANG DI ATAS LOT 46016
( PT 32614 ), NO. 15, JALAN PJU 3/12, MUKIM PEKAN BARU SUNGAI BULOH, DAERAH PETALING,
NEGERI SELANGOR DARUL EHSAN UNTUK TETUAN DATO TING YEW TONG

May-16 Schedule Ahead/ Overall Actual


Actual
No. Description 16 (Behind) Scheduled W/Done

49 Plumbing/Sanitary Fittings Installation 68% 68% 5% -63% 3.69% 0.27%

50 Sewage Piping, Manhole and Rain Water System 71% 50% -21% 2.96% 2.09%

51 R.C Ramp, Dry Yard, Fencing Wall, Main and Side Gate 0% 0% 0% 0.00% 0.00%

52 External Wall Finishes 0% 0% 0% 0.00% 0.00%

53 External Floor Finishes and Koi Pond Finishes 0% 0% 0% 0.00% 0.00%

54 Timber Decking Koi Pond and Pump Room 0% 0% 0% 0.00% 0.00%

55 Lighting and Electrical Work Installation 0% 0% 0% 0.00% 0.00%

56 Koi pond / Swimming Pool System Installation 33% 0% -33% 0.74% 0.00%

57 Built-in Furniture and ID Works 0% 0% 0% 0.00% 0.00%

58 Turfing / Lanscape Work 0% 0% 0% 0.00% 0.00%

59 Touch-up and Cleaning 0% 0% 0% 0.00% 0.00%

60 Testing, Commissioning and Hand Over 0% 0% 0% 0.00% 0.00%

33.25% 20.04%
* : Delayed items