DIRECT COST:
1. COMPLETION OF ROOF FRAMING AND FASCIA RUNNER
A. Materials
44 lgths 1.2mm x 2" x 4" C-purlins @ 535.00 23,540.00
24 lgths 4.5mm x 1" x 1" Angle steel bar for fascia runnner @ 610.00 14,640.00
2 pcs Grinder disc 4" Ø @ 50.00 100.00
4 pcs Cut off blade 12" Ø @ 140.00 560.00
₱ 38,840.00
C. Labor
1 Const. Foreman 8 days @ 400.00 3,200.00
2 Welders 10 days @ 350.00 7,000.00
2 Helpers/Laborers 10 days @ 300.00 6,000.00
₱ 16,200.00
C. Labor
1 Const. Foreman 6 days @ 400.00 2,400.00
4 Carpenters 10 days @ 350.00 14,000.00
₱ 16,400.00
3. PAINTING
A. Materials
1 gal Epoxy primer @ 672.00 672.00
2 gals QDE enamel grey @ 500.00 1,000.00
1 gal Paint thinner @ 240.00 240.00
4 gals Latex flat wall @ 390.00 1,560.00
2 gals Semi gloss white @ 549.00 1,098.00
2 pcs 2" Steel brush @ 300.00 600.00
2 gal Rust converter @ 380.00 760.00
₱ 5,930.00
B. Labor
3 Painter 10 days @ 350.00 ₱ 10,500.00
B. Labor
2 Electrician 3 days @ 350.00 ₱ 2,100.00
INDIRECT COST:
1. PHYSICAL CONTINGENCIES 5,860.00
2. ADMINISTRATIVE EXPENSES 3,000.00
3. SUPERVISION AND MONITORING 7,000.00
TOTAL INDIRECT COST: ₱ 15,860.00
DIRECT COST:
1. BUILD-UP STEEL COLUMN AND ROOF FRAMING
A. Materials to be procured
44 lgths 1.2mm x 2" x 4" C-purlins @ 535.00 23,540.00
24 lgths 4.5mm x 1" x 1" Angle steel bar for fascia runnner @ 610.00 14,640.00
38,180.00
B. Materials purchased
60 kgs Welding rod 6013 1/8 @ 79.00 4,740.00
5 lgths 10mmØ PSB sag rod @ 190.00 950.00
2 pcs Cutting disc for cut-off machine @ 45.00 90.00
2 pcs Grinder disc @ 50.00 100.00
5,880.00
D. Labor
1 Const. Foreman 15 days @ 400.00 6,000.00
2 Welders 20 days @ 350.00 14,000.00
2 Helpers/Laborers 20 days @ 300.00 12,000.00
₱ 32,000.00
B. Materials purchased
3000 pcs 2 1/2" Tekscrew for metal @ 1.29 3,870.00
500 pcs 1 1/2" Tekscrew for metal @ 1.20 600.00
1 gal Roof/gutter sealant @ 378.00 378.00
4 pcs Cutting disc @ 45.00 180.00
2 pcs Grinding disc @ 50.00 100.00
2 pcs Dust mask @ 59.00 118.00
2 pcs Tekscrew adaptor @ 59.00 118.00
₱ 5,364.00
C. Labor
1 Const. Foreman 6 days @ 400.00 2,400.00
4 Carpenters 10 days @ 350.00 14,000.00
₱ 16,400.00
3. PAINTING
A. Materials to be procured
6 gals Red oxide primer @ 298.00 1,788.00
6 gals QDE enamel grey @ 500.00 3,000.00
3 gals Paint thinner @ 239.99 719.97
8 pcs 2" paint brush @ 14.60 116.80
5 gal Latex flat wall @ 800.00 4,000.00
3 gal Semi gloss white @ 549.00 1,647.00
4 pcs 4" Paint brush @ 48.00 192.00
1L Body filler @ 570.00 570.00
4 pcs Sand paper #180 @ 8.00 32.00
2 pcs 2" Steel brush @ 300.00 600.00
2 gal Rust converter @ 380.00 760.00
₱ 13,425.77
B. Labor
3 Painter 6 days @ 350.00 ₱ 6,300.00
4. ELECTRICAL
A. Materials to be procured
2 pcs Outlet 3 gang set @ 320.00 640.00
4 pcs LED tube @ 345.00 1,380.00
2 pcs Double snap switch flush type @ 280.00 560.00
2 rolls Electrical tape (big) @ 35.00 70.00
4 pcs 2" x 4" Utility box @ 15.00 60.00
100 lm 1/2" Ø Poly flexible pipe @ 6.50 650.00
100 lm #12 TW AWG @ 24.00 2,400.00
₱ 5,760.00
B. Labor
2 Electrician 3 days @ 350.00 ₱ 2,100.00
B. Materials to be procured
1 kg 4" CWN @ 60.00 60.00
0.5 kg 2 1/2" CWN @ 29.00 14.50
100 g Nylon string @ 0.50 50.00
₱124.50
C. Labor
1 Const. Foreman 4 days @ 380.00 1,520.00
2 Carpenters 2 days @ 320.00 1,280.00
5 Laborers 4 days @ 250.00 5,000.00
₱7,800.00
B. Materials purchased
1 cu m Gravel (ordinary) @ 800.00 800.00
4 cu m Fine gravel @ 880.00 3,520.00
3 cu m Sand @ 710.00 2,130.00
6 lgths 10mmØ x 6.0m PSB (available)
₱6,450.00
D. Labor
1 Const. Foreman 4 days @ 380.00 1,520.00
2 Masons 3 days @ 320.00 1,920.00
2 Steelmen 2 days @ 320.00 1,280.00
4 Laborers 4 days @ 250.00 4,000.00
₱8,720.00
B. Materials purchased
2 pcs Cutting disc for cut-off machine @ 45.00 90.00
2 pcs Grinder disc @ 50.00 100.00
₱190.00
D. Labor
1 Const. Foreman 15 days @ 380.00 5,700.00
2 Welders 25 days @ 320.00 16,000.00
2 Helpers/Laborers 25 days @ 250.00 12,500.00
₱ 34,200.00
C. Labor
1 Const. Foreman 6 days @ 380.00 2,280.00
4 Carpenters 10 days @ 320.00 12,800.00
₱ 15,080.00
6. PAINTING
A. Materials Purchased
6 gals Red oxide primer @ 298.00 1,788.00
6 gals QDE enamel grey @ 500.00 3,000.00
3 gals Paint thinner @ 239.99 719.97
8 pcs 2" paint brush @ 14.60 116.80
1 gal Flatawall latex @ 390.00 390.00
1g Semi gloss white @ 549.00 549.00
4 pcs 4" Paint brush @ 48.00 192.00
1L Body filler @ 570.00 570.00
4 pcs Sand paper #180 @ 8.00 32.00
₱ 7,357.77
B. Labor
3 Painter 4 days @ 320.00 ₱ 3,840.00
INDIRECT COST:
1. PHYSICAL CONTINGENCIES 25,312.73
2. ADMINISTRATIVE EXPENSES 20,000.00
3. SUPERVISION AND MONITORING 16,000.00
₱ 61,312.73