Program of Works: Upgrading of School Building Distribution Lines Beff 2018
Program of Works: Upgrading of School Building Distribution Lines Beff 2018
KAGAWARAN NG EDUKASYON
Rehiyon XI
SANGAY NG LUNGSOD NG DAVAO
Lungsod ng Davao
PROGRAM OF WORKS
UPGRADING OF SCHOOL BUILDING DISTRIBUTION LINES BEFF 2018
I. DIRECT COST
GENERAL REQUIREMENTS 7.11% lot 1.00 239,099.62
PANEL BOARDS CABLES & GROUNDINGS 54.22% lot 1.00 1,822,060.00
PVC CONDUITS, BOXES AND FITTINGS 6.88% lot 1.00 231,144.50
AREA LIGHTINGS 7.11% lot 1.00 238,973.05
CIVIL AND RECTIFICATION WORKS 4.02% lot 1.00 135,200.54
2,666,477.71
II Indirect Cost 22% of (I-General Requirement)
Overhead Expenses (8%) 5.78% 194,190.25
Contingencies (3%) 2.17% 72,821.34
Miscellaneous (1%) 0.72% 24,273.78
Contractor's Profit (10%) 7.22% 242,737.81
Sub-Total 534,023.18
III. TAX 5% of (I+II) 5% 160,025.04
IV. TOTAL CONSTRUCTION COST (I + II + III) 100.00% 3,360,525.93
FELIX P. MACARANDAN, PEE, SCE ENGR. ARMANDO S. MORALES TERESITA F. DEL VALLE, PH.D
DepEd Project Engineer III EPS Chief SGOD
Page 1 of 4
Republika ng Pilipinas
KAGAWARAN NG EDUKASYON
Rehiyon XI
SANGAY NG LUNGSOD NG DABAW
Lungsod ng Dabaw
Distribution Transformer
2 of 4
ITEM UNIT COST TOTAL COST
DESCRIPTION UNIT QTY GRAND TOTAL
NO. MATERIAL LABOR MATERIAL LABOR
Yellow mtrs 100.00 1,800.00 810.00 180,000.00 81,000.00 261,000.00
Sub-total 1,822,060.00
FELIX P. MACARANDAN, PEE, SCE ENGR. ARMANDO S. MORALES TERESITA F. DEL VALLE, PH.D
DepEd Project Engineer III EPS Chief SGOD
3 of 4
ITEM UNIT COST TOTAL COST
DESCRIPTION UNIT QTY GRAND TOTAL
NO. MATERIAL LABOR MATERIAL LABOR
ENGR. NIGEL MARVIN S. BORJA ENGR. ANNABELLE R. PANGAN
Division Engineer III Chief, EFD-AS
4 of 4