CW duct / ECW system / Condenser water box charging

1. Record clearance from OS/TMD/BMD RP/BMD MILLS/C&I/EMD GEN

2. Ensure closing of Condenser I/L & O/L v/vs.

3. Close MOT cooler I/L & O/L v/vs.

4. Close Hydrogen cooler I/L & O/L v/vs.

5. Open ECW strainers I/L v/v , drain & vent.

6. Open any ECW p/p suction and discharge v/v.

7. Open ECW line vent at turbine side 8.5 mtr .

8. Open APH GB oil cooler vent v/v.

9. Open ID/FD cooler line drain/vent.

10. Open BFP cooler line drain.

11. Slowly open CW I/C v/v.

12. Close ECW strainer drain and vent after proper venting.

13. Close BFP cooler line drain.

14. Start ECW p/p.

15. After proper venting close APH GB cooler vent , ID/FD cooler line drain/vent.

16. Charge condenser water box by crack opening CW-1 and CW-2. Condenser water box drain/vent
should be in open condition and maintain normal hotwell level.

17. Close drain after flushing of water box.

18. Close vent v/vs after proper venting.

19. Open CW-1 and CW-2 fully.

20. Partially open CW-3 and CW-4.