Professional Documents
Culture Documents
CEP - WKT Manual - PDF
CEP - WKT Manual - PDF
CEP - WKT Manual - PDF
WKT
Installation/Operating
Manual
Legal information/Copyright
All rights reserved. Contents provided herein must neither be distributed, copied, reproduced, edited or
processed for any other purpose, nor otherwise transmitted, published or made available to a third party
without KSB´s express written consent.
WKT
Contents
1 General ...........................................................................................................................................................4
1.1 Principles ........................................................................................................................................................ 4
1.2 Target group ................................................................................................................................................... 4
1.3 Symbols .......................................................................................................................................................... 4
2 Safety ............................................................................................................................................................ 5
2.1 Key to safety symbols/markings .................................................................................................................... 5
2.2 General .......................................................................................................................................................... 5
2.3 Intended use .................................................................................................................................................. 5
2.4 Personnel qualification and training ............................................................................................................... 6
2.5 Consequences and risks caused by non-compliance with these operating instructions ............................... 7
2.6 Safety awareness .......................................................................................................................................... 7
2.7 Safety information for the operator/user ........................................................................................................ 7
2.8 Safety information for maintenance, inspection and installation work ........................................................... 7
2.9 Unauthorized modes of operation .................................................................................................................. 8
3 Transport/Temporary Storage/Disposal ..................................................................................................... 9
3.1 Checking the condition upon delivery ............................................................................................................ 9
3.1.1 Markings ......................................................................................................................................................... 9
3.1.2 Lifting Accessories (e.g. ropes, lifting gear) ................................................................................................. 10
3.1.3 Transport Symbols ....................................................................................................................................... 10
3.2.1 Condition on Delivery ................................................................................................................................... 11
3.2.2 Transport Options ......................................................................................................................................... 11
3.2.3 Transporting pump in horizontal / vertical position ....................................................................................... 12
3.3 Storage/Preservation ................................................................................................................................... 14
3.3.1 Period of storage longer than 12 months ..................................................................................................... 15
3.4 Return to supplier ......................................................................................................................................... 15
3.5 Disposal ....................................................................................................................................................... 15
4 Description of the Pump (Set) .................................................................................................................. 16
4.1 General description ...................................................................................................................................... 16
4.2 Designation .................................................................................................................................................. 16
4.3 Name plate ................................................................................................................................................... 16
4.4 Design details .............................................................................................................................................. 16
4.5 Configuration and function ........................................................................................................................... 18
4.6 Scope of supply ........................................................................................................................................... 19
4.7 Dimensions and weights .............................................................................................................................. 19
WKT
5 Installation at Site ...................................................................................................................................... 20
5.1 Safety regulations ........................................................................................................................................ 20
5.2 Checks to be carried out prior to installation ................................................................................................ 21
5.3 Installing the base frame .............................................................................................................................. 22
5.4 Fitting Can .................................................................................................................................................... 24
5.5 Lowering the pump ...................................................................................................................................... 25
5.6 Mounting the Drive ....................................................................................................................................... 27
5.7 Mounting the Drive End coupling Hub ......................................................................................................... 27
5.8 Connection to power supply ......................................................................................................................... 29
5.9 Checking the direction of rotation ................................................................................................................ 29
5.10 Connecting the piping & strainer .................................................................................................................. 30
5.11 Fitting the monitoring equipment (if applicable and not fitted at the factory) ............................................... 36
5.12 Fitting the auxiliary connections ................................................................................................................... 38
5.13 Fitting the protective equipment ................................................................................................................... 38
5.14 Installation checklist ..................................................................................................................................... 39
5.15 Preservation for standstill ............................................................................................................................. 39
6 Commissioning/Start-up/Shutdown ......................................................................................................... 40
6.1 Work to be carried out prior to commissioning ............................................................................................. 40
6.2 Commissioning/start-up ............................................................................................................................... 44
6.3 Operating limits ............................................................................................................................................ 48
6.4 Measures to be taken for shutdown ............................................................................................................. 49
6.5 Returning to service ..................................................................................................................................... 52
7 Supervision /Servicing/Maintenance ....................................................................................................... 53
7.1 Monitoring schedule ..................................................................................................................................... 53
7.2 Servicing schedule ....................................................................................................................................... 54
7.3 Gland packing variant .................................................................................................................................. 55
7.4 Dismantling the pump set ............................................................................................................................ 61
7.5 Dismantling pump set with large installation depth ...................................................................................... 69
7.6 Reassembling the pump set ........................................................................................................................ 71
7.7 Examination of individual Components ........................................................................................................ 79
7.8 Spare parts stock ......................................................................................................................................... 84
8 Trouble-shooting ........................................................................................................................................ 86
9 Related Documents ................................................................................................................................... 89
9.1 Tightening torques ....................................................................................................................................... 89
9.2 General assembly drawings and lists of components .................................................................................. 94
9.3 Table of clearances ...................................................................................................................................... 98
9.4 Bearing Lubrication .................................................................................................................................... 102
WKT
Chapter 1 General
1 General
1.1 Principles
This operating manual is supplied as an integral part of the type series and variants
indicated on the front cover. The manual describes the proper and safe use of this
equipment in all phases of operation.
The name plate indicates the type series and size, the main operating data, the order
number and the order item number. The order number and order item number uniquely
identify the pump (set) and serve as identification for all further business processes.
In the event of damage, contact your nearest KSB service centre immediately to
maintain the right to claim under warranty.
1.3 Symbols
Table 1 : Symbols used in this manual
Symbol Description
Conditions which need to be fulfilled before proceeding with
the step-by step instructions
Safety instructions
Result of an action
Cross-references
Symbol Description
1. Step-by-step instructions
Note
Recommendations and important information on how to
handle the product
WKT
4
Chapter 2 Safety
2 Safety
All the information contained in this chapter refers to hazardous situations.
DANGER
DANGER This signal word indicates a high-risk hazard which, if not
avoided, will result in death or serious injury.
WARNING
WARNING This signal word indicates a medium-risk hazard which, if not
avoided, could result in death or serious injury.
CAUTION
CAUTION This signal word indicates a hazard which, if not avoided,
could result in damage to the machine and its functions.
General hazard
In conjunction with one of the signal words this symbol
indicates a hazard which will or could result in death or
serious injury.
Electrical hazard
In conjunction with one of the signal words this symbol
indicates a hazard involving electrical voltage and identifies
information about protection against electrical voltage.
Machine damage
In conjunction with the signal word CAUTION this symbol
indicates a hazard for the machine and its functions.
2.2 General
This manual contains general installation, operating and maintenance instructions that
must be observed to ensure safe pump operation and prevent personal injury and damage
to property.
The safety information in all chapters of this manual must be complied with.
This manual must be read and completely understood by the specialist personnel/
operators responsible prior to installation and commissioning.
The contents of this manual must be available to the specialist personnel at the site at all
times.
Information attached directly to the pump must always be complied with and be kept in a
perfectly legible condition at all times. This applies to, for example:
• Arrow indicating the direction of rotation
• Markings for connections
• Name plate
The operator is responsible for ensuring compliance with all local regulations not taken
into account in this manual.2.3
WKT
5
Chapter 2 Safety
Training on the pump (set) must always be supervised by technical specialist personnel.
WKT
6
Chapter 2 Safety
WKT
7
Chapter 2 Safety
§ As soon as the work is completed, re-install and/or re-activate any safety-relevant and
protective devices. Before returning the product to service, observe all instructions on
commissioning.
WKT
8
Chapter 3 Transport / Temporary Storage / Disposal
DANGER
The pump or individual components could slip out of the suspension arrangement
Danger to life from falling parts!
Ø Always transport the pump or components in the specified position.
Ø Refer to the weights indicated for the individual components.
Ø Use suitable permitted lifting accessories, e.g. self-tightening lifting tongs.
Ø Never attach the suspension arrangement to the free shaft end of the pump.
Ø Observe the applicable local accident prevention regulations.
Ø Use appropriate personal protective equipment.
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select lifting accessories which are suitable for the component weight.
Ø Always use the attachment points provided for the lifting accessories.
Ø Comply with the applicable health and safety regulations.
DANGER
Installation on installation surfaces which are unsecured and cannot support the load
Personal injury and damage to property!
Ø Use a concrete make ACC cement ”SHRINKKOMP “ / FORSORC
“CONBEXTRA - GP2” Or Equivalent Portland cement
Ø Make sure the concrete of the installation surface has set firmly and the surface is
truly horizontal and even.
Ø Observe the weights indicated.
3.1.1 Markings
Fastening points
The fastening points of the individual transport crates are
indicated by the chain symbol.
Centre of gravity
The centre of gravity of packaged pump and pump set
components is marked on the crate by the centre of gravity
symbol.
WKT
9
Chapter 3 Transport / Temporary Storage / Disposal
P For selection and attachment of the lifting accessories, only follow the instructions given
by the person responsible for this.
P If the lifting accessories come into contact with sharp edges, edge protectors must be
fitted at the contact points.
NOTE
Damage to the pump components, coat of paint or protective coating!
§ Do not place any chains or steel ropes around the pump components with nothing in
between.
§ Do not use chains, if possible.
DANGER
Improper selection or handling of lifting accessories may result in the
pump or pump set components falling down.
Danger to life from falling parts!
§ Use sufficiently dimensioned and suitable lifting accessories.
§ Do not use any damaged or untested lifting accessories.
§ Never attach the ropes to the free shaft end, the column pipes or the bearing
housings.
§ Secure against overturning.
§ Make sure the lifting accessories are used correctly in accordance with the
manufacturer's instructions.
§ Observe the weights indicated, for example, in the tables of weights and the
installation plan in chapter 9
1 2 3 4 5 6 7
8 9
Transport symbols
1 This way up 6 Centre of gravity
2 Fragile 7 Fasten here
3 Keep dry 8 Do not use forklift truck here
4 Store away from heat 9 Do not destroy barrier
5 No hand hooks
WKT
10
Chapter 3 Transport / Temporary Storage / Disposal
The individual components are supplied in transport boxes. Refer to the packing list
for the exact contents and weight of each box.
NOTE
The pump set is supplied by the manufacturer/supplier in packaging which largely.
Prevents sagging or other damage during transport and/or storage.
WARNING
Improper unpacking of transport boxes
Risk of injury from falling parts and/or transport boxes tipping over
Ø Observe the applicable local accident prevention regulations.
Ø Secure parts against tipping over backwards (e.g. box lids).
Ø Wear suitable protective clothing such as a safety helmet and safety shoes with toe
caps as well as safety goggles and protective gloves.
WKT
11
Chapter 3 Transport / Temporary Storage / Disposal
NOTE
For transporting the drive or other accessories the respective manufacturer's product
literature must be observed.
< 120o
WKT
12
Chapter 3 Transport / Temporary Storage / Disposal
DANGER
Pump in vertical position tipping over
Danger to life from pump tipping over!
Ø Never place the pump in vertical position.
Transporting the Can If the can is included in KSB's scope of supply, observe the following transport options.
WKT
13
Chapter 3 Transport / Temporary Storage / Disposal
CAUTION
Damage during storage by humidity, dirt, or vermin
Corrosion / contamination of the pump (set)!
Ø For outdoor storage cover the packed or unpacked pump (set) and accessories with
waterproof material.
CAUTION
Wet, contaminated or damaged openings and connections
Leakage or damage to the pump set!
Ø Only remove caps/covers from the openings of the pump set at the time of
installation.
Store the pump (set) in a dry, protected room where the atmospheric humidity is as
constant as possible.
If properly stored indoors, the pump set is protected for a maximum of 12 months.
New pumps/pump sets are supplied by our factory duly prepared for storage.
For storing a pump (set) which has already been operated, observe the instructions.
WKT
14
Chapter 3 Transport / Temporary Storage / Disposal
WARNING
If stored for more than five years, the sealing function could be impaired
Risk of injury, e.g. cuts caused by fluid jets, scalds by hot, pressurized fluid escaping!
Ø After a storage period of more than five years, dismantle the pump before it is
installed and replace the sealing elements, e.g. O-rings.
Ø Check sealing elements, e.g. O-rings, for any damage before fitting them.
Preservation If the requisite preservation measures have not been performed by KSB (special
preservation), they must be discussed with and approved by KSB prior to putting the
pump into storage.
3.5 Disposal
WARNING
Fluids posing a health hazard and/or hot fluids
Hazard to persons and the environment!
Ø Collect and properly dispose of flushing liquid and any residues of the fluid handled.
Ø Wear safety clothing and a protective mask, if required.
Ø Observe all legal regulations on the disposal of fluids posing a health hazard.
1. Dismantle the pump (set). Collect greases and other lubricants during dismantling.
2. Separate and sort the pump materials, e.g. by:
- Metal / Plastics
- Electronic waste
- Greases and other lubricants
3. Dispose of materials in accordance with local regulations or in another controlled
Manner.
WKT
15
Chapter 4 Description of the Pump (Set)
4.2 Designation
Example : WKT 80 / 6
Code Description
WKT Type series
80 Size
6 Number of stages
Capacity ltrs
IN 03083 D B74x37
WKT
16
Chapter 4 Description of the Pump (Set)
Installation
§ The can is installed in a pit below the mounting surface.
§ The pump is connected to the structure by means of the Base frame.
Bearings
§ Radial bearing
– Product-lubricated radial plain bearing in the pump
§ Thrust bearing
– Rolling element bearing, oil bath lubrication above the shaft seal
Shaft seal
Depending on pump size and design:
§ Single or double mechanical seal
§ Gland packing with lantern ring to prevent ingress of air
Flanges
§ Mating dimensions to ASME
WKT
17
Chapter 4 Description of the Pump (Set)
The hydraulic axial thrust is balanced by means of two casing wear rings and balancing
holes in the impellers. Above the distributor casing the fluid area is sealed off by a shaft
seal housing (441) or Gland packing (461) through which the shaft (213) passes. The
shaft passage is sealed towards the atmosphere with a dynamic seal. The shafts (211,
212, etc.) are supported by product-lubricated radial plain bearings and rolling element
bearings (320). The rolling element bearings (320) are located in a bearing housing (350),
which is mounted on the distributor casing
Sectional drawing
350 320
441 213
461
10-1
211 212
711
107
108
151
171
231 106
WKT
18
Chapter 4 Description of the Pump (Set)
WKT
19
Chapter 5 Installation at Site
5 Installation at Site
5.1 Safety regulations
The operator ensures that all maintenance, inspection and installation work is performed
by authorized, qualified specialist personnel who are thoroughly familiar with the manual.
For all work involving assembly, reassembly and installation, observe the following safety
information:
DANGER
Operation of the pump in combination with an impermissible component, especially can
or base frame
Danger to life!
Ø The pump must only be operated with matching components selected by KSB,
especially can and base frame.
DANGER
Work on the pump set carried out at great heights
Risk of personal injury from falling down!
Ø Provide suitable safety measures, e.g. scaffolding, barriers.
Ø Wear suitable protective clothing.
Ø Comply with all relevant safety regulations.
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select lifting accessories which are suitable for the component weight.
Ø Always use the attachment points provided for the lifting accessories.
Ø Comply with the applicable health and safety regulations.
DANGER
Vertically positioned pump (set) could tip over
Danger to life from pump or components tipping over!
Ø Attach the components to be installed to the hoisting tackle and keep them secured
until the screwed connections have been fastened.
Ø Always install the pump (set) in the sequence described.
Ø Always place components in their centre of gravity position on a suitable surface to
prevent them from tipping over.
WKT
20
Chapter 5 Installation at Site
NOTE
The vibration values and noise emissions indicated by KSB are based on proper
installation of the pump (set) in accordance with this chapter. Improper isolation of the
pump (set) from the building/plant or an inappropriate piping layout may increase noise
emission and/or the vibration level.
Place of installation
WARNING
Installation on installation surfaces which are unsecured and cannot support the load
Personal injury and damage to property!
Ø Make sure the concrete of the installation surface has set firmly and the surface is
truly horizontal and even.
Ø Observe the weights indicated.
WKT
21
Chapter 5 Installation at Site
Preparation:
The following preparation is followed in case the Base frame and Can. (equal to the
number of foundation bolts) are in scope of KSB. Otherwise the user is requested to follow
the preparation as under:
Ø The base frame is provided with the pads, having surface finish 25 micron & 50 micron
face parallality which are welded at the top of base frame, machined in one setting.
12 Tapped Holes
M20 x 30 Deep
Flat Pad
Reinforcement
Plate
Plate
Channel (ISMC)
Flat Pad
Fig. 1
WKT
22
Chapter 5 Installation at Site
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select hoisting tackles/lifting accessories which are suitable for the component
weight.
Ø Always use the attachment points provided for suspending components from the
hoisting tackle.
Ø Comply with the applicable health and safety regulations.
WARNING
People falling into the unsecured pump pet.
Risk of personal injury!
Ø Take suitable precautions during the entire installation/dismantling process to
protect people from falling into the open discharge tube.
Ø Fence off the work area appropriately.
Master Level
Straight Edge EL+###
~###
T.O. Floor
EL+###
~ ###
Fig. 2
Straight Edge
Master Level
Fig. 2a
EL+###
~###
T.O. Floor
EL+###
~ ###
Fig. 3
WKT
23
Chapter 5 Installation at Site
P Suitable hoisting tackle incl. lifting accessories are available and ready for use
1. Attach lifting accessories to base frame
2. Carefully lower base frame on the concrete block. (Ref. Fig2)
3. Check the levels by master level on machine pads. Level should be 0.04mm per meter.
4. Place the straight edge on the base frame on X & Y direction. (Ref. Fig 2 & 2a)
5. Grout the entire base frame up to top of the base frame. Using conventional grouting
mix i.e. Portland cement, sand and aggregate in proportion 1:2:2 and gravel size not
exceed 20mm (Ref. Fig 3)
6. Complete grouting without major interruptions.
7. Use a vibrator to make sure that no cavities remain.
8. Allow curing time of min 72 hrs depending upon the grout used.
CAUTION
Improper handling of the vibrator
Possible misalignment!
Ø Make sure the vibrator does not touch the base frame and the fastening/aligning
parts.
NOTE
When grouting the recess in the base frame, make sure that no concrete enters the
pump sump.
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select hoisting tackles/lifting accessories which are suitable for the component
weight.
Ø Always use the attachment points provided for suspending components from the
hoisting tackle.
Ø Comply with the applicable health and safety regulations.
WARNING
People falling into the pump sump
Risk of personal injury!
Ø Take suitable precautions during the entire installation/dismantling process to
protect people from falling into the pump sump.
Ø Fence off the work area appropriately.
WKT
24
Chapter 5 Installation at Site
Fig. 4
NOTE
NOTE
The numbers in parentheses, e.g. (412.17), refer to pump components shown in the
general assembly drawings. (_ Chapter 9)
WKT
25
Chapter 5 Installation at Site
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select hoisting tackles/lifting accessories which are suitable for the component
weight.
Ø Always use the attachment points provided for suspending components from the
hoisting tackle.
Ø Comply with the applicable health and safety regulations.
WARNING
People falling into the unsecured Can
Risk of personal injury!
Ø Take suitable precautions during the entire installation/dismantling process to
protect people from falling into the Can
Ø Fence off the work area appropriately.
WKT
26
Chapter 5 Installation at Site
N2 N1
Fig. 5
5.6 Mounting the drive
The driver is automatically centered in the flange of the motor lantern after being placed
and bolted on the motor lantern.
Also see
§ Relevant documentation [_ Chapter 9]
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select hoisting tackles/lifting accessories which are suitable for the component
weight.
Ø Always use the attachment points provided for suspending components from the
hoisting tackle.
Ø Comply with the applicable health and safety regulations.
WARNING
Components heated up for installation
Risk of burns at hands!
Ø Wear protective gloves suitable for installation work.
Ø Let components cool down after installation.
NOTE
Observe the coupling manufacturer’s product literature. (_ Chapter 9)
Observe the motor manufacturer’s product literature. (_ Chapter 9)
WKT
27
Chapter 5 Installation at Site
7. Fit the flexible elements of the coupling and the spacer sleeve to the pump-end
coupling hub.
8. Place the drive including the fitted coupling hub on motor stool (341).
9. Temporarily fasten the drive with hexagon nuts (920) to allow alignment of the
connecting coupling.
NOTE
Observe the coupling manufacturer’s product literature. (_ Chapter 9)
Observe the motor manufacturer’s product literature. (_ Chapter 9)
The pump is connected to the driver by a flexible coupling. In most cases, a meta flex
coupling with spacer is used. The pump and drive shafts must be aligned very accurately,
because any misalignment, whether lateral or angular of the shafts can only be
compensated to a limited extent by the flexibility of the coupling at the prevailing rotational
speeds, and may therefore result in damage to the transmission elements and to the
pump. The alignment of the shafts is effected automatically by a centering fit on the motor
lantern. The coupling requires no special maintenance during operation.
WKT
28
Chapter 5 Installation at Site
DANGER
Work on the pump set by unqualified personnel
Danger of death from electric shock!
Ø Always have the electrical connections installed by a trained and qualified
electrician.
Ø Observe the motor manufacturer's operating instructions.
WARNING
Unintentional starting of pump set
Risk of injury by moving parts!
Ø Make sure that the pump set cannot be started up unintentionally.
Ø Always make sure the electrical connections are disconnected before carrying out
work on the pump set.
NOTE
It is recommended to fit a motor protection device.
1. Check the available mains voltage against the data on the motor name plate.
2. Select an appropriate start-up method
WARNING
Incorrect connection to the mains
Damage to the mains network, short circuit!
Ø Observe the technical specifications of the local energy supply companies.
CAUTION
Incorrect direction of rotation with non-reversible mechanical seal
Damage to the mechanical seal and leakage!
Ø Separate the pump from the motor to check the direction of rotation.
CAUTION
Drive and pump running in the wrong direction of rotation
Damage to the pump!
Ø Refer to the arrow indicating the direction of rotation on the pump.
Ø Check the direction of rotation. If required, check the electrical connection and
correct the direction of rotation.
WKT
29
Chapter 5 Installation at Site
The correct direction of rotation of the motor and pump is anti clockwise
(viewed from driver to pump).
1. Start the motor and stop it again immediately to determine the motor's direction of
rotation.
2. Check the direction of rotation.
The motor's direction of rotation must match the arrow indicating the direction of
rotation on the pump.
3. If the motor runs in the wrong direction of rotation, check the electrical connection of the
motor and the control system, if applicable.
NOTE
KSB's scope of supply as well as the arrangement of piping and valves are illustrated
in the general arrangement drawing and in the P+I diagram in chapter 9.
(_ Chapter 9)
DANGER
Impermissible loads acting on the pump nozzles
Danger to life from leakage of hot, toxic, corrosive or flammable fluids!
Ø Do not use the pump as an anchorage point for the piping.
Ø Anchor the pipelines in close proximity to the pump and connect them without
transmitting any stresses or strains.
Ø Observe the permissible forces and moments at the pump nozzles.
Ø Take appropriate measures to compensate thermal expansion of the piping.
CAUTION
Incorrect earthing during welding work at the piping
Destruction of rolling element bearings (pitting effect)!
Ø Never earth the electric welding equipment on the pump or base plate.
Ø Prevent current flowing through the rolling element bearings.
§ Remove the temporary holders and fit the pipes to the pump nozzles.
§ The pipes must be fully supported by the supports or spring hangers provided.
§ The spring hangers must have full adjustment and must not be at their lower limit.
P If short pipes are used in the plant, their nominal diameters should be at least equal to
the nominal diameters of the pump nozzles. For long pipelines, the most economical
nominal diameter has to be determined from case to case.
P Adapters to larger diameters should have a diffuser angle of approximately 8o in order
to avoid any pressure losses caused by the formation of air pockets. Prevent harsh
transitions.
WKT
30
Chapter 5 Installation at Site
P The suction lift line/suction head line has been laid with a rising/downward slope
towards the pump.
P It is recommended to install check valves and shut-off elements.
P The internal piping is supplied completely fitted. See general arrangement drawing.
(_ Chapter 9)
P Do not remove blind flanges or closure covers on pump nozzles and pipe
connections including any packaging with desiccants possibly attached to them until
immediately before the relevant pipes are connected. The responsibility for disposal of
the parts supplied lies with the consignee.
P Make and adapt any possibly required connecting pipes in accordance with the
general arrangement drawing. Offset at flange connections and pipe unions is not
permitted.
P Pipes supplied by KSB have been cleaned and closed. Nevertheless their interiors
must be checked for impurities which might have been caused afterwards and be
cleaned, if required.
P As a general rule, pipes made on site must be cleaned prior to final mounting.
1. Connect the pump nozzles with the piping.
CAUTION
Welding beads, scale and other impurities in the piping
Damage to the pump!
Ø Free the piping from any impurities.
NOTE
Do not clean the valves in the piping with a high-pressure steam-jet air ejector as the
valves' plastic parts cannot handle the steam temperature.
NOTE
The strainer in the inlet pipe is destined to stop welding beads, scale and other
impurities (that come off the piping with time) from entering the pump. It is not destined
to remove any inadmissible particles entrained in the fluid handled due to an excessive
solids content.
For installing the strainer refer to the manufacturer's product literature. (_ Chapter 9)
WKT
31
Chapter 5 Installation at Site
CAUTION
Improper handling Damage to the strainer
Ø Do not exert pressure on the strainer element and strainer meshes or damage them.
Ø Transport by hand is recommended. If this is not an option because of the weight,
observe the transport options described in this manual. (_ Chapter 3)
1. Prior to installation, perform a visual inspection of the inlet pipe between strainer and
pump. Clean it, if required.
2. Install the strainer in the inlet pipe as close to the pump nozzle as possible.
3. For differential pressure monitoring a drilled hole is provided upstream and
downstream of the strainer insert or at the strainer housing.
Installation example C C
conical strainer
A B
D
E Strainer insert
Installation example
Y-strainer
E
A C D C B
E Strainer insert
WKT
32
Chapter 5 Installation at Site
Also see
§ Relevant documentation [_ Chapter 9]
Isolating Valves
An isolating valve (gate valve) should be provided in the suction line, to cut the supply of
fluid to a pump if necessary. An isolating valve should also be incorporated in the
discharge line of every pump, as close as possible to the pump itself. This valve can be
used to adjust the operating point (rate of flow) apart from its function of isolating the
discharge line. Isolating valves in suction line should only be used to isolate the line. (in
the event of repairs etc.) They must always remain fully open when the pump is running. If
the pump operates under vacuum, the isolating valve should be provided with a sealing
liquid connection or with a closed water seal, to prevent any ingress of air into the stuffing
box of the valve stem. To facilitate venting the isolating valves should be fitted in the line
with their stems horizontal.
2
15
6
18
16
21
3
8
19
11
10
20
9
23
22
13
12
17
14
1
Fig. 9
WKT
33
Chapter 5 Installation at Site
24 25
Fig. 10
*) Not applicable for temperature above 130o C and valve pressure rating above PN 100
(Metal to metal sealing provided). Parts 8-13 (complete leak-off nozzle) can be replaced
individually.
WKT
34
Chapter 5 Installation at Site
2. Arrange the minimum flow system (if applicable) as shown on the P + I diagram.
(_ Chapter 9)
(For the protection of the pump when operating at low loads).
General :-
The power absorbed by the pump does not decrease proportionately with decreasing rate
of flow, but on the contrary still amounts to more than 50% of the power absorbed at the
design duty point at zero flow (pump shut off point). In order to carry off this energy which
is converted into heat inside the pump, it is necessary to maintain a minimum rate of flow
through the pump. In the case of pumps with discharge nozzles of nominal sizes between
40 and 150 this minimum rate of flow normally amounts to 0.15 Qopt, taking the heat
conditions and the pattern of the characteristic curve into account. In the case of pumps
with larger sizes of discharge nozzle, this minimum rate of flow amounts to 0.2 Qopt. Qopt
= Rate of flow at maximum efficiency of the pump.
N.B.
The pump should only be operated at rates of flow below the minimum rate of flow during
the switching on and switching off process. Excessive wear and damage to the pump
cannot be excluded under these circumstances.
Switching off
Close valve in discharge line. If a non return valve or check valve is incorporated in the
discharge line, the isolating valve may remain open, provided that adequate back
pressure is present. Switch off the driver and observe the pump running down to a
standstill smoothly and quietly. In the event of prolonged shutdowns, close the isolating
valve in the suction line. Close the auxiliary connections and only turn off the cooling liquid
supply (if provided) after the pump has cooled down. In case of frost and / or of a
prolonged shutdown, the pump and any cooling compartments provided on it should be
drained or safeguarded by other means against freezing.
WKT
35
Chapter 5 Installation at Site
CAUTION
Damage to the minimum flow valve caused by impermissible piping layout
Damage to the machinery!
Ø When installing the bypass line, observe the minimum flow diagram.
Ø Install an orifice immediately upstream of the capacitor to avoid vaporization in the
bypass line.
5.11 Fitting the monitoring equipment (if applicable and not fitted at the
factory)
If available and not already fitted, fit the monitoring equipment (measuring instruments) as
follows:
§ Thermometer (bearings):
Insert the seal element. Screw in the thermometer.
§ Pressure gauge :
Insert the sealing washer and fasten the pressure gauge with a lock nut.
§ Constant-level oiler:
Apply sealing tape or liquid seal and screw in the Constant-level oiler.
Any extensions, if required, are included in the scope of supply
WKT
36
Chapter 5 Installation at Site
4M.3
4M.1 4M.2
1M.1 1M.2
WKT
37
Chapter 5 Installation at Site
7A.2
7A.1
5B 7E.1 8B 7E.2
WARNING
Failure to re-install or re-activate protective devices
Risk of personal injury from moving parts.
Ø As soon as the work is completed, re-install and/or re-activate all safety-relevant
and protective devices.
CAUTION
Heat build-up in the bearing housing
Damage to the bearing!
Ø Never insulate the bearing housing and bearing cover.
WKT
38
Chapter 5 Installation at Site
NOTE
The final check required to release the pump set must be performed by KSB personnel.
WKT
39
Chapter 6 Commissioning / Start-up / Shutdown
WARNING
Fluids posing a health hazard and/or hot fluids
Hazardous to persons and the environment!
Ø Collect and properly dispose of flushing liquid and any liquid residues.
Ø Wear safety clothing and a protective mask, if required.
Ø Observe all legal regulations on the disposal of fluids posing a health hazard.
Internal preservation
If the pump has been filled with a glycol / water mixture for preservation, this mixture has
to be drained prior to any further work.
NOTE
Observe the manufacturer's instructions for application/removal of the preservative.
External preservation
Remove the preservation of the pump set components in accordance with the relevant
manufacturer's product literature. (_ Chapter 9)
1. Wash the preserved exterior parts with petrol, petroleum, diesel oil or general purpose
cleaner such as Shell Collina 2306.
6.1.2 Work to be carried out prior to restart after standstill > 12 months
WARNING
If stored for more than five years, the sealing function could be impaired Risk of injury,
e.g. cuts caused by fluid jets, eye injuries, burns, scalds, and respiratory system burns!
Ø After a storage period of more than five years, dismantle the pump before it is
installed and replace the sealing elements, e.g. O-rings.
Ø Check sealing elements, e.g. O-rings, for any damage before fitting them.
1.Check sealing elements, e.g. O-rings, for any damage before fitting them.
WKT
40
Chapter 6 Commissioning / Start-up / Shutdown
CAUTION
Insufficient lubricating oil in the reservoir of the constant-level oiler
Damage to the bearings!
Ø Regularly check the oil level.
Ø Always fill the oil reservoir completely.
Ø Keep the oil reservoir properly filled at all times.
CAUTION
Too much lubricating oil
Leakage of the fluid handled or oil
Ø Regularly check the oil level.
After a standstill of > 12 months, check the quality of the oil. If required, clean or replace
the oil.
Do not clean the oil until immediately before commissioning/start-up! If
Commissioning / start-up is delayed by more than one month, clean the oil again.
Filter the oil prior to topping up; filter mesh size 30 µm.
WKT
41
Chapter 6 Commissioning / Start-up / Shutdown
5B
Back to suction
(in vapour state)
NOTE
Faulty alignment through packed stuffing box.
The stuffing boxes shall not be packed before the final alignment of the pump set has
been effected and not until commissioning/start-up.
NOTE
The leakage of the gland packing is adjusted later. (See chapter 6)
WARNING
Failure to re-install or re-activate protective devices
Risk of personal injury from moving parts or escaping fluid!
Ø As soon as the work is completed, re-install and/or re-activate all safety-relevant
and protective devices.
WKT
42
Chapter 6 Commissioning / Start-up / Shutdown
1. Mount cover plates (68-2) to motor stool (341) by means of bolts (901) and discs (550).
In compliance with the accident prevention regulations the pump must not be operated
without a coupling guard. If the customer specifically requests not to include a coupling
guard in our delivery, then the operator must supply one. In this case, it is important to
make sure that the materials selected for coupling and coupling guard are non
sparking in the event of mechanical contact. KSB's scope of supply meets this
requirement.
CAUTION
Increased wear due to dry running
Damage to the pump (set)/bearings!
Ø Never operate the pump set without liquid fill.
Ø Never operate the pump set in incompletely primed or incompletely vented
condition.
Ø Never close the shut-off element in the suction line and/or supply line during pump
operation.
WKT
43
Chapter 6 Commissioning / Start-up / Shutdown
NOTE
Do not cool down cooling chambers and heat exchangers with aggressive raw water.
6. If fitted, check the filter in the barrier fluid system of the mechanical seal. Clean it, if
required.
7. Open the valves in the minimum flow system.
8. Check the oil levels and top up with oil, if required. (_ Chapter 6)
9. Fully open the valve in the inlet pipe.
10. Fill the inlet pipe, pump and discharge line with cold condensate.
11. Vent the pump at connection (5B) by loosening the screwed plug of the vent hole until
no more air escapes.
NOTE
The screwed plug (connection 5B) must not be opened if the system is under vacuum,
otherwise air would enter the system.
12. Vent all pressure gauge lines until there is no more air to escape.
13. Check whether inlet pressure is available.
NOTE
For design-inherent reasons, the existence of some spaces not filled with liquid after
the pump has been filled prior to commissioning cannot be excluded. However, once
the drive is started up the pumping effect will immediately fill these spaces with the
fluid handled.
6.2 Commissioning/start-up
WKT
44
Chapter 6 Commissioning / Start-up / Shutdown
§ The inlet tank, inlet pipe, pump and discharge line have been primed and vented.
§ The screwed plug (connection 5B) has been closed.
§ The valve of the inlet pipe has been opened completely.
§ The valve in the discharge line is closed. If the discharge line is equipped with a check
valve, the valve in the discharge line may remain open as long as there is some back
pressure.
§ The vacuum balance line (connection 25A) has been opened.
§ The barrier fluid line (connection 10A) has been opened.
§ The barrier fluid pressure must not exceed the value indicated in the general
arrangement drawing. (_ Chapter 9)
§ Open the shut-off valves in the bypass line, if any.
§ The cooling water system (connection 7E/7A) is in operation.
§ The cooling liquid pressure and temperature must not exceed the values indicated in
the general arrangement drawing. (_ Chapter 9)
§ All temperatures indicated are below the limit values.
§ All pipes, flanges, screw/bolt connections and pipe unions have been checked for
leakage.
§ Disengage locking discs (552) by swivelling them out of the groove in shaft sleeve
(523) and secure them with bolts (901).
§ Mechanical seal variant: Locking discs (552) must have been disengaged from the
groove in shaft sleeve (523) and secured by means of fastening bolts (901).
§ Gland packing variant: The gland packing must drip.
WARNING
Non-compliance with operating limits for pressure, temperature and speed
Hot fluid could escape!
Explosion hazard!
Ø Comply with the operating data indicated in the data sheet.
Ø Avoid prolonged operation against a closed shut-off element.
Ø Never operate the pump at temperatures exceeding those specified in the data
sheet or on the name plate unless the written consent of the manufacturer has been
obtained.
WARNING
Sound pressure level above 85 dB(A) when starting up the pump set
Injury to or impairment of hearing!
Ø Wear ear protection.
Ø Access to the pump set permitted to authorized specialist personnel only.
Ø Observe the applicable local occupational health and safety regulations.
WKT
45
Chapter 6 Commissioning / Start-up / Shutdown
WARNING
The pump casing takes on the same temperature as the fluid handled
Heat or freeze burns!
Ø Fit additional protective devices.
CAUTION
Abnormal noises, vibrations, temperatures or leakage
Damage to the pump!
Ø Switch off the pump (set) immediately.
Ø Eliminate the causes before returning the pump set to service.
P All checks described in the previous chapters have been completed with successful
outcomes.
1. Switch the drive on as described in the manufacturer's product literature.
(_ Chapter 9)
2. Check the temperature and smooth running of the bearings.
3. Check the pump pressures and differential pressures.
4. Pay attention to the power output and the current input of the drive motor.
5. Monitor the measuring and monitoring instruments.
6. If fitted, monitor the minimum flow valve (hydrodynamic noise).
7. Check the mechanical seal or Gland packing
8. After the mechanical seal has been checked for correct functioning, slowly open the
valve of the discharge line until it is completely open. When starting against an open
valve in the discharge pipe, consider the higher power input required.
9. Continuously monitor the operating behavior and smooth running of the pump set.
NOTE
Should warning signals or problems occur during starting or trial run, proceed as
described in the chapter on "Trouble-shooting". (_ Chapter 8)
DANGER
Contact with unprotected rotating parts
Risk of personal injury!
Ø Do not reach into rotating parts.
Ø Always have this work performed by trained specialist personnel.
Ø Take particular caution when performing this work.
After start-up and as part of maintenance work, check the mechanical seal for leakage.
The mechanical seal must only leak slightly during operation (< 15 drops/minute).
WKT
46
Chapter 6 Commissioning / Start-up / Shutdown
CAUTION
Damage to the shaft seal components!
Ø Excessive and non-uniform tightening of gland follower (452) causes premature
wear of packing material (461) and shaft protecting sleeve (524).
Ø Tighten the gland follower (452) uniformly and not too firmly.
NOTE
The gland packing must drip during operation! Leakage approximately 2-3 l/h.
Excessive leakage:
Repeat steps 1 and 2 until the minimum value has been reached.
No leakage:
Immediately switch off the pump set.
Loosen the gland follower and repeat start-up.
NOTE
On variable--speed pumps, the necessary gland packing leakage must be set for the
minimum fluid pressure; higher leakage rates are to be expected for other operating
conditions.
WKT
47
Chapter 6 Commissioning / Start-up / Shutdown
DANGER
Non-compliance with operating limits for pressure, temperature and speed
Explosion hazard!
Hot fluid could escape!
Ø Comply with the operating data indicated in the data sheet.
Ø Avoid prolonged operation against a closed shut-off element.
Ø Never operate the pump at temperatures exceeding those specified in the data
sheet or on the name plate unless the written consent of the manufacturer has been
obtained.
NOTE
These values apply to the pump only.
The frequency of starts is usually determined by the maximum temperature increase of
the motor. This largely depends on the power reserves of the motor in steady-state
operation and on the starting conditions (DOL, star-delta, moments of inertia, etc). See
the manufacturer's instructions. (_ Chapter 9)
CAUTION
Re-starting while motor is still running down
Damage to the pump (set)!
Ø Do not re-start the pump set before the pump rotor has come to a standstill.
Also see
§ Relevant documentation [_ chapter 9]
WKT
48
Chapter 6 Commissioning / Start-up / Shutdown
DANGER
The operating limits have been exceeded
Explosion hazard!
Ø Comply with the operating data indicated in the data sheet.
Ø Avoid operation against a closed shut-off element.
Ø Never operate the pump at ambient or fluid temperatures specified in the data sheet
or on the name plate.
Ø Never operate the pump set outside the limits specified.
DANGER
Insufficient preparation of work on the pump (set)
Risk of personal injury!
Ø Properly shut down the pump set.
Ø Close the shut-off elements in the suction and discharge line.
Ø Drain the pump and release the pump pressure.
Ø Close any auxiliary connections.
Ø Allow the pump set to cool down to ambient temperature.
WARNING
Hot fluid may escape
Scalding!
Ø Wear appropriate protective clothing (e.g. safety gloves, safety goggles) when
venting the pump set.
Ø Protect the electric components against escaping fluid.
WARNING
Fluids posing a health hazard and/or hot fluids
Risk of personal injury!
Ø Observe all relevant laws.
Ø When draining the fluid take appropriate measures to protect persons and the
environment.
WARNING
Hot surface
Risk of personal injury!
Ø Allow the pump set to cool down to ambient temperature.
WKT
49
Chapter 6 Commissioning / Start-up / Shutdown
NOTE
The cooling water system remains ON!
NOTE
Keep the shut-off element in the inlet pipe open.
The shut-off valve should only be closed if the pump is taken out of service for a
prolonged period of time and drained.
The screwed plug (connection 5B) must not be opened if the system is ready for
operation (under vacuum), otherwise air would enter the system.
If the period of standstill is longer than 2 weeks, the other pump set components must be
protected against water ingress and humidity as described in the manufacturer's
preservation instructions.
Further work
Carry out the following measures every 4 to 6 weeks:
1. Start up the pump set. (Chapter 6)
2. After approximately 10 minutes shut down the pump set. (Chapter 6)
3. Make sure that the rotor runs down smoothly to a standstill.
6.4.2 Shut down for maintenance of the pump set or prolonged standstill
DANGER
Insufficient preparation of work on the pump (set)
Risk of personal injury!
Ø Properly shut down the pump set.
Ø Close the shut-off elements in the suction and discharge line.
Ø Drain the pump and release the pump pressure.
Ø Close any auxiliary connections.
Ø Allow the pump set to cool down to ambient temperature.
WARNING
Hot fluid may escape
Ø Wear appropriate protective clothing (e.g. safety gloves, safety goggles) when
venting the pump set.
Ø Protect the electric components against escaping fluid.
WKT
50
Chapter 6 Commissioning / Start-up / Shutdown
WARNING
Fluids posing a health hazard and/or hot fluids
Risk of personal injury!
Ø Observe all relevant laws.
Ø When draining the fluid take appropriate measures to protect persons and the
environment.
Ø Decontaminate pumps which handle fluids posing a health hazard.
WARNING
Hot surface
Risk of personal injury!
Ø Allow the pump set to cool down to ambient temperature.
Final work
P The pump set has been shut down.
P The drive has been secured against start-up.
P A container for collecting the fluid is on hand.
1. Secure all shut-off elements against opening.
2. Place suitable containers under the drain holes.
3. Open all drains and/or drain pipes.
If the period of standstill is longer than 2 weeks, the other pump set components must be
protected against water ingress and humidity as described in the manufacturer's
preservation instructions.
WKT
51
Chapter 6 Commissioning / Start-up / Shutdown
NOTE
o
This mixture ensures protection against freezing up to approximately -42 C.
WKT
52
Chapter 7 Supervision / Servicing / Maintenance
WKT
53
Chapter 7 Supervision / Servicing / Maintenance
WKT
54
Chapter 7 Supervision / Servicing / Maintenance
914.31
184 X
452
524
10E
451
457
CAUTION
Strong heating up of the shaft seal.
Risk of burns!
Ø The gland packing temperature should not exceed the temperature of the medium
o
handled by more than approx. 20 to 60 C.
Ø In case of a sudden temperature rise and a sudden drop in the leakage rate,
immediately unscrew the gland follower.
If the suction pressure exceeds 15 bar, we recommend the rings be die-formed. We can
supply the die on request. Pressure approx. 50 bar.
WKT
55
Chapter 7 Supervision / Servicing / Maintenance
Then insert the remaining packing rings individually. Leave a sufficient clearance gap at
the entrance of the stuffing box for the positive guidance of the gland. The inserted
packing rings should only be lightly compressed by the gland and the nuts.
Then the nuts should be slackened and tightened again by hand. The even seating of the
gland should be checked with a feeler gauge, with the pump subjected to suction
pressure.
Now adjust the shaft protecting sleeve to the installation dimension ..X.. (see Fig. 13) with
clamping ring (184).
Pull the top packing rings out of stuffing box housing (451)with the aid of a packing ring
extractor, pull out seal cage ring (458), then remove the remaining packing rings and
examine shaft protection sleeve (524) for signs of damage.
N.B.
The stuffing box should drip slightly whilst the pump is running; the leakage rate should
amount to between 2 and 3 l/h. If your pump has sealing and cooling liquid connections in
use, they should be checked for unimpeded flow. When the stuffing box gland has been
repeatedly tightened in service until it abuts, it is time to renew the packing in the stuffing
box.
Packing Material
When selecting the packing material, remember to ascertain its compatibility with the
product pumped. Always use new packing material, preferably material which has been
stored for a certain period, to repack the stuffing box.
WKT
56
Chapter 7 Supervision / Servicing / Maintenance
NOTE
Do not re-pack the gland packing with fresh packing material until immediately before
commissioning.
Packing of the gland packing, see description in chapter 6
524
914.31
902.31
184 920.31
452 451
10E
457 458
902.32 461
920.32
412.31
400.31
914.31 524
184 902.31
920.31
452
451
10E
457 458
461
902.32
920.32 412.31
400.31 509.31
15A 400.31
562.31 542
WKT
57
Chapter 7 Supervision / Servicing / Maintenance
914.31
452 184
461 524
902.31
914.32
920.31
411.31 451
920.33 412.33
710.31 7A.1
10E 458
7E.1 66-2
457 412.32
400.31 412.31
66-1 7A.2
7E.2
540 902.32
920.32
400.31
WKT
58
Chapter 7 Supervision / Servicing / Maintenance
If the temperature of the product pumped exceeds 105oC, a heat barrier (66-1) is fitted
between the distributor casing and the stuffing box housing (451) The stuffing box housing
is provided with a cooling cover (66-2) with connections 7E/7A for the cooling liquid.
If an aggressive coolant (e.g. saline water) is used, the parts in contact with the coolant
must be made of suitably resistant material.
Table 7 : Cooling fluid consumption in l/s and m3/h for an inlet temperature of 20oC and
t of 15oC
Pump Size 40 50/65 80/100 125/150
Rate of cooling fluid flow
l/s 0.083 0.11 0.14 0.17
3
m /h 0.3 0.4 0.5 0.6
Sealing liquid is fed to the stuffing box via connection 10E and the lantern ring, at a
pressure of 1 to 3 bar, in order to prevent the ingress of air in the case of operation under
partial vacuum, or during the shutdown of the pump. A non-return valve is installed in the
sealing liquid line to prevent the pump discharge pressure from being released via the
lantern ring during operation, thus starving the top packing rings of fluid and causing them
to run dry.
A solenoid valve can also be installed in the sealing liquid line, if the sealing liquid is
tapped from the main discharge line. This solenoid valve should be in the closed position
when the pump is running.
5B Venting
7A.1 Outlet, cooling liquid
7A.2 Outlet, cooling liquid
7E.1 Inlet, cooling liquid
7E.2 Inlet, cooling liquid
8B Leakage drain
10E Inlet, sealing liquid
15A Outlet, balancing liquid
15E Inlet, balancing liquid
WKT
59
Chapter 7 Supervision / Servicing / Maintenance
864
15E 940
851
863
500
These are fitted inside diffuser first stage (171.01), discharge casing (107), bearing spider
(383) and adaptor (145) (mechanical seal execution). These shall be replaced if clearance
is increased beyond the specified limit. (_ Chapter 9)
No special maintenance of these bearings is necessary, but the pump must not be allowed
to run dry. These shall be replaced if clearance is increased beyond the specified limit.
212
529.3
212 Intermediate shaft
545.3 383 Bearing spider
383 400.2 Gasket
529.3 Bearing sleeve
400.2
545.3 Bearing bush
711.1 711.1 Column Pipe
WKT
60
Chapter 7 Supervision / Servicing / Maintenance
DANGER
Insufficient preparation of work on the pump (set)
Risk of personal injury!
Ø Properly shut down the pump set.
Ø Close the shut-off elements in the suction and discharge line.
Ø Drain the pump and release the pump pressure.
Ø Close any auxiliary connections.
Ø Allow the pump set to cool down to ambient temperature.
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select hoisting tackles/lifting accessories which are suitable for the component
weight.
Ø Close the shut-off elements in the suction and discharge line.
Ø Always use the attachment points provided for suspending components from the
hoisting tackle.
Ø Comply with the applicable health and safety regulations.
WARNING
Unqualified personnel performing work on the pump (set)
Risk of personal injury!
Ø Always have repair and maintenance work performed by specially trained, qualified
personnel.
WARNING
Pump set started up inadvertently
Risk of injury by moving parts!
Ø Make sure that the pump set cannot be started up accidentally.
Ø Always make sure the electrical connections are disconnected before carrying out
work on the pump set.
WARNING
Hot surface
Risk of personal injury!
Ø Allow the pump set to cool down to ambient temperature.
WKT
61
Chapter 7 Supervision / Servicing / Maintenance
WARNING
Components with sharp edges
Risk of cutting or shearing injuries!
Ø Always use appropriate caution for installation and dismantling work.
Ø Wear work gloves.
WKT
62
Chapter 7 Supervision / Servicing / Maintenance
1 3 2
NOTE
Observe the coupling manufacturer's instructions! (_ Chapter 9)
3. Undo the screwed connection of the spacer sleeves at the connecting coupling to
disconnect the drive from the pump.
4. Store the connecting elements appropriately.
5. Undo, remove, mark and store the spacer of the connecting coupling - if possible - as
described in the manufacturer's product literature.
6. Remove hexagon nuts (920.16).
7. Servicing/Maintenance
8. Lift up the drive including the drive-end coupling hub and place it on the assembly
supports.
9. Remove the flexible elements and spacer sleeves - if any - from the coupling hubs,
mark them and store them properly.
WKT
63
Chapter 7 Supervision / Servicing / Maintenance
NOTE
To facilitate removing the coupling hub may be heated uniformly to a temperature of
80oC max.
NOTE
Antifriction bearing designation in accordance with DIN 628 bearing clearance group
C3.
WKT
64
Chapter 7 Supervision / Servicing / Maintenance
Slots for
Assembly/Dismantling
Lugs Key-way
Slots
Key-way
Slots
213
350
WKT
65
Chapter 7 Supervision / Servicing / Maintenance
NOTE
The locking discs and hexagon head bolts are included in the special tools of the
pump.
2. Engage the locking discs in the groove of the shaft sleeve and fasten them on the seal
cover using hexagon head bolts.
3. Remove any dirt accumulation that has formed on the shaft or shaft sleeve.
4. Undo and remove hexagon nuts (920.15). Undo grub screws at the shaft sleeve of the
mechanical seal.
5. Use screws to force off the seal cover along with the shaft sleeve and mechanical seal
(433) and pull them off the shaft completely.
6. Undo the hexagon head bolts and swivel the locking discs to disengage them from the
groove in the shaft sleeve.
7. Separate the seal cover with the stationary parts of the mechanical seal from the shaft
sleeve with the rotating parts of the mechanical seal.
8. Check the mechanical seal.
_ If the seal faces are clean and undamaged, the mechanical seal may be reinstalled.
NOTE
Dismantle the mechanical seal as descried in the manufacturer's product literature.
(Chapter _ 9)
WKT
66
Chapter 7 Supervision / Servicing / Maintenance
904.20
523.20 901.20
920.10 552.01
471.22
471.21
441.02
213
WKT
67
Chapter 7 Supervision / Servicing / Maintenance
DANGER
The pump or individual components could slip out of the suspension arrangement
Danger to life from falling parts!
Ø Always transport the pump or components in the specified position.
Ø Never attach the lifting tackle to the free shaft end of the pump.
Ø Refer to the weights indicated for the individual components.
Ø Observe the local accident prevention regulations.
Ø Use suitable, permitted lifting tackle.
DANGER
Lifting lugs of pump/motor/base frame overloaded
Danger to life from falling parts!
Ø Never transport the pump set components (pump/motor / base plate) in any way
other than those illustrated in the chapter on transport options.
Ø Refer to the weights of the individual components stated in the manufacturer's
product literature.
DANGER
Falling hazard at the open pump sump or can
Danger of death from falling!
Ø Observe the applicable local occupational safety and accident prevention
regulations.
Ø Protect installation personnel against falling by using safety harnesses and ropes.
Ø Provide protection at the opening of the can or pump sump.
WKT
68
Chapter 7 Supervision / Servicing / Maintenance
N.B. If the vertical can and the Column are coated with a special coating, take care not to
damage same.
WKT
69
Chapter 7 Supervision / Servicing / Maintenance
1. Unscrew fastening bolts (902.2) between distributor casing (10-1) and column pipe
main, force off pump body together with column pipe, and dismantle distributor casing.
Carefully underpin the drive shaft (213).
2. Dismantle the column pipe.
3. Slacken conical coupling (851) with the aid of an extractor device and remove it. (see
section). Remove drive shaft (213).
4. Unscrew nuts (920.1) of tie rods (905) at suction end, remove them and pull out the tie
rods.
5. Force off suction casing (106)
6. Undo hex. bolt (901.6) and remove it together with the washer (550.2)
7. Pull suction impeller (231) off pump shaft (211), and remove key. Under pin the stage
casing.
8. Force off and remove stage casing (108) including first stage diffuser (171.1) and
suction side bearing. Do not damage the sealing faces.
9. Pull the bearing sleeve (529.1) from the shaft and remove the split ring (501).
10. Pull the impeller (230) off the pump shaft (211) and remove key.
Support the stage casing.
11. Press off and remove the stage casing (108) and diffuser(171.2).
12. Press the stage sleeve (521) from the shaft.
13. Dismantle all the remaining stages in the same way as described in points 10 to 12
above. In the case of multistage pumps, mark the impellers and stage casings in
their correct sequence, to facilitate reassembly.
14. Pull discharge casing (107) off the shaft and store the shaft with due care.
WKT
70
Chapter 7 Supervision / Servicing / Maintenance
DANGER
The pump or individual components could slip out of the suspension arrangement
Danger to life from falling parts!
Ø Always transport the pump or components in the specified position.
Ø Never attach the lifting tackle to the free shaft end of the pump.
Ø Refer to the weights indicated for the individual components.
Ø Comply with the applicable health and safety regulations.
Ø Use suitable, approved lifting accessories e.g. self-tightening lifting tongs.
DANGER
Improper transport
Risk of personal injury from lifting heavy components!
Ø Select hoisting tackles/lifting accessories which are suitable for the component
weight.
Ø Always use the attachment points provided for suspending components from the
hoisting tackle.
Ø Comply with the applicable health and safety regulations.
WARNING
Unqualified personnel performing work on the pump (set)
Risk of personal injury!
Ø Always have repair and maintenance work performed by specially trained, qualified
personnel.
WARNING
Pump set started up inadvertently
Risk of injury by moving parts!
Ø Make sure that the pump set cannot be started up accidentally.
Ø Always make sure the electrical connections are disconnected before carrying out
work on the pump set.
CAUTION
Improper reassembly
Damage to the pump!
Ø Reassemble the pump (set) in accordance with the general rules of sound
engineering practice.
Ø Replace any damaged/worn parts.
Ø Use original spare parts only.
WKT
71
Chapter 7 Supervision / Servicing / Maintenance
WARNING
Components heated up for installation
Risk of burns at hands!
Ø Wear protective gloves suitable for installation work.
Ø Let components cool down after installation.
For any work on the motor, observe the instructions of the relevant motor manufacturer.
For dismantling and reassembly refer to the general assembly drawing. In the event of
damage you can always contact our service staff. Always reassemble the pump in
accordance with the corresponding general assembly drawing and installation instructions.
§ Never use O-rings that have been glued together from material sold by the meter.
§ Replace all O-rings and V-rings and clean their locating fits on the shaft. Fit all seal
elements on the relevant components before starting with the assembly.
§ Observe the installation instructions regarding cleaning, lubricating and sealing agents.
§ Remove any residues of liquid sealants before starting with the assembly. When
reassembling the pump set, tighten all screws/bolts as indicated.
7.6.2 Preparations
Before reassembly of ring section pumps, the stage sleeve E. of each stage casing (108)
and of the associated impeller (230,231) with stage sleeve (521) must be measured. Any
discrepancy in lengths must be compensated by machining the stage sleeve (521) only,
and the end result must be E1 = E2. (See Fig.27.)
A
C
B
3
2
108
230
E2
171
521
E1
1
Fig. 24
If machining of the stage sleeve is required, it should be shortened at both end faces in
one operation on the machine tool. The permissible end face whobble (deviation from
plane parallelism) is 5 microns.
Do not damage the contact faces on the casing components, diffusers, impellers, spacer
and stage sleeves before and during assembly. All pump components, particularly the end
contact faces, should be thoroughly cleaned. If new impellers are fitted, or if the old ones
are touched up, the rotor must be balanced dynamically.
WKT
72
Chapter 7 Supervision / Servicing / Maintenance
WKT
73
Chapter 7 Supervision / Servicing / Maintenance
N.B.
Do not damage the special coating inside Can and column pipe main.
WKT
74
Chapter 7 Supervision / Servicing / Maintenance
7.6.5 Reassembly of the radial bearing and the stuffing box housing
NOTE
The numbers in parentheses, e.g. (412.17), refer to pump components shown in the
general assembly drawings. (Chapter _ 9)
P Suitable hoisting tackle incl. lifting accessories are available and ready for use.
5. Make sure the connections are positioned correctly! See general arrangement drawing.
(_ Chapter 9 )
6. Insert studs (902.15) into distributor casing (451)
P The radial bearing and the stuffing box housing have been fitted.
P The mechanical seal has been checked for any damage. A new mechanical seal is
available, if required.
P The manufacturer's product literature is available. (_ Chapter 9)
1. Insert the seat ring including the O-ring into the seal cover.
2. Slide the complete rotating unit onto the shaft sleeve. Apply Loctite 243 to the grub
screws and tighten them.
_ Check that the spring-loaded ring can move axially.
3. Slide the complete seal cover on the shaft sleeve.
4. Engage the locking discs in the groove of the shaft sleeve and fasten them on the seal
cover using hexagon head bolts.
WKT
75
Chapter 7 Supervision / Servicing / Maintenance
5. Clean drive shaft (213) and the holes for the shaft sleeve. Apply a thin coat of a
suitable lubricant to the area of the mechanical seal.
6. Insert the gasket in stuffing box housing (451).
7. Slide the completely assembled mechanical seal cartridge (433) on drive shaft (213)
and insert it into stuffing box housing (451). Fit and tighten hexagon nuts (920.15).
Observe the tightening torques! (_ Chapter 9)
NOTE
The numbers in parentheses, e.g. (412.17), refer to pump components shown in the
general assembly drawings. (Chapter _ 9)
To prevent the seal elements from jamming, slowly rotate the pump rotor when
tightening hexagon nuts (920.15).
8. Make sure the connections are positioned correctly! See general arrangement drawing.
(_ Chapter 9)
9. Fit the clamping ring, but do not tighten it.
WKT
76
Chapter 7 Supervision / Servicing / Maintenance
WKT
77
Chapter 7 Supervision / Servicing / Maintenance
7. Rotate either centering sleeve or adjusting nut by 900 to align key-way slots of both
parts with each other.
8. Rotor adjustment can be done with the help of drive shaft key (motor end) by
engaging it in centering sleeve and adjusting nut simultaneously. By rotating the
centering sleeve with adjusting nut.
Ø in clock wise direction, causes the rotor to move in upward direction and
Ø in anti clockwise direction, causes the rotor to move in downward direction.
9. Once the rotor adjustment is done, fix the key on the drive shaft engaging it with key
way slots on centering sleeve and adjusting nut.
WKT
78
Chapter 7 Supervision / Servicing / Maintenance
Carry out an out-of-round check on a lathe between dead centres. The max. permissible
shaft whip must not exceed 0.03 mm.
N.B.
Make sure the shaft is accurately centered on the lathe, as otherwise the readings will be
erroneous.
If certain rotor components are replaced by new ones, or have been touched up, or if a
new shaft has been fitted, the pump rotor must be balanced dynamically, preferably at the
max, operating speed of the pump, but at least at 1000 1/min. The maximum permissible
residual eccentricity is 5 microns.
WKT
79
Chapter 7 Supervision / Servicing / Maintenance
Ensure all the sealing faces are in perfect condition. Check the plane parallelism of the
faces at 4 points on the circumference with a micrometer. The deviation must not exceed
0.02 mm. Damaged faces can be machined on a lathe. The surface roughness must not
exceed 0.8 microns.
The stage casings (108) and diffusers (171) are fitted with renewable casing wearing rings
(502).
Check the impellers and wearing rings for galling and check the rotor clearances per
(Chapter 9).
The casing wearing rings must be machined when fitted and the max. permissible
clearances must be respected. Any increase in clearance must be made uniform at all
wearing points inside the pump.
If the bearing clearances are the same as or greater than the max. permissible clearances
per (Chapter 9). Fit new oversized wearing parts and re-establish the “as new” clearances.
Single deep grooves can be left untouched. (See Fig. 26 & Table. 9)
Shim
Diffuser Lever
WKT
80
Chapter 7 Supervision / Servicing / Maintenance
smooth here
Fig. 26 : Smoothing out the throttling sections on the impellers, See Table. 9
Table 9 : Smallest permissible impeller neck dia. and max. diffuser bore dia.
1) st
not for 1 stage (for single wearing ring execution).
If these limiting values are exceeded replace with new spares.
Pump Body
Suction casing (106), discharge casing (107), stage casings (108),impellers(230,
231),impeller wearing rings (503),casing wearing rings (502), inter stage bushes (541),
distance bushes(521), or sleeves (520) with pump size 150.
Ensure all the sealing faces are in perfect condition. Check the plane parallelism of the
faces at 4 points on the circumference with a micrometer. The deviation must not exceed
0.02 mm. Damaged faces can be machined on a lathe. The surface roughness must not
exceed 0.8 microns.
The impellers (230,231), stage casings (108), and diffusers (171), are fitted with
renewable wearing parts - impeller wearing rings (503), casing wearing rings (502), and
inter stage bushes(541). Check the wearing parts for galling and check the rotor
clearances per clearance sheet (Chapter 9).
The wearing parts must only be machined when fitted and the maximum permissible
clearances must be respected. Any increase in clearance must be made uniform at all
wearing parts inside the pump.
WKT
81
Chapter 7 Supervision / Servicing / Maintenance
541
(503.1)
503.2
Fig. 27 : Full Chrome design with impeller wearing rings and inter stage bushes, pressure
rating 20 / 40.
If the rotor clearances are the same as or greater than the max. permissible clearances
specified in clearance sheet (Chapter 9) fit new over sizes wearing parts and reestablish
the..as new..clearances.
Shim
Diffuser
Diffuser Lever
Lever
Inter stage
bush
5. Align the stage casing (108) and diffuser (171) with fitted casing wearing ring to the
outer fit and machine the wearing ring without changing the setting.
WKT
82
Chapter 7 Supervision / Servicing / Maintenance
smooth here
Fig. 29 : Smoothing out the throttle sections on the impeller wearing rings, See Table. 10
Assembly proceeds from the front end; slip stage sleeve (521) onto pump shaft (211) until
it abuts against the shaft shoulder. Insert the key and slip final stage impeller (230) onto
the shaft until it abuts.
Mount the stage sleeve (521) (sleeve (520), on pump size 150), - keys and impellers (230)
of the remaining stages in sequence, as described above. Fit the split ring (501) and key
(940.4). Push on the bearing sleeve (529.1) and suction impeller (231)
Slip on lock washer (931.1) and clamp the mounted components together on pump shaft
(211) with the aid of shaft nut (920.2).
Before dynamic balancing, the rotor should be checked for true running (out-of-round) at
the impellers (230) and at the bearings. The measured out-of-round value must not
exceed 0.03mm. The rotor should then be balanced dynamically at max. pump operating
speed if possible but at least at 1000 1/ min. The max permissible residual eccentricity
must not exceed 5 microns. Before final assembly in the pump, the pump rotor must be
dismantled again in reverse sequence to the assembly procedure described above.
WKT
83
Chapter 7 Supervision / Servicing / Maintenance
WKT
84
Chapter 7 Supervision / Servicing / Maintenance
We recommend keeping the following spare parts in stock in order to remedy rapidly any
operating fault which might arise :
WKT
85
Chapter 8 Trouble-shooting
8. Trouble-shooting
Fault Possible cause Remedial action
Usable flow rate Pump delivers against an excessively Keep opening the valve in the discharge line
< specified value high discharge pressure. until the duty point is re-adjusted.
NPSH available (positive suction head) is too Adjust the fluid level in the inlet tank.
low. Completely open the valve in the inlet pipe.
Change suction line if the friction losses in
the suction line and too high.
Check any strainers installed.
Excessive speed of pressure fall Observe permissible speed of pressure fall.
Excessive suction head Clean the filter element and the inlet pipe.
Correct/alter the fluid level.
Alter the inlet pipe.
Check any strainers installed.
Pressure ps < specified value Damaged measuring instrument Replace the measuring instrument.
Excessive differential pressure in the filter. Dismantle and clean the filter element.
Valve in the inlet pipe not completely opened. Open the valve.
Pressure in the inlet tank is too low. Check the inlet tank and/or increase the
pressure.
Pressure ps < specified value Damaged measuring instrument Replace the measuring instrument.
Inlet pressure too low Check inlet pressure and inlet tank.
Fluid temperature too low or too high. Increase or reduce the temperature.
Shaft seal leakage Defective shaft seal Check and, if required, replace it.
WKT
86
Chapter 8 Trouble-shooting
Contaminated cooling liquid chamber or cooler Clean the cooling liquid chamber or cooler.
Check the cooling liquid and, if required,
clean it.
Excessive bearing temperature Defective bearing Check and, if required, replace it.
The pump set has not been aligned properly. Check the alignment; re-align, if required.
Pump temperature > specified Pump or piping are not completely vented or Vent and/or prime.
value primed.
NPSH available (positive suction head) Adjust the fluid level in the inlet tank.
is too low. Completely open the valve in the inlet pipe.
Change suction line if the friction losses in the
suction line are too high.
Check any strainers installed.
Pump leakage Defective O-rings and/or metallic sealing Replace the O-rings and/or re-machine the
surfaces metallic sealing surfaces.
Contact KSB Service.
Pump runs rough. Pump or piping are not completely vented or Vent and/or prime.
primed.
NPSH available (positive suction head) Adjust the fluid level in the inlet tank.
is too low. Completely open the valve in the inlet pipe.
Change suction line if the friction losses in
the suction line are too high.
Check any strainers installed.
WKT
87
Chapter 8 Trouble-shooting
Cavitation noise in the pump Damaged inlet pipe Check the inlet pipe.
and/or piping
Valve in the inlet pipe not completely opened Open the valve.
Pressure in the inlet tank is too low. Check the inlet vessel and/or increase the
pressure.
Air ingress at the sealing element/valves/ Check the piping. Check shaft seal
shaft seal for leakage.
Pump back pressure lower then specified in Re-adjust to duty point by means of the
the purchase order valve in the discharge line.
In the case of persistent overloading, turn
down impeller(s), if possible.
Contact KSB Service.
WKT
88
Chapter 9 Related Documents
9 Related Documents
9.1 Tightening torques
Prerequisites
§ The threads of the screws/bolts and nuts are not damaged.
§ The threads and bearing surfaces of the screws/bolts and nuts are plane, deburred
and cleaned thoroughly.
§ The threads move smoothly.
§ Lubricant has been applied to the threads of screws/bolts and nuts.
NOTE
Observe the drawing in the next chapter! (_ Chapter 9.1.3)
WKT
89
Chapter 9 Related Documents
Discharge Nozzle
Nominal Bolt
Flange Rating Material Torque Nm
Diameter Size
DN
50 M16 8.8 138
80 ASME B16.5 M20 8.8 268
100 Class 300 RF M20 8.8 268
150 M20 8.8 268
200 M24 8.8 462
Suction Nozzle
Nominal Bolt
Flange Rating Material Torque Nm
Diameter Size
DN
80 M20 8.8 268
100 ASME B16.5 M20 8.8 268
150 Class 150 RF M20 8.8 268
200 M24 8.8 462
250 M24 8.8 462
WKT
90
Chapter 9 Related Documents
For item 1 Table 13 : Can to Distributor casing (Refer figure no. 30)
WKT
91
Chapter 9 Related Documents
For item 3 Table 15 : Adaptor / Stuffing box (Refer figure no. 30)
WKT
92
Chapter 9 Related Documents
1 4
WKT
93
Chapter 9 Related Documents
WKT
94
Chapter 9 Related Documents
646 638
914.1
400.6 731.2
641 720.1
931.2
213
914.31 920.8
920.31
411.4
451 903.4
458 184
10E
461 452
5B 902.31
457
902.3 524
411.8 920.3
903.6 412.31
8B
851
902.1
920.1
904.3
10-1
400
400
545.01 902.2
920.2 151
529.2 502.2
550.1
171.2
107 904.1
230 108
521 211
(520) 904
940.1 501
503
502
412
529.1
905
171.01
108.01 400
503 231
545.1 502.1
920.1 550.2
904.1 901.6
940.4 Directly flanged on pump
106
VSM shaft seal
Note : Sectional drawings shown in this section are only indicative. Users are requested to follow
specific cross sectional drawing submitted to them with the pump order.
WKT
95
Chapter 9 Related Documents
151
10-1
902.1 383.4
920.1
400.2
400.2
904.3
400.4
545.3
902.2
920.2 529.3
383.1/2/3
213
400.8
851
901.2
711.1 920.6
901.1 212
920.5
400.3 711.2
904.3
545.2
550.1
529.2
107 151
521
503
171.2 502.2
108
412.1
230
211
501, 904.2
940.1
529.1
905
171.01
545.1
400.1
940.4
904.1 108.01
231
920.4
502.1
550.2
901.6
106
Pump with upper Pump with upper column pipe main &
Column pipe main one or two lengths of Column pipe main
WKT
96
Chapter 9 Related Documents
WKT
97
Chapter 9 Related Documents
Diametral
Material Wearing ring Impeller
Pump clearance
ID Neck Dia.
size As new Worn out
Impeller Wearing ring (mm) (mm)
(mm) (mm)
CI/LG2 CI/BZ 15
Ø79.7 -0.05 0.3 0.6
CA6NM Ni CI +0.106
40 Ø80.0 +0.060
CA6NM/CF8M CR.H.400
Ø79.5 -0.05 0.5 0.1
CF8M CF8M Col. coated
CI/LG2 CI/BZ 15
Ø89.7 -0.05 0.3 0.6
CA6NM Ni CI +0.126
50 Ø90.0 +0.072
CA6NM/CF8M CR.H.400
Ø89.5 -0.05 0.5 0.1
CF8M CF8M Col. coated
CI/LG2 CI/BZ 15
Ø99.7 -0.05 0.3 0.6
CA6NM Ni CI +0.106
65 Ø100.0 +0.060
CA6NM/CF8M CR.H.400
Ø99.5 -0.05 0.5 0.1
CF8M CF8M Col. coated
CI/LG2 CI/BZ 15
Ø114.7 -0.05 0.3 0.6
CA6NM Ni CI +0.126
80 Ø115.0 +0.072
CA6NM/CF8M CR.H.400
Ø114.5 -0.05 0.5 0.1
CF8M CF8M Col. coated
CI/LG2 CI/BZ 15
Ø129.7 -0.05 0.3 0.6
CA6NM Ni CI +0.148
100 Ø130.0 +0.085
CA6NM/CF8M CR.H.400
Ø129.5 -0.05 0.5 0.1
CF8M CF8M Col. coated
CI/LG2 CI/BZ 15
Ø149.7 -0.05 0.3 0.6
CA6NM Ni CI +0.148
125 Ø150.0 +0.085
CA6NM/CF8M CR.H.400
Ø149.5 -0.05 0.5 0.1
CF8M CF8M Col. coated
CI/LG2 CI/BZ 15
Ø199.7 -0.05 0.3 0.6
CA6NM Ni CI +0.172
150 Ø200.0 +0.01
CA6NM/CF8M CR.H.400
Ø199.5 -0.05 0.5 0.1
CF8M CF8M Col. coated
WKT
98
Chapter 9 Related Documents
Diametral
Material Wearing ring Impeller
Pump clearance
ID Neck Dia.
size As new Worn out
Impeller Wearing ring (mm) (mm)
(mm) (mm)
1.4024.19 Ni CI Ø84.7 -0.05 0.3 0.6
+0.126
40 1.4024.19 CR.H.400 Ø85.0 +0.072
Ø84.5 -0.05 0.5 1.0
CF8M CF8M Col. coated
1.4024.19 Ni CI Ø99.7 -0.05 0.3 0.6
+0.126
50 1.4024.19 CR.H.400 Ø100.0 +0.072
Ø99.5 -0.05 0.5 1.0
CF8M CF8M Col. coated
1.4024.19 Ni CI Ø109.7 -0.05 0.3 0.6
+0.126
65 1.4024.19 CR.H.400 Ø110.0 +0.072
Ø109.5 -0.05 0.5 1.0
CF8M CF8M Col. coated
1.4024.19 Ni CI Ø124.7 -0.05 0.3 0.6
+0.148
80 1.4024.19 CR.H.400 Ø125.0 +0.085
Ø124.5 -0.05 0.5 1.0
CF8M CF8M Col. coated
1.4024.19 Ni CI Ø141.7 -0.05 0.3 0.6
+0.148
100 1.4024.19 CR.H.400 Ø142.0 +0.085
Ø141.5 -0.05 0.5 1.0
CF8M CF8M Col. coated
1.4024.19 Ni CI Ø161.7 -0.05 0.3 0.6
+0.148
125 1.4024.19 CR.H.400 Ø162.0 +0.085
Ø161.5 -0.05 0.5 1.0
CF8M CF8M Col. coated
1.4024.19 Ni CI Ø214.7 -0.05 0.3 0.6
+0.172
150 1.4024.19 CR.H.400 Ø215.0 +0.1
Ø214.5 -0.05 0.5 1.0
CF8M CF8M Col. coated
WKT
99
Chapter 9 Related Documents
Diametral
Material ID of Stage
Pump clearance
Diffuser sleeve
size Diffuser / As new Worn out
Stage sleeve Bore (mm) OD (mm)
Interstage bush (mm) (mm)
CI/LG2 CI/BZ 15
Ø44.7 -0.03 0.3 0.6
CA6NM Ni CI
40 Ø45.0 +0.039
410 H 410 A/316 Ø44.6 -0.05 0.4 0.8
316 316 Co. coated Ø44.5 -0.05 0.5 1.0
CI/LG2 CI/BZ 15
Ø47.7 -0.03 0.3 0.6
CA6NM Ni CI
50, 65 Ø48.0 +0.039
410 H 410 A/316 Ø47.6 -0.05 0.4 0.8
316 316 Co. coated Ø47.5 -0.05 0.5 1.0
CI/LG2 CI/BZ 15
Ø51.7 -0.03 0.3 0.6
CA6NM Ni CI
80, 100 Ø52.0 +0.046
410 H 410 A/316 Ø51.6 -0.05 0.4 0.8
316 316 Co. coated Ø51.5 -0.05 0.5 1.0
CI/LG2 CI/BZ 15
Ø64.7 -0.03 0.3 0.6
CA6NM Ni CI
125 Ø65.0 +0.046
410 H 410 A/316 Ø64.6 -0.05 0.4 0.8
316 316 Co. coated Ø64.5 -0.05 0.5 1.0
CI/LG2 CI/BZ 15
Ø79.7 -0.03 0.3 0.6
CA6NM Ni CI
150 Ø80.0 +0.046
410 H 410 A/316 Ø79.6 -0.05 0.4 0.8
316 316 Co. coated Ø79.5 -0.05 0.5 1.0
WKT
100
Chapter 9 Related Documents
50 Ø45 0.100 0.178 Ø42 0.100 0.178 Ø42 0.100 0.178 Ø42 0.100 0.178
65 Ø46 0.100 0.178 Ø42 0.100 0.178 Ø42 0.100 0.178 Ø42 0.100 0.178
80 Ø50 0.100 0.178 Ø42 0.100 0.178 Ø42 0.100 0.178 Ø55 0.120 0.212
100 Ø52 0.120 0.212 Ø55 0.120 0.212 Ø42 0.100 0.178 Ø55 0.120 0.212
125 Ø63 0.120 0.212 Ø70 0.120 0.212 Ø55 0.120 0.212 Ø55 0.120 0.212
150 Ø76 0.120 0.212 Ø70 0.120 0.212 Ø70 0.120 0.212 Ø55 0.120 0.212
WKT
101
Chapter 9 Related Documents
WKT
102
Notes:
WKT
Notes:
WKT
1766.841/02-18 G3