Project Management Professional (PMP®) Exam PMBOK® Guide - Fifth Edition Aligned
Project Management Professional (PMP®) Exam PMBOK® Guide - Fifth Edition Aligned
Knowledge Area
Integration Copyrights
Scope
• PMP®: “PMP” and the PMP logo are
Time
certification marks of the Project Management
Institute which are registered in the United
Cost States and other nations
Quality
• PMBOK®: “PMBOK” is a trademark of the
Project Management Institute, Inc. which is
HR registered in the United States and other
nations
Communications
• Note: The PMBOK is the primary source for
Risk this slide deck. When other sources are
references, citations are provided.
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 2
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Introductions &
Integration
Course Expectations
Scope
• Personal Background
Time – Name
Cost
– Organization, Title
– Formal Education
Quality
• Project Management Experience
HR
• Expectations for this course
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 3
Distribution © 2014, Innovative Management Solutions, LLC
Course Syllabus
Knowledge Area
Knowledge Area
Knowledge Area
Student Presentations: Assignments
Integration
• Integration Management • Human Resource
Scope – Instructor assigned Management
• Chapter 4 – Instructor assigned
• Chapter 9
Time • Scope Management
• Communications
– Instructor assigned Management
Cost • Chapter 5
– Instructor assigned
• Time Management • Chapter 10
Quality – Instructor assigned • Risk Management
• Chapter 6 – Instructor assigned
• Cost Management • Chapter 11
HR • Procurement Management
– Instructor assigned
• Chapter 7 – Instructor assigned
Communications • Chapter 12
• Quality Management
– Instructor assigned
• Stakeholder Management
Risk • Chapter 8
– Instructor assigned
• Chapter 13
• Ethics & Prof Responsibility
Procurement – Instructor assigned
• Chapter 14
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 7
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 8
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Scope
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 9
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Study Time Commitment (PMPath™)
Source: Dr. Robert Amason, PMP
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 10
Distribution © 2014, Innovative Management Solutions, LLC
Study Groups
Knowledge Area
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 12
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 13
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 14
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Thomson Prometric Test Center U of L Belknap Campus
Cost
7400 New La Grange Road, Suite #110 106 East Brandeis
Louisville, KY 40222 Louisville, KY 40208
Quality
Phone: (502) 423-0478 Phone: (502) 852-6607
HR Site Code: 1101 Site Code: 1102
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 15
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 16
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 17
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 18
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 22
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration Definitions
Scope
• Project Management: The application of
Time
management methods (knowledge, skills,
tools, techniques) to project activities
Cost (planning, scheduling and controlling) to
deliver the product of the project
Quality
• Project Management provides process or
HR task focus; it provides specifics of who, what,
when, and how
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 23
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 24
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications Project
Planning
Project
Risk Execution
(Charter,
WBS, etc…)
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 25
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 26
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Program vs Project: Important
Integration
Differentiators
Scope
Time
Program Project
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 27
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Program vs Multi-Project: Important
Integration Differentiators
Scope
Program Multi-project
Time Management of a group of Manage several projects
interrelated projects independently
Cost
Program level responsibility Fully accountable for each
Quality
and manages project individual project
managers for component
projects
HR
Optimize resources across Manage resources assigned to
Communications program tasks for projects
Manage multiple stakeholders; Focused on meeting needs for
Risk complex communications different project stakeholders
Procurement
Balanced time across program Balance between concurrent
related activities projects competing for time
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 28
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 29
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Scope
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 30
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 31
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 32
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
1.5 Project vs Operations
Integration
Management
Scope • Operations
– On-going activities
Time
– Business process or operations management
– Product life cycle vs project life cycle
Cost
– Intersection points (product enhancements, new product
Quality
development, product close-out or disposal, etc…)
• Similarities
HR – Performed by people
– Limited by constraints
Communications – Planned, executed, monitored & controlled
– Achieve organizational goals & contributes to strategic
Risk plans
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 33
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 34
Distribution © 2014, Innovative Management Solutions, LLC
Organizational Influences and Project Life
Cycle
Knowledge Area
Quality
• Formal or informal
• Updated throughout the project
HR
• Responsibility primarily rests with project team
Communications members
• Categories
Risk
– Processes & procedures
Procurement – Corporate knowledge base
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 37
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
2.1.5 Enterprise Environmental
Integration
Factors
Scope • Internal & external factors that influence a project’s
success
Time
• Not under the project team’s control
Cost • Negative or positive
• Inputs to most processes
Quality • Such as
– Organizational culture, structure, processes
HR
– Industry standards
Communications
– Existing human resources (capabilities)
– Personnel administration (staffing, performance reviews)
Risk – Work authorization systems
– The PMIS
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 38
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
• Grouping and naming stakeholders is the
HR primary aid to identifying who views
themselves as stakeholders
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 39
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 40
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
2.4 Project Lifecycle
Scope
• Generally defines…
Time
– What
– When
Cost – Who
– How
Quality
• Common Characteristics
HR – Cost & staffing requirements start low and peak
during implementation (intermediate phases)
Communications
– Level of uncertainty is highest at the beginning
Risk – Ability to influence “product” characteristics is
highest at the beginning
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 41
Distribution © 2014, Innovative Management Solutions, LLC
Let’s Dig Into PMBOK Figure 2-8
Knowledge Area
Communications
• Deliverable = measurable, verifiable
product or service
Risk
• One-size-does-not-fit-all
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 43
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 44
Distribution © 2014, Innovative Management Solutions, LLC
Project Management Processes
Knowledge Area
Integration
Project Management Processes Groups
Scope
Initiating Planning
Time Process Process
Cost
Quality
Controlling Executing
HR
Process Process
Communications
Risk Closing
Process
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 46
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 47
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Chapters 1 - 3
Knowledge Area
Integration
Integration Project Interfaces
Scope • Interface Management is critical during execution
• Interfaces:
Time
– Product
Cost – Infrastructure
– Resources
Quality – People interfaces (cross organization)
– System interfaces (organization, information)
HR • Goal of project integration: coordinate people,
product, infrastructure, system (organization,
Communications
information) together toward accomplishing the project
goals.
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 53
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration 4.1 Develop Project Charter
Scope
Document that formally authorizes the
Time project & provides PM authority to
allocate resources
Cost
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 54
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration Constraints & Assumptions
Scope
• Constraint – a restriction that well affect
Time the performance of the project
• Assumptions – factors, that for planning
Cost
purposes, are considered to be true,
Quality real, or certain
HR
• Assumptions – affect all aspects of the
project planning, and are part of the
Communications progressive elaboration of the project
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 55
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration 4.1 Develop Project Charter
Scope
4.1.2 Tools & Techniques
Time .1 Expert Judgment
Cost
Quality
HR
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 56
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration Reasons to Authorize a Project
Scope
• Market Demand
Time • Business Need
Cost • Customer Request
Quality • Technological Advance
HR
• Legal Requirement
• Social Need
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 57
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration Models
Scope
• Non-numeric • Numeric
Time
– Sacred Cow – Payback Period
– Operating Necessity – Average Rate of
Cost – Competitive Return
Necessity What about TVM?
Quality
– Product Line – DCF or IRR (NPV)
Extension
HR
– Comparative Benefit
Communications
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 58
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration Models
Scope
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 59
Distribution © 2014, Innovative Management Solutions, LLC
NPV Exercise
Knowledge Area
Integration
Integration 4.1 Develop Project Charter
Scope
4.1.3 Outputs (Figure 4-3)
Time .1 Project Charter
• Project purpose of justification
Cost • Objectives (SMART)
• High level
Quality – Requirements
– Project description
HR
– Risks
• Summary milestone schedule
Communications
• Summary budget
Risk • Approval requirements
• Assign PM (responsibility and authority)
Procurement • Charter approval (sponsor)
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 62
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
4.2 Develop Project Management
Integration
Integration
Plan
Scope
The PM Plan documents the collection of outputs
Time
from each of the processes in the “Planning”
process group
Cost
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 63
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
4.2 Develop Project Management
Integration
Integration
Plan
Scope
4.2.2 Tools & Techniques
Time
.1 Expert Judgment
.2 Facilitation Techniques
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 64
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
4.2 Develop Project Management
Integration
Integration
Plan
Scope
4.2.3 Outputs (Figure 4-5)
Time .1 PM Plan
• Integrates and consolidates all of the subsidiary
Cost
management plans and baselines from planning
processes
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 65
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
4.3 Direct & Manage Project
Integration
Integration
Execution
Scope
4.3.1 Inputs
Time .1 PM Plan
Cost
.2 Approved Change Requests
.3 Enterprise Environmental Factors
Quality
.4 Organizational Process Assets
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 66
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Communications
• Defect repair
– Documented identification and
Risk recommendation to repair or replace
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 67
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
4.3 Direct & Manage Project
Integration
Integration
Execution
Scope
4.3.2 Tools & Techniques
Time .1 Expert Judgment
Cost
.2 PMIS
.3 Meetings
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 68
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration Work Authorization System
Scope • Authorizes work to begin
– Commits resources (people, funds, etc.) to the work
Time
– Starts the clock on that portion of the plan and
schedule
Cost
• Large projects
Quality
– Formal written system
– Frequently, organizational form to prepare
HR
• Small projects
Communications
– Verbal, email, etc.
Risk
– Still a ‘formal system’ and emphasis is needed to
retain control of the work
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 69
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
4.3 Direct & Manage Project
Integration
Integration
Execution
Scope
4.3.3 Outputs (Figure 4-7)
Time .1 Deliverables
Cost
Unique…verifiable product, result,
capability…
Quality .2 Work Performance Data
HR .3 Change Requests
.4 Project Management Plan Updates
Communications
.5 Project Document Updates
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 70
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration PM Plan Updates
Scope
• Requirements Management Plan
Time • Schedule Management Plan
• Cost Management Plan
Cost
• Quality Management Plan
Quality
• Human Resource Plan
HR • Communications Management Plan
• Risk Management Plan
Communications
• Procurement Management Plan
Risk
• Project Baselines
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 71
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Integration Product Document Updates
Scope
• Requirements Documents
Time • Project Logs
Cost – Issues log
– Assumptions
Quality
• Risk Register (log)
HR
• Stakeholder Register
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 72
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration 4.4 Monitor & Control Project Work
Scope
Track, review, regulate…
Time
Knowledge Area
Integration
Integration 4.4 Monitor & Control Project Work
Scope
4.4.2 Tools & Techniques
Time .1 Expert Judgment
Cost
.2 Analytical Techniques
.3 PMIS
Quality
.4 Meetings
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 74
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration Track Key Data
Scope • Cost Performance
Time
• Schedule Performance
• Quality
Cost – Conformance to requirements and specifications
(product quality)
Quality – Quality of project reporting and tracking, too (project
quality)
HR
• Plan performance -- maintain the project plan
Communications • Resource utilization -- compare to schedule
and costs
Risk
• Team performance (group and individual)
Procurement • Risk triggers
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 75
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration 4.4 Monitor & Control Project Work
Scope
4.4.3 Outputs (Figure 4-9)
Time .1 Change Requests
Cost
.2 Work Performance Reports
.3 Project Management Plan Updates
Quality
.4 Project Document Updates
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 76
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Change Control
Integration
Integration
Outcomes
Scope
• Identify and influence factors that create
Time
change
– e.g., add-on requirement during execution phase of
Cost project
• Drives scope change
Quality • Cost
• Schedule
HR
• Recognize when a change has occurred
Communications
– Taking action to reflect the change in the plan
Risk – Identifying changes in performance baselines
Procurement
• Manage actual changes when they occur
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 77
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration Integrated Change Control
Scope
• Key activity in Execution Phase
Time • Retain control of revisions
– Scope: Schedule, Cost, Staffing
Cost
– Requirements and specifications: Quality
Quality • Important to keep performance baselines
intact
HR
(baselines = the plan)
Communications
• Not necessary to ‘ban’ changes…just identify,
Risk control (and manage) them
– Identify & Influence, Recognize, Manage
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 78
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration
4.5 Perform Integrated Change Control
Scope
4.5.1 Inputs
Time .1 PM Plan
.2 Work Performance Reports
Cost
.3 Change Requests
Quality .4 Enterprise Environmental Factors
.5 Organizational Process Assets
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 79
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration Configuration Management
Scope
• Three main objectives:
Time – Establish processes to identify, request,
and assess value of changes
Cost
– Continuously validate and improve through
Quality considering impact of changes
HR
– Processes used to communicate changes
to stakeholders
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 80
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration
4.5 Perform Integrated Change Control
Scope
4.5.2 Tools & Techniques
Time .1 Expert Judgment
Cost
.2 Meetings
.2 Change Control Tools
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 81
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Integration
Integration
4.5 Perform Integrated Change Control
Scope
4.5.3 Outputs (Figure 4-11)
Time .1 Approved Change Requests
Cost
.2 Change Log
.3 Project Management Plan Updates
Quality
.4 Project Document Updates
HR
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 82
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Integration
Integration 4.6 Close Project or Phase
Scope
4.6.1 Inputs
Time .1 PM Plan
Cost
.2 Accepted Deliverables
.3 Organizational Process Assets
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 83
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Integration
Integration Impact of Termination
Scope
• Project transfer
Time • Ongoing operations
Cost • Project personnel
Quality • Equipment/material assets
HR
• Future projects
• PM
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 84
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Integration
Integration Termination by...
Scope • Extinction
– Successful or not
Time
– Deliverable is external to or not a fundamental
Cost function of the parent organization
• Addition
Quality – Institutionalized
– New Division
HR
• Integration
Communications – Most Common
– Project assets redistributed
Risk
• Starvation
Procurement – Budget decrement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 85
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Integration
Integration 4.6 Close Project or Phase
Scope
4.6.2 Tools & Techniques
Time .1 Expert Judgment
Cost
.2 Analytical Techniques
.3 Meetings
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 86
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Integration
Integration 4.6 Close Project or Phase
Scope
4.6.3 Outputs (Figure 4-13)
Time .1 Final Product, Service, or Result Transition
Cost
.2 Organizational Process Asset Updates
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 87
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 91
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 93
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 94
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 96
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 97
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 98
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
Requirement Stability
Limited executive
Scope
Scope involvement:
requirements
Number of changes
Time
never stabilize
Cost
Quality
Focused, early
agreement =
HR requirement stability!
Time
Communications
Risk
Source: Tuttle, Q.C., Implementing Concurrent Project Management, Prentice Hall, 1994
Procurement Moral: Agree upon requirements early
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 99
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 100
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 101
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 102
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 103
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 104
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 105
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 106
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 107
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 108
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 109
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 110
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Source: Practice Standards for Work Breakdown Structures. (2001). PMI.
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 111
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 112
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Source: Practice Standards for Work Breakdown Structures. (2001). PMI.
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 113
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 114
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 115
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 117
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 118
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Note this is in the “Monitoring and Control”
Procurement Process Group
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 119
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 120
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Source: Lewis, J. (2001). Project Planning, Scheduling, and Control. 3rd ed.
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 121
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 122
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 123
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 124
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Scope Change
Integration
Control
Scope
Scope
• Concerned with three things:
Time – “…influencing factors that create scope
changes to ensure changes are agreed
Cost upon,
– determining that a scope change has
Quality
occurred
HR – managing actual changes when and if they
occur.”
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 125
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 129
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 130
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 131
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 132
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 133
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 134
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 135
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 136
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 137
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Network Diagram
Integration
“Facts”
Scope
• All have beginning point and an end point
Time
Time • Represent “predecessor” relationships
– Complex relationships can be represented in AON
Cost • F-S, S-S, S-F, F-F
– All activities have predecessors
Quality
– Exception: first task of network has no predecessor
HR • No “hangers”
– Every task has a “successor”
Communications
– Exception: last task has no “successor”
Risk • No “loops”
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 138
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 139
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 140
Distribution © 2014, Innovative Management Solutions, LLC
Network Flow Diagram Exercise
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 142
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 143
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 145
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 146
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 147
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 148
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
Activity duration estimates should always
HR include some indication of range of
Communications possible results (e.g.: +/- time, or %
probability)
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 149
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
• SD = P – O
Cost 6
2
P–O
Quality • Variance = ( 6 )
tO + tM + tP
HR • Triangular distribution: tE = 3
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 150
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Time
Cost
q=99.7%
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 151
Distribution © 2014, Innovative Management Solutions, LLC
Pert Exercise
• If P = 24, ML = 12, O = 6
• Variance: 32 = 9
Student Copy – Not for Reproduction or Distribution
Path Standard Deviation and
Variances
Standard
Variance
Optimistic Most Likely Pessimistic Triangulation PERT Weighted Average Deviation
SD Squared
(P - O)/6
Activity A 12 15 24 17 16 2 4
Activity B 6 8 12 8.67 8.33 1 1
Activity C 15 22 33 23.33 22.67 3 9
Activity D 8 11 20 13 12 2 4
56 62 59 18
Knowledge Area
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 155
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 156
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 157
Distribution © 2014, Innovative Management Solutions, LLC
Gantt Chart Diagram Exercise
Knowledge Area
Project Crashing
Integration
17
12 days
Scope
Activity
Activity
Predecessors Foundation
Foundation
Prep
Prep Successors
Time
Time
Cost
• Cost implications
Quality
• Resource implications
HR • Advantages?
Communications • Disadvantages?
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 159
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 160
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 161
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 162
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 163
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 164
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 165
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 169
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 170
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 171
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 172
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 173
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Cost
Cost
7.2.1 Inputs
Quality .1 Cost Management Plan
.2 HR Management Plan
HR
.3 Scope Baseline
Communications .4 Project Schedule
.5 Risk Register
Risk
.6 Enterprise Environmental Factors
Procurement
.7 Organizational Process Assets
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 174
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 175
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Cost Estimation
Integration
Techniques
Scope
• Analogous (Top Down)
Time
– Actual cost of similar project
– Less costly, less accurate
Cost
Cost
• Bottom Up estimating
Quality
– Estimating individual work items and summing
– More Accurate, time consuming
HR – General approach used by software tools
Communications
• Parametric
– Using known rates and quantities
Risk – Accurate
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 176
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Source: Schwalbe, K. (2001). Information Technology Project Management. 2nd ed.
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 177
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
• SD = P – O
Cost
Cost 6
2
P–O
Quality • Variance = ( 6 )
cO + cM + cP
HR • Triangular distribution: cE = 3
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 178
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 179
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Cost
Cost 7.3.1 Inputs
.1 Cost Management Plan
Quality .2 Scope Baseline
.3 Activity Cost Estimates
HR .4 Basis of Estimates
.5 Project Schedule
Communications
.6 Resource Calendars
Risk
.7 Risk Register
.8 Agreements
Procurement .0 Organizational Process Assets
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 180
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 181
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration Reserves
Scope
• Contingency Reserves
Time
– Can be partially planned for
– Known-unknowns
Cost
Cost – e.g., known rate of personnel turnover
Quality
• Management Reserves
– Unpredictable
HR – Unknown-unknowns
Communications
• Not a part of the baseline, but included in the
project budget (which means not a part of
Risk EVA)
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 182
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 183
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 184
Distribution © 2014, Innovative Management Solutions, LLC
Budget Estimate Question
Knowledge Area
Cost
Cost
7.4.1 Inputs
.1 PM Plan
Quality
.2 Project Funding Requirements
HR .3 Work Performance Data
.4 Organizational Process Assets
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 186
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 187
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Earned Value
Integration
Management (EVM)
Scope
• Budgeted Cost of Work Performed (EV):
Time
– Earned Value
– Amount budgeted for the work “as of” a date
Cost
Cost
• Actual Cost of Work Performed (AC):
Quality – Actual Costs for the work ‘as of’ a date
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 188
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Variance
Integration
(Earned Value)
Scope
• Cost Variance (CV) = EV - AC
Time
– Negative indicates over budget
– CPI: Represent as a % by EV/AC
Cost
Cost
• Schedule Variance (SV) = EV - PV
Quality
– Negative indicates behind schedule
– SPI: Represent as a % by EV/PV
HR
• Budget at Completion (BAC = Baseline or
Communications
revised budget)
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 189
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Cost/Schedule Performance Index
Integration (CPI/SPI)
Scope
• Indicates Cost or Schedule Efficiency
Time for accomplished work.
Cost
Cost
> 1.0 - Ahead of Schedule
= 1.0 - On Schedule
Quality
< 1.0 - Behind Schedule
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 190
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Knowledge Area
Quality
TCPI = (BAC – EV)/(BAC – AC)
HR
or
Communications
TCPI = Work Remaining / Funds Remaining
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 192
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
$70K 70K
Time
$60K
Cost
Cost
50K
$50K
ACWP 45
Quality
$40K 40K
BCWS
SV CV
HR $30K
$20K
20K
Communications BCWP 30
$10K
Risk
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 193
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
IF :
Scope
Time
EV = $6000
Cost
Cost
PV = $7000
Quality
AC = $8000
HR
Communications
Find CV, SV, CPI, SPI
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 194
Distribution © 2014, Innovative Management Solutions, LLC
Budget Variance
Today
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 196
Distribution © 2014, Innovative Management Solutions, LLC
EVM Exercise
Knowledge Area
Integration Remember…
Scope
• Cost Management should consider
Time effect of decisions on the following
Cost
Cost
costs as related to the project
product/service…
Quality
– Using
HR – Maintaining
– Supporting
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 200
Distribution © 2014, Innovative Management Solutions, LLC
Project Quality Management
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 203
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 204
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
Quality • Albrecht’s Theory of Service Relativity
– V=R-E
HR
– Determines net gain or loss
Communications
Risk
Procurement Source: Goetsch, D., and Davis, S. (2000). Quality Management: Introduction to Total Quality
Management for Production, Processing, and Services. 3rd ed.
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 205
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 206
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 207
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 208
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Cost
Quality
Quality q=99.7%
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 209
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 210
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 211
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Cost
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 212
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement Source: Goetsch, D., and Davis, S. (2000). Quality Management: Introduction to Total Quality
Management for Production, Processing, and Services. 3rd ed.
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 213
Distribution © 2014, Innovative Management Solutions, LLC
The Seven Basic Quality Tools
Knowledge Area
1. Cause-n-Effect Analysis
Integration
(Fishbone, Ishikawa)
Scope • Visual tool used to logically organize possible causes
for a problem by graphically displaying them in
Time increasing detail
• Helps to identify root causes and ensures common
Cost
understanding of the causes
Quality
Quality People Policies
Crowded Hallways
HR
Sign Limitations
No Directions Provided
Training
Hallway Layout
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 215
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 216
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration 3. Checksheets
Scope
• Tally sheet
Time • Use for…
Cost – Gathering data
– Organizing facts
Quality
– Collecting attribute data during inspections
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 217
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 218
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration 5. Histograms
• Distribution of variables
Scope
• Summarize data collected over a period of
Time
time
Cost • Helps identify the cause from the shape &
width of the distribution.
Quality
Quality
– Exam scores
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 219
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Cost
• The closer the points...the more closely the
variables are related
Quality
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 221
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 222
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 223
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 224
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Cost
8.2.1 Inputs to Quality Assurance
Quality
Quality .1 Quality Management Plan
.2 Process Improvement Plan
HR
.3 Quality Metrics
Communications
.4 Quality Control Measurements
.5 Project Documents
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 225
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 226
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 227
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Quality
Quality Key benefits
• Identify the causes of poor process or product
HR
quality and recommended and/or taking action
Communications to eliminate the causes
• Validating that deliverables and work meet
Risk
requirements for final acceptance
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 228
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 229
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 230
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Knowledge Area
9.1 Plan Human Resource
Integration
Management
Scope
9.1.1 Inputs
Time
.1 Project Management Plan
.2 Activity Resource Requirements
Cost .2 Enterprise Environmental Factors
Organizational – Working arrangements,
Quality
formal/informal relationships
HR Technical – What disciplines and specialties are
required
Communications Interpersonal – Formal/informal “reporting”
relationships, cultural impacts, language, etc…
Risk .3 Organizational Process Assets
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 235
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
9.1 Plan Human Resource
Integration
Management
Scope
9.1.2 Tools & Techniques
Time
.1 Organizational Charts and Position Descriptions
OBS
Cost Resource Breakdown Structure (RBS) – breaks
down the project by “types” of resources
Quality
Matrix-based – RAM: e.g. RACI (Responsible,
HR
Accountable, Consult, Inform)
.2 Networking
Communications .3 Organizational Theory
.4 Expert Judgment
Risk
.5 Meetings
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 236
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Organizational
Integration
Influences
Scope
• Project-based organizations have
Time
management systems that help projects
– Matrix (PM budget authority varies…highest in
Cost “strong”)
– Projectized (PM has almost total authority)
Quality
• Project management is more difficult in non-
HR project-based organizations
– Functional
Communications
• The maturity of an organization with respect to
Risk PM systems, culture, style, structure, and
PMO can influence project work
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 237
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Departments VP VP VP
Finance Marketing Manufacturing
Functional
Managers
Manager Manager Manager Manager
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 240
Distribution © 2014, Innovative Management Solutions, LLC
CEO
PM
PM
PM
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 242
Distribution © 2014, Innovative Management Solutions, LLC
CEO
Marketing
Manufacturing
Project B R&D
Manager Finance
Personnel
Knowledge Area
9.1 Plan Human Resource
Integration
Management
Scope
9.1.3 Outputs (Figure 9-3)
Time .1 Human Resource Management Plan
Cost
Roles & responsibilities
Project organizational chart
Quality
Staffing management plan
HR Staff release plan
Communications
Training needs
Recognition and rewards
Risk
Compliance (regulation, unions, etc.)
Procurement Safety
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 244
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 245
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Communications
• May need contract (third-party) help
– Procurement Planning
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 247
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 248
Distribution © 2014, Innovative Management Solutions, LLC
Responsibility Assignment
Matrix
3.1.1 Primary
Knowledge Area
HR 9.3.1 Inputs
.1 Human Resource Management Plan
Communications
.2 Project Staff Assignments
Risk .3 Resource Calendars
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 250
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 251
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 252
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 253
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 254
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Integration Theory X
Scope
• People inherently dislike work
Time • People must be coerced or controlled to
Cost do work to achieve objectives
Quality
• People prefer to be directed
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 255
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Integration Theory Y
Scope
• People view work as being as natural
Time as play and rest
Cost • People will exercise self-direction and -
control towards achieving objectives
Quality
they are committed to
HR
• People learn to accept and seek
Communications responsibility
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 256
Distribution © 2014, Innovative Management Solutions, LLC
Maslow’s Hierarchy of Needs
Knowledge Area
Integration
Motivator vs Hygiene Factors Theory
Scope • Motivator factors increase job satisfaction
– Achievement
Time – Recognition
– Work itself
Cost – Responsibility
– Advancement
Quality
– Growth
HR • Hygiene factors are those whose absence can create
job dissatisfaction
Communications – Supervision
– Company policy
Risk – Working conditions
– Salary
Procurement – Peer relationship
– Security
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 258
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 259
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 260
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Blanchard & Hershey’s Leadership
Integration
Behavior
Scope • D4 Competent / Commitment
– Experienced at the job, and comfortable with their own
Time ability to do it well
• D3 Competent / Variable Commitment
Cost
– Experienced and capable, but may lack the
confidence/motivation to go it alone
Quality
• D2 Some Competence / Low Commitment
HR – May have some relevant skills, but won't be able to do the
job without help
Communications • D1 Low Competence / Low Commitment
– Lacks the specific skills required for the job in hand & and
Risk lacks confidence/motivation
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 261
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 262
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Integration
Team Building Ground Rules
Scope • Start early - it takes time
Time
• Don’t stop - it takes effort
• Get the right team and manage toward
Cost success
– Best qualified members
Quality
– People who want to be on the team
HR • Get team agreement on all major points
• Don’t manipulate members, but do review and
Communications evaluate team success/effectiveness
Risk
• Watch for symptoms of team breakdown
• Plan and use a team building process
Procurement
Source: Verma, V. (1995). Managing the Project Team.
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 264
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 265
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 267
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 268
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 270
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 274
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 275
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
10.1 Plan Communications
Integration
Management
Scope
The majority of Communications Planning should
Time
be completed in the early phases
Cost
10.1.1 Inputs
Quality .1 Project Management Plan
.2 Stakeholder Register
HR
.3 Enterprise Environmental Factors
Communications
Communications
.4 Organizational Process Assets
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 276
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
10.1 Plan Communications
Integration
Management
Scope
10.1.2 Tools & Techniques
Time .1 Communications Requirements Analysis
Cost
.2 Communications Technology
.3 Communications Models
Quality
.4 Communications Methods
HR .5 Meetings
Communications
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 277
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Communications
# of Channels = (N2 – N)/2
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 278
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 279
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Time
Cost
Quality
HR
Communications
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 280
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 281
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
10.1 Plan Communications
Integration
Management
Scope
10.1.3 Outputs (Figure 10-3)
Time .1 Communications Management Plan
Cost
Describes how project communications will
be planned, structured, monitored and
Quality controlled
HR
.2 Project Documentation Updates
Communications
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 282
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 283
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 284
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 285
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Communications Status – where the project stands related to schedule &
budget
Risk
Progress – what has been accomplished
Procurement Forecasting – predict future status and progress
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 286
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 287
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
HR
Communications
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 288
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 289
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
HR
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 294
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 295
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 296
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 297
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 298
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 299
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 300
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 301
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 302
Distribution © 2014, Innovative Management Solutions, LLC
Project
Management
Integration
Information/
Scope Communi-
cations
Life Cycle and
Environment Variables
Expectations
Ideas, Directives,
Feasibility
Data Exchange Accuracy
Quality
Requirements Project Availability Human
Standards Productivity
Risk Resources
Contract/
Time
Procurement
Cost
Source: Wideman, R.M. (1992). Project and Program Risk Management: A Guide to
Managing Project Risks and Opportunities.
Student Copy – Not for Reproduction or Distribution
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 305
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 306
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
11.3 Perform Qualitative Risk Analysis
Scope
Methods for prioritizing risks, improving project
Time
performance, etc…by focusing on high priority
risks
Cost
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 307
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
11.3 Perform Qualitative Risk Analysis
Scope
11.3.2 Tools & Techniques
Time .1 Risk Probability & Impact Assessment
Cost
.2 Probability & Impact Matrix
.3 Risk Data Quality Assessment
Quality
.4 Risk Categorization
HR .5 Risk Urgency Assessment
Communications
.6 Expert Judgment
Risk
Risk
• Probability, Impact, Timing, Frequency
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 308
Distribution © 2014, Innovative Management Solutions, LLC
Probability & Impact Matrix (See
PMBOK 5th Edition Figure 11-10)
Quantification
Risk Impact Likelihood (I X L) Response
A High High 25 X
B High Med 15 Y
C Med Med 9 Z
High = 5
Med = 3
Low = 1
Student Copy – Not for Reproduction or Distribution
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
11.3 Perform Qualitative Risk Analysis
Scope
11.3.3 Outputs (Figure 11-9)
Time .1 Project Document Updates
Cost
Quality
HR
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 310
Distribution © 2014, Innovative Management Solutions, LLC
Charles F Millhollan, MBA, MPM, PMP, PgMP 311
© 2011, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
11.4 Perform Quantitative Risk Analysis
Scope
Performed on risks prioritized in Qualitative Risk
Time
Analysis as potentially and substantially
impactful
Cost
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 312
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration
11.4 Perform Quantitative Risk Analysis
Scope
11.4.2 Tools & Techniques
Time
.1 Data Gathering and Representation Techniques
.2 Quantitative Risk Analysis and Monitoring
Cost Techniques
Monte Carlo simulation: numerically analyze the
Quality probability of each event and the event’s
consequences
HR
Decision Tree Analysis
Communications Expected Monetary Value (EMV) Analysis:
statistically calculates average outcomes in
Risk
Risk uncertainty
.3 Expert Judgment
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 313
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Risk
Expect Monetary Value = $275 * .01 =
Procurement
$2.75
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 314
Distribution © 2014, Innovative Management Solutions, LLC
Expected Monetary Value
B 30% $50,000
C 68% $20,000
Knowledge Area
Integration
11.4 Perform Quantitative Risk Analysis
Scope
11.4.3 Outputs (Figure 11-12)
Time .1 Project Documents Updates
Cost
Probabilistic analysis, probability of meeting
cost/time objectives, prioritized list of
Quality “quantified” risks, etc…
HR
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 318
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 319
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 321
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 322
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Communications
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 323
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 324
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 325
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
Integration
Procurement Management
Scope
• Includes the processes required to
Time acquire goods and services, to attain
Cost
project scope, from outside the
performing organization
Quality
• Key thought: make or buy
HR
• Note: Project procurement
Communications management is discussed from the
perspective of the buyer in the buyer-
Risk
seller relationship.
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 329
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 330
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 331
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 332
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 333
Distribution © 2014, Innovative Management Solutions, LLC
Make or Buy Exercise
You are trying to decide whether to buy or lease an item for your project.
The daily lease cost is $120. To purchase the item the investment cost
is $1000 and the daily cost is $20. How long will it take for the lease
cost to be the same as the purchase cost?
Let D = the number of days when the purchase and lease costs are equal.
$120D = $1,000 + 20D
$120D - $20D = $1000
$100D = $1000
D = 10. What does this mean?
Knowledge Area
Integration
Buy vs. Lease vs. Rent
Scope
• Length of use (future projects?)
Time • Cash flow; cost of money; financial
Cost statement
Quality
• Technology life span
• Depreciation and taxes
HR
• Maintenance; cost & expertise
Communications
• Insurance
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 335
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 336
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
• Cost Reimbursable
– Cost plus fixed fee (CPFF)
HR – Cost plus incentive fee (CPIF)
– Cost plus award fee (CPAF)
Communications
– Cost plus percentage of cost (illegal in Gov)
Risk • Time and Materials
Procurement
Procurement
• Purchase Order (unilateral agreement)
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 337
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Fixed Price Contract Type
Integration
Comparison
Scope • Advantages • Disadvantages
– Know cost up front – May not get consistent
Time quality
– Risk to seller
– Competition – Not flexible
Cost
– Compare multiple – Can be costly
Quality
vendors bids – Seller may under
– Little experience price the work and try
needed - less work for to make up profits on
HR
buyer to manage change orders
– Seller has strong – Seller may not
Communications
incentive to control complete some of the
costs scope of work if they
Risk
begin to lose money.
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 338
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Cost Plus Contract Type
Integration
Comparison
Scope
• Advantages • Disadvantages
Time
– More influence & – Level of involvement
flexibility - auditing of seller
Cost – Could be less invoices
expensive – No incentive to finish
Quality – Share risk quickly or control
– Scope definition costs
HR – Harder to evaluate
can be more
flexible proposals
Communications
– Total cost unknown
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 339
Distribution © 2014, Innovative Management Solutions, LLC
Contracts and Procurement
Risk
Knowledge Area
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 342
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
Knowledge Area
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 344
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 345
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 346
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 347
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 348
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 349
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Communications
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 350
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Communications
Risk
Procurement
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 351
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 352
Distribution © 2014, Innovative Management Solutions, LLC
Incentive Contract
Example
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 361
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 362
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 363
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 364
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating
Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 365
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 366
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
HR
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 367
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 368
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning
Planning Executing Monitoring & Controlling Closing
Knowledge Area
Quality
HR
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 369
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
13.3 Manage Stakeholder
Integration
Engagement
Scope
13.3.1 Inputs
Time .1 Stakeholder Management Plan
Cost
.2 Communications Management Plan
.3 Change Log
Quality
.4 Organizational Process Assets
HR
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 370
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
13.3 Manage Stakeholder
Integration
Engagement
Scope
13.3.2 Tools & Techniques
Time .1 Communications Methods
Cost
.2 Interpersonal Skills: building trust, conflict
resolution, active listening, etc.
Quality .3 Management Skills: facilitation, negotiate
HR
agreements, etc.
Communications
Note the fine line between what the PMI
Risk considers interpersonal and management
skills
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 371
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing
Executing Monitoring & Controlling Closing
Knowledge Area
13.3 Manage Stakeholder
Integration
Engagement
Scope
13.3.3 Outputs (Figure 13-9)
Time .1 Issue Log
Cost
.2 Change Requests
.3 PM Plan Updates
Quality
.4 Project Documents Updates
HR .5 Organizational Process Assets Updates
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 372
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
13.4 Control Stakeholder
Integration
Engagement
Scope
13.4.1 Inputs
Time .1 PM Plan
Cost
.2 Issue Log
.3 Work Performance Data
Quality
.4 Project Documents
HR
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 373
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
13.4 Control Stakeholder
Integration
Engagement
Scope
13.4.2 Tools & Techniques
Time .1 Information Management Systems
Cost
.2 Expert Judgment
.3 Meetings
Quality
HR
Communications
Risk
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 374
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring &&Controlling
Monitoring Controlling Closing
Knowledge Area
13.4 Control Stakeholder
Integration
Engagement
Scope
13.4.3 Outputs (Figure 13-11)
Time .1 Work Performance Information:
Remember, work performance data is
Cost
transformed into work performance
Quality information
.2 Change Requests
HR
.3 PM Plan Updates
Communications .4 Project Documents Updates
Risk .5 Organizational Process Assets Updates
Procurement
Stakeholder
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 375
Distribution © 2014, Innovative Management Solutions, LLC
PMI-ism Break
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 379
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 380
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 381
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Communications
Risk
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 382
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 383
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration Responsibility
• Ownership of decisions we make or fail to make
Scope • Aspirational
– Based on the best interests of society, public safety and
Time environment
– Accept assignments consistent w/ our background, experience,
Cost skills and qualifications
– Fulfill commitments
Quality – Ownership of errors (early communication)
– Protect proprietary or confidential info
HR – Hold others accountable to Code
• Mandatory
Communications – Inform ourselves and uphold policies, rules, regulations and laws
that govern our work and volunteer activities
Risk – Report unethical or illegal conduct
– Bring violations of the Code to attention
Procurement – Only file complaints when substantiated by facts
– Pursue disciplinary action for retaliation
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 384
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration Respect
• High regard for self, others and resources entrusted to
Scope us
• Respect fosters trust, confidence, and mutual
Time
cooperation
Cost • Aspirational
– Inform selves of norms and customers of others and avoid
Quality disrespectful behavior
– List to others’ point of view
HR – Approach conflict or disagreement directly
– Professional, even when not reciprocated
Communications
• Mandatory
Risk – Negotiate in good faith
– Do not exercise power for personal benefit
Procurement – Do not act abusively
– Respect others’ property rights
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 385
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration Fairness
• Make decisions and act impartially and objectively
Scope • Aspirational
– Transparency in decision making
Time – Constantly reexamine ourselves and make corrective action
– Provide equal access to information to those authorized
Cost – Make opportunities equally available to qualified candidates
• Mandatory
Quality
– Proactively disclose conflicts of interests
– Refrain from decision making process or influencing outcomes if
HR there is a potential conflict of interest
– Do not hire/fire, reward/punish, award/deny contracts based on
Communications personal considerations (favoritism, nepotism, bribery)
– Do not discriminate (gender, race, age, religion, disability, etc…)
Risk – Apply the rules of the organization (employer, PMI or other group)
without favoritism or prejudice
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 386
Distribution © 2014, Innovative Management Solutions, LLC
Process Group Initiating Planning Executing Monitoring & Controlling Closing
Knowledge Area
Integration Honesty
• Duty to understand the truth and act truthfully
Scope
• Aspirational
Time
– Earnestly seek to understand the truth
– Truthful in communications and conduct
Cost – Provide accurate info in a timely manner
– Make commitments or promises in good faith (implied or
Quality explicit)
– Create an environment that others feel safe to tell the truth
HR • Mandatory
– Do not engage in behavior that is designed to deceive
Communications
others (false statements, half-truths, provide info out of
context, etc…)
Risk
– Do not engage in dishonest behavior w/ the intent of
personal gain or expense of others
Procurement
Stakeholder Student Copy – Not for Reproduction or Chuck Millhollan, MBA, MPM, PMP, PgMP 387
Distribution © 2014, Innovative Management Solutions, LLC
Practice Test Time!