PEKERJAAN REVITALISASI PASAR RAKYAT KLEWER (Lanjutan)

LOKASI : SURAKARTA
ID Task Name Duration M1 M2 M3 M4 M5 M6 M7 M8 M9
W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40
1 PEKERJAAN REVITALISASI PASAR RAKYAT KLEWER (Lanjutan) 255 days
2 Start 0 days
3 PEKERJAAN PERSIAPAN 2 days
4 Uitzet dan bouwplank 2 days
5 PEKERJAAN SIPIL 82 days
6 PEKERJAAN BONGKARAN 14 days
7 Pekerjaan bongkaran secant pile 7 days
8 Pekerjaan bongkaran pilecap secant pile 7 days
9 PEKERJAAN TANAH & PASIR 66 days
10 Galian tanah biasa basement menggunakan alat 3 days
11 Galian tanah keras basement menggunakan alat 3 days
12 Dewatering galian tanah basement 60 days
13 Galian tanah keras pile cap (dibuang keluar lokasi) 7 days
14 Urugan pasir bawah pile cap 7 days
15 Urugan pasir bawah plat basement 7 days
16 PEKERJAAN PONDASI 38 days
17 Mob de mob alat bor 2 days
18 Bored Pile Ø 80,L=10 m,K-250 dengan tulangan 3 days
19 Secant Pile Ø 60,L=14 m,K-250 dengan tulangan 7 days
20 Secant Pile Ø 60,L=14 m,K-250 tanpa tulangan 7 days
21 PDA Test 1 day
22 PEKERJAAN STRUKTUR 115 days
23 STRUKTUR LANTAI BASEMENT (ELV -06.00) 21 days
24 Lantai kerja K-100,t=5 cm bawah pilecap 7 days
25 Pile cap P1 (150x150) 7 days
26 Pile cap Secant pile (150x80) 7 days
27 Plat lantai elv. -6.00, t= 50 cm 7 days
28 Kolom K2 (70x70) 7 days
29 Integral waterproofing 7 days
30 STRUKTUR LANTAI BASEMENT (ELV -05.00) 21 days
31 Lantai kerja K-100,t=5 cm bawah pilecap 7 days
32 Pile cap P3 (360x160) 7 days
33 Pile cap PL (pile cap lift) (1160x400) 7 days
34 Plat lantai elv. -5.00, t= 50 cm 7 days
35 Kolom K1 (70x70) 7 days
36 Integral waterproofing 7 days
37 STRUKTUR LANTAI SEMI BASEMENT (ELV. -02.50) 14 days
38 Beam Elv.-2.50 7 days
39 Plat lantai elv. -02.50, t= 15 cm 7 days
40 Kolom K3 (70x70) 7 days
41 STRUKTUR LANTAI SEMI BASEMENT (ELV. -01.50) 14 days
42 Beam Elv.-1.50 7 days
43 Plat lantai elv. -1,5.00, t= 15 cm 7 days
44 Kolom K2 (70x70) 7 days
45 Rabat beton penutup pasar barat - pasar timur 7 days
46 STRUKTUR LANTAI 1 (ELV. +3.50) 14 days

Task Project Summary Manual Task Start-only Deadline Manual Progress

Project: Pasar Klewer Solo Split Inactive Task Duration-only Finish-only Critical

Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Page 1
PEKERJAAN REVITALISASI PASAR RAKYAT KLEWER (Lanjutan)
LOKASI : SURAKARTA
ID Task Name Duration M1 M2 M3 M4 M5 M6 M7 M8 M9
W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40
47 Beam Elv.+3.50 7 days
48 Plat lantai elv. +3.50, t= 15 cm 7 days
49 Kolom (70x70) 7 days
50 STRUKTUR LANTAI 2 (ELV. +8.50) 14 days
51 Beam Elv. +8.50 7 days
52 Plat lantai elv. +8.50, t= 15 cm 7 days
53 Kolom K3 (70x70) 7 days
54 STRUKTUR LANTAI ATAP (ELV. +13.50) 14 days
55 Beam Elv. +13.50 7 days
56 Plat lantai elv. +13.50, t= 12 cm 7 days
57 Kolom K4 (70x70) 7 days
58 STRUKTUR LANTAI ATAP (ELV. +15.00) 10 days
59 Ringbalk BR (40x65) Elv. +15.00 10 days
60 STRUKTUR TANGGA 28 days
61 TANGGA Basement 7 days
62 TANGGA Lantai 1 7 days
63 TANGGA Lantai 2 7 days
64 TANGGA Atap 7 days
65 STRUKTUR RAMP 42 days
66 RAMP DROP OFF 21 days
67 RAMP GEROBAK 21 days
68 STRUKTUR LIFT 21 days
69 PEKERJAAN ATAP 14 days
70 PEKERJAAN ARSITEKTUR 129 days
71 PEKERJAAN PASANGAN DAN PLESTERAN 67 days
72 LANTAI BASEMENT ELV. -5.00 & ELV. -3.50 15 days
73 LANTAI SEMI BASEMENT ELV. -1.50 & ELV. +0.00 15 days
74 LANTAI 1 ELV. +3.50 15 days
75 LANTAI 2 ELV. +8.50 15 days
76 LANTAI ATAP DAK ELV. +13.50 7 days
77 PEKERJAAN KUSEN, DAUN PINTU, JENDELA DAN KACA 67 days
78 LANTAI BASEMENT ELV. -5.00 & ELV. -3.50 15 days
79 LANTAI SEMI BASEMENT ELV. -1.50 & ELV. +0.00 15 days
80 LANTAI 1 ELV. +3.50 15 days
81 LANTAI 2 ELV. +8.50 15 days
82 LANTAI ATAP DAK ELV. +13.50 7 days
83 PEKERJAAN PENUTUP LANTAI & DINDING 61 days
84 LANTAI BASEMENT ELV. -5.00 & ELV. -3.50 7 days
85 LANTAI SEMI BASEMENT ELV. -1.50 & ELV. +0.00 7 days
86 LANTAI 1 ELV. +3.50 7 days
87 LANTAI 2 ELV. +8.50 7 days
88 LANTAI ATAP DAK ELV. +13.50 7 days
89 PEKERJAAN PLAFON 52 days
90 LANTAI BASEMENT ELV. -5.00 & ELV. -3.50 7 days
91 LANTAI SEMI BASEMENT ELV. -1.50 & ELV. +0.00 7 days
92 LANTAI 1 ELV. +3.50 7 days

Task Project Summary Manual Task Start-only Deadline Manual Progress

Project: Pasar Klewer Solo Split Inactive Task Duration-only Finish-only Critical

Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Page 2
PEKERJAAN REVITALISASI PASAR RAKYAT KLEWER (Lanjutan)
LOKASI : SURAKARTA
ID Task Name Duration M1 M2 M3 M4 M5 M6 M7 M8 M9
W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40
93 LANTAI 2 ELV. +8.50 7 days
94 PEKERJAAN SANITAIR 47 days
95 LANTAI BASEMENT ELV. -5.00 & ELV. -3.50 2 days
96 LANTAI SEMI BASEMENT ELV. -1.50 & ELV. +0.00 2 days
97 LANTAI 1 ELV. +3.50 2 days
98 LANTAI 2 ELV. +8.50 2 days
99 PEKERJAAN FINISHING 35 days
100 LANTAI BASEMENT ELV. -5.00 & ELV. -3.50 7 days
101 LANTAI SEMI BASEMENT ELV. -1.50 & ELV. +0.00 7 days
102 LANTAI 1 ELV. +3.50 7 days
103 LANTAI 2 ELV. +8.50 7 days
104 LANTAI DAK ELV. +13.50 7 days
105 PEKERJAAN RUMAH GENSET 30 days
106 PEKERJAAN ELEKTRIKAL DAN MEKANIKAL 129 days
107 PEKERJAAN ELEKTRIKAL 94 days
108 PEKERJAAN TRANSFORMATOR 94 days
109 PEKERJAAN INSTALASI GENSET 94 days
110 PEKERJAAN PANEL LISTRIK 94 days
111 PEKERJAAN KABEL FEEDER 94 days
112 PEKERJAAN INSTALASI LISTRIK 94 days
113 PEKERJAAN PENANGKAL PETIR 2 days
114 PEKERJAAN ELEKTRONIKA 94 days
115 PEKERJAAN TELEPON 94 days
116 PERALATAN UTAMA TELEPON 94 days
117 PEKERJAAN PLUMBING 94 days
118 PEKERJAAN AIR BERSIH 94 days
119 PEKERJAAN AIR KOTOR & BEKAS 94 days
120 PEKERJAAN AIR HUJAN 94 days
121 PEKERJAAN HYDRANT 94 days
122 PEKERJAAN EXHAUST FAN 94 days
123 PEKERJAAN ESCALATOR 120 days
124 Pengadaan Escalator 30 days
125 Pemasangan Escalator 90 days
126 Finish 1 day

Task Project Summary Manual Task Start-only Deadline Manual Progress

Project: Pasar Klewer Solo Split Inactive Task Duration-only Finish-only Critical

Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Page 3