Professional Documents
Culture Documents
Method Statement Installation of Generator
Method Statement Installation of Generator
PROJECT TITLE:
Document no.:
DOC TITLE: METHOD STATEMENT
Submittal ref:
METHOD STATEMENT
INSTALLATION OF GENERATOR
FOR
00 Signature: Signature: Signature:
APPROVAL
PROJECT TITLE:
Document no.:
DOC TITLE: METHOD STATEMENT
Submittal ref:
CONTENT
1. SCOPE/OBJECTIVE
2. REFERENCE S/ DOCUMENTATION
3. RESPONSIBLE/SUPERVISION
5. PROCEDURE
7. QUALITY CONTROL
8. ATTACHMENT
CLIENT: CONSULTANT: CONTRACTOR:
PROJECT TITLE:
Document no.:
DOC TITLE: METHOD STATEMENT
Submittal ref:
2.0 REFERENCES/DOCUMENTATION
2.1 Electrical Contract Specification
2.2 Approved Shop drawings/Manufacturer’s drawings/ Schematic Diagram
2.3 Approved material submittal
3.0 RESPONSIBILITY/SUPERVISION
3.1 Construction Manager
3.1.1 Is responsible for ensuring that all works are carried out as per the specifications,
drawing/shop drawings and method statement as per the manufacturer instructions,
coordinated with other works and will plan for the required labors and tools for all activities.
3.2 Site Engineer
3.2.1 Ensure the supervisor is aware of lighting foundations, lighting poles, lighting fittings,
accessories and cable installation procedures & splicing procedures.
3.2.2 Check periodically that the job executed is safely and following the standards installation
procedures.
3.2.3 Ensure that the installation complies with the approved shop drawings and specifications.
3.2.4 Maintain records of work done and submit the progress report to the authorities concerned.
3.2.5 Follow the ITP procedures and coordinate with the QA/QC team for inspection
3.3 Supervisor
3.3.1 Will be directly responsible for the day to day job in the site and handling technicians and
other labors assigned to his area. Supervisor will be reporting to Project Engineer.
b. Fire Precautions
General fire precautions will be maintained in the site as per the approved safety procedure .
c. Communication
CLIENT: CONSULTANT: CONTRACTOR:
PROJECT TITLE:
Document no.:
DOC TITLE: METHOD STATEMENT
Submittal ref:
Communication will be carried out in accordance with safety procedures and reporting all
issues in the site.
5.2.1 When lift or hoist equipment used to lift the generator and move it to position, be careful
not to contact overhead wires or other obstacles. Used proper lift equipment and
methods to avoid injury. Lift only by tubular metal frame.
5.2.2 Make sure the lifting equipment will be using has sufficient capacity to handle the
weight of the generator.
5.2.3 Set the generator onto concrete foundation pad secure the base frame of the generator
to the pad with bolts or other fastener.
5.2.4 The generator to be grounding lug on the base frame and to approved earth ground or
grounding rod as specified local regulations.
5.2.5 Mount the Generator on a concrete slab capable of supporting the weight of the
Generator. The slab must extend on all sides beyond the Frame by at least one foot.
Contact a cement contractor for slab specifications if necessary.
CLIENT: CONSULTANT: CONTRACTOR:
PROJECT TITLE:
Document no.:
DOC TITLE: METHOD STATEMENT
Submittal ref:
5.3 INSPECTION
5.3.1 Submit request for inspection to ensure conformance of the installation work.
5.3.2 Carry out inspection by consultant and obtain their approval in the prescribed Format.
5.3.3 Provide maintenance manual to the engine and generator set as described in the
engine and generator maintenance section in accordance to manual maintenance
5.3.4 After installation check must be performed prior to starting engine. Monthly/Weekly
Maintenance to be performed and the system operation are verified to be good.
5.3.5 Refer to product maintenance manual for periodic checks that must be performed at
schedule intervals to ensure continued operation with minimal problems.
8.0 ATTACHEMENT
8.1 Approved Site Clearance
8.2 Risk Assessment Form