YASH ASSOCIATES

CONCRETE POUR CARD


PROJECT:- LOCATION:- DATE:-
GRID LEVEL FLOOR POUR NO:-
DRAWING REFERENCE
STRUCTURE:- SLAB / COLUMN / WALL / OTHER DESCRIBE:-
CONCRETE GRADE:- START TIME:- EXPECTED END TIME:-
ADMIXTURE:- YES / NO CONCRETE QUANTITY:-
CONSTRUCTION JOINT LOCATION:-
NO. DESCRIPTION REQUIRED ACTUAL TOLERANCE REMARKS
A REINFORCEMENT
1 Cover ± 5mm - 2mm
2 Cleaning NIL
3 Spacing ± 10mm
4 Main reinforcement
5 Distribution steel
6 Anchorage Length ± 10 mm
7 Laps Dimention
8 Chairs
9 Strippus
10 Spacers
Any other extra
11
reinforcement
B FORM WORK
1 Shuttering Material
Level- Slab / Beam
2
Bottom
Beam / Column
3
Diamention
4 Chember / Slope
5 Electrical Inserts
6 Plumbing Inserts
7 Cutouts
± 5mm in
8 Length / Height
±3000mm
5mm in
9 Width / Thickness
3000mm
10 Plumbing Inserts
Tierod / Props / Support ± 5mm in
11
as per approval 3000mm
C LINES AND LEVELS
1 Top of Concrete Level ± 3mm
2 Top of Shutter Level ± 3mm

Contractors Representative
Contractor's / Engineer
Development Projects
Area
Beam Bottom 2 7.5 0.5 7.5
1 5.5 0.5 2.75
1 5 0.5 2.5
1 11.5 0.5 5.75
3 5.5 0.5 8.25
Puzzale 1 10 5.5 55
1 7.7 5.5 42.35
Puzzale 2 7.7 5.5 84.7
208.8 Sqm
Material Rent
2 Month Rent Rate Month Amount
Vertical 3.0 m 436 70 2 61040
Vertical 2.0 m 108 50 2 10800
Vertical 2.5 m 110 60 2 13200
Joint Pin 326 11.25 2 7335
Base Plate 218 25 2 10900
U Jack 218 25 2 10900
Ledger 1.2 m 1504 25 2 75200
Ledger 1.0 m 312 20.25 2 12636
202011 Rent
Labour
Area 209 Sqm
2247 Sqf 85 190968.5 Labour

Total Amount
202011 Rent
190968.5 Labour
Total Amount 392979.5

Total Shuttering of 9.6 ht Slab 350.558 Sqm

Rate per Sqm Labour & Cuplock Material Excluding Shuttering Material
392979.5/350.338 1121.011 per Sqm