Professional Documents
Culture Documents
Calculating The Cash Flow For A Project
Calculating The Cash Flow For A Project
Calculating The Cash Flow For A Project
for a Project
Introduction
This example of the calculation of the cash flow for a small construction project
is based on a similar example to show how, based on initial value data, the maxi-
mum amount of cash required to complete the work may be calculated. For sim-
plicity and ease of understanding, a number of assumptions have been made when
undertaking the calculations. The data used to represent the calculations of cost
and value are purely illustrative and not representative of the true costs and value
of actual construction work.
Chapter 4 indicates that the following data are required to calculate the cash flow
for a project:
■
a graph of contract value against time;
■
a graph of contract cost against time;
■
the measurement and certification interval;
A Handbook for Construction Planning and Scheduling, First Edition. Andrew Baldwin and David Bordoli.
© 2014 John Wiley & Sons, Ltd. Published 2014 by John Wiley & Sons, Ltd.
■
the delay in payment between certification and the contractor receiving the
cash;
■
the retention conditions and repayment arrangements;
■
the project costs broken down into labour, plant, materials and subcontractor
categories and
■
the terms of payment for the cost of the resources used.
Each of these is now discussed.
In this example, it is assumed that the total value of the construction work is
£54,000. (This value is calculated from the bid rates and quantities in the Bill of
Quantities document.)
The value of the work for each month of the project is shown in Table 1 together
with the profit margin covering all overheads is shown as a percent of value for
each month of the project. (It is assumed that the profit margin varies with the
type of construction work.)
The project costs broken down into labour, plant, materials and subcontractor categories
In practice, the activity costs will probably comprise labour, plant, materials and
subcontractor costs. It is important to know the build up of these costs because
the payment terms for each type of resource may vary. In this example, it has been
assumed that all costs are subcontractor costs.