Work Progress

Expected date
Current status % Reason for delay
Sno Description Est. End Date to start work
Work completed No
1 BASEMENT Manpower
a 4th may , until final lift
RCC wall Waterproofing 25% 1 In progress On site situation
Area shuttering gets off
b Waterproofing material + cement slurry in
90% 24-4-2019 1 In progress On site situation
Area b/w the agra stone and brickwall.
C
Shuttering IInd lift 20% 24-04-2019 6 24-04-2019 Manpower shortage
Area
d
Casting 25-04-2019 25-04-2020 Manpower shortage
Area
2 COMMON PASSAGE
a Dismantling of Obstructions in the passage Because of security
30% 2 In progress Non Scheduled
Area connectivity of new and old house issue
b
Area
c
Area
d
Area
e
Area
f
Area
g
Area
h
Area
i
Area