Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

The Evaluation of Vertical-Lift Performance in

Producing Wells
R. V. McAFEE AXELSON·GARRETT DIY. OF U. S. INDUSTRIES, INC.
MEMBER AIME HOUSTON, TEX.

ABSTRACT produced with gas-well gas. Today, the majority are


produced by closed rotative gas-lift systems. This per-
The fundamentals of vertical-lift performance are mits a direct evaluation of well performance in terms
examined with the aid of computer-calculated flowing of horsepower requirements and has resulted in mixed
gradient charts. conclusions as to the success of gas lift based upon the
Flowing and gas-lift well performance characteristics relative efficiency of a particular system. An increased
are determined from available well test data. The effect awareness of the need to resolve vertical-lift perform-
of tubing size, gas-liquid ratio and wellhead pressure is ance on a readily usable, scientific basis was inevitable.
discussed for both flowing and gas-lift wells. The effect An indication of the need for better applied science
of gas-injection pressure, formation gas, bottom-hole in this field is the often-asked question of whether or
pressure and valve spacing is also discussed for gas lift not gas-lift can efficiently deplete a given well or reser-
wells. From these studies conclusions may be reached voir. This question cannot possibly be answered without
for improving or prolonging natural flow, obtaining first evaluating reservoir, surface and vertical-lift per-
optimum lift efficiency when natural flow ceases and formance both as encountered today and as anticipated
improving existing gas-lift systems. throughout the life of the well or wells.
The techniques perfected satisfy the requirement that The technique presented in this paper was originally
the time involved to conduct an evaluation be practical developed to upgrade gas-lift installation design from
for operating personnel. an applied art to an applied science. It has since been
successfully used not only for this purpose, but also for
INTRODUCTION the whole field of vertical-lift performance in its broad-
est sense. Lift efficiency should be considered important
Flowing pressure gradients furnish the key to success- while the well is still flowing, as well as after natural
ful evaluation of vertical-lift performance in producing flow ceases. Correct interpretation and proper modifica-
wells. tion of the vertical-lift performance of a producing well
Command of mUltiphase flow gradients in some can provide dramatic improvement in production per-
readily usable form is a necessity before operating formance and/or efficiency.
personnel can competently include vertical-lift perform-
ance evaluation of both flowing and artificial-lift wells STATEMENT OF THEORY AND DEFINITIONS
in their over-all consideration of production efficiency.
A readily usable form cannot be overemphasized since Fig. 1 illustrates the three divisions of production
most of the decisions which confront the production which will be used in this paper.
engineer with a problem well must be made quickly. The terms are a modified version of those presented
In moving a barrel of oil from the reservoir to the in the very fine paper by Gilbert.' The fields of reser-
stock tank, the major portion of energy generally is voir and surface performance both have been greatly
expended in the vertical-lift phase. This mayor may improved over the years. A study of those writings
not be of concern during the flowing life of a well, which may be found indicates that the field of vertical-
depending upon the production requirements. It be- lift performance has not progressed as well. There are
comes of some concern when the flow performance of two possible reasons for this lack of progress.
the well becomes erratic, and a conscious effort must 1. It has not been recognized as a scientific field in
be made to maintain natural flow. It is at this time that itself by the oil companies, as has reservoir engineering.
the first steps may be taken to modify existing conditions 2. The equipment companies have confined their ef-
to relieve unnecessary limitations to proper flow. forts to mechanical design research rather than the more
When natural flow ceases and some form of artificial basic study of vertical-lift performance of producing
lift must be installed, the amount of energy expended wells.
in lifting liquids becomes quite obvious. It is at this Both organizations must have an economic stimulus
time, if no other, that lifting efficiency becomes im- for doing research in this field, and most of the results
portant because that part which must be supplied from obtained in past work has been so erratic as to arouse
an outside source is now related directly as a cost per little enthusiasm.
barrel of oil produced. The basic purpose of interpreting vertical-lift per-
Ten years ago, the majority of gas-lift wells were formance is to predict operating conditions below the
surface of the ground from available data. The success
Original manuscript received in Society of Petroleum Engineers
office Sept. 12, 1960. Revised manuscript received Jan. 30, 1961. of the interpretation depends upon the accuracy with
Paper presented at 35th Annual Fall Meeting of SPE, Oct. 2-5,
1960, in Denver. 'References given at end of paper.
SPE 1557-G
390 JOURNAL OF PETROLEUM TECHNOLOGY
40

t-
) - - - - - SURFACE PERFORMANCE - - - - - - - ' 32~
~
r.:z
w
24S! 2" TBG.
n: 800 BLPD
l?
0.195 PSI./FT.
RTICAL LIFT PERFORMANCE

.08

) - - - - - RESERVOIR PERFORMANCE----_,.
PROOUCTION. BLPD
400 800 1200 1600

FIG. I-THE THREE PHASES OF PRODUCTION.


FIG. 2-PSI/FT GRADIENT CHART.

which the pressure gradient of the producing well can


be predicted. The gas-lift industry elected to express
this interpretation as a linear gradient for a given tubing
size and rate of liquid flow, as shown in Fig. 2. Un-
fortunately, this is a completely invalid concept.
Fig. 3 shows the true nature of the gradients which
exist in vertical flow. The gradient line marked "Liquid-
STATIC
Static" is a straight line since it is all liquid and may
be expressed as a linear gradient in psi/ft. The lin~
FLOWI~:::;

FLOWI~G

marked "Liquid-Flowing" is also a straight line since


it too is all liquid. It differs from the static gradient
because the liquid is in motion and flow resistance in- 4000 2 Mer6

Creases the pressure drop per unit of length. This


gradient would ocur in artesian flow. It may also be 800
PRESSURE. PSI<>.

expressed as a linear gradient in psi/ft.


A radical change takes place when gas is present with
the liquid in the vertical column. This is shown in Fig. FIG. 3-ILLUSTRATION OF VARIOUS GRADIENTS.

3 as "Liquid and Gas-Flowing". The pressure gradient It should also be noted that the viscosity was not
becomes less because of the presence of the gas. The
considered to be of influence on the pressure gradient.
gradient is no longer a straight line because the fluid is
now a compressible mixture and the density increases It was evident that an attempt should be made to
with the increased pressure at increasing depths in the resolve the mathematics to a language common to
well. The latter is the key to all proper thinking with standard oilfield data, and to fewer significant variables.
respect to flowing gradients. Gilbert' stated in his paper that " ... there is a different
depth pressure gradient for each size of pipe, each rate
A final pOint to be made is that the amount of gas
of liquid flow, and each gas-liquid ratio". In a footnote
?er volume of liquid determines the density; variations he further stated that, "Gradients presumably are also
IJ?- gas volume per volume of liquid will vary the den- affected by many other factors including liquid surface
SIty and, therefore, the flowing gradient. Thus, it can
tension, viscosity and gravity, flowing temperatures, gas
be seen that, at a given rate of liquid flow and other gravity and gas-liquid solubilities".
constant conditions, there must be a different depth-
pressure gradient for each gas-liquid ratio. "However, there is a reasonably close correspondence
between results which have been obtained in the light-
Recognizing this to be true places a responsibility
oil (~5° to 40 0 API) fields of Long Beach, Santa Fe,
~pon the individual to then seek a practical method of
Dommguez, Ventura, Canal and Ten Section and sev-
Interpreting gradients in their true form as a curve and eral foreign fields without adjusting for such factors.
asa function of the volume of gas per volume of liquid.
Also, it has not been found necessary to correct gradients
~he ~ost commonly accepted mathematical interpreta-
for water cuts. However, the gradients are inadquate to
tron IS that presented in the excellent paper by Poett-
predict the effects of emulsions."
mann and Carpenter.' Use of their mathematics was
f~)Und to give an acceptable accuracy; however, it was
Using this philosophy, the listed variables of Poett-
tIme-consuming because the following 12 variables mann and Carpenter were evaluated and the following
were taken into consideration for each calculation: was determined.
tubing size, rate of liquid flow, gas-liquid ratio, flowing 1. Liquid gravity, gas gravity and average flowing
wellhead pressure, liquid composition, flowing friction temperature could be fixed as a field constant without
factor, .compressibility factor of gas, gas-liquid solubility, impairing the accuracy of the calculations from a prac-
formatIon volume factor, average flowing temperature, tical-use standpoint.
gas gravity, and liquid gravity. 2. The formation volume factor and gas-liquid solu-

APRIL, 1961 391


bility are significant variables when oil is the liquid, but r-~APH BASIS-- '-'- --r~' --
GAS SPECIfiC GRAVITV • 0,65
V L L
not when water is the liquid. These variables were taken ..00 r-- 2.1. OIL A.P.1. GRAVITY - 32- A.P.I.-
3. AVERAGE FLOWING TEMP. - !!l0· F.
/ V V
into consideration in the oil calculations. 2400

3. The flowing friction factor and the compressibility 2200 / V /


./
factor of gas are both significant, but they can be re- 2000
i,,-!>
~""g,V
/ / / /
solved at a given moment in the calculation. ~
~~'Ij / V / V ~
1800
\..>~~
4. The liquid composition is significant in the high 1600 - .~ " .. oj' oV <j ~ o~V oJ/'
flowing density range (low gas-liquid ratio) but becomes 1"00
w
§ / V L / /' / ' o~ ~
less significant as the flowing density decreases. 1200 ~ / V / / V ,/' k::: ~ ¢if" ,.'
5. Tubing size, rate of liquid flow, gas-liquid ratio 1000 W
~
z / V 1/ V / ' V b:& ~ I""
and flowing wellhead pressure are significant and must 800
~
~ / / V / 'V ~ ;;;¢ 1P
be considered individually with each problem. / / / ~~~
600

The mathematics then could be resolved to four 400 L / L.-::::;; ~ ~


significant variables and plotted in a charted form for V ~P APPENDIX B -67
BI0-~.371" T~BINI-
direct use. 2 ~oo 2000 3000 4000
WELL DEPTH
~OOO
IN FEET
6000
8f<'
7000 8000 9000

An electronic computer program was set up to run


FIG. 5-FLOWING PRESSURE GRADIENTS AT VARIOUS GAs-LIQUID
the necessary calculations, and master charts were RA TIOS-OIL.
plotted as a pressure-depth relationship for tubing sizes
of 1, 11;4, 1V2, 2, 2V2, 3 and 4-in.; rates of liquid flow This is of much greater importance than single pressure
from 50 to 10,000 B/D of liquid as applicable for each readings because a single reading does not provide an
tubing size; and gas-liquid ratios from 0.0 to 4.0 opportunity to determine the cause of any error. Usually,
Mcf/bbl. One complete set was plotted for 1.074 specific the pressure bomb reading and well test data are ac-
gravity water, and another for 32° API oil. cepted as accurate and the calculated approach in ques-
The calculations were run to a pressure of 4,000 psig. tion.
The published charts' are plotted to 2,800 psig. A set Fig. 6 shows one of the many "picture-book" correla-
of charts plotted to 4,000 psig will be available, as will tions that have been made. The curvature of both flow-
a set for 1~ -in. nominal tubing size. An example of ing gradients is apparent, and the gradient lines drawn
the water and oil charts are shown in Figs. 4 and 5. are the actual curves from the master charts for the
corresponding tubing size and gas-liquid ratio using
ACCURACY OF THE CURVES the 600 BID of liquid water chart.
Fig. 7 shows a correlation which required an inter-
The original accuracy checks run against the curves polation for gas-liquid ratio both above and below the
were based upon flowing bottom-hole pressures and point of gas injection. Again, the multi-point correla-
related test data which permitted a flowing bottom- tion is invaluable in determining the validity of the
hole pressure correlation from the charts. It was found curves. This figure can be used to demonstrate the
that the average error over all the checks made was stated weakness in single-point correlations. If all con-
3.87 per cent. However, it should be pointed out that ditions remained the same except that the formation
these checks were subject to the usual errors found gas-liquid ratio had been estimated or calculated to be
in the measurement of gas (or reading thereof), meas- 0.10 Mcf/bbl rather than the actual 0.066 Mcf/bbl,
urement of water production involved and measurement the error at 6,000 ft would have been 100 psig in 2,600
of flowing wellhead pressure. These three variables are psig, or 3.85 per cent. The average error for single-
each significant and subject a chart interpretation to point correlations was 3.87 per cent.
apparent error if any are, in themselves, in error. This
is not intended to challenge testing practices so much ADJUSTING FOR WELLHEAD PRESSURE
as it is to point out the inherent weakness in single-point
correlations. The most important checks that have been The method of adjusting for wellhead pressure IS
made are those that permit a mUlti-point correlation shown in Fig. 8. "A" and "B" represent two pressure
from the top to the bottom of a well. It is here that the gradients which have the same tubing size, rate of liquid
actual slope of the pressure gradient can be correlated. flow and gas-liquid ratio. The fourth significant variable,
wellhead pressure, requires an adjustment before a
GRAPH BASIS
I. GAS SP[CIFIC GRAVITY - 0.15 V / V / /
2600 t--- 2; • •Anlt SP[CIFIC GRAVITY· 1.014

2400
3. AVE""G! FLOWING TEMP. -150·f.
V / V / / 2000

2~O
/ / / / / /
2000
I,,-!>.
(to......,
..'" / / / / V 11
2.5 TBG.
~
~~Q~ 00/ o~.;/ ~/ oY
,/ 1600
608 BLPD
1'00 r ~\v.f
o)' oY o'
<3 0.05 "'(FB FORMATION GAS
V / 1.1" ~ ./ ~ g;
1000

1400§
.
!
w
~ . . *'
V / / /
/
/ V
/'
/ ' 1-0V ~ t200~~
0.40

o
MCFB

PRESSURE
PRODUCED GAS

BOMB SURVEY
:~-OOS MCFB
,/ ,/
/ ' ~ 8;;; ~
:::>
1200 .. / / / / if)

:3a:
/ 1/ / ~ ~ F""
~
z ./ /' /" n.
lOOOi
.00 co / / / / ~ v-: ~ ~ 800

600 J / V ~ ~ ~ F"'"
400
V 1,,('/ k::;,; tIi¢ ~ 400
/~ ~ ~ APPENDIX B-23
800 BPO- 2.375" TUBING-
- - - O A O MCFB

Z~~ 2000 .000 4000


WE1.l0
.000
DEPTH iN FEET
1000 7000 ! ac100 ~ 9~OO 1 1000 2000 3000
DEPTH. FT.
4000 5000 6000 7000
FIC. 4--FLOWING PRESSURE GRADIENTS AT VARIOUS GAs-LIQUID
RATIOS-WATER. FIG. 6-CORRELATING PRESSURE SURVEYS.

392 JOURNAL OF PETROLEUM TECHNOLOGY


correlation can be achieved. The correlation must be decrease in flowing bottom-hole pressure would normally
made along constant pressure planes. This is related result in an increase in production rate. This increase in
to the flowing density of the fluid. The section of rate might be considered the source of an offsetting in-
Gradient B from 300 psig to the surface has no correla- crease in flowing bottom-hole pressure. However, so
tive counterpart in Gradient A. The section of Gradient long as the change in rate occurs between the extremes
A from 1,600 psig to depth also has no correlative of friction and slippage, no appreciable change in pres-
counterpart in Gradient B. sure gradient would occur at the increased rate at a
The remaining sections of the two gradients can be given gas-liquid ratio.
correlated by shifting one laterally to the other. This For example, with a P.I. of 1.0 B/D of liquid/psi, the
procedure applies to all wellhead pressure adjustments well in Fig. 9 would produce 330 BID of liquid more,
made on the master charts. These charts are designed or a total of 930 BID of liquid, at the decreased flow-
for direct overlay with a graph work sheet, and all ing bottom-hole pressure if no change occurred in the
pressure adjustments are made by lateral shifting of the characteristic of the flowing gradient. Fig. 10 shows a
work sheet keeping the abscissas aligned. Having made plot of inflow performance against tubing intake per-
the pressure adjustment, the desired segment of the pres- formance for 160 psi and 60 psig. The well would
sure gradient is traced directly upon the work sheet. actually produce 890 BID of liquid at the reduced well-
head pressure. The example is based upon a constant
EVALUATION OF FLOWING WELL gas-liquid ratio.
PERFORMANCE One particular production decline characteristic is
pointed out since it is related to changes in gas-liquid
The effect of wellhead pressure upon flowing bottom- ratio in the vertical column. Fig. 11 shows the progres-
hole pressure is shown in Fig. 9. When the pressure sive deterioration of well performance brought about
is lowered 100 psig at the surface, the flowing bottom- by a change in water-oil ratio. None of the other con-
hole pressure is reduced 330 psig. Again, this relates ditions is allowed to vary. The change is not the presence
directly to flowing density and the over-all change in of the heavier liquid but, rather, the change in total gas-
slope characteristic of the pressure gradient at the lower liquid ratio as the produced gas declines with oil pro-
wellhead pressure. It should be noted that this evaluation duction. This is based on produced gas being solution
is made at a constant rate of flow. In the field, any gas only. To ensure a true relation to change in gas-
liquid ratio, the 100 per cent water chart was used for
all curves and no water-oil interpolation was made. The
2400
comparison including the water-oil interpolation would

2000
2000

[, PWH = 160 - 60 = 100 PSIG

1600 ['PBHF =2130 - 1800 = 330 PSIG.


1600
<5 <5
~ iii
0..

1200";
a: o PRESSvRE BOMB SURVEY 1200~~
::J ::J
<f) <f)
<f) <f)
w w
a: a:
0.. 0..
800 2.5" TBG. 800
1438 BLPD
0.158 MCFB PRODUCED GAS
0.092 MCFB INJECTED GAS
0.066 MCFB FORMATION GAS
MCFB
MCFB
MCFB
2" TBG.
DEPTH. Fl. DEPTH, FT.
1000 2000 a 0 4000 5000 6000 7000 2000 3000 4000 5000 6000 7000

FIG. 7 - CORRELATION OF A PRESSURE SURVEY REQUIRING AN FIG. 9-EFFECT OF WELLHEAD PRESSURE UPON FLOWING
INTERPOLATION FOR THE MEASURED GAs-LIQUID RATIO. BOTTOM-HOLE PRESSURE.

2000
2800

<5
~ TBG BLPD MeFB PWH
A. 2" 800 06 300 0
1200~£ B. 2" 800 0.6 100 0 /

0~0
::J
<f)
<f)
w
8:
800
A/ B/0

400 ..-/-~0_/_.~~
C>""'----."....,~--~---- ----.-.-
1600
0.2 MCFB
NO CORRELATION
11...::::::.----20
- - 3000DEPTH;Jclb BLPD
00 6000 7000 200 400 600 800

FIG. 8- CORRELATIONOF Two PRESSURE SURVEYS SHOWING FIG. 10---PLOT OF 2.0-IN. TUBING PERFORMANCE
METHOD OF ADJUSTING FOR WELLHEAD PRESSURE. AT 6,500 FT VS INFLOW PERFORMANCE OF WELL.

APRIL, 1961 393


show the decline to be even more pronounced. Unless tained before cessation of natural flow, and the infoI'·
gas-liquid ratio is considered in vertical-lift performance mation obtained was used to design a proper gas-lift
evaluations, this occurrence would be overlooked. installation for re-starting and supplementing natural
The method of obtaining a P.I. from a given static flow.
bottom-hole pressure and well test data is shown in There is another method of using the charts when
Fig. 12. The technique is used when a static bottom- a flowing bottom-hole pressure reading is all that is
hole pressure and well test information is all that is needed. Instead of using a graph work sheet, the pres-
available. It is also used to check the results of a flow- sure reading is made directly from the master chart
ing pressure survey which was run to establish a P.I. after first correcting for wellhead pressure. This correc-
For this check, well test data for a period of several tion is made by determining the depth from zero at
weeks before or after the study are used in conjunction which the wellhead pressure occurs for the given gas-
with the available static bottom-hole pressure. These liquid ratio, and adding that depth to the reference
well tests should include some that are under stable depth of the well. The flowing bottom-hole pressure
conditions and permit the calculation of a true produc- point is then read from the applicable gas-liquid ratio
ing P.1. The majority of the checks made to date show curve at the corrected reference depth on the master
a calculated P.1. approximately one-half that obtained chart.
from the pressure survey. These were not permitted to
EVALUATION OF GAS-LIFT WELL
reach their stabilized, flowing bottom-hole pressures
PERFORMANCE
before the bomb was pulled and readings were made.
Fig. 13 shows a method of obtaining a P.I. when no The basic layout shown in Fig. 14 will be used
bottom-hole pressure survey information is available. throughout the gas-lift discussion. The design is pre-
The P.I. is based upon the change in flowing bottom- dicated upon a knowledge of the productivity of the
hole pressure at different rates of flow. When good test well. It will be shown that, if you are unable to deter-
data were available, this method gave satisfactory results. mine the expected characteristics of a well, any degree
The P.I. of a well is not necessarily a constant, but of success can only be attributed to pure chance.
can change with different rates of flow. The method Efficient supplementing of natural flow must be tailored
outlined in Fig. 13 provides an economical way to ob- to well performance characteristics.
tain a flow performance curve, or IPR, by producing Each illustration in this section is a study of the
the well at several different rates and accurately meas- effect of one variable upon lift efficiency. This is done
uring the necessary test data. This has also been suc- for two reasons: (1) the relative importance of each
cessfully carried out on well data which had been ob- variable can be better resolved; and (2) questions arising
in daily operations involve only one variable.

NA-
-~ S_·(,", -:::::
2C'~ -' -' 2000
i:-'C
"
~ : 0
C(, I : c' :' -' " 2 ~BG 2 2'
50 50 : 4 ::-EPT .... '7000' 7000'
160C
'" 75 4 : ,- s 160e
PWr 440 Ps 400 ~S
s ... pc 200 280
:;c~ 07 MCFS Q:MCrB

J20.)~
12000:
"
v'
(L
i1:
~
"- a:

I
80e "-
800
-Sl"lrl:: 810 ;;:S;u.
~A BCD::

~
?BHF2 = 1730 PSiG.

400 ? r.

/ D[PTH,FT
100 000 3000 4000 5000 6000 7000 DEPTH, FT
1000 2000 3000 4000 5000 6000 7000
FIG. ll-PRODUCTION DECLINE FROM CHANGE IN WATER CUT.
FIG. 13-0BTAINING PRODUCTIVITY INDEX FROM
SURFACE TEST DATA.

2000
PSHS
GIVEN,
2000 PBHF
PBHS 2000 PSIG PBHF A, REFERENCE DEPTH
TBG B, CASING PRESSURE GRADIENT
1600 DEPTH 7000'
C, FLOWING GRADIENT BELOW THE POINT
PWH 440 PSIG
1600 OF GAS INJECTION
g;" BLPD
GLR
200
07 McFB 200 BLPD 2 D, OPTIMUM POINT OF GAS INJECTION
C.
1200~~ 0.70 MCFB le E, FLOWING GRADIENT ABOVE THE POINT
=>
if)
1200:l OF GAS INJECTION
B
a:
=>
if) A.
if)
"- W
800 g:
800-----
PBHF = 1810 PSIG

400 PI 105

DEPTH, FT
1000 2000 3000 4000 5000 6000 7000
1000 2000 5000 6000 7000
FIG 12-0BTAINING PRODUCTIVITY INDEX FROM STATIC
BOTTOM-HOLE PRESSURE AND SURFACE TEST DATA. FIG 14-FuNDAMENTALS OF GAs-LIFT DESIGN.

394 JOURNAL OF PETROLEUM TECHNOLOGY


Ii the effect of more than one variable is involved III In addition to the relative efficiency of various tubing
a particular problem, it may develop that the best sizes, there are problems encountered where the desired
economic solution lies not in making all possible cor- production rate is either impossible or requires a high
rections but, rather, in making only those which effect horsepower commitment for the given operating condi-
the major improvements in operation. Studying the tions. A larger tubing size often will permit the desired
problem with each individual variable provides such rate with reasonable horsepower requirements. In this
an opportunity. manner, a well was successfully produced at 800 BjD
The effect of the variables is expressed as horsepower of liquid and an injected gas-liquid ratio of 0.7 Mcf/bbl
requirements. The requirements are shown in block with 2l1z -in. tubing, when it could not be produced at
graph form and do not have a numerical value assigned. over 400 BID of liquid with 2-in. tubing installed.
They have been scaled off very accurately and are de- Combination strings should not be overlooked when
signed to show the relative change in horsepower as the confronted with such problems as a well which will not
variable changes. produce the desired rate with 2-in. tubing but requires
Fig. 15 shows the effect of wellhead pressure. This its use in the lower section of the well because of a
illustration is based upon a constant intake pressure at liner. Swaging to 2l1z -in. tubing above the liner often will
the compressor of 25 psig. The higher-than-necessary permit prodUction of the desired rate. Whenever more
wellhead pressure would be the result of: (l) too long than one size is used, a switch from one tubing gradient
a flow line; (2) too small a flow line for the amount to the other is made at the depth where the change is
of fluid produced; (3) reduced ID from deposition or to be made.
paraffination; (4) too many right angle turns, choke Gas-injection pressure has a definite effect upon lift
cages, chokes, restricted opening valves, or lack of efficiency. As shown in Fig. 18, a point of injection at
streamlining at the tree; and (5) too high a separator 3,800 ft using 600-psig pressure would require four
pressure. times the horsepower required at a point of injection at
Over four times the horsepower would be required 6,800 ft using 1,700-psig pressure. By far the largest
at 200-psig wellhead pressure as is required at 50 psig. number of gas-lift systems in operation today are in-
An alternate example is shown in Fig. 16. This figl:lre jecting in the 500- to 700-psig range.
is the same except that the compressor intake pressure Although no arbitrary control normally can be ex-
is set at 15-psig less than wellhead pressure. Although erted upon the amount of formation gas produced, it
the compression requirements are now less at the higher too has a very definite effect upon gas-lift performance
wellhead pressure, it stilI takes over four times the as shown in Fig. 19. It should never be ignored when
volume of gas to produce against the 200-psig wellhead
pressure, and more horsepower is required to handle a
larger volume of gas. More than twice the horsepower 2000
is still required to lift the fluid at 200-psig wellhead
pressure as is required at 50 psig.
t600
Fig. 17 shows the effect of tubing size upon horse-
power requirements. As stated earlier, this would vary "
iii
"- 800 BLPD
with rate of liquid flow and gas-liquid ratio, with the 1200~~
005 MerB

larger tubing sizes becoming even more favorable as ::>

the rate increases. There is not enough data available '"'"w


on flow performance in small tubing sizes (l and 1¥.4 800- "-~---------------------y~--
in.) to determine their relative value at lower rates of
flow.
MCFB
400
Particularly where depletion must be at high with- McrB
MCFB
drawal rates, vertical-lift performance should be con- MCFB 2" TBG.
sidered before wells are completed slim hole. In the 2000 3000
DEPTH. FT
4000 5000 6000 7000
example shown, five times the horsepower would be re-
quired for l.5-in. tubing as for 2.5-in. tubing. FIG. 16-EFFECT OF FLOWING WELLHEAD PRESSURE UPON HORSE-
POWER REQUIREMENTS-COMPRESSOR INTAKE = P WH - 15 PSIG.

2000 HORSEPOWER REQUIREMENTS PBHF 2000

HORSEPOWER REQUIREMENTS

1600

~
1200l;!
d

D
1600

1200~rr
<)
~ DI. 51!
D2" CJ
25" 800 BLPD
0.05 MerB
::> 50 :::>
'"'" <f)
<f)

~ ~
8001~---------:Ji7'"-

MerB
MerB
MerB
MerB 2" TBG.
DEPTH. FT. DEPTH, FT
2000 3000 4000 5000 6000 7000 2000 3000 4000 5000 6000 7000

FIG. IS-EFFECT OF FLOWING WELLHEAD PRESSURE UPON HORSE· FIG. I7-EFFECT OF TU~ING SIZE UPON HORSEPOWER
POWER REQUIREMENTS-COMPRESSOR INTAKE = 25 PSIG. REQUIREMENTS.

APRIL. 1961 395


working out a design problem. It is one of several ex- fABLE I-RESULTS fOR ONE WELL
Before After
planations why two installations in presumably "identi- Tubing 2 in. 2.5 in.
cal" wells will perform at widely divergent injected gas- BID of Total Liquid 162 540
Oil 10% 14%
liquid ratios. Injected Gas-Liquid Ratio 0.5 Mcf/bbl 0.09 Mcf/bbl
Lift M"thod Intermittent Continuous
The change in performance is affected by two factors. P. I. 0.67 31.8
One is that the point of gas injection is not as deep for
higher formation ratios. The other is that the formation higher withdrawal rate than any previous time in the
gas is deducted from the total produced-gas require- life of the well. Using a reverse line of reasoning with
ment; the more the formation gas volume, the less the Fig. 20, it may be shown that for a given well with
injected gas required. This is illustrated in the ultimate producing conditions the same as PBHF3 an improvement
by the O.3-Mcf/bbl curve. With that formation gas- in productivity that would permit withdrawal at the
liquid ratio, the well would be flowing naturally with same rate at bottom-hole conditions the same as PBHF1
a wellhead pressure of 150 psig. would reduce horsepower requirements to 26 per cent
The effect of flowing bottom-hole pressure is shown of the original requirements.
in Fig. 20. In many cases, nothing can be done except Table 1 lists the results for one particular well.
to anticipate the condition that actually exists in the No other operating conditions such as wellhead and
well. This condition can range from some degree of injection pressure changed. The combination of 2.5-in.
satisfactory operation to the extreme of an impossible tubing and continuous lift permitted a greater sustained
situation for the desired volume of liquid as PBIIF4 • downdraw across the sand face with the resultant change
Four times the horsepower would be required to in productivity. Summarizing part of this data, the well
produce at P BIIF3 as would be required at PBIIF1 • This is being produced at 3.3 times the previous rate of flow
change in PBIIF would be the result of either a normal with 60 per cent of the original horsepower requirement.
decline in reservoir pressure or the necessity for in- The measured flowing bottom-hole pressure at 540 BID
creased drawdown at a constant reservoir pressure but of liquid is now actually higher than the measured
deteriorating P.I. Thus, horsepower requirements would flowing pressure at 162 BID of liquid.
increase with time under these conditions. Both P.I.'s were carefully obtained with bottom-hole
The most interesting work done in connection with pressure surveys and correlated with the master curves.
flowing bottom-hole pressure has been to obtain an The production is now held to 540 B/D of liquid for
improvement in productivity after producing wells at a allowable reasons. To check the measured production
potential, the well was opened up and produced at the
rate of 1,460 BID of liquid. This type of well response
has been encountered many times in our work, and it

_~~~~ ----------------------~~
has been discussed in various published papers. If it can
2000._ noo PSIG __ be anticipated from a calculated P.I. using formation
data that the actual producing P.I. is appreciably less
1600
HORSEPOWER REQUIREMENTS
than the formation P.1. of the well, steps can be taken

Do
600 800
PSIG
o
to clean up the well and permit operation at greatly
reduced horsepower requirements.
Fig. 21 shows the importance of correct valve place-
800 PSIG
ment with respect to horsepower requirements. If a
point of injection were located at "A", the horsepower
requirements would be over twice that required if it
were located at "B". If the point were located at "e",
injection would be impossible. Not only must the point
2'1 TBG. of injection be properly located, but so also must any
5000 6000 7000
valves used to unload to the point of injection. All must
be located in a manner which will accommodate the
FIG. IS-EFFECT OF GAs-INJECTION PRESSURE UPON HORSE- productivity of the well and achieve the desired point
POWER REQUIREMENTS.
of injection. Any design which does not take well per-

2000 HORSEPOWER REQUIREMENTS HORSEPOWER REQUIREMENTS


PBHF 2000

1600
<5
iii
0..
00
·005 0.10
D
0.20
MeFB
i<
~
030
'-'
z
0
1600

1200~­
<5
~

:>

00-
['"'"____________________ ~~r:J7~~--

400

2" TBG. 2" TBG.


5000 6000 7000 1000 2000 5000 6000 7000

FIG. 19-EFFECT OF FORMATION GAS UPON HORSEPOWER FIG. 20-EFFECT OF FLOWING BOTTOM-HOLE PRESSURE UPON
REQUIREMENTS. HORSEPOWER REQUIREMENTS.

396 JOURNAL OF PETROLEUM TECHNOLOGY


formance into consideration is relying upon pure chance jection which will produce the desired 800 BID of
that it will be successful. liquid is very close to the static pressure gradient. All
valves above this final point would unload static fluid,
NOTES ON SPECIAL DESIGN PROBLEMS but none would sustain a drawdown in bottom-hole
pressure. When the final point of injection is reached,
No attempt is made to demonstrate a method of the drawdown at bottom would increase from 0 to 100
installation design. Once the vertical-lift performance of psig, and the sustained production rate from 0 to 800
a well has been evaluated, the design becomes a straight- BID of liquid. If the point of injection were located
forward procedure to fulfill the requirements dictated 50-ft higher in the hole, either through mis-design or
by the well. However, the design of an installation both mis-spacing, the well would only produce 480 BID of
from the standpoint of valve spacing, pressure setting liquid. Care should be exercised to prevent missing the
and gas throughput requirements should be based upon correct evaluation of high-P.1. wells.
sound engineering principles to insure attaining the de- There is a distinction to be made between restarting
sired performance. a well and supplementing natural flow. In wells with
Fig. 22 shows the difficulty encountered in gas-lifting little or no formation gas, this may be possible from
wells with formation ratios of 0.6 Mcf/bbl and higher. the same injection point. When a well will produce with
The change in flowing gradient created by adding gas any appreciable formation gas, it must be re-started
does not have the dramatic effect which is encountered from one depth and supplemented at another. This is
in low-ratio wells. In the example, more than doubling shown in Fig. 24. Formation Gradient A is the 0.0-
the amount of gas in the vertical column from 5,000 ft Mcf/bbl curve with the well producing at the rate of
to the surface raises the flowing wellhead pressure from of 600 BID of liquid. The necessary point of injection
40 to 100 psig. In contrast, a like injection of an is at 4,500 ft. When the normal 0.2-Mcf/bbl formation
additional 0.6 Mcf/bbl of gas at the same depth in a gas-liquid ratio returns to the vertical column, the point
well with a formation gas-liquid ratio of 0.05 Mcf/bbl of injection will move up to 3,650 ft. Two completely
would raise the wellhead from 40 psig to 660 psig. separate points of injection are required for proper
Higher-ratio wells, which can no longer flow on their operation of the well.
own, present a more difficult artificial-lift problem than The higher the formation gas-liquid ratio, the farther
wells with low ratios. apart the two points. The extreme example of this con-
The need for caution in designing an installation for dition is Fairbanks field where wells are unloaded to,
a high-P.1. well is shown in Fig. 23. The point of in- and produced from, bottom until formation gas breaks
in, at which time they will return to natural flow.

2000 HORSEPOWER REQUIREMENTS PBHF PBHS


2000 PBHF

oD
w
--'
ro
<Ii
if)
1600
Ii' 1600 SI"AT1C
0.465
GRADIENT
PSI. /F T. _______
"
g; A B
l
c
g;"
1200~~ ABC
:>
if)
1200k!~
::>
~ if)
c:: ~
80,~~~-----------------t~1l------- c::
oo,~~~-----------------;J,r

400
400
2" TBG.
2" TBG. P.1. 8.0
30ooDEPTH4&li,
2000 5000 6000 7000
1000 2000 5000 6000 7000

FIG. 21-EFFECT OF INCORRECT VALVE SPACING UPON


FIG. 23-DESIGN PROBLEM WITH A HIGH-P. I. WELL.
HORSEPOWER.

2000
2000 PBHS
A. RESTARTING
8. SUPPLEMENTING
1600
1600 STATIC
0465
GRADIENT
PSI/FT "
g;
0.0
0.2

1200~r
:>
if)

::l
IE

2" TBG.
600 BLPD
2" TBG
2000 600 7000
5000 6000 7000
FIG. 24-DESIGN PROBLEM WITH SEPARATE POINTS OF INJEC-
FIG. 22-DESIGN PROBLEM WITH ApPRECIABLE FORMATION GAS. TION REQUIRED FOR RE-STARTING AND SUPPLEMENTING FLOW.

APRIL, 1961 397


2000 2000
STATIC GRAD,EN r
0.465 PSI./FT.-
STATIC GRADIENT
1600 1600 0465 PSL/FT.--
C?
g>
1200~~
::>
if}
if}
w
a:
80o:n.~-------17T--

2" TBe. 211 TBG


600 BLPD 600 BLPD
DEPTH, FT.
1000 2000 3000 4000 5000 6000 7000 1000 5000 6000 7000

FIC. 25-DESICN PROBLEM WITH FINAL POINT OF INJECTION FIC. 26---SPECIAL RE-STARTINC PROBLEM WITH FINAL POINT OF
ABOVE STATIC PRESSURE GRADIENT. INJECTION ABOVE STATIC PRESSURE GRADIENT.

Fig. 25 illustrates a design problem with the final with good results, and even our aJ;lProach to intermittent
point of gas injection above the static pressure gradient. gas lift has been greatly improved by the knowledge
This is brought about by the 0.2-Mcf/bbl formation gained from the work with the techniques. There is an
gas-liquid ratio creating a flowing gradient which crosses uncounted amount of work still to be done to resolve
the static pressure gradient below the final point of gas all phases of vertical-lift performance to a true applied
injection. The final point of injection shown is not science.
capable of creating sustained production from the for- For those whose interest is maximum rate rather than
mation until gas evolves; and, as discussed with Fig. 24, optimum efficiency, it should be pointed out that the
no formation gas can be counted upon until after for- study of every variable in the paper can be revised with
mation fluid is produced. increased production as the main objective.
Unless additional valves are run deeper to re-start A definite advantage to the techniques developed is
formation flow, this well will not produce. their use of charted flowing gradients. This permits the
Fig. 26 is a composite of Figs. 24 and 25, illustrating techniques to be applied to any approach to flowing
re-starting below the static pressure gradient at 4,500 gradients so long as the approach can be resolved to a
ft with a required injected gas-liquid ratio of 0.8 Mcfl depth-pressure relationship.
bbl, finally supplementing at a point above the static It is the author's sincere belief that vertical-lift per-
pressure gradient with an injected gas-liquid ratio of formance is the true field of petroleum production
0.2 Mcf/bbl. engineering and that it is a scientific field as important
economically as the field of reservoir engineering. In
LIMITATIONS OF THE MASTER CHARTS comparison, it is virtually untouched. Though some may
regard this paper as an oversimplification of the prob-
The following are the listed areas in which the curves lem, they may also agree that some simplification would
are either unproven or suspect. serve to promote improved practices in the evaluation
1. The 1- and 1;4 -in. curves have not been verified of vertical-lift performance in producing wells,
because of the lack of available pressure survey data
for these sizes. NOMENCLATURE
2. The curves plotted for gas-liquid ratios above 2.0- P WH = flowing wellhead pressure, psig
Mcf/bbl have not correlated with pressure surveys at PBHB = static bottom-hole pressure, psig
rates of flow of 400 BID of liquid or less. It is believed PBHP = flowing bottom-hole pressure, psig
that this point marks a transition from foam flow to P.1. = Productivity Index in BID of total produced
mist flow and exceeds the mathematics of Poettman liquid/psi drop in bottom-hole pressure
and Carpenter. The curves of Gilbert have given a good IPR = inflow performance relationship
correlation when used in this range. D = reference depth of well
3. These curves are for continuous flow and will not
provide suitable data for intermittent flow. ACKNOWLEDGMENT

CONCLUSIONS The author wishes to thank W. K. ~OOdward and


B. A. Abercrombie of Axelson-Garrett f r their contri-
Some of the work accomplished to date on a practical butions to the material contained in this p per.
approach to the evaluation of vertical-lift performance
in producing wells is summarized. The material dis- REFERENCES
cussed is only a part of the total work which has been
1. Gilbert, W. E.: Drill. and Prod. Prac., API (1954).
done. Evaluations have been made and gas-lift designs
2. Poettmann, Fred H. and Carpenter, Paul G.: Drill. and
run in dual completions and casing-flow installations Prod. Prac., API (1952).
with excellent success. The vertical-lift performance in 3. Handbook of Gas Lift, Axelson-Garrett, Div_ of U. S. In-
rod and hydraulic-pump installations has been evaluated dustries, Inc. *k*

JOURNAL OF PETROLEUM TECHNOLOGY

You might also like