Professional Documents
Culture Documents
Project Training Report: Name of The Project
Project Training Report: Name of The Project
The design of a roof slab consists of thickness of slab, size of bars, spacing
of bars, hooks, cranks and laps of bars, minimum cover of concrete etc. The
mix of concrete for the slab is usually by volume and is of proportion 1:2:4 (
cement, sand and aggregate)
Depending upon the span, an RCC slab may be designed as either one way
reinforced slab or two way reinforced slab. The slab which is supported on two
opposite supports is called as one way slab. This slab is considered to be
supported on two longer opposite sides. When the ratio between the length
and breadth of the room over which the slab is provided is more than 2. One
way slab consists of main reinforcement spanning between the supports with
distribution of reinforcement at right angles to it. Two way slab is said to be
spanning in two directions, when the length to breadth ratio falls below 2. In
such case, main reinforcement is provided in both directions in the form of a
mesh.
Spacing of bars of main reinforcement shall not be more than 3 times the
effective depth of slab and that for the distribution bars not more than five
times the effective depth. Spacing of not more than 20 cm diameter for main
bars and not more than 40 cm for distribution bars is usually provided.
Bars smaller than 6 mm diameter or greater than 18 mm are not used for
slabs. 10 mm or 12 mm plain M.S. bars or 8 mm or 10 mm tor-steel bars are
generally used. They are provided at the bottom of the slab allowing minimum
cover of 25 mm of concrete.
In addition to bars along the main direction, provided at the bottom, bars
along the longer span are also placed on top of the main bars and at right
angles to them. These are called ‘ distribution’ bars or ‘temperature
reinforcement’ or ‘ transverse bars’. The distribution bars function to resist
cracks due to variation of temperature and shrinkage stresses. They also assist
in distribution of loads. The area of such reinforcement is usually 20 % of that
of main reinforcement. Plain M.S. bars of 6 mm diameter are usually used for
this purpose.
In all buildings, slabs covers the full width of the wall over which walls are
raised. This creates partially fixed conditions for the slab. In such cases, every
alternate bar is bent up. This arrangement is economical as compared to
providing additional bars at the top. The main bottom bar is cranked at one-
fifth of the span at either end and taken up.
Main and distribution bars are tied together with black mild steel wire of 16
gauge by providing a cross and twisting the ends. If smaller diameter of wire
is used, double strands of wire shall be provided in place of single strand.
About 5 kg. of binding wire is required for tying 1 tonne of reinforcing bars.
Two-Way Slab
In providing steel for a two-way slab, the bars in both directions shall be of
the same diameter and of the same kind i.e. either plain or tor-steel. The
bottommost layer will be along the shorter span. Same size bars along the
longer span shall be placed on top of these bars and at right angles to them.
No extra distribution bars are necessary. Cranking of alternate bars shall be
done at 1/5th span from support on all the four sides and cranked bars taken
to the top which come at the top of slabs over the supports allowing usual
cover.
If the slab of one room continues over the adjacent room the portion of the
slab over the common intermediate support needs top reinforcement. The
bars in the middle portions in short span direction will be at the bottom
whereas those over the intermediate supports will be at the top. The spacing
of a given size of bar in all these positions depends upon the lengths of spans
and upon the loading conditions and is determined by design considerations.
Shear stress in concrete is generally small and bond stress within allowable
limits. Stirrups are not used in slabs whether it is reinforced one way or both
ways.
Thickness of the slab is decided based on span to depth ratio specified in
IS456-2000. Minimum reinforcement is 0.12% for HYSD bars and 0.15% for
mild steel bars. The diameter of bar generally used in slabs are: 6 mm, 8
mm, 10 mm, 12mm and 16mm.
The maximum diameter of bar used in slab should not exceed 1/8 of the
total thickness of slab. Maximum spacing of main bar is restricted to 3 times
effective depth or 300 mm whichever is less. For distribution bars the
maximum spacing is specified as 5 times the effective depth or 450 mm
whichever is less.
Batching plant:
FORMWORK (SHUTTERING)
1. It should be strong enough to withstand all types of dead and live loads.
5. The material of the formwork should be cheap, easily available and should
be suitable for reuse.
6. The formwork should be set accurately to the desired line and levels
should have plane surface.
8. The material of the formwork should not warp or get distorted when
exposed to the elements.
It shall be as per BBS prepared according to approved drawing. The R/F shifting
and binding shall be started as soon as shuttering is completed. R/F binding
shall continue as formwork and shuttering work is progresses.
CONCRETING
Construction joint
The construction joint shall be pre decided and fixed prior to start of the
concreting. It is planned to have two construction joints for main building as
decided. In case of major break down of the Batching plant, the additional
Construction joint may be left. The location of the construction joint shall be
at the one-third span. Construction joint shall be straight and have profile of
‘L’ shape so that successive layer of concrete shall be perfectly bonded with
previous laid layer.
All plant and machinery are checked and made in working conditions.
Concrete of grade M-25 shall be produced from our batching plant and directly
pumped to the location of concrete placement through the pipeline. The
pouring sequence shall be from grid A towards construction joint. Since the
grade of concrete for column is M-40 and surrounding concrete is M-25,
sufficient offset around column shall be casted with M-40. The offset
dimensions shall be provided by PMC.
The curing shall be started immediately after thumb set of the concrete laid.
Hessian clothe /Plastic shall be covered over the set concrete to reduce
moisture evaporation from the concrete during hardening and thus to
minimize shrinkage crazy cracks. These cracks are inheriting property of the
concrete specially appears during casting of flat surfaces.
Final curing shall be done by ponding and stacking water for minimum
period of 7 days.