STATE OF QATAR

Public Works Authority


PAYMENT CERTIFICATE PWA
Payment Certificate No.: 24 Period Ending 21-Aug-18
Budget Ref.: 11320/1440470
Date : 4-Sep-18 Payment Type : Advance/First ✘ Interim Penultimate (PCC) Final
Payment for : ✘ Contractor Consultant PMC/MC GEC Secondment Supplier

Project Title : Design and Build of Al Khor Expressway


Project ID : Original Contract Sum QAR 7,600,000,000.00
Commitment No. : C2017/113 Total Value of Addenda/Variation to date QAR 0.00
Contractors : TEKFEN Construction and Installation Co., Inc Adjusted Contract Sum QAR 7,600,000,000.00
Reserve Amount (15%) of the Adjusted Contract Value QAR 1,140,000,000.00

Valuation Total Limit (85%) of the Adjusted Contract Value QAR 6,460,000,000.00
Consultant : KEO International Consultants Last Addendum / Variation No. 0

1 Work ValueTo Date QAR 4,825,636,632.93


2 Materials on Site QAR 66,807,750.87
3 Consultant Fees QAR 0.00

Key Performance Indicator (KPI) Total QAR 4,892,444,383.80


4 KPI Addition: (* to be added)
Determined KPI amount in the Agreement Price QAR 0.00

Forecasted KPI Amount for Year One QAR 0.00

Adjusted KPI Amount after Year One QAR 0.00

Less KPI Amount from Year one QAR 0.00

* Total KPI Amount Certified at the End of Year One QAR 0.00 Total Additions QAR 0.00
5 KPI Deduction : (* to be subtracted)
* Held KPI amount (from Work Value to Date) QAR 0.00

KPI amount held from Previous certificiates QAR 0.00

New KPI amount QAR 0.00

* Core Team engaged in Schedule A1 QAR 0.00

Core Team amount held from previous certficates QAR 0.00

New Core Team engaged in Schedule A1 QAR 0.00


Deduction :(* to be subtracted)
6 Retention
* Retention % (From Work Value To Date) QR QAR 244,622,219.19
Retention from Previous certificiates QAR 203,496,186.02
New Retention QAR 41,126,033.17
Retention to be released QAR 203,496,186.02
7 Penalties
* Penalties to date QAR 0.00
Penalties for this period QAR 0.00
* Penalties Under Adjustments to date QAR 0.00
Penalties Under Adjustments for this period QAR 1,000,419.00
8 Other Deductions
* Income Tax QAR 0.00
* Contribution to Development Projects or Sports Activities QAR 0.00
* Miscellaneous QAR 0.00 Total Deductions QAR 42,126,452.17

9 Deduction of additional Supervision charge for Consultants / Sub Consultants


Consultant / Sub Consultant / Sub Contractor
(* To be paid to Consultant and subtracted from the payment of Contractor)

Total Consultant Fee to date QAR 0.00

Total Consultant Fee paid previously QAR 0.00

Total Consultant Fee for this period QAR 0.00 Total QAR 0.00

10 Advance Payment : (* to be added)


Advance Payment No.1 …. % (from Contractual Amount) QAR 1,520,000,000.00

Total Recovery of Advance Payment no.1 (….. from Work Value To Date) QAR 978,488,876.76

Unrecovered from Advance Payment No.1 QAR 541,511,123.24


Previously Recovered from Advance Payment no.1 QAR 813,984,744.08
Recovered by this Certificate from Advance Payment No.1 QAR 164,504,132.68

Additional Advance Payment No.2 ..% (from remaining Contract Amt... QAR) QAR 0.00

Total Recovery from Advance Payment No.2 QAR 0.00


Unrecovered from Advance Payment No.2 QAR 0.00
Previously Recovered from Advance Payment no.2 QAR 0.00
Recovered by this Certificate from Advance Payment No.2 QAR 0.00
Unrecovered from Advance Payment No.1 & 2 QAR 541,511,123.24 Total QAR 541,511,123.24

Total sum certified by this certificate QAR 5,391,829,054.87

Total sum certified by previous certificates QAR 4,774,938,557.33

Net Sum Certified by this Certificate QAR 616,890,497.54


Recommended by Supervision Consultant (If Applicable) Verified PMC / MC (If Applicable)
Name : Stuart Horne Name :
Signature: Signature:
Date : / / Date : / /

Checked by PWA - EBD (Payments Team) Approved by Project Coordinator/Head of Section


Name : Name : Yousef A. Rahman Al-Emadi
Signature: Signature:
Date : / / Date : / /
Note: ………………………………………………………………………………………………………………………………………….
………………………………………………………………………………………………………………………………………….
Contract No : C2017/113
Description : Design and Build of Al Khor Expressway Interim Payment No : 24
Employer : Public Works Authority Period Ending : 21-Aug-2018
Consultant : KEO International Consultants Recommend. Date : 4-Sep-2018
Contractor : TEKFEN Construction and Installation Co., Inc

REPORT FOR PAYMENT CERTIFICATE NO.24 - PERIOD ENDING 21 AUGUST 2018


CONSULTANT AMOUNT (QR) CONTRACTOR AMOUNT (QR) DIFFERENCE
BILL No. DESCRIPTION AMOUNT (QR) % %
(a) - (b)
REMARKS COMMENTS
PREVIOUS THIS MONTH TO-DATE (a) PREVIOUS THIS MONTH TO-DATE (b)

1 GENERAL ITEMS 739,024,000.00 575,813,939.20 0.00 575,813,939.20 77.92% 575,813,939.20 0.00 575,813,939.20 77.92% 0.00
2 DESIGN 147,820,000.00 147,184,374.00 0.00 147,184,374.00 99.57% 147,184,374.00 0.00 147,184,374.00 99.57% 0.00
3 CONSTRUCTION OF BU THELAH ROAD 119,928,000.00 119,014,148.64 0.00 119,014,148.64 99.24% 119,014,148.64 0.00 119,014,148.64 99.24% 0.00
AL KHOR EXPRESSWAY ROAD WORKS
4.1 AKE-ROAD WORKS - PACKAGE 1 809,783,600.90 377,139,641.08 0.00 377,139,641.08 46.57% 377,152,288.01 0.00 377,152,288.01 46.57% (12,646.93)
4.2 AKE-ROAD WORKS - PACKAGE 2 & 3 818,197,463.60 473,805,523.76 0.00 473,805,523.76 57.91% 473,807,812.81 0.00 473,807,812.81 57.91% (2,289.05)
4.3 AKE-ROAD WORKS - PACKAGE 4 906,314,935.50 535,358,230.26 0.00 535,358,230.26 59.07% 535,358,282.07 0.00 535,358,282.07 59.07% (51.81)
INTERCHANGES WORKS
5.1 INTERCHANGE A 221,616,000.00 205,471,803.20 0.00 205,471,803.20 92.72% 205,471,842.09 0.00 205,471,842.09 92.72% (38.89)
5.2 INTERCHANGE B 263,720,000.00 239,295,928.24 0.00 239,295,928.24 90.74% 239,295,852.59 0.00 239,295,852.59 90.74% 75.65
5.3 INTERCHANGE C 285,228,000.00 247,495,186.66 0.00 247,495,186.66 86.77% 247,495,169.47 0.00 247,495,169.47 86.77% 17.19
5.4 INTERCHANGE D 217,360,000.00 203,827,521.40 0.00 203,827,521.40 93.77% 203,827,523.69 0.00 203,827,523.69 93.77% (2.29)
5.5 INTERCHANGE E 56,772,000.00 51,373,777.50 0.00 51,373,777.50 90.49% 50,894,724.08 0.00 50,894,724.08 89.65% 479,053.42
5.6 INTERCHANGE F & F1 272,536,000.00 261,990,479.97 0.00 261,990,479.97 96.13% 261,990,479.96 0.00 261,990,479.96 96.13% 0.01
5.7 INTERCHANGE G & G1 185,744,000.00 176,970,650.05 0.00 176,970,650.05 95.28% 176,970,628.05 0.00 176,970,628.05 95.28% 22.00
5.8 INTERCHANGE H 173,432,000.00 151,634,766.03 (903,718.01) 150,731,048.02 86.91% 151,634,762.12 0.00 151,634,762.12 87.43% (903,714.10)
UTILITIES WORKS
6.1 STORMWATER DRAINAGE 613,139,644.80 307,443,295.01 (58,680,765.76) 248,762,529.25 40.57% 307,444,240.00 0.00 307,444,240.00 50.14% (58,681,710.75)
6.2 STORM WATER TUNNEL AND SHAFTS 315,400,000.00 210,614,265.32 (31,305,222.54) 179,309,042.78 56.85% 210,447,452.89 0.00 210,447,452.89 66.72% (31,138,410.11)
6.3 CONSTRUCTION OF PUMP STATION 3,753,676.80 0.00 0.00 0.00 0.00% 0.00 0.00 0.00 0.00% 0.00
7 KAHRAMAA - WATER WORKS 131,691,494.40 104,501,200.26 (10,095,244.77) 94,405,955.49 71.69% 104,501,111.59 0.00 104,501,111.59 79.35% (10,095,156.10)
8 TSE WORKS 311,261,918.40 126,999,531.28 (33,872,234.57) 93,127,296.71 29.92% 127,000,302.00 0.00 127,000,302.00 40.80% (33,873,005.29)
9 FOUL SEWER 20,293,315.20 16,378,006.29 (40,586.64) 16,337,419.65 80.51% 16,378,006.29 0.00 16,378,006.29 80.71% (40,586.64)
10 KAHRAMAA - ELECTRICAL WORKS 370,147,723.20 325,409,962.99 (58,092,604.93) 267,317,358.06 72.22% 325,409,743.92 0.00 325,409,743.92 87.91% (58,092,385.86)
11 STREET LIGHTING 252,473,865.60 67,622,789.52 (36,487,964.87) 31,134,824.65 12.33% 67,623,112.35 0.00 67,623,112.35 26.78% (36,488,287.70)
12.0 TELECOM - QNBN, OOREDOO AND VODAFONE WORKS 53,528,995.20 43,884,301.43 (1,524,318.44) 42,359,982.99 79.13% 43,884,230.50 0.00 43,884,230.50 81.98% (1,524,247.51)
13 QAF WORKS 41,231,793.60 21,017,226.47 (5,188,821.26) 15,828,405.21 38.39% 20,984,050.24 0.00 20,984,050.24 50.89% (5,155,645.03)
UGN WORKS
14 157,517,572.80 90,929,964.48 (19,091,098.32) 71,838,866.16 45.61% 90,929,906.86 0.00 90,929,906.86 57.73% (19,091,040.70)
(MOI - SSD)
15 TESTING, COMMISSIONING AND HANDING OVER 12,084,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00
16 PROVISIONAL SUM - LANDSCAPE AND IRRIGATION NETWORK 100,000,000.00 0.00 0.00 0.00 0.00

Total - BoQ Items 7,600,000,000.00 5,081,176,513.04 (255,282,580.11) 4,825,893,932.93 63.50% 5,080,513,983.42 0.00 5,080,513,983.42 66.85% (254,620,050.49)

OTHER WORKS / ADDITIONS (INCLUDED BY CONTRACTOR) Refer to Appendix


B10 - Works other than SI/VO 0.00

(A) Total Sum QR 7,600,000,000.00 5,081,176,513.04 (255,282,580.11) 4,825,893,932.93 5,080,513,983.42 0.00 5,080,513,983.42 (254,620,050.49) (A)
(B) Payment on Account for Variations (Appendix-B5), QR 0.00 (B) Refer to Appendix B5 for the details.
(C) Day works, QR 0.00 (C )
(D) NEW RATES (Appendix B5 added by contractor ),QR 0.00 (D)
(E) Material on Site (Appendix-B8),QR 43,978,553.77 22,829,197.10 66,807,750.87 43,978,553.77 20,467,526.43 64,446,080.20 2,361,670.67 (E)
(F) Less: Deduction for NCR & Other Items (257,300.00) 0.00 (257,300.00) (257,300.00) (F)
(G) Total Valuation,QR 7,600,000,000.00 5,124,897,766.81 (232,453,383.01) 4,892,444,383.80 64.37% 5,124,492,537.19 20,467,526.43 5,144,960,063.62 67.70% (252,515,679.82) (A+B+C+D+F)= (G)
(H) Add Unrecovered Advance Payment (Appendix_B7),QR 706,015,255.92 (164,504,132.68) 541,511,123.24 495,101,492.56 (4,093,505.28) 491,007,987.28 50,503,135.96 (H)
(I) Less Retention (Appendix-B6),QR (203,496,186.02) (41,126,033.17) (244,622,219.19) (256,224,626.86) (1,023,376.32) (257,248,003.18) 12,625,783.99 (G *0.05)= (I)
Add: Release of Retention 203,496,186.02 - 203,496,186.02 158,244,532.63 - 158,244,532.63 45,251,653.39 (J)
Less: Penalty for Delay (1,000,419.00) - (1,000,419.00) (1,000,419.00)
- 0.00
Other Additions (by contractor as financial costs) 0.00
EOT for Completion and Recovery Costs 0.00
(J) Total Certified (QR) - Incl Adv.P 5,829,912,603.73 (438,083,548.86) 5,391,829,054.87 5,521,613,935.52 15,350,644.83 5,536,964,580.35 J=G+H+I
(K) Less Advance Payment ,QR (1,520,000,000.00) (1,520,000,000.00) (1,520,000,000.00) (1,520,000,000.00) 0.00 (K)

(L) Net Valuation (QR) 4,309,912,603.73 (438,083,548.86) 3,871,829,054.87 50.95% ### 15,350,644.83 4,016,964,580.35 52.85% (145,135,525.48) L= J+K

SC Recommendation Page 2 of 351 Design and Build of Al Khor Expressway


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway Interim Payment No : 24
Employer : Public Works Authority Period Ending : 21-Aug-18
Consultant : KEO International Consultants Recommend. Date : 4-Sep-18
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B1 - SUMMARY FOR VALUE OF WORK
GROSS CERTIFIED VALUE (QR) PERCENTAGE COMPLETION
BILL No. DESCRIPTION AMOUNT Remarks
PREVIOUS THIS MONTH TO-DATE PREVIOUS THIS MONTH TO-DATE

1 GENERAL ITEMS 739,024,000.00 519,264,321.28 56,549,617.92 575,813,939.20 70.26% 7.66% 77.92%


2 DESIGN 147,820,000.00 147,184,374.00 0.00 147,184,374.00 99.57% 0.00% 99.57%
3 CONSTRUCTION OF BU THELAH ROAD 119,928,000.00 119,014,148.64 0.00 119,014,148.64 99.24% 0.00% 99.24%
AL KHOR EXPRESSWAY ROAD WORKS 0.00 0.00%
4.1 AKE-ROAD WORKS - PACKAGE 1 809,783,600.90 272,675,925.73 104,463,715.35 377,139,641.08 33.67% 12.90% 46.57%
4.2 AKE-ROAD WORKS - PACKAGE 2 & 3 818,197,463.60 322,946,278.19 150,859,245.57 473,805,523.76 39.47% 18.44% 57.91%
4.3 AKE-ROAD WORKS - PACKAGE 4 906,314,935.50 396,932,367.14 138,425,863.12 535,358,230.26 43.80% 15.27% 59.07%
INTERCHANGES WORKS 0.00 0.00%
5.1 INTERCHANGE A 221,616,000.00 189,555,542.75 15,916,260.45 205,471,803.20 85.53% 7.19% 92.72%
5.2 INTERCHANGE B 263,720,000.00 196,524,960.36 42,770,967.88 239,295,928.24 74.52% 16.22% 90.74%
5.3 INTERCHANGE C 285,228,000.00 203,039,558.93 44,455,627.73 247,495,186.66 71.19% 15.58% 86.77%
5.4 INTERCHANGE D 217,360,000.00 192,395,243.89 11,432,277.51 203,827,521.40 88.51% 5.26% 93.77%
5.5 INTERCHANGE E 56,772,000.00 32,738,286.03 18,635,491.47 51,373,777.50 57.67% 32.82% 90.49%
5.6 INTERCHANGE F 272,536,000.00 253,527,296.23 8,463,183.74 261,990,479.97 93.03% 3.10% 96.13%
5.7 INTERCHANGE G 185,744,000.00 142,627,039.36 34,343,610.69 176,970,650.05 76.79% 18.49% 95.28%
5.8 INTERCHANGE H 173,432,000.00 91,239,067.53 59,491,980.49 150,731,048.02 52.61% 34.30% 86.91%
UTILITIES WORKS 0.00 0.00%
6.1 STORMWATER DRAINAGE 613,139,644.80 225,304,689.34 23,457,839.91 248,762,529.25 36.75% 3.82% 40.57%
6.2 STORM WATER TUNNEL AND SHAFTS 315,400,000.00 154,353,009.90 24,956,032.88 179,309,042.78 48.94% 7.91% 56.85%
6.3 CONSTRUCTION OF PUMP STATION 3,753,676.80 0.00 0.00% 0.00% 0.00%
7 KAHRAMAA - WATER WORKS 131,691,494.40 87,190,004.34 7,215,951.15 94,405,955.49 66.21% 5.48% 71.69%
8 TSE WORKS 311,261,918.40 72,385,566.52 20,741,730.19 93,127,296.71 23.26% 6.66% 29.92%
9 FOUL SEWER 20,293,315.20 9,293,466.57 7,043,953.08 16,337,419.65 45.80% 34.71% 80.51%
10 KAHRAMAA - ELECTRICAL WORKS 370,147,723.20 249,282,165.65 18,035,192.41 267,317,358.06 67.35% 4.87% 72.22%
11 STREET LIGHTING 252,473,865.60 22,886,162.61 8,248,662.04 31,134,824.65 9.06% 3.27% 12.33%
12 TELECOM - QNBN, OOREDOO AND VODAFONE WORKS 53,528,995.20 42,236,598.66 123,384.33 42,359,982.99 78.90% 0.23% 79.13%
13 QAF WORKS 41,231,793.60 13,841,214.18 1,987,191.03 15,828,405.21 33.57% 4.82% 38.39%
UGN WORKS
14 157,517,572.80 69,765,178.81 2,073,687.35 71,838,866.16 44.29% 1.32% 45.61%
(MOI - SSD)
15 TESTING, COMMISSIONING AND HANDING OVER 12,084,000.00 0.00 0.00% 0.00% 0.00%

16 PROVISIONAL SUM - LANDSCAPE AND IRRIGATION NETWORK 100,000,000.00 0.00 0.00% 0.00% 0.00%

Sum 7,600,000,000.00 4,026,202,466.64 799,691,466.29 4,825,893,932.93 52.98% 10.52% 63.50%

Summary of Contract Variation Orders (Appendix B5) - -

Deduction for NCR & Other Items - (257,300.00) 0.00 (257,300.00)

Work Value To Date 4,025,945,166.64 799,691,466.29 4,825,636,632.93

Material on Site Summary (Appendix-B8) 43,978,553.77 22,829,197.10 66,807,750.87

Total Valuation (QR) 4,069,923,720.41 822,520,663.39 4,892,444,383.80 53.55% 10.82% 64.37%

DESIGN AND BUILD AL KHOR EXPRESSWAY Page3/351 APPENDIX B1


Contract No: C2017/113
Description: Design and Build of Al Khor Expressway
Employer: Public Works Authority
Consultant: KEO International Consultants Interim Payment No : 24
Contractor: TEKFEN Construction and Installation Co., Inc Period Ending : 21-Aug-2018
Recommend. Date : 4-Sep-2018

APPENDIX B3 - BREAKDOWN OF PRELIMINARY ITEMS


BILLS OF QUANTITIES BREAKDOWN

Time Related Fixed Charges Physical Payment


Item CESMM3 Contract Amount Grand Total Remarks
Progress Related Code
Item Description Unit Qty Rate Cost of Cost of
Ref. QAR % Per Month Total Other (specify) Total
Mobilization Demobilization

1 GENERAL ITEMS

Performance Bond; in accordance with the Clause 4.2 of


A Item 1.00 123,120,000.00 123,120,000.00 100% 100% 100% A
General Conditions of Contract

All insurances required for the contract; in accordance with


B the Clauses 18.1, 18.2, 18.3 & 18.4 of General Conditions of Incuded Included A
Contract

Provision of Engineer's Site Office and Facilities as per QCS


C Item 1.00 8,436,000.00 8,436,000.00 10% 100% 100% B1
2014 Section 1 - General Part 11

Provision of Contractor's Site Office and Facilities as per


D Item 1.00 70,300,000.00 70,300,000.00 10% 100% 100% B1
QCS 2014 Section 1 - General Part 12

Allow for mobilizing Contractor's Equipment/Plant; as per


E Item 1.00 33,744,000.00 33,744,000.00 10% 100% 100% B1
Conditions of Contract

Allow for Obligations & Liabilities complying with Conditions


F Item 1.00 32,000,000.00 32,000,000.00 2.78% 100% 100% B
of Contract

Allow for Quality Assurance, Testing and Health & Safety as


G Item 1.00 443,464,000.00 443,464,000.00 2.78% 100% 100% B
per required by Conditions of Contract

Allow for other all necessary reuirements; such as


superindendence, maintenance works and etc as per the
H Item 1.00 27,960,000.00 27,960,000.00 2.78% 100% 100% B
Conditions of Contract, except the temporary road measured
under bill 5.

TOTAL OF Bill 01, GENERAL ITEMS SUMMARY 739,024,000.00

Payment Code Description:


A To be paid in full once it is Provided
A1 Paid as a proportion of Premiums paid
B To be paid equally as per Contract duration (% of 36 months)
B1 To be paid equally once it provided as per balance duration (% of 10 months)
C To be paid as per agreed % of value of work completed (excl. Prelim & PS)
C1 To be paid as per agreed % of value of work completed (excl.Prov. Sum)
C2 To be paid as per agreed % of value of work completed of Utility Works only
C3 To be paid as per agreed % in full once it is Provided
C4 To be paid as per agreed % of value of work completed of Structure (B of Q no.21,22,23 & 24) Works only
D To be paid equally as per Programme (Baseline) Duration of item provided.
E Re-measurable
F To be paid as per % of submittals received

DESIGN AND BUILD OF AL KHOR EXPRESSWAY Page 1 of 351 APPENDIX B3


Contract No: C2017/113
Description: Design and Build of Al Khor Expressway
Employer: Public Works Authority
Consultant: KEO International Consultants
Contractor: TEKFEN Construction and Installation Co., Inc
APPENDIX B4 - PREVIOUS PAYMENT CERTIFICATES

S/N Description Date Amount (QR)

1 Payment Certificate No.1 - Advance Payment 1,520,000,000.00


2 Payment Certificate No. 2 12-Feb -2017 21,653,592.00

3 Payment Certificate No. 3 02-Mar -2017 140,836,857.38


4 Payment Certificate No. 4 03-Apr -2017 90,619,386.30
5 Payment Certificate No. 5 03-May -2017 90,160,427.84

6 Payment Certificate No. 6 06-Jun -2017 80,746,959.31


7 Payment Certificate No. 7 02-Jul -2017 76,394,135.03
8 Payment Certificate No. 8 02-Aug -2017 80,493,662.34
9 Payment Certificate No. 9 28-Aug -2017 119,928,582.44

10 Payment Certificate No. 10 10-Oct -2017 195,245,862.48


11 Payment Certificate No. 11 22-Nov -2017 59,735,499.10
12 Payment Certificate No. 12 22-Nov -2017 165,135,197.37
13 Payment Certificate No. 13 22-Nov -2017 237,997,969.97

14 Payment Certificate No. 14 30-Jan -2018 259,688,571.59


15 Payment Certificate No. 15 05-Mar -2018 261,103,914.13
16 Payment Certificate No. 16 05-Apr -2018 217,413,669.11

17 Payment Certificate No. 17 09-Apr -2018 107,909,113.54


18 Payment Certificate No. 18 10-May -2018 276,513,703.08
19 Payment Certificate No. 19 28-May -2018 50,335,419.09
20 Payment Certificate No. 20 05-Jun -2018 263,220,825.82

21 Payment Certificate No. 21 01-Jul -2018 185,239,929.68


22 Payment Certificate No. 22 01-Aug -2018 229,313,626.34
23 Payment Certificate No. 23 09-Aug -2018 45,251,653.39

TOTAL SUM OF PREVIOUS PAYMENT 4,774,938,557.33

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 2/351 APPENDIX B4


Interim Payment No: 24
Period Ending : 21-Aug-2018
Recommend. Date : 4-Sep-2018
IX B4 - PREVIOUS PAYMENT CERTIFICATES

Remarks

Advance Payment
Interim Payment (Nov & Dec 2016)

Interim Payment (Jan 2017)


Interim Payment (Feb & Mar 2017\)
Interim Payment (Apr 2017)

Interim Payment (May 2017)


Interim Payment (June 2017)
Interim Payment (July 2017)
Interim Payment (Aug 2017)

Interim Payment (10 Oct 2017)


Interim Payment (21 Oct 2017)
Interim Payment (21 Nov 2017)
Interim Payment (10 Dec 2017)

Interim Payment (21 Jan 2018)


Interim Payment (21 Feb 2018)
Interim Payment (21 Mar 2018)

Release of Retention
Interim Payment (21 Apr 2018)
Release of Retention
Interim Payment (21 May 2018)

Interim Payment (21 June 2018)


Interim Payment (21 July 2018)
Release of Retention

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 3/351 APPENDIX B4


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B5 - SUMMARY OF CONTRACT VARIATION ORDERS
(APPROVED SITE INSTRUCTIONS)
CERTIFIE
SITE ESTIMATED AMOUNT ON CR (QR)
VARIATION AM
Sr. No. S.I No. DESCRIPTION INSTRUCTION
ORDER NO
STATUS Additions Omissions TOTAL PREVIOUS

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 4/351 APPENDIX B5


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B5 - SUMMARY OF CONTRACT VARIATION ORDERS
(APPROVED SITE INSTRUCTIONS)
CERTIFIE
SITE ESTIMATED AMOUNT ON CR (QR)
VARIATION AM
Sr. No. S.I No. DESCRIPTION INSTRUCTION
ORDER NO
STATUS Additions Omissions TOTAL PREVIOUS

Total in QR 0.00 0.00 0.00 -

Total Carried To Appendix B5 (Summary of Contract Variations) in QR -

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 5/351 APPENDIX B5


Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 4-Sep-2018
OF CONTRACT VARIATION ORDERS
SITE INSTRUCTIONS)
CERTIFIED FOR PAYMENT CERTIFIED PERCENTAGE
AMOUNT (QR) AMOUNT Variation Order Amount
THIS MONTH (Estimate)
THIS MONTH TO-DATE PREVIOUS QR TO-DATE QR
QR

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 6/351 APPENDIX B5


Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 4-Sep-2018
OF CONTRACT VARIATION ORDERS
SITE INSTRUCTIONS)
CERTIFIED FOR PAYMENT CERTIFIED PERCENTAGE
AMOUNT (QR) AMOUNT Variation Order Amount
THIS MONTH (Estimate)
THIS MONTH TO-DATE PREVIOUS QR TO-DATE QR
QR

- -

- -

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 7/351 APPENDIX B5


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B6 - RETENTION SUMMARY

Net Retention
Payment Cumulative Gross Cumulative
S/N Description Date Amount
No. Certified Retention
(a)
1 1 Advance Payment
2 2 Payment for Works done as of End 25 December 2016 12-Feb-17 28,871,456.00 1,443,572.80 1,443,572.80
3 3 Payment for Works done as of End 25 January 2017 2-Mar-17 216,653,932.50 10,832,696.63 9,389,123.83
4 4 Payment for Works done as of End 25 March 2017 3-Apr-17 337,479,780.91 16,873,989.05 6,041,292.42
5 5 Payment for Works done as of End 25 April 2017 3-May-17 457,693,684.70 22,884,684.24 6,010,695.19
6 6 Payment for Works done as of End 25 May 2017 6-Jun-17 565,356,297.11 28,267,814.86 5,383,130.62
7 7 Payment for Works done as of End 25 June 2017 2-Jul-17 667,215,143.81 33,360,757.19 5,092,942.33
8 8 Payment for Works done as of End 25 July 2017 2-Aug-17 774,540,026.94 38,727,001.35 5,366,244.16
9 9 Payment for Works done as of End 25 August 2017 28-Aug-17 934,444,803.52 46,722,240.18 7,995,238.83
10 10 Payment for Works done as of End 10 October 2017 10-Oct-17 1,194,772,620.16 59,738,631.01 13,016,390.83
11 11 Payment for Works done as of End 21 October 2017 22-Nov-17 1,274,419,952.30 63,720,997.62 3,982,366.61
12 12 Payment for Works done as of End 21 November 2017 22-Nov-17 1,494,600,215.45 74,730,010.77 11,009,013.15
13 13 Payment for Works done as of End 10 December 2017 17-Dec-17 1,811,930,842.08 90,596,542.10 15,866,531.33
14 14 Payment for Works done as of End 21 January 2018 30-Jan-18 2,158,182,270.86 107,909,113.54 17,312,571.44
15 15 Payment for Works done as of End 21 February 2018 5-Mar-18 2,506,320,823.04 125,316,041.15 17,406,927.61
16 16 Payment for Works done as of End 21 March 2018 5-Apr-18 2,796,205,715.19 139,810,285.76 14,494,244.61

17 17 Payment for Release of Retention Money 9-Apr-18 2,796,205,715.19 139,810,285.76 0.00

18 18 Payment for Works done as of End 21 April 2018 10-May-18 3,164,890,652.63 158,244,532.63 18,434,246.87

19 19 Payment for Release of Retention Money 28-May-18 3,164,890,652.63 158,244,532.63 0.00

20 20 Payment for Works done as of End 21 May 2018 5-Jun-18 3,515,851,753.72 175,792,587.69 17,548,055.06
21 21 Payment for Works done as of End 21 June 2018 1-Jul-18 3,762,838,326.63 188,141,916.33 12,349,328.64

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 8/351 APPENDIX B6


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B6 - RETENTION SUMMARY

Net Retention
Payment Cumulative Gross Cumulative
S/N Description Date Amount
No. Certified Retention
(a)
22 22 Payment for Works done as of End 21 July 2018 1-Aug-18 4,069,923,720.41 203,496,186.02 15,354,269.69

23 23 Payment for Release of Retention Money 9-Aug-18 4,069,923,720.41 203,496,186.02 0.00

24 24 Payment for Works done as of End 21 August 2018 4-Sep-18 4,892,444,383.80 244,622,219.19 41,126,033.17

TOTAL QAR 244,622,219.19


Balance Retention Amount after Release of Retention (QAR) 41,126,033.17

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 9/351 APPENDIX B6


Interim Payment No: 24
Period Ending : 21-Aug-2018
Recommend. Date: 4-Sep-2018
B6 - RETENTION SUMMARY

Release of Retention
Remarks
(b)

No retention in Advance Payment


Retention 5% (From Total Work Value To Date)
Retention 5% (From Total Work Value To Date)
Retention 5% (From Total Work Value To Date)
Retention 5% (From Total Work Value To Date)
Retention 5% (From Total Work Value To Date)
Retention 5% (From Total Work Value To Date)
Retention 5% (From Total Work Value To Date)
Retention 5% (From Total Work Value including material on site)
Retention 5% (From Total Work Value including material on site)
Retention 5% (From Total Work Value including material on site)
Retention 5% (From Total Work Value including material on site)
Retention 5% (From Total Work Value including material on site)
Retention 5% (From Total Work Value including material on site)
Retention 5% (From Total Work Value including material on site)
Retention 5% (From Total Work Value including material on site)

Release of Retention by providing Bank Gurantee (The amount of


107,909,113.54
retention upto the period ending 21 January 2018)

Retention 5% (From Total Work Value including material on site)

Release of Retention by providing Bank Gurantee (Months of Feb,


50,335,419.09
Mar & Apr 18)

Retention 5% (From Total Work Value including material on site)


Retention 5% (From Total Work Value including material on site)

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 10/351 APPENDIX B6


Interim Payment No: 24
Period Ending : 21-Aug-2018
Recommend. Date: 4-Sep-2018
B6 - RETENTION SUMMARY

Release of Retention
Remarks
(b)

Retention 5% (From Total Work Value including material on site)

Release of Retention by providing Bank Gurantee (Months of May,


45,251,653.39
Jun & Jul 18)

Retention 5% (From Total Work Value including material on site)

203,496,186.02
41,126,033.17 c=a-b

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 11/351 APPENDIX B6


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B7 - ADVANCE PAYMENT
Payment
S/N Description Date Amount
No.

1 1 Advance Payment (20% of Contract Sum) 1,520,000,000.00

2 Recovery of Advance Payment


2 Works done as of End 25 December 2016 12-Feb-17 5,774,291.20
3 Works done as of End 25 January 2017 2-Mar-17 37,556,495.30
4 Works done as of End 25 March 2017 3-Apr-17 24,165,169.68
5 Works done as of End 25 April 2017 3-May-17 24,042,780.76
6 Works done as of End 25 May 2017 6-Jun-17 21,532,522.48
7 Works done as of End 25 June 2017 2-Jul-17 20,371,769.34
8 Works done as of End 25 July 2017 2-Aug-17 21,464,976.63
9 Works done as of End 25 August 2017 28-Aug-17 31,980,955.31
10 Works done as of End 10 October 2017 10-Oct-17 52,065,563.33
11 Works done as of End 21 October 2017 22-Nov-17 15,929,466.43
12 Works done as of End 21 November 2017 22-Nov-17 44,036,052.63
13 Works done as of End 10 December 2017 17-Dec-17 63,466,125.33
14 Works done as of End 21 January 2018 30-Jan-18 69,250,285.75
15 Works done as of End 21 February 2018 5-Mar-18 69,627,710.44
16 Works done as of End 21 March 2018 5-Apr-18 57,976,978.43
17 Release of Retention Money 9-Apr-18 0.00
18 Works done as of End 21 April 2018 10-May-18 73,736,987.49
19 Release of Retention Money 28-May-18 0.00
20 Works done as of End 21 May 2018 5-Jun-18 70,192,220.21
21 Works done as of End 21 June 2018 1-Jul-18 49,397,314.59
22 Works done as of End 21 July 2018 1-Aug-18 61,417,078.75
23 Release of Retention Money 9-Aug-18 0.00
24 Works done as of End 21 August 2018 21-Aug-18 164,504,132.68

Total Recovery of Advance Payment 978,488,876.76

Remaining Unrecovered Advance Payment QR 541,511,123.24

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 12/351 APPENDIX B7


Interim Payment No: 24
Period Ending : 21-Aug-2018
Recommend. Date: 4-Sep-2018
X B7 - ADVANCE PAYMENT

Remarks

a-b = c

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 13/351 APPENDIX B7


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority Interim Paym
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc Recommen

APPENDIX "B8" MATERIAL ON SITE SUMMARY

Certified MOS
S.No BoQ Bill Material Type Amount (QR)
Previous This Month

1 10 KAHRAMAA - ELECTRICAL WORKS -

2 6.2 STORM WATER TUNNEL AND SHAFTS 591,910.80 -

3 7 KAHRAMAA - WATER WORKS - -

4 4.1-4.4 AL KHOR EXPRESSWAY ROAD WORKS 43,386,642.97 11,174,273.82

5 11 STREET LIGHTING WORKS - 11,654,923.28

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 14/351 APPENDIX B8


Total QR 43,978,553.77 22,829,197.10

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 15/351 APPENDIX B8


Interim Payment No : 24
Period Ending : 21-Aug-18
Recommend. Date: 4-Sep-18

B8" MATERIAL ON SITE SUMMARY

Certified MOS
Amount (QR) Remarks
To Date

591,910.80

54,560,916.79

11,654,923.28

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 16/351 APPENDIX B8


66,807,750.87

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 17/351 APPENDIX B8


Project Name: DESIGN AND BUILD OF AL KHOR EXPRESSWAY
Employer: Public Works Authority Interim P
Consultant: KEO International Consultants
Contractor: TEKFEN Construction and Installation Co., Inc Recom

APPENDIX B8A - MATERIAL ON SITE - DETAILS


As per BOQ Material Delivered to Site Material Used Balance Qty
% Allow for
Ref Material Invoice Rate Total Material Cost Material On
Qty claimed in Work Site
Unit Qty Rate Previous This Month Cumulative (A) Qty used (B) (A-B)
Done

BOQ Items Contract Work


10 KAHRAMAA - ELECTRICAL WORKS
i CU/XLPE/CW/LEAD/HDPE (66KV) 1x2000 m NA NA 2,253.00 2,253.00 2,253.00 0.00 947.10 0.00 80%
ii CU/XLPE/CW/LEAD/HDPE (132KV) 1x2000 m NA NA 13,077.00 13,077.00 13,077.00 0.00 973.78 0.00 80%
LV Cables (4C 300mm2 Cu/XLPE/SWA/PVC
iii m NA NA 4,543.00 0.00 4,543.00 4,543.00 0.00 366.50 0.00 80%
Cable)
MV Cables (3C 240mm2 Cu/XLPE/SWA/PVC
iv m NA NA 3,603.00 0.00 3,603.00 3,603.00 0.00 355.80 0.00 80%
Cable+Pilot Cable)
Subtotal

11 STREET LIGHTING WORKS

i H: 8m Single Bracket; 1x45W no. 942 942 1,162.53 1,095,103.26 80%

ii H: 10m Single Bracket; 1x45W no. 7 7 1,608.56 11,259.92 80%


iii H: 10m Single Bracket; 1x250W no. 768 768 1,608.56 1,235,374.08 80%
iv H: 10m Single Bracket; 2x250W no. 8 8 1,665.60 13,324.80 80%

v H: 14m Single Bracket; 1x45W no. 10 10 2,429.44 24,294.40 80%


vi H: 14m Single Bracket; 1x250W no. 6 6 2,429.44 14,576.64 80%
vii H: 14m Single Bracket; 1x400W no. 430 430 2,429.44 1,044,659.20 80%
viii H: 14m Double Bracket; 2x400W no. 154 154 22 132 2,514.85 331,960.20 80%

ix H: 30m High Mast Column Pole; 3x400W no. 130 130 22,776.00 2,960,880.00 80%
x H: 30m High Mast Column Pole; 3x600W no. 204 204 21,447.40 4,375,269.60 80%
xi H: 30m High Mast Column Pole; 3x600W no. 312 312 160 152 22,776.00 3,461,952.00 80%

Subtotal
6.2 STORM WATER TUNNEL AND SHAFTS
RC Jacking Pipe (ID-3000mm Dia) - for Storm
i m NA NA 3,366.00 0.00 3,366.00 3,366.00 0.00 5,100.00 0.00 80%
Water Micro Tunnel

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 18/351 APPENDIX B8A


RC Jacking Pipe (ID-2400mm Dia) - for Storm
ii m NA NA 195.00 0.00 195.00 195.00 3,794.30 739,888.50 80%
Water Micro Tunnel
Subtotal
7 KAHRAMAA - WATER WORKS

i 600mm Dia DI pipes for Portable Water Works m NA NA 4,998.00 0.00 4,998.00 4,998.00 0.00 486.80 0.00 80%
Subtotal

4.1-4.4 AL KHOR EXPRESSWAY ROAD WORKS

i Gabbro 0-5mm t NA NA 156,900.99 83.00 13,022,782.17 80%

ii Gabbro 5-32mm t NA NA 523,592.49 93.00 48,694,101.57 80%

iii Lime Stone 0-5 mm t NA NA 1,012.06 0.00 1,012.06 1,012.06 0.00 76.46 0.00 80%

iv Lime Stone 5-32 mm t NA NA 74,997.25 86.46 6,484,262.24 80%

Subtotal
SubTotal (BOQ Items)

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 19/351 APPENDIX B8A


Interim Payment No: 24
Period Ending : 21-Aug-2018
Recommend. Date: 4-Sep-2018

ATERIAL ON SITE - DETAILS

MOS Amount Remarks

0.00
0.00
0.00

0.00

876,082.61

9,007.94
988,299.26
10,659.84

19,435.52
11,661.31
835,727.36
265,568.16

2,368,704.00
3,500,215.68
2,769,561.60

11,654,923.28

0.00

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 20/351 APPENDIX B8A


591,910.80

591,910.80

0.00
0.00

Invoice Rate = QAR 71.00 for Cost of Material (B4-QT1) +QAR


10,418,225.74 12.00 for Transportation (B4-QT2) = 83.00 QAR

Invoice Rate = QAR 81.00 for Cost of Material (B4-QT1) +QAR


38,955,281.26 12.00 for Transportation (B4-QT2) = 93.00 QAR

Invoice Rate = QAR 71.00 for Cost of Material (B4-QT1) +QAR


0.00 5.46 for Average Cost of Transportation per (B4-QT3 & QT44) =
76.46 QAR

Invoice Rate = QAR 81.00 for Cost of Material (B4-QT1) +QAR


5,187,409.79 5.46 for Average Cost of Transportation per (B4-QT3 & QT44) =
86.46 QAR

54,560,916.79
66,807,750.87

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 21/351 APPENDIX B8A


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B9 - SUMMARY OF DEDUCTION FOR NCR & OTHER ITEMS

Amount of De
S/N REFERENCE # Description
Previous

1 AKE-BTR-KEO-NCR-UT-00046 400mm Potable Water Dry Leg… 51,500.00

2 AKE-BTR-KEO-NCR-RD-00050 & 55 Duduction for poor quality 46,700.00

3 AKE-BTR-KEO-NCR-SG-00072 Obscured Standard Traffic and Directional Sign…. 24,000.00

The insitu air voids and density of Asphalt Wearing Course at CH22+240 to
4 AKE-BTR-KEO-NCR-RD-00076 75,000.00
CH23+880 LHS (both lanes)….

The Supervision Consultant observed the poor quality work and many uncompleted
5 AKE-PH0-KEO-NCR-SL-00097 12,000.00
items related to Street lighting system at TTM2….

Please find attached Asphalt Base Course class A- 151 layer (Location CH:11+190
6 AKE-PH0-KEO-NCR-RD-00172 to 11+430 RHS}, Core samples in place air voids tests results not complying with 11,500.00
QCS 2014 requirements between 6 to 8 % (ACES and Fugro labs).

Package 1, IC-A - Ch. 1 +300 - One portion of EN6 road crossing ducts was found
7 AKE-PH0-KEO-NCR-EL-00204 10,000.00
demolished due to clashing with wet utility line as…..
Layers of BC Class A at 0+324 to 0+615 (RHS). No coring was done on the
8 AKE-PH0-KEO-NCR-RD-00224 14,600.00
preceding layers (BC Class A….
With reference to ACES lab Test Report no. TMR 18051435 Asphalt Base Course,
9 AKE-PH0-KEO-NCR-QA-00231 Class A (1st layer) In-place Air Voids and Relative Density of 6 pairs of cores from 12,000.00
Ch. 0+330 to Ch. 0+570…

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 22/351 APPENDIX B9


Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc
APPENDIX B9 - SUMMARY OF DEDUCTION FOR NCR & OTHER ITEMS

Amount of De
S/N REFERENCE # Description
Previous

Total Amount carried forward to summary sheet (QR) 257,300.00

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 23/351 APPENDIX B9


Interim Payment No: 24
Period Ending : 21-Aug-2018
Recommend. Date: 4-Sep-2018
Y OF DEDUCTION FOR NCR & OTHER ITEMS

Amount of Deduction (QR)


Remarks
This Month To Date

0.00 51,500.00

0.00 46,700.00

0.00 24,000.00

0.00 75,000.00

0.00 12,000.00

0.00 11,500.00

0.00 10,000.00

0.00 14,600.00

0.00 12,000.00

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 24/351 APPENDIX B9


Interim Payment No: 24
Period Ending : 21-Aug-2018
Recommend. Date: 4-Sep-2018
Y OF DEDUCTION FOR NCR & OTHER ITEMS

Amount of Deduction (QR)


Remarks
This Month To Date

0.00 257,300.00

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 25/351 APPENDIX B9


Contract No: C2017/113
Project Name: Design and Build of Al Khor Expressway Interim Payment No : 24
Contractor: TEKFEN Construction and Installation Co., Inc Period Ending : 21-Aug-18

Consultant: KEO International Consultants Recommend. Date: 4-Sep-18

APPENDIX B10 - STATUS OF CLAIMS / MISSING ITEMS / OTHER DISPUTES CLAIMED BY CONTRACTOR

AMOUNT CLAIMED BY
REF DESCRIPTION
CONTRACTOR
REMARKS

OTHER WORKS / ADDITIONS (INCLUDED BY CONTRACTOR)

Total Amount QR 0.00

DESIGN AND BUILD OF AL KHOR EXPRESSWAY Page 26 of 351 Appendix B10 - Works other than SI/VO
PAYMENT CERTIFICATE LEDGER
Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc

Certificate No Less
Period Certificate Previous Monthly Valuation Less
Total Valuation Advance Payment Recovery of Less KPI Net Valuation
New Old Ending Date Valuation (Certified) Retention
Advance Payment
1 1,520,000,000.00
2 1 25-Dec-16 12-Feb-17 28,871,456.00 - 28,871,456.00 - (5,774,291.20) (1,443,572.80) 21,653,592.00
3 2 25-Jan-17 2-Mar-17 216,653,932.50 28,871,456.00 187,782,476.50 (37,556,495.30) (9,389,123.83) 140,836,857.37
4 3 25-Mar-17 3-Apr-17 337,479,780.91 216,653,932.50 120,825,848.41 (24,165,169.68) (6,041,292.42) 90,619,386.31
5 4 25-Apr-17 3-May-17 457,693,684.70 337,479,780.91 120,213,903.79 (24,042,780.76) (6,010,695.19) 90,160,427.84
6 5 25-May-17 6-Jun-17 565,356,297.11 457,693,684.70 107,662,612.41 (21,532,522.48) (5,383,130.62) 80,746,959.31
7 6 25-Jun-17 2-Jul-17 667,215,143.81 565,356,297.11 101,858,846.70 (20,371,769.34) (5,092,942.33) 76,394,135.03
8 7 25-Jul-17 2-Aug-17 774,540,026.94 667,215,143.81 107,324,883.13 (21,464,976.63) (5,366,244.16) 80,493,662.34
9 8 25-Aug-17 28-Aug-17 934,444,803.52 774,540,026.94 159,904,776.58 (31,980,955.31) (7,995,238.83) 119,928,582.44
10 9 10-Oct-17 10-Oct-17 1,194,772,620.16 934,444,803.52 260,327,816.64 (52,065,563.33) (13,016,390.83) 195,245,862.48
11 21-Oct-17 21-Nov-17 1,274,419,952.30 1,194,772,620.16 79,647,332.14 (15,929,466.43) (3,982,366.61) 59,735,499.10
12 21-Nov-17 21-Nov-17 1,494,600,215.45 1,274,419,952.30 220,180,263.15 (44,036,052.63) (11,009,013.15) 165,135,197.37
13 10-Dec-17 17-Dec-17 1,811,930,842.08 1,494,600,215.45 317,330,626.63 (63,466,125.33) (15,866,531.33) 237,997,969.97
14 21-Jan-18 30-Jan-18 2,158,182,270.86 1,811,930,842.08 346,251,428.78 (69,250,285.75) (17,312,571.44) 259,688,571.59
15 21-Feb-18 5-Mar-18 2,506,320,823.04 2,158,182,270.86 348,138,552.18 (69,627,710.44) (17,406,927.61) 261,103,914.13
16 21-Mar-18 5-Apr-18 2,796,205,715.19 2,506,320,823.04 289,884,892.15 (57,976,978.43) (14,494,244.61) 217,413,669.11
17 21-Mar-18 9-Apr-18 2,796,205,715.19 2,796,205,715.19 0.00 0.00 107,909,113.54 107,909,113.54
18 21-Apr-18 10-May-18 3,164,890,652.63 2,796,205,715.19 368,684,937.44 (73,736,987.49) (18,434,246.87) 276,513,703.08
19 21-Apr-18 28-May-18 3,164,890,652.63 3,164,890,652.63 0.00 0.00 50,335,419.09 50,335,419.09
20 21-May-18 5-Jun-18 3,515,851,753.72 3,164,890,652.63 350,961,101.09 (70,192,220.21) (17,548,055.06) 263,220,825.82
21 21-Jun-18 1-Jul-18 3,762,838,326.63 3,515,851,753.72 246,986,572.91 (49,397,314.59) (12,349,328.64) 185,239,929.68

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 27/351 PAYMENT LADGER


PAYMENT CERTIFICATE LEDGER
Contract No : C2017/113
Description : Design and Build of Al Khor Expressway
Employer : Public Works Authority
Consultant : KEO International Consultants
Contractor : TEKFEN Construction and Installation Co., Inc

Certificate No Less
Period Certificate Previous Monthly Valuation Less
Total Valuation Advance Payment Recovery of Less KPI Net Valuation
New Old Ending Date Valuation (Certified) Retention
Advance Payment
22 21-Jul-18 1-Aug-18 4,069,923,720.41 3,762,838,326.63 307,085,393.78 (61,417,078.75) (15,354,269.69) 230,314,045.34
23 21-Jul-18 9-Aug-18 4,069,923,720.41 4,069,923,720.41 0.00 0.00 45,251,653.39 45,251,653.39
24 21-Aug-18 4-Sep-18 4,892,444,383.80 4,069,923,720.41 822,520,663.39 (164,504,132.68) (41,126,033.17) 616,890,497.54

TOTAL (QR) 4,892,444,383.80 1,520,000,000.00 (978,488,876.76) (41,126,033.17) 0.00 ###

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 28/351 PAYMENT LADGER


CERTIFICATE LEDGER
Period Ending : 21-Aug-18
PC. No. : 24

Original Contract Amount (QAR): 7,600,000,000.00


Variation (QAR):
Revised Contract Amount (QAR): 7,600,000,000.00
Less: L&A
Cumulative Net Payment On
Damages, OT of
Payable Amount This Certificate
Consultant
1,520,000,000.00
21,653,592.00 0.00 21,653,592.00
162,490,449.37 0.00 140,836,857.37
253,109,835.68 0.00 90,619,386.31
343,270,263.52 0.00 90,160,427.84
424,017,222.83 0.00 80,746,959.31
500,411,357.86 0.00 76,394,135.03
580,905,020.20 0.00 80,493,662.34
700,833,602.64 0.00 119,928,582.44
896,079,465.12 0.00 195,245,862.48
955,814,964.22 0.00 59,735,499.10
1,120,950,161.59 0.00 165,135,197.37
1,358,948,131.56 0.00 237,997,969.97
1,618,636,703.15 0.00 259,688,571.59
1,879,740,617.28 0.00 261,103,914.13
2,097,154,286.39 0.00 217,413,669.11
2,205,063,399.93 0.00 107,909,113.54
2,481,577,103.01 0.00 276,513,703.08
2,531,912,522.10 0.00 50,335,419.09
2,795,133,347.92 0.00 263,220,825.82
2,980,373,277.60 0.00 185,239,929.68

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 29/351 PAYMENT LADGER


CERTIFICATE LEDGER
Period Ending : 21-Aug-18
PC. No. : 24

Original Contract Amount (QAR): 7,600,000,000.00


Variation (QAR):
Revised Contract Amount (QAR): 7,600,000,000.00
Less: L&A
Cumulative Net Payment On
Damages, OT of
Payable Amount This Certificate
Consultant
3,210,687,322.94 (1,000,419.00) 229,313,626.34
3,255,938,976.33 0.00 45,251,653.39
3,872,829,473.87 0.00 616,890,497.54

5,391,829,054.87

DESIGN AND BUILD OF AL KHOR EXPRESSWAY 30/351 PAYMENT LADGER


PAYMENT CERTIFICATE RECOMMENDATION REPORT

Contract No : C2017/113
Project Name : Design and Build of Al Khor Expressway
Employer: Public Works Authority Interim Payment No :
Consultant : KEO International Consultants Period Ending :
Contractor : TEKFEN Construction and Installation Co., Inc Recommend. Date :

1. Assessment and Evaluation

Contractor Claimed
SC Certified Amount
Amount
Description
(A) (B)
(QAR) (QAR)
a) Preliminaries 575,813,939.20 575,813,939.20

b) Design Works 147,184,374.00 147,184,374.00

c) Value of executed Works 4,357,515,670.22 4,102,895,619.73

d) Value of Variation Works 0.00 0.00

e) Materials on site 64,446,080.20 66,807,750.87

f) Claims / Variations 0.00 0.00

g) Less: Deduction for NCR & Other Items 0.00 (257,300.00)

Gross Cum. Amount 5,144,960,063.62 4,892,444,383.80

h) Less: Retention (257,248,003.18) (244,622,219.19)

j) Release of Retention 158,244,532.63 203,496,186.02

k) Less: Penalty for Delay 0.00 (1,000,419.00)

m) Unrecovered advance Payment 491,007,987.28 541,511,123.24

Net Cum. Amount 5,536,964,580.35 5,391,829,054.87

Previous Net Cum. Amount 5,521,613,935.52 5,829,912,603.73

Net Period Certified Amount 15,350,644.83 (438,083,548.86)

2. Valuation Comments

Description Difference Justification

N/A N/A

DESIGN AND BUILD OF AL KHOR EXPRESSWAY Page 31 of 351 PAYMENT CERTIFCATE RECOMMENDATION REPORT
PAYMENT CERTIFICATE RECOMMENDATION REPORT

Contract No : C2017/113
Project Name : Design and Build of Al Khor Expressway
Employer: Public Works Authority Interim Payment No :
Consultant : KEO International Consultants Period Ending :
Contractor : TEKFEN Construction and Installation Co., Inc Recommend. Date :

3. Bonds, Insurances & Commercial Registration

SN Description Expiry Date

i Performance Bond 29 March 2021

ii Advance Payment Bond 26 November 2019

iii Contractors All Risk Policy 26 November 2019

iv Third Party Liability Insurance 26 November 2019

v Workmen Compensation Policy 30 December 2020

vi Professional Indemnity Cover 30 December 2020

vii Contractor Commercial Registration 12 April 2020

viii Retention Money Guarantee 30 December 2020

4. Recommendation

Pursuant to Clause 13.3 of General Conditinos of Contract, the Supervision Consultant recommendations that
IPC-24 for works executed by the Contractor up to 21 August 2018 in the net cumulative amount of
QAR 5,391,829,054.87 and period net amount of -QAR 438,083,548.86 be approved by the Authority and
subsequently paid to the Contractor.

Prepared and Recommended By:

Thomas Connolly
Senior Quantity Surveyor
KEO International Consultants

DESIGN AND BUILD OF AL KHOR EXPRESSWAY Page 32 of 351 PAYMENT CERTIFCATE RECOMMENDATION REPORT
TION REPORT

24
21 Aug 2018
4 Sep 2018

Difference

(A-B)
(QAR)
0.00

0.00

254,620,050.49

0.00

(2,361,670.67)

0.00

257,300.00

(12,625,783.99)

(45,251,653.39)

(50,503,135.96)

145,135,525.48

(308,298,668.21)

453,434,193.69

Referenced
Attachment

DESIGN AND BUILD OF AL KHOR EXPRESSWAY Page 33 of 351 PAYMENT CERTIFCATE RECOMMENDATION REPORT
TION REPORT

24
21 Aug 2018
4 Sep 2018

Days valid to date

938

449

449

449

849

849

587

849

nt recommendations that
ive amount of
d by the Authority and

and Recommended By:

ntity Surveyor
ational Consultants

DESIGN AND BUILD OF AL KHOR EXPRESSWAY Page 34 of 351 PAYMENT CERTIFCATE RECOMMENDATION REPORT
Contract No : C2017/113
Project Name : Design and Build of Al Khor Expressway
Employer: Public Works Authority Interim Payment No :
Consultant : KEO International Consultants Period Ending :
Contractor : TEKFEN Construction and Installation Co., Inc Recommend. Date :

A. Recommended Gross Value vs Planned Gross Value


THIS MONTH VALUE (QAR)

Bill Planned Gross Value Recommended Gross Planned Vs


Description Contract Amount (QAR) (QAR) Month of Aug Value Month of Aug Recommended
No.
2018 2018 Variance (QAR)

A B C = B-A

1 GENERAL ITEMS 739,024,000.00 16,091,178 56,549,618 40,458,440


2 DESIGN 147,820,000.00 0 0
3 CONSTRUCTION OF BU THELAH ROAD 119,928,000.00 0 0
0 AL KHOR EXPRESSWAY ROAD WORKS 0
4.1 AKE-ROAD WORKS - PACKAGE 1 809,783,600.90 104,463,715
4.2 AKE-ROAD WORKS - PACKAGE 2 & 3 818,197,463.60 153,418,011 150,859,246 240,330,813
4.3 AKE-ROAD WORKS - PACKAGE 4 906,314,935.50 138,425,863
0 INTERCHANGES WORKS 0
5.1 INTERCHANGE A 221,616,000.00 9,088,806 15,916,260 6,827,454
5.2 INTERCHANGE B 263,720,000.00 13,444,583 42,770,968 29,326,385
5.3 INTERCHANGE C 285,228,000.00 10,448,237 44,455,628 34,007,391
5.4 INTERCHANGE D 217,360,000.00 7,617,497 11,432,278 3,814,781
5.5 INTERCHANGE E 56,772,000.00 4,722,841 18,635,491 13,912,650
5.6 INTERCHANGE F 272,536,000.00 17,189,971 8,463,184 (8,726,787)
5.7 INTERCHANGE G 185,744,000.00 16,647,342 34,343,611 17,696,269
5.8 INTERCHANGE H 173,432,000.00 12,929,163 59,491,980 46,562,817
0 UTILITIES WORKS 0
6.1 STORMWATER DRAINAGE 613,139,644.80 49,936,156 23,457,840 (26,478,316)
6.2 STORM WATER TUNNEL AND SHAFTS 315,400,000.00 23,594,933 24,956,033 1,361,100
6.3 CONSTRUCTION OF PUMP STATION 3,753,676.80 428,683 0 (428,683)
7 KAHRAMAA - WATER WORKS 131,691,494.40 14,406,288 7,215,951 (7,190,337)
8 TSE WORKS 311,261,918.40 37,169,358 20,741,730 (16,427,628)
Page 35 of 351
Contract No : C2017/113
Project Name : Design and Build of Al Khor Expressway
Employer: Public Works Authority Interim Payment No :
Consultant : KEO International Consultants Period Ending :
Contractor : TEKFEN Construction and Installation Co., Inc Recommend. Date :

9 FOUL SEWER 20,293,315.20 3,925,016 7,043,953 3,118,937


10 KAHRAMAA - ELECTRICAL WORKS 370,147,723.20 19,860,378 18,035,192 (1,825,186)
11 STREET LIGHTING 252,473,865.60 19,880,653 8,248,662 (11,631,991)
12 TELECOM - QNBN, OOREDOO AND VODAFONE WORKS 53,528,995.20 772,267 123,384 (648,883)
13 QAF WORKS 41,231,793.60 3,959,051 1,987,191 (1,971,860)
UGN WORKS
14 (MOI - SSD)
157,517,572.80 15,387,434 2,073,687 (13,313,747)
15 TESTING, COMMISSIONING AND HANDING OVER 12,084,000.00 0 0
0
16 PROVISIONAL SUM - LANDSCAPE AND IRRIGATION NETWORK 100,000,000.00 4,866,667 0 (4,866,667)
0
Add Material On Site 22,829,197 22,829,197
Less Deduction for NCR 0 0
TOTAL 7,600,000,000.00 455,784,510 822,520,662 366,736,152

Page 36 of 351
B.

2,000,000,000
3,000,000,000
4,000,000,000
5,000,000,000
6,000,000,000
7,000,000,000
8,000,000,000
Contract No : C2017/113

187,782,477.00
187,782,477.00
120,825,848.00
Employer: Public Works Authority

120,825,848.00
120,213,904.00
120,213,904.00
Consultant : KEO International Consultants

107,662,612.00
107,662,612.00
101,858,847.00
101,858,847.00
107,324,883.00
Project Name : Design and Build of Al Khor Expressway

107,324,883.00
Contractor : TEKFEN Construction and Installation Co., Inc

159,904,777.00
159,904,777.00
260,330,000.00
260,327,817.00
,647,332.00
,647,332.00
Recommended Gross Value vs Planned Gross Value Histogram

220,180,263.00
220,180,263.00
317,330,627.00
317,330,627.00
346,251,429.00
346,251,429.00
355,843,819.00
348,138,551.00

Page 37 of 351
389,474,330.00
289,884,892.00
441,123,149.00
368,684,937.00
409,595,467.00
350,961,101.00
327,038,000.00
246,986,573.00
412,538,958.00
307,085,394.00
455,784,510.00

379,100,000.00

295,212,000.00

414,374,000.00

297,034,000.00

285,483,805.00

293,543,246.00

208,293,879.00

111,083,769.00

,803,322.00
Recommend. Date :
Interim Payment No :
Period Ending :

10.00
Employer:

1,000,000,000
2,000,000,000
3,000,000,000
4,000,000,000
5,000,000,000

0
IPC-2 28,871,456.00
(25-Dec-16) 28,871,456.00 Contract No : C2017/113

IPC-3 187,782,477.00
(25-Jan-17) 187,782,477.00
IPC-4 120,825,848.00
(25-Mar-17)
Public Works Authority

120,825,848.00
IPC-5 120,213,904.00
(25-Apr-17) 120,213,904.00
Consultant : KEO International Consultants

IPC-6 107,662,612.00
(25-May-17) 107,662,612.00
IPC-7 101,858,847.00
(25-Jun-17) 101,858,847.00
IPC-8 107,324,883.00
Project Name : Design and Build of Al Khor Expressway

(25-Jul-17) 107,324,883.00
Contractor : TEKFEN Construction and Installation Co., Inc

IPC-9 159,904,777.00
(25-Aug-17) 159,904,777.00
IPC-10 260,330,000.00
(10-Oct-17) 260,327,817.00
IPC-11 79,647,332.00
(21-Oct-17) 79,647,332.00
Monthly Cashflow IPC-12 220,180,263.00
(21-Nov-17) 220,180,263.00
IPC-13 317,330,
(21-Dec-17) 317,330,
IPC-14 34
(21-Jan-18) 34
IPC-15
(21-Feb-18) 3

Page 38 of 351
IPC-16
(21-Mar-18) 289,884,892.0
Recommended Amount

IPC-18
(21-Apr-18)

IPC-20
(21-May-18) 3
IPC-21 327,03
(21-Jun-18) 246,986,573.00
IPC-22
(21-Jul-18) 307,085,39
IPC-24
(21-Aug-18)
Accumulative Cashflow

IPC-25
(21-Sep-18)

IPC-26 295,212,000.
(21-Oct-18)

IPC-27
(21-Nov-18)

IPC-28 297,034,000.
(21-Dec-18)

IPC-29 285,483,805.00
(21-Jan-19)

IPC-30 293,543,246.0
(21-Feb-19)

IPC-31 208,293,879.00
(21-Mar-19)
Accumulative Recommended Amount

IPC-32 111,083,769.00
(21-Apr-19)

IPC-33 80,803,322.00
(21-May-19)
Recommend. Date :
Interim Payment No :
Period Ending :

IPC-34 53,520,910.00
(21-Jun-19)
24
21 Aug 2018
4 Sep 2018

Planned %

Remarks

Page 39 of 351
24
21 Aug 2018
4 Sep 2018

Page 40 of 351
409,595,467.00
350,961,101.00
327,038,000.00
246,986,573.00
412,538,958.00
307,085,394.00
455,784,510.00

379,100,000.00

295,212,000.00

414,374,000.00

297,034,000.00

285,483,805.00

293,543,246.00

208,293,879.00

111,083,769.00

,803,322.00

10.00

,354,218.00

1,131.00

.00
24

4 Sep 2018
21 Aug 2018

Page 41 of 351
100,000,000
150,000,000
200,000,000
250,000,000
300,000,000
350,000,000
400,000,000
450,000,000
500,000,000
IPC-20
(21-May-18) 3
IPC-21 327,03
(21-Jun-18) 246,986,573.00
IPC-22
(21-Jul-18) 307,085,39
IPC-24
(21-Aug-18)

Accumulative Cashflow
IPC-25
(21-Sep-18)

IPC-26 295,212,000.
(21-Oct-18)

IPC-27
(21-Nov-18)

IPC-28 297,034,000.
(21-Dec-18)

IPC-29 285,483,805.00
(21-Jan-19)

IPC-30 293,543,246.0
(21-Feb-19)

IPC-31 208,293,879.00
(21-Mar-19)

Accumulative Recommended Amount


IPC-32 111,083,769.00
(21-Apr-19)

IPC-33 80,803,322.00
(21-May-19)

IPC-34 53,520,910.00
(21-Jun-19)

IPC-35 79,354,218.00
(21-Jul-19)

IPC-36 67,261,131.00
(21-Aug-19)

IPC-37 43,342,671.00
(21-Sep-19)
24

IPC-38 26,724,602.00
(21-Oct-19)
4 Sep 2018
21 Aug 2018

IPC-39 15,290,000.00

Page 42 of 351
(25-Nov-19)
-
50,000,000
100,000,000
150,000,000
200,000,000
250,000,000
300,000,000
350,000,000
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 1 GENERAL ITEMS


CONTRACTUAL REQUIREMENTS

B01/1/A Performance Bond; in accordance with the Clause 4.2 of 123,120,000.00 100.00% 0.00% 100.00%
General Conditions of Contract

B01/1/B All insurances required for the contract; in accordance with Included
the Clauses 18.1, 18.2, 18.3 & 18.4 of General Conditions
of Contract

SPECIFIED / OTHER REQUIREMENTS

B01/1/C Provision of Engineer's Site Office and Facilities as per 8,436,000.00 100.00% 0.00% 100.00%
QCS 2014 Section 1 - General Part 11

B01/1/D Provision of Contractor's Site Office and Facilities as per 70,300,000.00 100.00% 0.00% 100.00%
QCS 2014 Section 1 - General Part 12

B01/43 Bill.1
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B01/1/E Allow for mobilizing Contractor's Equipment/Plant; as per 33,744,000.00 100.00% 0.00% 100.00%
Conditions of Contract

B01/1/F Allow for Obligations & Liabilities complying with Conditions 32,000,000.00 67.580% 0.000% 67.580%
of Contract

B01/1/G Allow for Quality Assurance, Testing and Health & Safety as 27,960,000.00 67.580% 0.000% 67.580%
per required by Conditions of Contract

B01/1/H Allow for other all necessary reuirements; such as 443,464,000.00 67.580% 0.000% 67.580%
superindendence, maintenance works and etc as per the
Conditions of Contract, except the temporary road
measured under bill 5.

B01/44 Bill.1
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO. 1 - GENERAL ITEMS Carried to Appendix B1


739,024,000.00
(Grand Summary Sheet)

B01/45 Bill.1
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

123,120,000.00 - 123,120,000.00

8,436,000.00 - 8,436,000.00

70,300,000.00 - 70,300,000.00

B01/46 Bill.1
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
33,744,000.00 - 33,744,000.00

18,031,040.00 3,594,560.00 21,625,600.00

15,754,621.20 3,140,746.80 18,895,368.00

249,878,660.08 49,814,311.12 299,692,971.20

B01/47 Bill.1
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

519,264,321.28 56,549,617.92 575,813,939.20

B01/48 Bill.1
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 2 - DESIGN WORKS

B02/1/A Design Works 147,820,000.00 99.570% 0.000% 99.570%

B02/49 Bill.2
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO. 2 - DESIGN WORKS Carried to Appendix B1


147,820,000.00
(Grand Summary Sheet)

B02/50 Bill.2
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

147,184,374.00 - 147,184,374.00

B02/51 Bill.2
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

147,184,374.00 - 147,184,374.00

B02/52 Bill.2
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 3. CONSTRUCTION OF BU THELAH


ROAD

CONSTRUCTION OF FARM ROAD

B03/1/A Site Clearance 111,982.77 100.00% 0.00% 100.00%

B03/1/B Relocation of Electrical Over Head Cables 562,162.50 100.00% 0.00% 100.00%

B03/1/C Road Diversions as required 972,915.90 100.00% 0.00% 100.00%


Earth Works including exacavation & filling works as
B03/1/D 8,657,002.68 95.00% 0.00% 95.00%
required
B03/1/E Road Crossing Ducts as required 3,746,250.90 100.00% 0.00% 100.00%

B03/1/F Aggregate Base Course Construction 4,310,811.96 100.00% 0.00% 100.00%

B03/1/G Asphalt Intermediate Course Construction 7,152,206.10 100.000% 0.000% 100.000%

B03/53 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B03/1/H Construction of Safety Guard Rail 2,254,346.58 95.000% 0.000% 95.000%

B03/1/J Road Markings 709,404.10 100.000% 0.000% 100.000%

B03/1/K Traffic Sings 266,060.27 100.00% 0.00% 100.00%

B03/1/L Street Lighting Works 1,238,856.24 100.00% 0.00% 100.00%

29,982,000.00 98.18% 0.00% 98.18%

B03/54 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF BU THELAH ROAD

B03/2/A Site Clearance 215,870.40 100.00% 0.00% 100.00%

B03/2/B Relocation of Electrical Over Head Cables 4,065,559.20 100.00% 0.00% 100.00%

B03/2/C Road Diversions as required 1,457,125.20 100.00% 0.00% 100.00%


Earth Works including exacavation & filling works as
B03/2/D 25,112,923.20 100.00% 0.00% 100.00%
required
B03/2/E Road Crossing Ducts as required 4,317,408.00 100.00% 0.00% 100.00%

B03/2/F Aggregate Base Course Construction 5,036,976.00 100.00% 0.00% 100.00%

B03/2/G Asphalt Base Course Construction 9,678,189.60 100.00% 0.00% 100.00%

B03/2/H Asphalt Intermediate Course Construction 6,961,820.40 100.00% 0.00% 100.00%

B03/55 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B03/2/J Asphalt Wearing Course Construction 5,360,781.60 100.00% 0.00% 100.00%

B03/2/K Construction of Safety Guard Rail 5,738,554.80 95.00% 0.00% 95.00%

B03/2/L Road Markings 1,390,565.16 100.00% 0.00% 100.00%

B03/2/M Traffic Sings 390,365.64 100.00% 0.00% 100.00%

B03/2/N Street Lighting Works 2,230,660.80 100.00% 0.00% 100.00%

71,956,800.00 99.60% 0.00% 99.60%

B03/56 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF OTHER ROADS (AL MAZROAA


ROAD, ROAD 5 & ROAD 6)

B03/3/A Site Clearance 23,985.60 100.00% 0.00% 100.00%

B03/3/B Relocation of Electrical Over Head Cables 503,697.60 100.00% 0.00% 100.00%
Earth Works including exacavation & filling works as
B03/3/C 3,813,710.40 100.00% 0.00% 100.00%
required
B03/3/D Road Crossing Ducts as required 239,856.00 100.00% 0.00% 100.00%

B03/3/E Aggregate Base Course Construction 887,467.20 100.00% 0.00% 100.00%

B03/3/F Asphalt Base Course Construction 1,607,035.20 100.00% 0.00% 100.00%

B03/3/G Asphalt Intermediate Course Construction 1,367,179.20 100.00% 0.00% 100.00%

B03/3/H Asphalt Wearing Course Construction 887,467.20 100.00% 0.00% 100.00%

B03/57 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B03/3/J Construction of Safety Guard Rail 1,607,035.20 95.00% 0.00% 95.00%

B03/3/K Road Markings 143,913.60 100.00% 0.00% 100.00%

B03/3/L Traffic Sings 71,956.80 100.00% 0.00% 100.00%

B03/3/M Street Lighting Works 839,496.00 100.00% 0.00% 100.00%

CONSTRUCTION OF SUBSTATIONS

Construction of 6 Nos of Package Substations and 1No


B03/3/N 5,996,400.00 99.983% 0.00% 99.983%
Indoor Substation

17,989,200.00 99.55% 0.00% 99.55%

B03/58 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B03/1 29,982,000.00 98.18% 0.00% 98.18%

From Page B03/2 71,956,800.00 99.60% 0.00% 99.60%

From Page B03/3 17,989,200.00 99.55% 0.00% 99.55%

B03/59 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 3. CONSTRUCTION OF BU THELAH ROAD


119,928,000.00 99.24% 0.00% 99.24%
Carried to Appendix B1 (Grand Summary Sheet)

B03/60 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

111,982.77 - 111,982.77

562,162.50 - 562,162.50

972,915.90 - 972,915.90

8,224,152.55 - 8,224,152.55

3,746,250.90 - 3,746,250.90

4,310,811.96 - 4,310,811.96

7,152,206.10 - 7,152,206.10

B03/61 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,141,629.25 - 2,141,629.25

709,404.10 - 709,404.10

266,060.27 - 266,060.27

1,238,856.24 - 1,238,856.24

29,436,432.54 - 29,436,432.54

B03/62 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

215,870.40 - 215,870.40

4,065,559.20 - 4,065,559.20

1,457,125.20 - 1,457,125.20

25,112,923.20 - 25,112,923.20

4,317,408.00 - 4,317,408.00

5,036,976.00 - 5,036,976.00

9,678,189.60 - 9,678,189.60

6,961,820.40 - 6,961,820.40

B03/63 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

5,360,781.60 - 5,360,781.60

5,451,627.06 - 5,451,627.06

1,390,565.16 - 1,390,565.16

390,365.64 - 390,365.64

2,230,660.80 - 2,230,660.80

71,669,872.26 - 71,669,872.26

B03/64 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

23,985.60 - 23,985.60

503,697.60 - 503,697.60

3,813,710.40 - 3,813,710.40

239,856.00 - 239,856.00

887,467.20 - 887,467.20

1,607,035.20 - 1,607,035.20

1,367,179.20 - 1,367,179.20

887,467.20 - 887,467.20

B03/65 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

1,526,683.44 - 1,526,683.44

143,913.60 - 143,913.60

71,956.80 - 71,956.80

839,496.00 - 839,496.00

5,995,395.60 - 5,995,395.60

17,907,843.84 - 17,907,843.84

B03/66 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

29,436,432.54 - 29,436,432.54

71,669,872.26 - 71,669,872.26

17,907,843.84 - 17,907,843.84

B03/67 Bill.3
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

119,014,148.64 - 119,014,148.64

B03/68 Bill.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 4.1 - AL KHOR EXPRESSWAY ROAD


WORKS - PACKAGE 1

B4.1/1/A Diversion Road (TTM) 56,879,200.13 98.830% 0.000% 98.830%

B4.1/1/B Site Clearance 27,289,707.35 100.000% 0.000% 100.000%

B4.1/1/C Excavation 65,762,526.23 95.190% 0.000% 95.190%

B4.1/1/D General Filling 101,036,699.88 84.410% 0.000% 84.410%

B4.1/1/E Selected Fill 59,000,833.16 61.980% 0.000% 61.980%

B4.1/1/F Subbase Course 34,326,726.84 39.590% 0.000% 39.590%

B4.1/1/G Aggregate Road Base Course 50,182,289.75 36.310% 0.000% 36.310%

B4.1/1/H Concrete Barrier 63,292,686.24 25.940% 0.000% 25.940%

B4.1/1/J Prime Coat and Asphalt Road Base Course 150,028,607.75 35.640% 0.000% 35.640%
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


B4.1/1/K Tack Coat and Asphalt Intermediate Course 91,359,785.85 6.420% 0.000% 6.420%

B4.1/1/L Tack Coat and Asphalt Wearing Course 71,771,120.55 0.960% 0.000% 0.960%

B4.1/1/M Traffic Signs 5,174,517.21 0.000%

B4.1/1/N Road Marking 22,431,005.74 4.143% 0.000% 4.143%

B4.1/1/P Guard Rails 882,664.12 0.000%

B4.1/1/Q Permanent Fencing 10,365,230.10 0.000%

BILL NO 4.1. ROAD WORKS - PACKAGE 1 Carried to


809,783,600.90 46.57% 0.00% 46.57%
Appendix B1 (Grand Summary Sheet)

B4.1/1
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 4.2 - AL KHOR EXPRESSWAY ROAD


WORKS - PACKAGE 2 & 3

B4.2/1/A Diversion Road (TTM) 39,797,124.63 96.991% 0.000% 96.991%

B4.2/1/B Site Clearance 16,773,048.00 100.000% 0.000% 100.000%

B4.2/1/C Excavation 21,502,229.34 98.913% 0.000% 98.913%

B4.2/1/D General Filling 113,696,719.54 96.620% 0.000% 96.620%

B4.2/1/E Selected Fill 50,392,781.78 85.550% 0.000% 85.550%

B4.2/1/F Subbase Course 42,145,351.35 70.562% 0.000% 70.562%

B4.2/1/G Aggregate Road Base Course 59,131,130.69 54.660% 0.000% 54.660%

B4.2/1/H Concrete Barrier 42,922,638.94 72.049% 0.000% 72.049%

B4.2/1/J Prime Coat and Asphalt Road Base Course 166,945,010.47 66.560% 0.000% 66.560%

B4.2/1/K Tack Coat and Asphalt Intermediate Course 97,880,962.57 39.530% 0.000% 39.530%
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


B4.2/1/L Tack Coat and Asphalt Wearing Course 87,326,215.30 0.330% 0.000% 0.330%

B4.2/1/M Traffic Signage 8,811,986.68 0.000%

B4.2/1/N Traffic Signs 5,841,929.90 0.000%

B4.2/1/P Road Marking 27,319,613.31 3.019% 0.000% 3.019%

B4.2/1/Q Guard Rails 23,457,721.28 1.239% 0.000% 1.239%

B4.2/1/R Permanent Fencing 14,252,999.82 0.000% 0.000%

BILL NO 4.2. ROAD WORKS - PACKAGE 2 & 3 Carried


818,197,463.60 57.91% 0.00% 57.91%
to Appendix B1 (Grand Summary Sheet)

B4.2/1
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 4.3 - AL KHOR EXPRESSWAY ROAD


WORKS - PACKAGE 4

B4.3/1/A Diversion Road (TTM) 15,226,090.92 96.941% 0.000% 96.941%

B4.3/1/B Site Clearance 37,530,501.48 100.000% 0.000% 100.000%

B4.3/1/C Excavation 41,989,570.96 97.450% 0.000% 97.450%

B4.3/1/D General Filling 193,643,249.12 93.750% 0.000% 93.750%

B4.3/1/E Selected Fill 71,617,006.20 79.790% 0.000% 79.790%

B4.3/1/F Subbase Course 38,880,910.73 64.892% 0.000% 64.892%

B4.3/1/G Aggregate Road Base Course 61,285,015.94 55.120% 0.000% 55.120%

B4.3/1/H Concrete Barrier 33,243,631.83 76.557% 0.000% 76.557%

B4.3/1/J Prime Coat and Asphalt Road Base Course 147,774,650.24 58.820% 0.000% 58.820%

B4.3/1/K Tack Coat and Asphalt Intermediate Course 102,359,208.82 30.156% 0.000% 30.156%
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


B4.3/1/L Tack Coat and Asphalt Wearing Course 83,353,784.62 0.000% 0.000% 0.000%

B4.3/1/M Traffic Signage 6,072,310.07 0.000%

B4.3/1/N Traffic Signs 5,320,068.67 0.000%

B4.3/1/P Road Marking 25,195,555.20 3.547% 0.000% 3.547%

B4.3/1/Q Guard Rails 31,603,201.80 1.017% 0.000% 1.017%

B4.3/1/R Permanent Fencing 11,220,178.90 0.000% 0.000%

BILL NO 4.4. ROAD WORKS - PACKAGE 4 Carried to


906,314,935.50 59.07% 0.00% 59.07%
Appendix B1 (Grand Summary Sheet)

B4.3/1
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

56,213,713.49 - 56,213,713.49

27,289,707.35 - 27,289,707.35

62,599,348.72 - 62,599,348.72

85,285,078.37 - 85,285,078.37

36,568,716.39 - 36,568,716.39

13,589,951.16 - 13,589,951.16

18,221,189.41 - 18,221,189.41

16,418,122.81 - 16,418,122.81

53,470,195.80 - 53,470,195.80
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


5,865,298.25 - 5,865,298.25

689,002.76 - 689,002.76

- - -

929,316.57 - 929,316.57

- - -

- - -

377,139,641.08 - 377,139,641.08

Bill 4.1
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

38,599,629.15 - 38,599,629.15

16,773,048.00 - 16,773,048.00

21,268,500.11 - 21,268,500.11

109,853,770.42 - 109,853,770.42

43,111,024.81 - 43,111,024.81

29,738,602.82 - 29,738,602.82

32,321,076.04 - 32,321,076.04

30,925,332.13 - 30,925,332.13

111,118,598.97 - 111,118,598.97

38,692,344.50 - 38,692,344.50
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


288,176.51 - 288,176.51

- - -

- - -

824,779.13 - 824,779.13

290,641.17 - 290,641.17

- - -

473,805,523.76 - 473,805,523.76

Bill 4.2
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

14,760,324.80 - 14,760,324.80

37,530,501.48 - 37,530,501.48

40,918,836.90 - 40,918,836.90

181,540,546.05 - 181,540,546.05

57,143,209.25 - 57,143,209.25

25,230,600.59 - 25,230,600.59

33,780,300.79 - 33,780,300.79

25,450,327.22 - 25,450,327.22

86,921,049.27 - 86,921,049.27

30,867,443.01 - 30,867,443.01
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


- - -

- - -

- - -

893,686.34 - 893,686.34

321,404.56 - 321,404.56

- - -
-

535,358,230.26 - 535,358,230.26

Bill 4.3
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.1 - CONSTRUCTION OF


INTERCHANGE A

FOUNDATION WORKS

B5.1/1/A Bridges - Excavation 4,797,532.38 100.000% 0.000% 100.000%


B5.1/1/B Bridges - Blinding Concrete 142,046.68 100.000% 0.000% 100.000%
B5.1/1/C Bridges - Waterproofing Under Found. 982,384.79 100.000% 0.000% 100.000%
B5.1/1/D Bridges - Foundation (or Bottom Slab) 31,787,030.31 100.000% 0.000% 100.000%
B5.1/1/E Subways - Excavation 894,391.27 100.000% 0.000% 100.000%
B5.1/1/F Subways - Blinding Concrete 36,454.46 100.000% 0.000% 100.000%
B5.1/1/G Subways - Waterproofing Under Found. 263,980.56 100.000% 0.000% 100.000%
B5.1/1/H Subways - Foundation (or Bottom Slab) 5,798,144.39 100.000% 0.000% 100.000%

B5.1/81 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.1/1/J Underpasses - Excavation 1,164,657.08 100.000% 0.000% 100.000%
B5.1/1/K Underpasses - Blinding Concrete 78,565.64 100.000% 0.000% 100.000%
B5.1/1/L Underpasses - Waterproofing Under Found. 355,116.70 100.000% 0.000% 100.000%
B5.1/1/M Underpasses - Foundation (or Bottom Slab) 16,552,209.50 100.000% 0.000% 100.000%

B5.1/82 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
62,852,513.76 100.00% 0.00% 100.00%

B5.1/83 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB-STRUCTURE WORKS

B5.1/2/A Bridges - Edge Wall 19,678,551.26 100.000% 0.000% 100.000%

B5.1/2/B Bridges - Pier 4,765,049.19 100.000% 0.000% 100.000%

B5.1/2/C Bridges - Pier Cap 4,160,177.59 100.000% 0.000% 100.000%

B5.1/2/D Subways - Wall 8,153,445.96 100.000% 0.000% 100.000%

B5.1/2/E Underpasses - Wall 9,735,596.64 100.000% 0.000% 100.000%

B5.1/84 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

46,492,820.64 100.00% 0.00% 100.00%

B5.1/85 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER-STRUCTURE WORKS

B5.1/3/A Bridges - Diaphragm 4,755,257.82 100.000% 0.000% 100.000%

B5.1/3/B Bridges - Top Slab (Girder) - Production 23,620,833.17 100.000% 0.000% 100.000%

B5.1/3/C Bridges - Top Slab (Girder) - Installation 7,354,142.04 100.000% 0.000% 100.000%

B5.1/3/D Bridges - Top Slab (Slab) 14,160,340.48 100.000% 0.000% 100.000%

B5.1/3/E Bridges - Drainage 2,072,488.96 95.000% 0.000% 95.000%

B5.1/3/F Bridges - Finishing 8,927,171.17 60.000% 0.000% 60.000%

B5.1/3/G Subways - Top Slab 5,343,989.36 100.000% 0.000% 100.000%

B5.1/3/H Subways - Finishing Works 1,781,586.32 50.000% 0.000% 50.00%


B5.1/3/J Underpasses - Slab 6,706,922.13 100.000% 0.000% 100.000%

B5.1/86 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.1/3/K Underpasses - Finishing Works 2,235,640.71 50.000% 0.000% 50.00%

76,958,372.16 92.62% 0.00% 92.62%

B5.1/87 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.1/4/A Excavation 3,531,229.34 69.935% 0.000% 69.935%

B5.1/4/B Foundation 5,296,844.02 69.935% 0.000% 69.935%


B5.1/4/C MSE Wall Panel - Production 7,062,458.69 99.268% 0.000% 99.268%
B5.1/4/D MSE Wall Panel - Installation 9,887,442.16 63.140% 0.000% 63.140%

B5.1/4/E Backfilling / Filling 9,534,319.23 56.885% 0.000% 56.885%

B5.1/88 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B5.1/89 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

35,312,293.44 70.38% 0.00% 70.38%

B5.1/90 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.1/1 62,852,513.76 100.00% 0.00% 100.00%

From Page B5.1/2 46,492,820.64 100.00% 0.00% 100.00%

From Page B5.1/3 76,958,372.16 92.62% 0.00% 92.62%

From Page B5.1/4 35,312,293.44 70.38% 0.00% 70.38%

B5.1/91 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.1 - CONSTRUCTION OF INTERCHANGE A


221,616,000.00 92.72% 0.00% 92.72%
Carried to Appendix B1 (Grand Summary Sheet)

B5.1/92 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

4,797,532.38 - 4,797,532.38
142,046.68 - 142,046.68
982,384.79 - 982,384.79
31,787,030.31 - 31,787,030.31
894,391.27 - 894,391.27
36,454.46 - 36,454.46
263,980.56 - 263,980.56
5,798,144.39 - 5,798,144.39

B5.1/93 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
1,164,657.08 - 1,164,657.08
78,565.64 - 78,565.64
355,116.70 - 355,116.70
16,552,209.50 - 16,552,209.50

B5.1/94 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
62,852,513.76 - 62,852,513.76

B5.1/95 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

19,678,551.26 - 19,678,551.26

4,765,049.19 - 4,765,049.19

4,160,177.59 - 4,160,177.59

8,153,445.96 - 8,153,445.96

9,735,596.64 - 9,735,596.64

B5.1/96 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

46,492,820.64 - 46,492,820.64

B5.1/97 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

4,755,257.82 - 4,755,257.82

23,620,833.17 - 23,620,833.17

7,354,142.04 - 7,354,142.04

14,160,340.48 - 14,160,340.48

1,968,864.51 - 1,968,864.51

5,356,302.70 - 5,356,302.70

5,343,989.36 - 5,343,989.36

890,793.16 - 890,793.16
6,706,922.13 - 6,706,922.13

B5.1/98 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
1,117,820.36 - 1,117,820.36

71,275,265.73 - 71,275,265.73

B5.1/99 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,469,565.24 - 2,469,565.24

3,704,347.87 - 3,704,347.87
7,010,761.49 - 7,010,761.49
6,242,930.98 - 6,242,930.98

5,423,597.49 - 5,423,597.49

B5.1/100 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

B5.1/101 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

24,851,203.07 - 24,851,203.07

B5.1/102 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

62,852,513.76 - 62,852,513.76

46,492,820.64 - 46,492,820.64

71,275,265.73 - 71,275,265.73

24,851,203.07 - 24,851,203.07

B5.1/103 Bill.5.1-IC A
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

205,471,803.20 - 205,471,803.20

B5.1/104 Bill.5.1-IC A
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.2 - CONSTRUCTION OF


INTERCHANGE B

FOUNDATION WORKS

B5.2/1/A Bridges - Excavation 2,376,559.19 100.000% 0.000% 100.000%

B5.2/1/B Bridges - Blinding Concrete 145,362.36 100.000% 0.000% 100.000%

B5.2/1/C Bridges - Waterproofing Under Found. 1,280,573.16 100.000% 0.000% 100.000%

B5.2/1/D Bridges - Foundation (or Bottom Slab) 38,746,375.12 100.000% 0.000% 100.000%

B5.2/1/E Subways - Excavation 656,822.51 100.000% 0.000% 100.000%

B5.2/1/F Subways - Blinding Concrete 40,762.99 100.000% 0.000% 100.000%

B5.2/1/G Subways - Waterproofing Under Found. 585,295.00 100.000% 0.000% 100.000%

B5.2/105 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.2/1/H Subways - Foundation (or Bottom Slab) 4,863,101.55 100.000% 0.000% 100.000%

B5.2/1/J Underpasses - Excavation 1,071,374.42 100.000% 0.000% 100.000%

B5.2/1/K Underpasses - Blinding Concrete 97,677.35 100.000% 0.000% 100.000%

B5.2/1/L Underpasses - Waterproofing Under Found. 919,090.04 100.000% 0.000% 100.000%

B5.2/1/M Underpasses - Foundation (or Bottom Slab) 26,128,307.11 100.000% 0.000% 100.000%

B5.2/106 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
76,911,300.80 100.00% 0.00% 100.00%

B5.2/107 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB-STRUCTURE WORKS

B5.2/2/A Bridges - Edge Wall 15,252,115.39 100.000% 0.000% 100.000%

B5.2/2/B Bridges - Pier 5,315,777.77 100.000% 0.000% 100.000%

B5.2/2/C Bridges - Pier Cap 7,086,393.38 100.000% 0.000% 100.000%

B5.2/2/D Subways - Wall 8,603,181.44 100.000% 0.000% 100.000%

B5.2/2/E Underpasses - Wall 19,899,068.82 100.000% 0.000% 100.000%

B5.2/108 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

56,156,536.80 100.00% 0.00% 100.00%

B5.2/109 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER-STRUCTURE WORKS

B5.2/3/A Bridges - Diaphragm 9,282,416.56 100.000% 0.000% 100.000%

B5.2/3/B Bridges - Top Slab (Girder) - Production 24,715,362.33 100.000% 0.000% 100.000%

B5.2/3/C Bridges - Top Slab (Girder) - Installation 9,075,418.67 100.000% 0.000% 100.000%

B5.2/3/D Bridges - Top Slab (Slab) 18,218,598.98 100.000% 0.000% 100.000%

B5.2/3/E Bridges - Drainage 4,398,937.21 50.000% 0.000% 50.000%

B5.2/3/F Bridges - Finishing 7,140,034.82 0.000% 0.000% 0.000%

B5.2/3/G Subways - Top Slab 4,641,208.28 100.000% 0.000% 100.000%

B5.2/3/H Subways - Finishing Works 1,547,378.84 50.000% 0.000% 50.00%

B5.2/110 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.2/3/J Underpasses - Slab 10,353,607.43 100.000% 0.000% 100.000%

B5.2/3/K Underpasses - Finishing Works 3,451,202.48 0.000% 0.000% 0.00%

B5.2/111 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
92,824,165.60 85.39% 0.00% 85.39%

B5.2/112 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.2/4/A Excavation 3,782,799.68 80.421% 0.000% 80.421%

B5.2/4/B Foundation 5,674,199.52 80.421% 0.000% 80.421%

B5.2/4/C MSE Wall Panel - Production 7,565,599.36 86.378% 0.000% 86.378%

B5.2/4/D MSE Wall Panel - Installation 10,591,839.10 63.550% 0.000% 63.550%

B5.2/4/E Backfilling / Filling 10,213,559.14 59.693% 0.000% 59.693%

B5.2/113 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B5.2/114 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

37,827,996.80 71.29% 0.00% 71.29%

B5.2/115 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.2/1 76,911,300.80 100.00% 0.00% 100.00%

From Page B5.2/2 56,156,536.80 100.00% 0.00% 100.00%

From Page B5.2/3 92,824,165.60 85.39% 0.00% 85.39%

From Page B5.2/4 37,827,996.80 71.29% 0.00% 71.29%

B5.2/116 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.2 - CONSTRUCTION OF INTERCHANGE B


263,720,000.00 90.74% 0.00% 90.74%
Carried to Appendix B1 (Grand Summary Sheet)

B5.2/117 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,376,559.19 - 2,376,559.19

145,362.36 - 145,362.36

1,280,573.16 - 1,280,573.16

38,746,375.12 - 38,746,375.12

656,822.51 - 656,822.51

40,762.99 - 40,762.99

585,295.00 - 585,295.00

B5.2/118 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
4,863,101.55 - 4,863,101.55

1,071,374.42 - 1,071,374.42

97,677.35 - 97,677.35

919,090.04 - 919,090.04

26,128,307.11 - 26,128,307.11

B5.2/119 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
76,911,300.80 - 76,911,300.80

B5.2/120 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

15,252,115.39 - 15,252,115.39

5,315,777.77 - 5,315,777.77

7,086,393.38 - 7,086,393.38

8,603,181.44 - 8,603,181.44

19,899,068.82 - 19,899,068.82

B5.2/121 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

56,156,536.80 - 56,156,536.80

B5.2/122 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

9,282,416.56 - 9,282,416.56

24,715,362.33 - 24,715,362.33

9,075,418.67 - 9,075,418.67

18,218,598.98 - 18,218,598.98

2,199,468.61 - 2,199,468.61

- - -

4,641,208.28 - 4,641,208.28

773,689.42 - 773,689.42

B5.2/123 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
10,353,607.43 - 10,353,607.43

- - -

B5.2/124 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
79,259,770.28 - 79,259,770.28

B5.2/125 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

3,042,165.33 - 3,042,165.33

4,563,248.00 - 4,563,248.00

6,535,013.42 - 6,535,013.42

6,731,113.75 - 6,731,113.75

6,096,779.86 - 6,096,779.86

B5.2/126 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

B5.2/127 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

26,968,320.36 - 26,968,320.36

B5.2/128 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

76,911,300.80 - 76,911,300.80

56,156,536.80 - 56,156,536.80

79,259,770.28 - 79,259,770.28

26,968,320.36 - 26,968,320.36

B5.2/129 Bill.5.2-IC B
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

239,295,928.24 - 239,295,928.24

B5.2/130 Bill.5.2-IC B
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.3 - CONSTRUCTION OF


INTERCHANGE C

FOUNDATION WORKS

B5.3/1/A Bridges - Excavation 4,214,803.20 100.000% 0.000% 100.000%

B5.3/1/B Bridges - Blinding Concrete 167,965.52 100.000% 0.000% 100.000%

B5.3/1/C Bridges - Waterproofing Under Found. 1,352,427.04 100.000% 0.000% 100.000%

B5.3/1/D Bridges - Foundation (or Bottom Slab) 39,489,303.19 100.000% 0.000% 100.000%

B5.3/1/E Subways - Excavation 1,892,005.40 100.000% 0.000% 100.000%

B5.3/1/F Subways - Blinding Concrete 147,948.90 100.000% 0.000% 100.000%

B5.3/1/G Subways - Waterproofing Under Found. 629,217.99 100.000% 0.000% 100.000%

B5.3/131 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B5.3/1/H Subways - Foundation (or Bottom Slab) 17,614,622.51 100.000% 0.000% 100.000%

B5.3/1/J Underpasses - Excavation 1,479,489.05 100.000% 0.000% 100.000%

B5.3/1/K Underpasses - Blinding Concrete 91,380.21 100.000% 0.000% 100.000%

B5.3/1/L Underpasses - Waterproofing Under Found. 849,400.77 100.000% 0.000% 100.000%

B5.3/1/M Underpasses - Foundation (or Bottom Slab) 19,100,203.57 100.000% 0.000% 100.000%

B5.3/132 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

87,028,767.35 100.00% 0.00% 100.00%

B5.3/133 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB-STRUCTURE WORKS

B5.3/2/A Bridges - Edge Wall 16,350,438.25 100.000% 0.000% 100.000%

B5.3/2/B Bridges - Pier 5,441,802.12 100.000% 0.000% 100.000%

B5.3/2/C Bridges - Pier Cap 5,684,874.99 100.000% 0.000% 100.000%

B5.3/2/D Subways - Wall 17,029,593.07 100.000% 0.000% 100.000%

B5.3/2/E Underpasses - Wall 21,366,698.16 100.000% 0.000% 100.000%

B5.3/134 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

65,873,406.59 100.00% 0.00% 100.00%

B5.3/135 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER-STRUCTURE WORKS

B5.3/3/A Bridges - Diaphragm 9,282,167.62 100.000% 0.000% 100.000%

B5.3/3/B Bridges - Top Slab (Girder) - Production 25,431,159.17 100.000% 0.000% 100.000%

B5.3/3/C Bridges - Top Slab (Girder) - Installation 9,222,391.13 100.000% 0.000% 100.000%

B5.3/3/D Bridges - Top Slab (Slab) 14,230,539.93 72.727% 0.000% 72.727%

B5.3/3/E Bridges - Drainage 6,682,824.44 66.667% 0.000% 66.667%

B5.3/3/F Bridges - Finishing 10,709,331.24 16.667% 0.000% 16.667%

B5.3/3/G Subways - Top Slab 6,419,434.30 100.000% 0.000% 100.000%

B5.3/3/H Subways - Finishing Works 2,139,811.43 30.000% 0.000% 30.00%

B5.3/3/J Underpasses - Slab 6,962,092.72 90.037% 0.000% 90.037%

B5.3/136 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B5.3/3/K Underpasses - Finishing Works 2,321,008.91 0.000% 0.000% 0.00%

93,400,760.89 79.07% 0.00% 79.07%

B5.3/137 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.3/4/A Excavation 3,892,506.52 48.000% 0.000% 48.000%

B5.3/4/B Foundation 5,838,759.77 48.000% 0.000% 48.000%

B5.3/4/C MSE Wall Panel - Production 7,785,013.04 82.047% 0.000% 82.047%

B5.3/4/D MSE Wall Panel - Installation 10,899,018.24 35.040% 0.000% 35.040%

B5.3/4/E Backfilling / Filling 10,509,767.60 55.762% 0.000% 55.762%

B5.3/138 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

38,925,065.17 53.28% 0.00% 53.28%

B5.3/139 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.3/1 87,028,767.35 100.00% 0.00% 100.00%

From Page B5.3/2 65,873,406.59 100.00% 0.00% 100.00%

From Page B5.3/3 93,400,760.89 79.07% 0.00% 79.07%

From Page B5.3/4 38,925,065.17 53.28% 0.00% 53.28%

B5.3/140 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.3 - CONSTRUCTION OF INTERCHANGE C


285,228,000.00 86.77% 0.00% 86.77%
Carried to Appendix B1 (Grand Summary Sheet)

B5.3/141 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

4,214,803.20 - 4,214,803.20

167,965.52 - 167,965.52

1,352,427.04 - 1,352,427.04

39,489,303.19 - 39,489,303.19

1,892,005.40 - 1,892,005.40

147,948.90 - 147,948.90

629,217.99 - 629,217.99

B5.3/142 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

17,614,622.51 - 17,614,622.51

1,479,489.05 - 1,479,489.05

91,380.21 - 91,380.21

849,400.77 - 849,400.77

19,100,203.57 - 19,100,203.57

B5.3/143 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

87,028,767.35 - 87,028,767.35

B5.3/144 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

16,350,438.25 - 16,350,438.25

5,441,802.12 - 5,441,802.12

5,684,874.99 - 5,684,874.99

17,029,593.07 - 17,029,593.07

21,366,698.16 - 21,366,698.16

B5.3/145 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

65,873,406.59 - 65,873,406.59

B5.3/146 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

9,282,167.62 - 9,282,167.62

25,431,159.17 - 25,431,159.17

9,222,391.13 - 9,222,391.13

10,349,444.77 - 10,349,444.77

4,455,238.57 - 4,455,238.57

1,784,924.24 - 1,784,924.24

6,419,434.30 - 6,419,434.30

641,943.43 - 641,943.43

6,268,459.42 - 6,268,459.42

B5.3/147 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

- - -

73,855,162.65 - 73,855,162.65

B5.3/148 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

1,868,403.13 - 1,868,403.13

2,802,604.69 - 2,802,604.69

6,387,369.65 - 6,387,369.65

3,819,015.99 - 3,819,015.99

5,860,456.61 - 5,860,456.61

B5.3/149 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

20,737,850.07 - 20,737,850.07

B5.3/150 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

87,028,767.35 - 87,028,767.35

65,873,406.59 - 65,873,406.59

73,855,162.65 - 73,855,162.65

20,737,850.07 - 20,737,850.07

B5.3/151 Bill.5.3-IC C
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

247,495,186.66 - 247,495,186.66

B5.3/152 Bill.5.3-IC C
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.4 - CONSTRUCTION OF


INTERCHANGE D

FOUNDATION WORKS

B5.4/1/A Bridges - Excavation 888,403.81 100.000% 0.000% 100.000%

B5.4/1/B Bridges - Blinding Concrete 261,899.39 100.000% 0.000% 100.000%

B5.4/1/C Bridges - Waterproofing Under Found. 823,112.37 100.000% 0.000% 100.000%

B5.4/1/D Bridges - Foundation (or Bottom Slab) 19,040,892.61 100.000% 0.000% 100.000%

B5.4/1/E Subways - Excavation 4,053,204.84 100.000% 0.000% 100.000%

B5.4/1/F Subways - Blinding Concrete 448,970.38 100.000% 0.000% 100.000%

B5.4/1/G Subways - Waterproofing Under Found. 2,109,867.35 100.000% 0.000% 100.000%

B5.4/153 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.4/1/H Subways - Foundation (or Bottom Slab) 43,448,155.06 100.000% 0.000% 100.000%

B5.4/1/J Underpasses - Excavation 305,182.48 100.000% 0.000% 100.000%

B5.4/1/K Underpasses - Blinding Concrete 22,741.96 100.000% 0.000% 100.000%

B5.4/1/L Underpasses - Waterproofing Under Found. 1,722,520.36 100.000% 0.000% 100.000%

B5.4/1/M Underpasses - Foundation (or Bottom Slab) 236,222.99 100.000% 0.000% 100.000%

B5.4/154 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

73,361,173.60 100.00% 0.00% 100.00%

B5.4/155 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB-STRUCTURE WORKS

B5.4/2/A Bridges - Edge Wall 11,692,276.40 100.000% 0.000% 100.000%

B5.4/2/B Bridges - Pier 4,446,366.15 100.000% 0.000% 100.000%

B5.4/2/C Bridges - Pier Cap 5,044,093.65 100.000% 0.000% 100.000%

B5.4/2/D Subways - Wall 28,991,119.25 100.000% 0.000% 100.000%

B5.4/2/E Underpasses - Wall 3,242,364.55 100.000% 0.000% 100.000%

B5.4/156 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

53,416,220.00 100.00% 0.00% 100.00%

B5.4/157 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER-STRUCTURE WORKS

B5.4/3/A Bridges - Diaphragm 7,493,270.62 100.000% 0.000% 100.000%


B5.4/3/B Bridges - Top Slab (Girder) - Production 18,255,486.53 100.000% 0.000% 100.000%
B5.4/3/C Bridges - Top Slab (Girder) - Installation 6,883,933.74 100.000% 0.000% 100.000%

B5.4/3/D Bridges - Top Slab (Slab) 11,245,718.90 100.000% 0.000% 100.000%

B5.4/3/E Bridges - Drainage 4,824,771.76 100.000% 0.000% 100.000%

B5.4/3/F Bridges - Finishing 7,141,756.42 40.000% 0.000% 40.000%

B5.4/3/G Subways - Top Slab 7,109,614.07 100.000% 0.000% 100.000%

B5.4/3/H Subways - Finishing Works 2,369,643.40 50.000% 0.000% 50.00%

B5.4/3/J Underpasses - Slab 2,297,836.02 100.000% 0.000% 100.00%

B5.4/158 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.4/3/K Underpasses - Finishing Works 765,945.34 50.000% 0.000% 50.00%

68,387,976.80 91.44% 0.00% 91.44%

B5.4/159 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.4/4/A Excavation 2,219,462.96 70.270% 0.000% 70.270%

B5.4/4/B Foundation 3,329,194.44 70.270% 0.000% 70.270%

B5.4/4/C MSE Wall Panel - Production 4,438,925.92 89.470% 0.000% 89.470%

B5.4/4/D MSE Wall Panel - Installation 6,214,496.29 44.240% 0.000% 44.240%

B5.4/4/E Backfilling / Filling 5,992,549.99 65.000% 0.000% 65.000%

B5.4/160 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

22,194,629.60 65.40% 0.00% 65.40%

B5.4/161 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.4/1 73,361,173.60 100.00% 0.00% 100.00%

From Page B5.4/2 53,416,220.00 100.00% 0.00% 100.00%

From Page B5.4/3 68,387,976.80 91.44% 0.00% 91.44%

From Page B5.4/4 22,194,629.60 65.40% 0.00% 65.40%

B5.4/162 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.4 - CONSTRUCTION OF INTERCHANGE D


217,360,000.00 93.77% 0.00% 93.77%
Carried to Appendix B1 (Grand Summary Sheet)

B5.4/163 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

888,403.81 - 888,403.81

261,899.39 - 261,899.39

823,112.37 - 823,112.37

19,040,892.61 - 19,040,892.61

4,053,204.84 - 4,053,204.84

448,970.38 - 448,970.38

2,109,867.35 - 2,109,867.35

B5.4/164 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
43,448,155.06 - 43,448,155.06

305,182.48 - 305,182.48

22,741.96 - 22,741.96

1,722,520.36 - 1,722,520.36

236,222.99 - 236,222.99

B5.4/165 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

73,361,173.60 - 73,361,173.60

B5.4/166 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

11,692,276.40 - 11,692,276.40

4,446,366.15 - 4,446,366.15

5,044,093.65 - 5,044,093.65

28,991,119.25 - 28,991,119.25

3,242,364.55 - 3,242,364.55

B5.4/167 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

53,416,220.00 - 53,416,220.00

B5.4/168 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

7,493,270.62 - 7,493,270.62
18,255,486.53 - 18,255,486.53
6,883,933.74 - 6,883,933.74

11,245,718.90 - 11,245,718.90

4,824,771.76 - 4,824,771.76

2,856,702.57 - 2,856,702.57

7,109,614.07 - 7,109,614.07

1,184,821.70 - 1,184,821.70
2,297,836.02 - 2,297,836.02

B5.4/169 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
382,972.67 - 382,972.67

62,535,128.58 - 62,535,128.58

B5.4/170 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

1,559,616.62 - 1,559,616.62

2,339,424.93 - 2,339,424.93

3,971,507.02 - 3,971,507.02

2,749,293.16 - 2,749,293.16

3,895,157.49 - 3,895,157.49

B5.4/171 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

14,514,999.22 - 14,514,999.22

B5.4/172 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

73,361,173.60 - 73,361,173.60

53,416,220.00 - 53,416,220.00

62,535,128.58 - 62,535,128.58

14,514,999.22 - 14,514,999.22

B5.4/173 Bill.5.4-IC D
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

203,827,521.40 - 203,827,521.40

B5.4/174 Bill.5.4-IC D
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.5 - CONSTRUCTION OF


INTERCHANGE E

FOUNDATION WORKS

B5.5/1/A Bridges - Excavation 1,551,414.45 100.000% 0.000% 100.000%

B5.5/1/B Bridges - Blinding Concrete 55,044.88 100.000% 0.000% 100.000%

B5.5/1/C Bridges - Waterproofing Under Found. 327,112.07 100.000% 0.000% 100.000%

B5.5/1/D Bridges - Foundation (or Bottom Slab) 8,457,830.59 100.000% 0.000% 100.000%

B5.5/1/E Subways - Excavation 833,360.21 100.000% 0.000% 100.000%

B5.5/1/F Subways - Blinding Concrete 15,511.40 100.000% 0.000% 100.000%

B5.5/1/G Subways - Waterproofing Under Found. 188,744.90 100.000% 0.000% 100.000%

B5.5/175 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.5/1/H Subways - Foundation (or Bottom Slab) 2,297,883.37 100.000% 0.000% 100.000%

13,726,901.87 100.00% 0.00% 100.00%

B5.5/176 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB-STRUCTURE WORKS

B5.5/2/A Bridges - Edge Wall 4,074,026.61 100.000% 0.000% 100.000%

B5.5/2/B Bridges - Pier 1,299,103.11 100.000% 0.000% 100.000%

B5.5/2/C Bridges - Pier Cap 1,548,682.59 100.000% 0.000% 100.000%

B5.5/2/D Subways - Wall 2,703,312.57 100.000% 0.000% 100.000%

B5.5/177 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

9,625,124.88 100.00% 0.00% 100.00%

B5.5/178 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER-STRUCTURE WORKS

B5.5/3/A Bridges - Diaphragm 2,156,699.62 100.000% 0.000% 100.000%

B5.5/3/B Bridges - Top Slab (Girder) - Production 4,707,233.14 100.000% 0.000% 100.000%

B5.5/3/C Bridges - Top Slab (Girder) - Installation 2,756,012.07 100.000% 0.000% 100.000%

B5.5/3/D Bridges - Top Slab (Slab) 5,777,124.49 100.000% 0.000% 100.000%

B5.5/3/E Bridges - Drainage 1,208,940.10 0.000% 0.000% 0.000%

B5.5/3/F Bridges - Finishing 1,789,685.21 0.000% 0.000% 0.000%

B5.5/3/G Subways - Top Slab 1,676,011.83 100.000% 0.000% 100.000%

B5.5/3/H Subways - Finishing Works 558,670.61 0.000% 0.000% 0.000%

B5.5/179 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

20,630,377.07 82.76% 0.00% 82.76%

B5.5/180 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.5/4/A Excavation 1,085,650.96 100.000% 0.000% 100.000%

B5.5/4/B Foundation 1,628,476.43 100.000% 0.000% 100.000%


B5.5/4/C MSE Wall Panel - Production 2,171,301.91 98.616% 0.000% 98.616%
B5.5/4/D MSE Wall Panel - Installation 3,039,822.68 68.750% 0.000% 68.750%

B5.5/4/E Backfilling / Filling 2,931,257.58 74.751% 0.000% 74.751%

B5.5/181 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

10,856,509.56 84.16% 0.00% 84.16%

B5.5/182 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF GUARD HOUSE

B5.5/5/A Foundation 289,962.99 100.000% 0.000% 100.000%

B5.5/5/B Columns, beams & Walls 289,962.99 100.000% 0.000% 100.000%

B5.5/5/C Top Slab 289,962.99 100.000% 0.000% 100.000%

B5.5/5/D Floor Finishes 193,308.66 100.000% 0.000% 100.000%

B5.5/5/E Wall & Ceiling Finishes 289,962.99 100.000% 0.000% 100.000%

B5.5/5/F MEP Works 386,617.32 95.000% 0.000% 95.000%

B5.5/5/G Road&Landscape Works 96,654.33 95.000% 0.000% 95.000%

B5.5/5/H Reoval of existing Guard Houses 96,654.35 0.000% 0.000% 0.000%

B5.5/183 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

1,933,086.62 93.75% 0.00% 93.75%

B5.5/184 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.5/1 13,726,901.87 100.00% 0.00% 100.00%

From Page B5.5/2 9,625,124.88 100.00% 0.00% 100.00%

From Page B5.5/3 20,630,377.07 82.76% 0.00% 82.76%

From Page B5.5/4 10,856,509.56 84.16% 0.00% 84.16%

From Page B5.5/5 1,933,086.62 93.75% 0.00% 93.75%

B5.5/185 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.5 - CONSTRUCTION OF INTERCHANGE E


56,772,000.00 90.49% 0.00% 90.49%
Carried to Appendix B1 (Grand Summary Sheet)

B5.5/186 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

1,551,414.45 - 1,551,414.45

55,044.88 - 55,044.88

327,112.07 - 327,112.07

8,457,830.59 - 8,457,830.59

833,360.21 - 833,360.21

15,511.40 - 15,511.40

188,744.90 - 188,744.90

B5.5/187 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
2,297,883.37 - 2,297,883.37

13,726,901.87 - 13,726,901.87

B5.5/188 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

4,074,026.61 - 4,074,026.61

1,299,103.11 - 1,299,103.11

1,548,682.59 - 1,548,682.59

2,703,312.57 - 2,703,312.57

B5.5/189 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

9,625,124.88 - 9,625,124.88

B5.5/190 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,156,699.62 - 2,156,699.62

4,707,233.14 - 4,707,233.14

2,756,012.07 - 2,756,012.07

5,777,124.49 - 5,777,124.49

- - -

- - -

1,676,011.83 - 1,676,011.83

- - -

B5.5/191 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

17,073,081.15 - 17,073,081.15

B5.5/192 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

1,085,650.96 - 1,085,650.96

1,628,476.43 - 1,628,476.43
2,141,251.09 - 2,141,251.09
2,089,878.09 - 2,089,878.09

2,191,144.35 - 2,191,144.35

B5.5/193 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

9,136,400.92 - 9,136,400.92

B5.5/194 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

289,962.99 - 289,962.99

289,962.99 - 289,962.99

289,962.99 - 289,962.99

193,308.66 - 193,308.66

289,962.99 - 289,962.99

367,286.45 - 367,286.45

91,821.61 - 91,821.61

- - -

B5.5/195 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

1,812,268.68 - 1,812,268.68

B5.5/196 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

13,726,901.87 - 13,726,901.87

9,625,124.88 - 9,625,124.88

17,073,081.15 - 17,073,081.15

9,136,400.92 - 9,136,400.92

1,812,268.68 - 1,812,268.68

B5.5/197 Bill.5.5-IC E
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

51,373,777.50 - 51,373,777.50

B5.5/198 Bill.5.5-IC E
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.6 - CONSTRUCTION OF


INTERCHANGE F

FOUNDATION WORKS

B5.6/1/A Tunnels - Excavation 13,665,863.95 100.000% 0.000% 100.000%

B5.6/1/B Tunnels - Blinding Concrete 250,579.14 100.000% 0.000% 100.000%

B5.6/1/C Tunnels - Waterproofing Under Found. 675,141.17 100.000% 0.000% 100.000%

B5.6/1/D Tunnels - Foundation (or Bottom Slab) 55,291,544.98 100.000% 0.000% 100.000%

B5.6/1/E Underpasses - Excavation 15,527,152.65 100.000% 0.000% 100.000%

B5.6/1/F Underpasses - Blinding Concrete 212,281.02 100.000% 0.000% 100.000%

B5.6/1/G Underpasses - Waterproofing Under Found. 1,690,588.50 100.000% 0.000% 100.000%

B5.6/199 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.6/1/H Underpasses - Foundation (or Bottom Slab) 22,110,052.60 100.000% 0.000% 100.000%

109,423,204.01 100.00% 0.00% 100.00%

B5.6/200 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB - STRUCTURE WORKS

B5.6/2/A Tunnels - Wall 36,278,734.57 100.000% 0.000% 100.000%

B5.6/2/B Underpasses - Wall 32,809,141.43 100.000% 0.000% 100.000%

B5.6/201 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

69,087,876.00 100.00% 0.00% 100.00%

B5.6/202 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER- STRUCTURE WORKS

B5.6/3/A Tunnels - Top Slab 21,989,693.07 100.000% 0.000% 100.000%

B5.6/3/B Tunnels - Finishing Works 7,329,897.69 50.000% 0.000% 50.000%

B5.6/3/C Underpasses - Top Slab 32,749,162.53 100.000% 0.000% 100.000%

B5.6/3/D Underpasses - Finishing Works 10,916,387.50 50.000% 0.000% 50.000%

B5.6/203 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

72,985,140.79 87.50% 0.00% 87.50%

B5.6/204 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.6/4/A Excavation 2,103,977.92 100.000% 0.000% 100.000%

B5.6/4/B Foundation 3,155,966.88 100.000% 0.000% 100.000%


B5.6/4/C MSE Wall Panel - Production 4,207,955.84 100.000% 0.000% 100.000%
B5.6/4/D MSE Wall Panel - Installation 5,891,138.18 85.620% 0.000% 85.620%

B5.6/4/E Backfilling / Filling 5,680,740.38 89.874% 0.000% 89.874%

B5.6/205 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B5.6/206 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
21,039,779.20 93.24% 0.00% 93.24%

B5.6/207 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.6/1 109,423,204.01 100.00% 0.00% 100.00%

From Page B5.6/2 69,087,876.00 100.00% 0.00% 100.00%

From Page B5.6/3 72,985,140.79 87.50% 0.00% 87.50%

From Page B5.6/4 21,039,779.20 93.24% 0.00% 93.24%

B5.6/208 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.6 - CONSTRUCTION OF INTERCHANGE F


272,536,000.00 96.13% 0.00% 96.13%
Carried to Appendix B1 (Grand Summary Sheet)

B5.6/209 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

13,665,863.95 - 13,665,863.95

250,579.14 - 250,579.14

675,141.17 - 675,141.17

55,291,544.98 - 55,291,544.98

15,527,152.65 - 15,527,152.65

212,281.02 - 212,281.02

1,690,588.50 - 1,690,588.50

B5.6/210 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
22,110,052.60 - 22,110,052.60

109,423,204.01 - 109,423,204.01

B5.6/211 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

36,278,734.57 - 36,278,734.57

32,809,141.43 - 32,809,141.43

B5.6/212 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

69,087,876.00 - 69,087,876.00

B5.6/213 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

21,989,693.07 - 21,989,693.07

3,664,948.85 - 3,664,948.85

32,749,162.53 - 32,749,162.53

5,458,193.75 - 5,458,193.75

B5.6/214 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

63,861,998.20 - 63,861,998.20

B5.6/215 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,103,977.92 - 2,103,977.92

3,155,966.88 - 3,155,966.88
4,207,955.84 - 4,207,955.84
5,043,992.51 - 5,043,992.51

5,105,508.61 - 5,105,508.61

B5.6/216 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

B5.6/217 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
19,617,401.76 - 19,617,401.76

B5.6/218 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

109,423,204.01 - 109,423,204.01

69,087,876.00 - 69,087,876.00

63,861,998.20 - 63,861,998.20

19,617,401.76 - 19,617,401.76

B5.6/219 Bill.5.6-IC F&F1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

261,990,479.97 - 261,990,479.97

B5.6/220 Bill.5.6-IC F&F1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.7 - CONSTRUCTION OF


INTERCHANGE G

FOUNDATION WORKS

B5.7/1/A Bridges - Excavation 2,514,698.49 100.000% 0.000% 100.000%

B5.7/1/B Bridges - Blinding Concrete 170,237.53 100.000% 0.000% 100.000%

B5.7/1/C Bridges - Waterproofing Under Found. 932,748.42 100.000% 0.000% 100.000%

B5.7/1/D Bridges - Foundation (or Bottom Slab) 33,067,682.98 100.000% 0.000% 100.000%

B5.7/1/E Subways - Excavation 1,153,345.61 100.000% 0.000% 100.000%

B5.7/1/F Subways - Blinding Concrete 65,686.51 100.000% 0.000% 100.000%

B5.7/1/G Subways - Waterproofing Under Found. 998,982.31 100.000% 0.000% 100.000%

B5.7/221 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.7/1/H Subways - Foundation (or Bottom Slab) 8,331,238.78 100.000% 0.000% 100.000%

B5.7/1/J Underpasses - Excavation 594,462.90 100.000% 0.000% 100.000%

B5.7/1/K Underpasses - Blinding Concrete 49,264.88 100.000% 0.000% 100.000%

B5.7/1/L Underpasses - Waterproofing Under Found. 105,645.80 100.000% 0.000% 100.000%

B5.7/1/M Underpasses - Foundation (or Bottom Slab) 6,754,762.59 100.000% 0.000% 100.000%

54,738,756.80 100.00% 0.00% 100.00%

B5.7/222 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB-STRUCTURE WORKS

B5.7/2/A Bridges - Edge Wall 10,823,460.39 100.000% 0.000% 100.000%

B5.7/2/B Bridges - Pier 4,562,169.83 100.000% 0.000% 100.000%

B5.7/2/C Bridges - Pier Cap 4,865,036.57 100.000% 0.000% 100.000%

B5.7/2/D Subways - Wall 9,978,117.16 100.000% 0.000% 100.000%

B5.7/2/E Underpasses - Wall 8,108,777.65 100.000% 0.000% 100.000%

B5.7/223 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

38,337,561.60 100.00% 0.00% 100.00%

B5.7/224 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER-STRUCTURE WORKS

B5.7/3/A Bridges - Diaphragm 5,858,019.53 100.000% 0.000% 100.000%

B5.7/3/B Bridges - Top Slab (Girder) - Production 12,949,824.64 100.000% 0.000% 100.000%

B5.7/3/C Bridges - Top Slab (Girder) - Installation 9,209,780.23 100.000% 0.000% 100.000%

B5.7/3/D Bridges - Top Slab (Slab) 14,604,954.32 100.000% 0.000% 100.000%

B5.7/3/E Bridges - Drainage 3,698,543.07 66.667% 0.000% 66.667%

B5.7/3/F Bridges - Finishing 3,571,225.40 50.000% 0.000% 50.000%

B5.7/3/G Subways - Top Slab 10,259,975.13 100.000% 0.000% 100.000%

B5.7/3/H Subways - Finishing Works 3,419,991.71 50.000% 0.000% 50.000%

B5.7/225 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.7/3/J Underpasses - Top Slab 5,076,528.21 100.000% 0.000% 100.000%

B5.7/3/K Underpasses - Finishing Works 1,692,410.56 50.000% 0.000% 50.000%

70,341,252.80 92.07% 0.00% 92.07%

B5.7/226 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.7/4/A Excavation 2,232,642.88 94.670% 0.000% 94.670%

B5.7/4/B Foundation 3,348,964.32 94.670% 0.000% 94.670%


B5.7/4/C MSE Wall Panel - Production 4,465,285.76 91.649% 0.000% 91.649%
B5.7/4/D MSE Wall Panel - Installation 6,251,400.06 84.860% 0.000% 84.860%

B5.7/4/E Backfilling / Filling 6,028,135.78 73.759% 0.000% 73.759%

B5.7/227 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

22,326,428.80 85.67% 0.00% 85.67%

B5.7/228 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.7/1 54,738,756.80 100.00% 0.00% 100.00%

From Page B5.7/2 38,337,561.60 100.00% 0.00% 100.00%

From Page B5.7/3 70,341,252.80 92.07% 0.00% 92.07%

From Page B5.7/4 22,326,428.80 85.67% 0.00% 85.67%

B5.7/229 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.7 - CONSTRUCTION OF INTERCHANGE G


185,744,000.00 95.28% 0.00% 95.28%
Carried to Appendix B1 (Grand Summary Sheet)

B5.7/230 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,514,698.49 - 2,514,698.49

170,237.53 - 170,237.53

932,748.42 - 932,748.42

33,067,682.98 - 33,067,682.98

1,153,345.61 - 1,153,345.61

65,686.51 - 65,686.51

998,982.31 - 998,982.31

B5.7/231 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
8,331,238.78 - 8,331,238.78

594,462.90 - 594,462.90

49,264.88 - 49,264.88

105,645.80 - 105,645.80

6,754,762.59 - 6,754,762.59

54,738,756.80 - 54,738,756.80

B5.7/232 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

10,823,460.39 - 10,823,460.39

4,562,169.83 - 4,562,169.83

4,865,036.57 - 4,865,036.57

9,978,117.16 - 9,978,117.16

8,108,777.65 - 8,108,777.65

B5.7/233 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

38,337,561.60 - 38,337,561.60

B5.7/234 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

5,858,019.53 - 5,858,019.53

12,949,824.64 - 12,949,824.64

9,209,780.23 - 9,209,780.23

14,604,954.32 - 14,604,954.32

2,465,707.71 - 2,465,707.71

1,785,612.70 - 1,785,612.70

10,259,975.13 - 10,259,975.13

1,709,995.86 - 1,709,995.86

B5.7/235 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
5,076,528.21 - 5,076,528.21

846,205.28 - 846,205.28

64,766,603.61 - 64,766,603.61

B5.7/236 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,113,643.01 - 2,113,643.01

3,170,464.52 - 3,170,464.52
4,092,389.75 - 4,092,389.75
5,304,938.09 - 5,304,938.09

4,446,292.67 - 4,446,292.67

B5.7/237 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

19,127,728.04 - 19,127,728.04

B5.7/238 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

54,738,756.80 - 54,738,756.80

38,337,561.60 - 38,337,561.60

64,766,603.61 - 64,766,603.61

19,127,728.04 - 19,127,728.04

B5.7/239 Bill.5.7-IC G&G1


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

176,970,650.05 - 176,970,650.05

B5.7/240 Bill.5.7-IC G&G1


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.8 - CONSTRUCTION OF


INTERCHANGE H

FOUNDATION WORKS

B5.8/1/A Bridges - Excavation 642,588.63 100.000% 0.000% 100.000%

B5.8/1/B Bridges - Blinding Concrete 81,566.98 100.000% 0.000% 100.000%

B5.8/1/C Bridges - Waterproofing Under Found. 837,553.60 100.000% 0.000% 100.000%

B5.8/1/D Bridges - Foundation (or Bottom Slab) 20,158,980.04 100.000% 0.000% 100.000%

B5.8/1/E Subways - Excavation 635,028.76 100.000% 0.000% 100.000%

B5.8/1/F Subways - Blinding Concrete 76,792.33 100.000% 0.000% 100.000%

B5.8/1/G Subways - Waterproofing Under Found. 629,060.44 100.000% 0.000% 100.000%

B5.8/241 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.8/1/H Subways - Foundation (or Bottom Slab) 5,470,955.80 100.000% 0.000% 100.000%

B5.8/1/J Underpasses - Excavation 892,064.21 100.000% 0.000% 100.000%

B5.8/1/K Underpasses - Blinding Concrete 73,609.22 100.000% 0.000% 100.000%

B5.8/1/L Underpasses - Waterproofing Under Found. 158,757.19 100.000% 0.000% 100.000%

B5.8/1/M Underpasses - Foundation (or Bottom Slab) 10,131,812.24 100.000% 0.000% 100.000%

B5.8/242 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

39,788,769.44 100.00% 0.00% 100.00%

B5.8/243 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUB-STRUCTURE WORKS

B5.8/2/A Bridges - Edge Wall 13,578,280.53 100.000% 0.000% 100.000%

B5.8/2/B Bridges - Pier 3,095,135.08 100.000% 0.000% 100.000%

B5.8/2/C Bridges - Pier Cap 4,137,223.55 100.000% 0.000% 100.000%

B5.8/2/D Subways - Wall 5,943,951.26 100.000% 0.000% 100.000%

B5.8/2/E Underpasses - Wall 12,158,347.42 100.000% 0.000% 100.000%

B5.8/244 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

38,912,937.84 100.00% 0.00% 100.00%

B5.8/245 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

SUPER-STRUCTURE WORKS

B5.8/3/A Bridges - Diaphragm 5,073,039.18 100.000% 0.000% 100.000%

B5.8/3/B Bridges - Top Slab (Girder) - Production 13,245,353.91 100.000% 0.000% 100.000%

B5.8/3/C Bridges - Top Slab (Girder) - Installation 8,182,609.05 100.000% 0.000% 100.000%

B5.8/3/D Bridges - Top Slab (Slab) 14,796,364.26 100.000% 0.000% 100.000%

B5.8/3/E Bridges - Drainage 4,085,471.08 25.000% 0.000% 25.000%

B5.8/3/F Bridges - Finishing 4,760,778.24 12.500% 0.000% 12.500%

B5.8/3/G Subways - Top Slab 5,640,599.16 100.000% 0.000% 100.000%

B5.8/3/H Subways - Finishing Works 1,880,428.48 0.000% 0.000% 0.00%

B5.8/246 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B5.8/3/J Underpasses - Top Slab 8,223,100.03 100.000% 0.000% 100.00%

B5.8/3/K Underpasses - Finishing Works 2,741,033.33 0.000% 0.000% 0.00%

68,628,776.72 82.73% 0.00% 82.73%

B5.8/247 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

CONSTRUCTION OF MSE WALLS / RETAINING WALLS

B5.8/4/A Excavation 2,610,151.60 78.760% 12.650% 91.410%

B5.8/4/B Foundation 3,915,227.40 78.760% 12.508% 91.268%

B5.8/4/C MSE Wall Panel - Production 5,220,303.20 30.701% 47.395% 78.096%

B5.8/4/D MSE Wall Panel - Installation 7,308,424.48 23.812% 13.782% 37.594%

B5.8/4/E Backfilling / Filling 7,047,409.32 22.828% 12.194% 35.022%

B5.8/248 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

26,101,516.00 38.66% 19.77% 58.43%

B5.8/249 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B5.8/1 39,788,769.44 100.00% 0.00% 100.00%

From Page B5.8/2 38,912,937.84 100.00% 0.00% 100.00%

From Page B5.8/3 68,628,776.72 82.73% 0.00% 82.73%

From Page B5.8/4 26,101,516.00 38.66% 19.77% 58.43%

B5.8/250 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 5.8 - CONSTRUCTION OF INTERCHANGE H


173,432,000.00 83.94% 2.98% 86.91%
Carried to Appendix B1 (Grand Summary Sheet)

B5.8/251 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

642,588.63 - 642,588.63

81,566.98 - 81,566.98

837,553.60 - 837,553.60

20,158,980.04 - 20,158,980.04

635,028.76 - 635,028.76

76,792.33 - 76,792.33

629,060.44 - 629,060.44

B5.8/252 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
5,470,955.80 - 5,470,955.80

892,064.21 - 892,064.21

73,609.22 - 73,609.22

158,757.19 - 158,757.19

10,131,812.24 - 10,131,812.24

B5.8/253 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

39,788,769.44 - 39,788,769.44

B5.8/254 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

13,578,280.53 - 13,578,280.53

3,095,135.08 - 3,095,135.08

4,137,223.55 - 4,137,223.55

5,943,951.26 - 5,943,951.26

12,158,347.42 - 12,158,347.42

B5.8/255 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

38,912,937.84 - 38,912,937.84

B5.8/256 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

5,073,039.18 - 5,073,039.18

13,245,353.91 - 13,245,353.91

8,182,609.05 - 8,182,609.05

14,796,364.26 - 14,796,364.26

1,021,367.77 - 1,021,367.77

595,097.28 - 595,097.28

5,640,599.16 - 5,640,599.16

- - -

B5.8/257 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
8,223,100.03 - 8,223,100.03

- - -

56,777,530.64 - 56,777,530.64

B5.8/258 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,055,755.40 330,184.18 2,385,939.58

3,083,633.10 489,716.64 3,573,349.74

1,602,685.29 2,474,162.70 4,076,847.99

1,740,282.04 1,007,247.06 2,747,529.10

1,608,782.60 859,361.09 2,468,143.69

B5.8/259 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

10,091,138.43 5,160,671.67 15,251,810.10

B5.8/260 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

39,788,769.44 - 39,788,769.44

38,912,937.84 - 38,912,937.84

56,777,530.64 - 56,777,530.64

10,091,138.43 5,160,671.67 15,251,810.10

B5.8/261 Bill.5.8-IC H
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

145,570,376.35 5,160,671.67 150,731,048.02

B5.8/262 Bill.5.8-IC H
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 6.1 - STORMWATER DRAINAGE

Pipe Works

B6.1/1/A Excavation 49,051,171.58 76.057% 10.210% 86.267%

B6.1/1/B Piping 85,839,550.27 67.840% 5.844% 73.684%

B6.1/1/C Bedding & Surrounding 16,554,770.41 67.840% 5.844% 73.684%

B6.1/1/D Testing 30,656,982.24 0.492% 0.531% 1.023%

B6.1/1/E Backfilling 6,131,396.45 47.090% 9.088% 56.178%

B6.1/1/F Main Road Crossings 3,065,698.22 37.931% 31.035% 68.966%

Manholes

B6.1/263 Bill 6.1 - SW


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B6.1/1/G Excavation 12,262,792.90 62.388% 8.806% 71.194%

B6.1/1/H Blinding / Waterproofing / Screed 6,131,396.45 57.612% 7.313% 64.925%

B6.1/1/J Concrete Base 12,262,792.90 37.612% 6.866% 44.478%

B6.1/1/K Concrete Walls 18,394,189.34 32.388% 8.209% 40.597%

B6.1/1/L Internal & External Waterproofing 3,065,698.22 12.836% 12.388% 25.224%

B6.1/1/M Concrete Cover Slab / Metal Cover & Frame 12,262,792.90 8.060% 6.119% 14.179%

B6.1/1/N Backfilling 3,065,698.22 12.687% 4.029% 16.716%

258,744,930.10 51.98% 6.88% 58.86%

B6.1/264 Bill 6.1 - SW


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 6.1 - STORMWATER DRAINAGE


(CONT'D)

Catch Basins

B6.1/2/A Catch Basins 18,394,189.34 18.330% 6.715% 25.045%

Channels, Swales & Beams

B6.1/2/B Channels 61,313,964.48 0.000% 0.000% 0.000%

B6.1/2/C Swales 73,576,757.38 13.513% 0.882% 14.395%


B6.1/2/D Berms 39,854,076.91 0.000% 0.000% 0.000%

R/C Pipe Culvert incl. Inlet & Outfall

B6.1/2/E R/C Pipe Culvert incl. Inlet & Outfall 41,693,495.85 63.610% 6.460% 70.070%

B6.1/265 Bill 6.1 - SW


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

R/C Box Culvert

B6.1/2/F R/C Box Culvert 34,948,959.75 51.000% 1.350% 52.350%

Gullies

B6.1/2/G Gullies 11,343,083.43 4.489% 5.388% 9.877%

Grating

B6.1/2/H Grating 11,343,083.43 0.000% 0.000%

Flood Basins
B6.1/2/J Flood Basins 61,927,104.13 52.708% 0.000% 52.708%

354,394,714.70 25.62% 1.60% 27.22%

B6.1/266 Bill 6.1 - SW


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B6.1/1 258,744,930.10 51.98% 6.88% 58.86%

From Page B6.1/2 354,394,714.70 25.62% 1.60% 27.22%

B6.1/267 Bill 6.1 - SW


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 6.1. STORMWATER DRAINAGE Carried to


613,139,644.80 36.75% 3.83% 40.57%
Appendix B1 (Grand Summary Sheet)

B6.1/268 Bill 6.1 - SW


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

37,306,849.57 5,008,124.62 42,314,974.19

58,233,550.90 5,016,463.32 63,250,014.22

11,230,756.25 967,460.78 12,198,217.03

150,832.35 162,788.58 313,620.93

2,887,274.59 557,221.31 3,444,495.90

1,162,849.99 951,439.44 2,114,289.43

B6.1/269 Bill 6.1 - SW


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

7,650,511.23 1,079,861.55 8,730,372.78

3,532,420.12 448,389.03 3,980,809.15

4,612,281.67 841,963.36 5,454,245.03

5,957,510.04 1,509,979.01 7,467,489.05

393,513.02 379,778.70 773,291.72

988,381.11 750,360.30 1,738,741.41

388,945.13 123,516.98 512,462.11

134,495,675.97 17,797,346.98 152,293,022.95

B6.1/270 Bill 6.1 - SW


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

3,371,654.91 1,235,169.81 4,606,824.72

- - -

9,942,427.22 648,947.00 10,591,374.22


- - -

26,521,232.71 2,693,399.83 29,214,632.54

B6.1/271 Bill 6.1 - SW


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

17,823,969.47 471,810.96 18,295,780.43

509,191.02 611,165.33 1,120,356.35

- - -

32,640,538.04 - 32,640,538.04

90,809,013.37 5,660,492.93 96,469,506.30

B6.1/272 Bill 6.1 - SW


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

134,495,675.97 17,797,346.98 152,293,022.95

90,809,013.37 5,660,492.93 96,469,506.30

B6.1/273 Bill 6.1 - SW


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

225,304,689.34 23,457,839.91 248,762,529.25

B6.1/274 Bill 6.1 - SW


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 6.2 - STORM WATER TUNNEL AND


SHAFTS

B6.2/1/A Boreholing 1,900,000.00 100.000% 0.000% 100.000%

B6.2/1/B Mob. of Excavators, TBMs and STPs 13,870,000.00 100.000% 0.000% 100.000%

CONSTRUCTION

B6.2/1/C Shaft Excavation 41,948,200.00 79.960% 6.980% 86.940%

B6.2/1/D Temporary Works within Shaft 8,988,900.00 73.684% 5.263% 78.947%

B6.2/1/E Microtunneling (Ø3000) 152,811,300.00 53.960% 6.503% 60.463%

B6.2/1/F Microtunneling (Ø2400) 2,996,300.00 0.000% 0.000%

B6.2/1/G Microtunneling (Ø1500) 2,996,300.00 0.000% 0.000%

B6.2/1/H Microtunneling (Ø1400) 2,097,410.00 0.000% 0.000%

B6.2/275 Bill 6.2 - SWT


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B6.2/1/J Microtunneling (Ø1200) 1,797,780.00 0.000% 0.000%

B6.2/1/K Microtunneling (Ø1000) 1,498,150.00 0.000% 0.000%

B6.2/1/L Microtunneling (Ø900) 299,630.00 0.000% 0.000%

B6.2/1/M Microtunneling (Ø750) 299,630.00 0.000% 0.000%

B6.2/1/N Installation of P/C Pipes 32,959,300.00 48.426% 4.570% 52.996%

B6.2/1/P Production of P/C Shaft Walls 14,981,500.00 0.000% 50.155% 50.155%

B6.2/1/Q Installation of P/C Shaft Walls 17,977,800.00 0.000% 14.448% 14.448%

B6.2/1/R Manhole Construction 11,985,200.00 0.000% 0.000%

B6.2/1/S Demobilization 5,992,600.00 0.000% 0.000%

BILL NO 6.2 - STORM WATER TUNNEL AND SHAFTS


315,400,000.00 48.94% 7.91% 56.85%
Carried to Appendix B1 (Grand Summary Sheet)

B6.2/276 Bill 6.2 - SWT


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

1,900,000.00 - 1,900,000.00

13,870,000.00 - 13,870,000.00

33,541,780.72 2,927,984.36 36,469,765.08

6,623,381.08 473,085.80 7,096,466.88

82,456,977.48 9,937,318.84 92,394,296.32

- - -

- - -

- - -

B6.2/277 Bill 6.2 - SWT


ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
- - -

- - -

- - -

- - -

15,960,870.62 1,506,240.01 17,467,110.63

- 7,513,971.33 7,513,971.33

- 2,597,432.54 2,597,432.54

- - -

- - -

154,353,009.90 24,956,032.88 179,309,042.78

B6.2/278 Bill 6.2 - SWT


INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 7 - KAHRAMAA WATER WORKS

Pipe Works

B07/1/A Excavation 23,704,468.99 79.891% 2.926% 82.817%

B07/1/B Bedding 6,584,574.72 69.848% 6.326% 76.174%

B07/1/C Piping 63,211,917.31 69.848% 6.326% 76.174%

B07/1/D Surrounding 15,802,979.33 69.848% 6.326% 76.174%


B07/1/E Testing 6,584,574.72 42.853% 11.762% 54.615%

B07/1/F Backfilling 5,531,042.76 45.112% 6.018% 51.130%

B07/1/G Main Road Crossings 1,316,914.94 64.286% 0.000% 64.286%

B07/279 Bill.7-PW
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Removal / Protection of Existing System

B07/1/H Removal / Protection of Existing System 3,950,744.83 0.485% 0.000% 0.485%

Chambers

B07/1/J Excavation 921,840.46 60.000% 0.000% 60.000%

B07/1/K Blinding / Waterproofing / Screed 395,074.48 57.143% 0.000% 57.143%


B07/1/L Concrete Base 921,840.46 54.286% 0.000% 54.286%

B07/1/M Concrete Walls 1,316,914.94 42.857% 0.000% 42.857%

B07/1/N Internal & External Waterproofing 263,382.99 42.857% 0.000% 42.857%

B07/1/P Concrete Cover Slab / Metal Cover & Frame 658,457.47 22.857% 0.000% 22.857%

B07/1/Q Backfilling 263,383.00 22.857% 0.000% 22.857%


B07/1/R Ductile Iron Fitting incl. Concrete Plinth 263,383.00 42.857% 0.000% 42.857%

B07/280 Bill.7-PW
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 7 - KAHRAMAA WORK WORKS Carried to


131,691,494.40 66.21% 5.48% 71.69%
Appendix B1 (Grand Summary Sheet)

B07/281 Bill.7-PW
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

18,937,737.32 693,592.76 19,631,330.08

4,599,193.75 416,540.20 5,015,733.95

44,152,260.00 3,998,785.89 48,151,045.89

11,038,065.00 999,696.47 12,037,761.47


2,821,687.80 774,477.68 3,596,165.48

2,495,164.01 332,858.15 2,828,022.16

846,591.94 - 846,591.94

B07/282 Bill.7-PW
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

19,161.11 - 19,161.11

553,104.28 - 553,104.28

225,757.41 - 225,757.41
500,430.31 - 500,430.31

564,390.24 - 564,390.24

112,878.05 - 112,878.05

150,503.62 - 150,503.62

60,201.45 - 60,201.45
112,878.05 - 112,878.05

B07/283 Bill.7-PW
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

87,190,004.34 7,215,951.15 94,405,955.49

B07/284 Bill.7-PW
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 8 - TREATED SEWAGE EFFUENT (TSE)


WORKS

Pipe Works

B08/1/A Excavation 58,186,025.12 36.770% 10.347% 47.117%

B08/1/B Bedding 12,930,233.18 27.664% 8.963% 36.627%

B08/1/C Piping 121,135,890.84 27.664% 8.963% 36.627%

B08/1/D Surrounding 17,153,794.32 27.664% 8.963% 36.627%

B08/1/E Testing 12,930,954.02 1.553% 1.923% 3.476%

B08/1/F Backfilling 15,859,352.54 13.403% 2.930% 16.333%

B08/1/G Main Road Crossings 20,767,420.82 30.798% 0.000% 30.798%

B08/285 Bill.8-TSE
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
Chambers

B08/1/H Excavation 6,223,014.64 2.463% 1.314% 3.777%

B08/1/J Blinding / Waterproofing / Screed 10,244,278.23 1.970% 0.821% 2.791%

B08/1/K Concrete Base 4,038,799.77 1.314% 2.791% 4.105%

B08/1/L Concrete Walls 4,038,799.77 0.657% 1.970% 2.627%

B08/1/M Internal & External Waterproofing 4,866,822.90 0.000% 1.970% 1.970%

B08/1/N Concrete Cover Slab / Metal Cover & Frame 12,565,154.98 0.000% 0.000% 0.000%

B08/1/P Backfilling 4,038,799.77 0.000% 0.000% 0.000%

B08/1/Q Ductile Iron Fitting incl. Concrete Plinth 6,282,577.50 0.000% 0.000% 0.000%

B08/286 Bill.8-TSE
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 8 - TREATED SEWAGE EFFUENT (TSE) WORKS


311,261,918.40 23.26% 6.66% 29.92%
Carried to Appendix B1 (Grand Summary Sheet)

B08/287 Bill.8-TSE
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

21,395,001.44 6,020,508.02 27,415,509.46

3,577,019.71 1,158,936.80 4,735,956.51

33,511,032.84 10,857,409.90 44,368,442.74

4,745,425.66 1,537,494.59 6,282,920.25

200,817.72 248,662.24 449,479.96

2,125,629.02 464,679.03 2,590,308.05

6,395,950.26 - 6,395,950.26

B08/288 Bill.8-TSE
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

153,272.85 81,770.41 235,043.26

201,812.28 84,105.53 285,917.81

53,069.83 112,722.90 165,792.73

26,534.91 79,564.36 106,099.27

- 95,876.41 95,876.41

- - -

- - -

- - -

B08/289 Bill.8-TSE
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

72,385,566.52 20,741,730.19 93,127,296.71

B08/290 Bill.8-TSE
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 9 - FOUL SEWER WORKS

Pipe Works

B09/1/A Excavation 4,464,529.34 46.882% 37.682% 84.564%

B09/1/B Bedding 1,014,665.76 45.997% 38.567% 84.564%

B09/1/C Piping 9,440,791.30 45.997% 38.567% 84.564%

B09/1/D Surrounding 2,232,264.67 45.997% 34.145% 80.142%

B09/1/D Testing 1,014,665.76 35.117% 0.000% 35.117%

B09/1/E Backfilling 1,319,065.49 37.152% 42.990% 80.142%

B09/1/E Main Road Crossings 604,399.73 85.714% 0.000% 85.714%

B09/291 Bill.9-FS
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
Chambers

B09/1/F Excavation 20,293.32 0.000% 0.000%

B09/1/G Blinding / Waterproofing / Screed 20,293.32 0.000% 0.000%

B09/1/G Concrete Base 30,439.97 0.000% 0.000%

B09/1/G Concrete Walls 60,879.95 0.000% 0.000%

B09/1/G Internal & External Waterproofing 20,293.32 0.000% 0.000%

B09/1/G Concrete Cover Slab / Metal Cover & Frame 30,439.97 0.000% 0.000%

B09/1/G Backfilling 10,146.65 0.000% 0.000%

B09/1/G Ductile Iron Fitting incl. Concrete Plinth 10,146.65 0.000% 0.000%

B09/292 Bill.9-FS
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
BILL NO 9 - FOUL SEWER WORKS Carried to Appendix
20,293,315.20 45.80% 34.71% 80.51%
B1 (Grand Summary Sheet)

B09/293 Bill.9-FS
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,093,060.65 1,682,323.94 3,775,384.59

466,715.81 391,326.14 858,041.95

4,342,480.77 3,641,029.98 7,983,510.75

1,026,774.78 762,206.77 1,788,981.55

356,320.17 - 356,320.17

490,059.21 567,066.25 1,057,125.46

518,055.18 - 518,055.18

B09/294 Bill.9-FS
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

- - -

- - -

- - -

- - -

- - -

- - -

- - -

- - -

B09/295 Bill.9-FS
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

9,293,466.57 7,043,953.08 16,337,419.65

B09/296 Bill.9-FS
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 10 - KAHRAMAA ELECTRICAL


WORKS

HV-EHV Cable Works


B10/1/A HV-EHV Excavation 5,182,068.12 100.000% 0.000% 100.000%
B10/1/B HV-EHV Bedding 2,220,886.34 100.000% 0.000% 100.000%
B10/1/C HV-EHV Cabling 48,859,499.46 100.000% 0.000% 100.000%

B10/1/D HV-EHV Protection / Surrounding 6,662,659.02 100.000% 0.000% 100.000%

B10/1/E HV-EHV Backfilling 2,220,886.34 100.000% 0.000% 100.000%

MV Cable Works
B10/1/F MV Excavation 8,513,397.63 83.146% 3.689% 86.835%
B10/1/G MV Bedding 4,441,772.68 82.004% 4.831% 86.835%

B10/1/H MV Cabling 47,008,760.85 82.004% 3.164% 85.168%

B10/297 Bill.10-EL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B10/1/J MV Protection / Surrounding 8,513,397.63 82.004% 3.164% 85.168%

B10/1/K MV Backfilling 4,441,772.68 82.004% 3.164% 85.168%

LV Cable Works

B10/1/L LV Excavation 17,767,090.71 48.808% 9.110% 57.918%

B10/1/M LV Bedding 8,883,545.36 44.982% 12.936% 57.918%

B10/1/N LV Cabling 65,516,147.01 44.982% 6.727% 51.709%


B10/1/P LV Protection / Surrounding 6,662,659.02 44.982% 6.727% 51.709%
B10/1/Q LV Backfilling 6,662,659.02 44.982% 6.727% 51.709%

Total to Collection Page 243,557,201.87 71.10% 4.31% 75.41%

B10/298 Bill.10-EL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 10 - KAHRAMAA ELECTRICAL


WORKS (Cont'd)

Road Crossing Ducts

B10/2/A Type H 16,656,647.54 98.992% 0.108% 99.100%


B10/2/B Type 2H 33,313,295.09 98.881% 0.119% 99.000%

B10/2/C Type EN2 1,110,443.17 73.274% 7.853% 81.127%

B10/2/D Type EN4 370,147.72 95.310% 0.000% 95.310%

B10/2/E Type EN6 15,916,352.10 90.652% 4.240% 94.892%

Substation Works

B10/2/F Substations - Foundation 8,143,249.91 22.500% 37.500% 60.000%

B10/2/G Substations - Walls&Top Slab 12,214,874.87 0.000% 30.000% 30.000%

B10/299 Bill.10-EL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
B10/2/H Substations - Electrical Works 20,358,124.77 0.000% 0.000% 0.000%

Removal / Protection of Existing System

B10/2/J Removal / Protection of Existing System 18,507,386.16 50.000% 0.000% 50.000%

Total to Collection Page 126,590,521.33 60.12% 5.95% 66.08%

B10/300 Bill.10-EL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B10/1 243,557,201.87 71.10% 4.31% 75.41%

From Page B10/2 126,590,521.33 60.12% 5.95% 66.08%

B10/301 Bill.10-EL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 10 - KAHRAMAA ELECTRICAL WORKS


370,147,723.20 67.35% 4.87% 72.22%
Carried to Appendix B1 (Grand Summary Sheet)

B10/302 Bill.10-EL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

5,182,068.12 - 5,182,068.12
2,220,886.34 - 2,220,886.34
48,859,499.46 - 48,859,499.46

6,662,659.02 - 6,662,659.02

2,220,886.34 - 2,220,886.34

7,078,549.59 314,059.24 7,392,608.83


3,642,431.27 214,582.04 3,857,013.31

38,549,064.25 1,487,357.19 40,036,421.44

B10/303 Bill.10-EL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

6,981,326.59 269,363.90 7,250,690.49

3,642,431.27 140,537.69 3,782,968.96

8,671,761.63 1,618,581.97 10,290,343.60

3,995,996.37 1,149,175.43 5,145,171.80

29,470,473.25 4,407,271.21 33,877,744.46


2,996,997.28 448,197.07 3,445,194.35
2,996,997.28 448,197.07 3,445,194.35

173,172,028.06 10,497,322.81 183,669,350.87

B10/304 Bill.10-EL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

16,488,748.53 17,989.18 16,506,737.71


32,940,519.32 39,642.82 32,980,162.14

813,666.13 87,203.10 900,869.23

352,787.79 - 352,787.79

14,428,491.51 674,853.32 15,103,344.83

1,832,231.23 3,053,718.72 4,885,949.95

- 3,664,462.46 3,664,462.46

B10/305 Bill.10-EL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE
- - -

9,253,693.08 - 9,253,693.08

76,110,137.59 7,537,869.60 83,648,007.19

B10/306 Bill.10-EL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

173,172,028.06 10,497,322.81 183,669,350.87

76,110,137.59 7,537,869.60 83,648,007.19

B10/307 Bill.10-EL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

DOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

249,282,165.65 18,035,192.41 267,317,358.06

B10/308 Bill.10-EL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 11 - STREET LIGHTING WORKS

High Mast Columns


B11/1/A High Mast Piles 25,247,386.56 63.202% 5.868% 69.070%

B11/1/B High Mast Pile Cap 3,787,107.98 17.854% 9.304% 27.158%

B11/1/C Supply & Installation of High Mast Columns 65,643,205.06 4.275% 9.137% 13.412%

Other Street Lighting Columns


B11/1/D Excavation (Street Lighting Foundation) 3,029,686.39 0.545% 0.000% 0.545%

B11/1/E Foundation Concrete 13,381,114.88 0.545% 0.000% 0.545%

B11/1/F Supply & Install. of Street Lighting Columns 30,296,863.87 0.545% 0.000% 0.545%

Street Lighting Road Crossing Ducts

B11/309 Bill.11-SL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE
Supply and Install Street Lighting ducts (Types SL1, SL2,
B11/1/G 11,361,323.95 26.164% 0.000% 26.164%
SL3 & SL4) including earth works, civil works as required.

Feeder Pillar
Supply and Install feeder pillar including foundations,
B11/1/H 15,148,431.94 0.000% 0.000% 0.000%
earthing and all necessary works as required.

Total to Collection Page 167,895,120.63 13.50% 4.66% 18.16%

B11/310 Bill.11-SL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 11 - STREET LIGHTING WORKS


(Cont'd)

Cable Works
B11/2/A Trench Excavation 26,509,755.89 0.346% 1.323% 1.669%

B11/2/B Cabling in Trenches 27,772,125.22 0.317% 0.164% 0.481%

B11/2/C Bedding & Surrounding 7,574,215.97 0.317% 0.164% 0.481%

B11/2/D Backfilling to Trenches 5,049,477.30 0.317% 0.164% 0.481%

Underpass / Bridges Lightings

Supply and Install lightings to Underpasses and bridges


B11/2/E including all cabling works, distribution boards and all 17,673,170.59 0.000% 0.000% 0.000%
necessary works as required.

B11/311 Bill.11-SL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Total to Collection Page 84,578,744.97 0.26% 0.49% 0.75%

B11/312 Bill.11-SL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

Collection Page

From Page B11/1 167,895,120.63 13.50% 4.66% 18.16%

From Page B11/2 84,578,744.97 0.26% 0.49% 0.75%

B11/313 Bill.11-SL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 11 - STREET LIGHTING WORKS Carried to


252,473,865.60 9.06% 3.27% 12.33%
Appendix B1 (Grand Summary Sheet)

B11/314 Bill.11-SL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

15,956,853.25 1,481,516.65 17,438,369.90

676,150.26 352,352.53 1,028,502.79

2,806,247.02 5,997,819.64 8,804,066.66

16,511.79 - 16,511.79

72,927.08 - 72,927.08

165,117.91 - 165,117.91

B11/315 Bill.11-SL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,972,576.80 - 2,972,576.80

- - -

22,666,384.11 7,831,688.82 30,498,072.93

B11/316 Bill.11-SL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

91,723.76 350,724.07 442,447.83

88,037.64 45,546.28 133,583.92

24,010.26 12,421.72 36,431.98

16,006.84 8,281.15 24,287.99

- - -

B11/317 Bill.11-SL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

219,778.50 416,973.22 636,751.72

B11/318 Bill.11-SL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

22,666,384.11 7,831,688.82 30,498,072.93

219,778.50 416,973.22 636,751.72

B11/319 Bill.11-SL
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

22,886,162.61 8,248,662.04 31,134,824.65

B11/320 Bill.11-SL
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 12 - TELECOM - QNBN, OOREDOO


AND VODAFONE WORKS

B12/1/A Excavation 5,352,899.52 82.485% 2.305% 84.790%

B12/1/B Bedding 3,211,739.71 78.923% 0.000% 78.923%

B12/1/C Road Crossing Ducts 9,635,219.14 86.533% 0.000% 86.533%

B12/1/D Ducting 17,664,568.42 78.923% 0.000% 78.923%

B12/1/E Protection / Surrounding 6,423,479.42 78.923% 0.000% 78.923%

B12/1/F Backfilling 2,676,449.76 78.923% 0.000% 78.923%

B12/1/G Manholes / Chambers / Joint Boxes 5,888,189.47 69.863% 0.000% 69.863%

B12/1/H Removal / Protection of Existing System 2,676,449.76 63.958% 0.000% 63.958%

B12/321 Bill.12-TELECOM
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B12/322 Bill.12-TELECOM
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 12 - TELECOM - QNBN, OOREDOO AND


VODAFONE WORKS Carried to Appendix B1 (Grand 53,528,995.20 78.90% 0.23% 79.13%
Summary Sheet)

B12/323 Bill.12-TELECOM
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

4,415,339.17 123,384.33 4,538,723.50

2,534,801.33 - 2,534,801.33

8,337,644.18 - 8,337,644.18

13,941,407.33 - 13,941,407.33

5,069,602.66 - 5,069,602.66

2,112,334.44 - 2,112,334.44

4,113,665.81 - 4,113,665.81

1,711,803.74 - 1,711,803.74

B12/324 Bill.12-TELECOM
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

B12/325 Bill.12-TELECOM
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

42,236,598.66 123,384.33 42,359,982.99

B12/326 Bill.12-TELECOM
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 13 - QAF WORKS

B15/1/A Excavation 7,627,881.82 34.985% 0.000% 34.985%

B15/1/B Bedding 3,504,702.46 28.291% 4.349% 32.640%

B15/1/C Road Crossing Ducts 5,566,292.14 70.404% 17.338% 87.742%

B15/1/D Ducting 10,720,266.34 28.291% 4.349% 32.640%

B15/1/E Protection / Surrounding 5,772,451.10 28.291% 4.349% 32.640%

B15/1/F Backfilling 3,504,702.45 28.291% 4.349% 32.640%

B15/1/G Manholes / Chambers / Joint Boxes 2,473,907.61 24.444% 0.000% 24.444%

B15/1/H Removal / Protection of Existing System 2,061,589.68 0.000% 0.000% 0.000%

B13/327 Bill.13-QAF
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 13 - QAF WORKS Carried to Appendix B1


41,231,793.60 33.57% 4.82% 38.39%
(Grand Summary Sheet)

B13/328 Bill.13-QAF
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

2,668,614.45 - 2,668,614.45

991,515.37 152,419.51 1,143,934.88

3,918,892.32 965,083.73 4,883,976.05

3,032,870.55 466,224.38 3,499,094.93

1,633,084.14 251,043.90 1,884,128.04

991,515.37 152,419.51 1,143,934.88

604,721.98 - 604,721.98

- - -

B13/329 Bill.13-QAF
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

13,841,214.18 1,987,191.03 15,828,405.21

B13/330 Bill.13-QAF
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 14 - UGN WORKS

B14/1/A Excavation 17,326,933.01 56.708% 0.612% 57.320%

B14/1/B Bedding 6,300,702.91 42.027% 0.000% 42.027%

B14/1/C Road Crossing Ducts 22,052,460.19 63.988% 0.000% 63.988%

B14/1/D Ducting 55,131,150.48 42.027% 0.000% 42.027%

B14/1/E Protection / Surrounding 26,777,987.38 35.862% 5.678% 41.540%

B14/1/F Backfilling 7,875,878.64 35.862% 5.678% 41.540%

B14/1/G Manholes / Chambers / Joint Boxes 22,052,460.19 34.386% 0.000% 34.386%

B14/331 Bill.14-UGN
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 16 - UGN WORKS Carried to Appendix B1


157,517,572.80 44.29% 1.32% 45.61%
(Grand Summary Sheet)

B14/332 Bill.14-UGN
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

9,825,757.17 106,040.83 9,931,798.00

2,647,996.41 - 2,647,996.41

14,110,928.23 - 14,110,928.23

23,169,968.61 - 23,169,968.61

9,603,121.83 1,520,454.13 11,123,575.96

2,824,447.60 447,192.39 3,271,639.99

7,582,958.96 - 7,582,958.96

B14/333 Bill.14-UGN
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

69,765,178.81 2,073,687.35 71,838,866.16

B14/334 Bill.14-UGN
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 19 - PEDESTRIAN / CYCLE WAY AND


FAST CYCLE TRACK

B19/1/A Site Clearance and Excavation 31,920,000.00 32.749% 4.630% 37.379%

B19/1/B Aggregate Base Course 53,200,000.00 0.000% 0.000%

B19/1/C Wearing Course / Pavement 21,280,000.00 0.000% 0.000%

B19/335 Bill.19-
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

B19/336 Bill.19-
INTERIM PAYMENT METHODOLOGY
Contract No: C2017/113
Description: Design and Build of Al Khor Expressway

APPENDIX B2 - BREAKDOWN FOR VALUE OF WORKS


CERTIFIED
ITEM DESCRIPTION AMOUNT (QR) QUANTITY
PREVIOUS CURRENT TO-DATE

BILL NO 19 - PEDESTRIAN / CYCLE WAY AND FAST


CYCLE TRACK Carried to Appendix B1 (Grand 106,400,000.00 9.82% 1.39% 11.21%
Summary Sheet)

B19/337 Bill.19-
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

10,453,480.80 1,477,896.00 11,931,376.80

- -

- -

B19/338 Bill.19-
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

B19/339 Bill.19-
ENT METHODOLOGY
Interim Payment No : 24
Period Ending : 21-Aug-2018
Recommend. Date : 04-Sep-2018

KDOWN FOR VALUE OF WORKS


CERTIFIED FOR PAYMENT
AMOUNT (QR) Remarks
PREVIOUS CURRENT TO-DATE

10,453,480.80 1,477,896.00 11,931,376.80

B19/340 Bill.19-
SUB 4 DESCRIPTION AMOUNT (QR) PREVIOUS % CURRENT % TO-DATE %

Performance Bond; in accordance with the Clause 4.2 of General 123,120,000.00 100.00% 0.00% 100.00%
Conditions of Contract
All insurances required for the contract; in accordance with the Clauses Included 0.00% 0.00% 0.00%
18.1, 18.2, 18.3 & 18.4 of General Conditions of Contract
Provision of Engineer's Site Office and Facilities as per QCS 2014 8,436,000.00 100.00% 0.00% 100.00%
Section 1 - General Part 11
Provision of Contractor's Site Office and Facilities as per QCS 2014 70,300,000.00 100.00% 0.00% 100.00%
Section 1 - General Part 12
Allow for mobilizing Contractor's Equipment/Plant; as per Conditions of 33,744,000.00 100.00% 0.00% 100.00%
Contract
Allow for Obligations & Liabilities complying with Conditions of Contract 32,000,000.00 67.58% 0.00% 67.58%

Allow for Quality Assurance, Testing and Health & Safety as per 27,960,000.00 67.58% 0.00% 67.58%
required by Conditions of Contract
Allow for other all necessary reuirements; such as superindendence, 443,464,000.00 67.58% 0.00% 67.58%
maintenance works and etc as per the Conditions of Contract, except
the temporary road measured under bill 5.
Design Works 147,820,000.00 99.570% 0.000% 99.570%

Site Clearance 111,982.77 100.000% 0.000% 100.000%

Relocation of Electrical Over Head Cables 562,162.50 100.00% 0.00% 100.00%

Road Diversions as required 972,915.90 100.00% 0.00% 100.00%

Earth Works including exacavation & filling works as required 8,657,002.68 95.00% 0.00% 95.00%

Road Crossing Ducts as required 3,746,250.90 100.00% 0.00% 100.00%

Aggregate Base Course Construction 4,310,811.96 100.00% 0.00% 100.00%

Asphalt Intermediate Course Construction 7,152,206.10 100.00% 0.00% 100.00%

Construction of Safety Guard Rail 2,254,346.58 95.00% 0.00% 95.00%

B01/341 Filter
SUB 4 DESCRIPTION AMOUNT (QR) PREVIOUS % CURRENT % TO-DATE %

Road Markings 709,404.10 100.00% 0.00% 100.00%


Traffic Sings
266,060.27 100.00% 0.00% 100.00%
Street Lighting Works
1,238,856.24 100.00% 0.00% 100.00%
Site Clearance
215,870.40 100.00% 0.00% 100.00%
Relocation of Electrical Over Head Cables
4,065,559.20 100.00% 0.00% 100.00%
Road Diversions as required
1,457,125.20 100.00% 0.00% 100.00%
Earth Works including exacavation & filling works as required
25,112,923.20 100.00% 0.00% 100.00%
Road Crossing Ducts as required
4,317,408.00 100.00% 0.00% 100.00%
Aggregate Base Course Construction
5,036,976.00 100.00% 0.00% 100.00%
Asphalt Base Course Construction
9,678,189.60 100.00% 0.00% 100.00%
Asphalt Intermediate Course Construction
6,961,820.40 100.00% 0.00% 100.00%
Asphalt Wearing Course Construction
5,360,781.60 100.00% 0.00% 100.00%
Construction of Safety Guard Rail
5,738,554.80 95.00% 0.00% 95.00%
Road Markings
1,390,565.16 100.00% 0.00% 100.00%
Traffic Sings
390,365.64 100.00% 0.00% 100.00%
Street Lighting Works
2,230,660.80 100.00% 0.00% 100.00%
Site Clearance
23,985.60 100.00% 0.00% 100.00%

B01/342 Filter
SUB 4 DESCRIPTION AMOUNT (QR) PREVIOUS % CURRENT % TO-DATE %

Relocation of Electrical Over Head Cables


503,697.60 100.00% 0.00% 100.00%
Earth Works including exacavation & filling works as required
3,813,710.40 100.00% 0.00% 100.00%
Road Crossing Ducts as required
239,856.00 100.00% 0.00% 100.00%
Aggregate Base Course Construction
887,467.20 100.00% 0.00% 100.00%
Asphalt Base Course Construction
1,607,035.20 100.00% 0.00% 100.00%
Asphalt Intermediate Course Construction
1,367,179.20 100.00% 0.00% 100.00%
Asphalt Wearing Course Construction
887,467.20 100.00% 0.00% 100.00%
Construction of Safety Guard Rail
1,607,035.20 95.00% 0.00% 95.00%
Road Markings
143,913.60 100.00% 0.00% 100.00%
Traffic Sings
71,956.80 100.00% 0.00% 100.00%
Street Lighting Works
839,496.00 100.00% 0.00% 100.00%
Construction of 6 Nos of Package Substations and 1No Indoor
Substation 5,996,400.00 99.98% 0.00% 99.98%

Diversion Road (TTM) 56,879,200.13 98.830% 0.000% 98.830%


Site Clearance 27,289,707.35 100.00% 0.00% 100.00%
Excavation 65,762,526.23 95.19% 0.00% 95.19%
General Filling 101,036,699.88 84.41% 0.00% 84.41%
Selected Fill 59,000,833.16 61.98% 0.00% 61.98%
Subbase Course 34,326,726.84 39.59% 0.00% 39.59%
Aggregate Road Base Course 50,182,289.75 36.31% 0.00% 36.31%
Concrete Barrier 63,292,686.24 25.94% 0.00% 25.94%
Prime Coat and Asphalt Road Base Course 150,028,607.75 35.64% 0.00% 35.64%

B01/343 Filter
SUB 4 DESCRIPTION AMOUNT (QR) PREVIOUS % CURRENT % TO-DATE %

Tack Coat and Asphalt Intermediate Course 91,359,785.85 6.42% 0.00% 6.42%
Tack Coat and Asphalt Wearing Course 71,771,120.55 0.96% 0.00% 0.96%

B01/344 Filter
PREVIOUS (QAR) CURRENT (QAR) TO-DATE (QAR)

123,120,000.00 - 123,120,000.00

- - -

8,436,000.00 - 8,436,000.00

70,300,000.00 - 70,300,000.00

33,744,000.00 - 33,744,000.00

18,031,040.00 3,594,560.00 21,625,600.00

15,754,621.20 3,140,746.80 18,895,368.00

249,878,660.08 49,814,311.12 299,692,971.20

147,184,374.00 - 147,184,374.00

111,982.77 - 111,982.77

562,162.50 - 562,162.50

972,915.90 - 972,915.90

8,224,152.55 - 8,224,152.55

3,746,250.90 - 3,746,250.90

4,310,811.96 - 4,310,811.96

7,152,206.10 - 7,152,206.10

2,141,629.25 - 2,141,629.25

B01/345 Filter
PREVIOUS (QAR) CURRENT (QAR) TO-DATE (QAR)

709,404.10 - 709,404.10

266,060.27 - 266,060.27

1,238,856.24 - 1,238,856.24

215,870.40 - 215,870.40

4,065,559.20 - 4,065,559.20

1,457,125.20 - 1,457,125.20

25,112,923.20 - 25,112,923.20

4,317,408.00 - 4,317,408.00

5,036,976.00 - 5,036,976.00

9,678,189.60 - 9,678,189.60

6,961,820.40 - 6,961,820.40

5,360,781.60 - 5,360,781.60

5,451,627.06 - 5,451,627.06

1,390,565.16 - 1,390,565.16

390,365.64 - 390,365.64

2,230,660.80 - 2,230,660.80

23,985.60 - 23,985.60

B01/346 Filter
PREVIOUS (QAR) CURRENT (QAR) TO-DATE (QAR)

503,697.60 - 503,697.60

3,813,710.40 - 3,813,710.40

239,856.00 - 239,856.00

887,467.20 - 887,467.20

1,607,035.20 - 1,607,035.20

1,367,179.20 - 1,367,179.20

887,467.20 - 887,467.20

1,526,683.44 - 1,526,683.44

143,913.60 - 143,913.60

71,956.80 - 71,956.80

839,496.00 - 839,496.00

5,995,395.60 - 5,995,395.60

56,213,713.49 - 56,213,713.49
27,289,707.35 - 27,289,707.35
62,599,348.72 - 62,599,348.72
85,285,078.37 - 85,285,078.37
36,568,716.39 - 36,568,716.39
13,589,951.16 - 13,589,951.16
18,221,189.41 - 18,221,189.41
16,418,122.81 - 16,418,122.81
53,470,195.80 - 53,470,195.80

B01/347 Filter
PREVIOUS (QAR) CURRENT (QAR) TO-DATE (QAR)

5,865,298.25 - 5,865,298.25
689,002.76 - 689,002.76

B01/348 Filter