ID Task Task Name Duration April 2019 May 2019

Mode 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
1 WILMAR PROJECT 60 days
2 PERSIAPAN 11 days
3 Mobilisasi 2 days
4 Peralatan kerja 2 days
5 Safety, PPE & Insurance 2 days
6 Setting dan Pembersihan 3 days
7 Approval dan Pengadaan 9 days
8 STRUCTURE WORK 49 days
9 STRUCTURE PLATFORM BE SILO 35 days
10 CIVIL WORK PONDASI GANTRY BE SILO 19 days
11 Bobok beton t 30 cm 2 days
12 bowplank 1 day
13 galian tanah dan buang bekas bobok 2 days
14 bekisting multiplek 2 days
15 besi D16 2 days
16 besi D10 2 days
17 angkur M19‐500 triplenut 1 day
18 Upah cor beton K300 1 day
19 finising bekas bobok beton 2 days
20 grouting t 5 cm 1 day
21 STUKTUR BAJA 9 days
22 Fabrikasi 5 days
23 Erection 4 days
24 STRUCTURE PLATFORM CHEMICAL TANK 10 days
25 STUKTUR BAJA 10 days
26 Fabrikasi 7 days
27 Erection 3 days
28 STRUCTURE PLATFORM FILTER 11 days
29 STUKTUR BAJA 11 days
30 Fabrikasi 7 days
31 Erection 4 days
32 STRUCTURE PLATFORM DEO 11 days
33 STUKTUR BAJA 11 days
34 Fabrikasi 5 days
35 Erection 6 days
36 STRUCTURE HOPPER DISCHARGE BE 12 days
37 Fabrikasi 7 days
38 Erection 5 days
39 STRUCTURE BASIN COOLING 20 days
40 Fabrikasi 10 days

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: SCHEDULE.mpp
Milestone Inactive Summary Start-only Critical
Date: Mon 01/04/19
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID Task Task Name Duration April 2019 May 2019
Mode 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30
41 Erection 10 days
42 STRUCTURE PLATFORM EL+28.000 13 days
43 STUKTUR BAJA 13 days
44 Fabrikasi 5 days
45 Erection 3 days
46 STRUCTURE MODIF GANTRY REFF 37 days
47 CIVIL WORK 19 days
48 bobok dinding existing 2 days
49 Bobok beton t 30 cm 2 days
50 bowplank 1 day
51 galian tanah dan buang bekas bobok 2 days
52 bekisting multiplek 2 days
53 besi D16 2 days
54 besi D10 2 days
55 angkur M19‐500 triplenut 1 day
56 Upah cor beton K300 1 day
57 finising bekas bobok beton 1 day
58 grouting t 5 cm 1 day
59 STUKTUR BAJA 9 days
60 Fabrikasi 5 days
61 Erection 4 days
62 STRUCTURE SUPPORT PIPA ISBL 12 days
63 Fabrikasi 5 days
64 Erection 7 days
65 PENUTUP LANTAI DENGAN CLADDING 16 days
66 Fabrikasi 11 days
67 Erection 5 days
68 PENYANGGA CHIMNEY 6 days
69 Fabrikasi 3 days
70 Erection 3 days
71 CIVIL WORK MODIF PONDASI CILLER  15 days
EXSISTING
72 bongkar keramik existing 1 day
73 bobok beton existing 2 days
74 stek beton d 13 panjang 40cm 1 day
75 cor beton K300 1 day
76 grouting t 5 cm 1 day
77 pasang ulang keramik 1 day

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: SCHEDULE.mpp
Milestone Inactive Summary Start-only Critical
Date: Mon 01/04/19
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress