Professional Documents
Culture Documents
Stability: Shedding
Stability: Shedding
Stability: Shedding
However, when work is being performed on insulator Northwest Power Pool load shedding program was completely
strings with a considerable amount of damage, the best solution of redesigned using improved design methods.
the risk factor problem appears to lie in limiting the line surge level to The disturbances of greatest concern are loss of generation
a known value. This can be achieved through the use of protective incidents or loss of interconnections with other regions. These
gaps. This leads into the third phase of the investigation during disturbances are more probable than the severe short
which the developmental testing of protective gaps was carried out, generating plants disturbances which may be morecircuits near
commonly
so as to extend safe working conditions to strings with damaged studied. Loss of a large block of generation followed by loss of
and/or punctured insulators.
Protective gaps have been developed for live line work methods imports
due to instability can result in very large generation-load
imbalance.
applied to 230 and 500 kV systems. These serve to eliminate the need reduced generator During light load conditions, reduced rotating inertia and
for line outages in cases where the insulator string has sustained faster frequency voltage support cause lower stability levels and
extensive damage. A set of protective gaps, designed for use on the decay.
500 kV system is shown in Figure 1. The desired mode of operation of load Islanding of the Pacific Northwest region with severe generation-
imbalance can lead to unpredictable and possibly severe
such a protective gap requires that it have a protective level, (CFO + consequences. Therefore, Bonneville Power Administration
3a ), lower than the lowest withstand value of the insulator string, adopted a philosophy of installing discrete controls to prevent
lineman, and tool configuration. A second desired characteristic is
that of a withstand level which is as high as possible. This serves to islanding
for relatively high probability disturbances.
eliminate unwanted flashovers due to minor system disturbances. A Discrete stability controls for direct tripping of aluminum re¬
full description of the protective gaps, and of their development for duction plant load have been applied on a much larger scale than
the 230 and 500 kV systems, is given in the paper. previous applications. Sensors at various locations are used to
transfer trip up to 3,000 MW of industrial load. In addition, for loss of
References the Pacific AC Intertie, fast power change controls have been im¬
[1] IEEE Committee Report, "Recommendations for Safety in Live controls plemented on the parallel Pacific HVDC Intertie. Arming levels forthe
are determined from off-line transient stability simulations.
Line Maintenance", IEEE Trans on Power Apparatus and Potential for misoperation is minimized by arming the controls only
Systems, Volume PAS-87, No. 2, February 1968. during critical system conditions.
Load shedding program design was challenging because of a high
coordinating frequency of 58 Hz due to relatively high under-
frequency trip settings at a coal-fired and a nuclear generating plant.
The numerous considerations in load shedding program design are
summarized.
Many load shedding programs have been designed using simple
calculations. This was not possible for the Northwest Power Pool. Of
the many advantages of using large-scale transient stability
programs for design, the ability to represent voltage sensitivity of
loads is particularly important. Because of the longer simulation
times (10-15 seconds) and because of the abnormal voltages and
frequencies which exist, some additions to conventional transient
stability programs are desirable. These additions are outlined in the
paper.
The load shedding program consists of seven steps between 59.3
and 58.7 Hz. For reasons discussed in the paper, substantial
overshedding followed by overfrequency on the order of 62 Hz is
possible. High speed automatic load restoration is used to limit
overfrequency. A unique method, also used to control over-
frequency, is energization of the Chief Joseph 1,400 MW dynamic
brake by an overfrequency relay. This allows more time for governor
Fig. 1. 500 kV Protective Gap control action to be effective.