Schedule Acceleration Practice Problem

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

232 Chapter 8 Schedule Compression and Time-Cost Trade-Off

Example 8.1

Calculate the normal, least-cost, and crash durations for the following project.
Calculate the cost associated with each duration. Indirect (overhead) costs
are $120 per day.

Duration (days) Cost ($)

Activity IPA Normal Crash Normal Crash

A – 5 4 500 600
B A 7 5 350 500
C A 8 5 800 920
D A 11 7 1,200 1,400
E B, C 6 4 600 700
F C 4 4 500 500
G D, F 7 5 700 1,000
H E, F 6 5 300 420

Solution
This simple project has five paths (see Figure 8.11). They are listed next, along
with their lengths in days:

5,12
B 13,19 19,25
7 E H
6,13 6 6
13,19 19,25 25
0,5 5,13
A C PF
5 8
0.5 5,13 13,17 17,24 25
F G
4 7
14,18 18,25
5,16
D
11
7,18
Figure 8.11 Precedence network for project in example 8.1—PF, project finish
Recovery Schedules 233

Cycle 0 (before crashing)


Patha Duration (days)

ABEH 24
ACEH 25
ACFH 23
ACFG 24
ADG 23
a When the letter representing an activity is crossed, e.g., F, it
means this activity cannot be crashed (such as activity F) or has
reached its minimum/crash duration

Let us prepare the time-cost trade-off calculation table (Figure 8.12). We


have to start with the critical (longest) path: ACEH. We choose activity C
because it costs the least to crash, $40 per day. We cut the duration of C
from 8 days to 7. This action affects three paths: Cycle 1

Figure 8.12 Time-cost trade-off calculation table for example 8.1

Cycle 1
Path Duration (days)

ABEH 24 24
ACEH 

2 5 24
ACFH 

2 3 22
ACFG 

24 23
ADG 23 23
234 Chapter 8 Schedule Compression and Time-Cost Trade-Off

This action increased the direct costs by $40 and decreased the indirect
costs by $120. The total impact on the cost is a net savings of $80.
We now have two paths that tie at 24 days’ duration: ABEH and ACEH.
We can compress a shared activity (A, E, or H) or a combination of unshared
activities (B and C). We choose activity E and compress it from 6 days to 5 days
at a cost of $50.
Cycle 2
Path Duration (days)

ABEH 24 

24 23
ACEH 

25 

24 23
ACFH 

23 22 22
ACFG 

24 23 23
ADG 23 23 23

The direct costs increase by $50, and the indirect costs decrease by
$120. This results in a net decrease of $70 in the total cost.
Now we have four paths that tie at 23 days’ duration: all but ACFH. We can
compress a shared activity (A) or a combination of unshared activities (plenty
of options exist). We choose activity A and compress it from 5 days to 4 at a
cost of $10011 . Activity A is now completely crashed.
Cycle 3
Path Duration (days)

ABEH 24 

24 

23 22
ACEH 

25 

24 

23 22
ACFH 

23 22 

22 21
ACFG 

24 23 

23 22
ADG 23 23 

23 22

With this action, we spent an extra $100 in direct costs and saved $120
in indirect costs. The total cost decreased by $20 (we are still saving money,
but the rate is decreasing).
Now we need to compress the same four paths using the least-cost com-
bination. After a simple mathematical inspection of the table, we find the
best combination to be C, D, and E, with a total combined cost of $140.

11
If activity A could be crashed by more than 1 day, we could have crashed it to the limit, since it is part of
any path on the network. This means any day cut from activity A would automatically mean a day cut from
the entire schedule.
Recovery Schedules 235

We compress each of these activities by 1 day to shorten the project duration


from 22 days to 21 days.
Cycle 4
Path Duration (days)

ABEH 24 

24 

23 

22 21
ACEH 

25 

24 

23 

22 20
ACFH 

23 22 

22 

21 20
ACFG 

24 23 

23 

22 21
ADG 23 23 

23 

22 21

Note that path ACEH was cut by 2 days because it contains both C and E.
Now the total cost has increased by $20 ($140 increase in direct costs and
$120 decrease in indirect costs). The next step is to find an alternative to
activity E because it is completely crashed. The next least-cost combination is
B, C, and D, at a total cost of $165. In this case, the total cost has increased
by $45.
Cycle 5
Path Duration (days)

ABEH 24 

24 

23 

22 

21 20
ACEH 

25 

24 

23 

22 

20 19
ACFH 

23 22 

22 

21 

20 19
ACFG 

24 23 

23 

22 

21 20
ADG 23 23 

23 

22 

21 20

Note that the critical paths may change in every round. Now, activity C is
also completely crashed. Our next choice is the combination of B and G at a
combined cost of $225, with a net increase of $105 in the total cost.
Cycle 6
Path Duration (days)

ABEH 24 

24 

23 

22 

21 

20 19
ACEH 

25 

24 

23 

22 

20 19 19
ACFH 

23 22 

22 

21 

20 19 19
ACFG 

24 23 

23 

22 

21 

20 19
ADG 23 23 

23 

22 

21 

20 19

Activity B is now completely crashed. All paths are tied at 19 days. The
only remaining option is to combine activities G and H at a cost of $270, with
an increase of $150 in the total cost.
236 Chapter 8 Schedule Compression and Time-Cost Trade-Off

Cycle 7
Path Duration (days)

ABEH 24 

24 

23 

22 

21 

20 

19 18
ACEH 

25 

24 

23 

22 

20 19 

19 18
ACFH 

23 22 

22 

21 

20 19 

19 18
ACFG 

24 23 

23 

22 

21 

20 

19 18
ADG 23 23 

23 

22 

21 

20 

19 18

Now the entire project is completely crashed, with a duration of 18 days.


The results may be summarized as follows:

• The normal duration is 25 days, at a total cost of $7,950.


• The least-cost is $7,780, at a duration of 22 days.
• The crash duration is 18 days, with a crash cost of $8,100.

Notes

1. Accelerating can become complicated even in a small network. For


larger projects, we use computers, as explained in the next section.
2. Activity D is not completely crashed, which demonstrates an important
point: to accelerate a project, we do not need to compress all activities.
If we did, we would be wasting money with no benefit to the schedule.
3. We assume linearity within each activity (e.g., it costs the same amount
of money to compress activity C from 8 days to 7, from 7 days to 6,
or from 6 days to 5). However, we see that the change in total cost for
the project is not linear.
4. The project manager may choose a project duration between 22 days
and 18 days to meet the contract-required finish date (22 days for least
cost and 18 days for least duration).

ACCELERATING PROJECTS USING COMPUTERS


Real-life projects usually contain hundreds or thousands of activities. There may be
tens or even hundreds of paths, each with 50, 60, or more than 100 activities. Per-
forming calculations such as those done in example 8.1 would be too cumbersome.
The practical approach is to use trial and error. However, nine guidelines follow:

1. Always make a backup copy of the schedule before you make any changes.
2. Focus on the critical path. A good idea is to sort activities by total float (first
criterion) and start date (second criterion), in ascending order. You may also

You might also like