DPR For 03-05-2019

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

Reporting

Daily Progress R
CEEKAY ASSOCIAT

Earth work

S.no AREA As per drg Up to date IN % on date

1 W.B & RCC BRIDGE 1231 1231.000 100.000 0


2 TG Building 4025 3790.890 94.184 0
3 ACC 1286 1286.000 100.000 0
4 FGCS 2633 2633.000 100.000 0
5 TR HALL 5868 4268.000 72.733 0
6 MSW PIT 9651 5590.000 57.921 0
7 BOILER 6506 6506.000 100.000 0
8 WTP 4800 2790.000 58.125 0
9 PIPE RACK 1416 1035.000 73.093 0
TOTAL 37416 29129.890 77.854 0
Man Power at site- Report on date:-03-05-2019
Si.no Location BarBin. Helper Carpenter Helper
1 Boiler 0 0 0 0

Tipping floor Area&


2 2 0 4 1
RCC Bridge

3 MSW 3 0 7 2
4 ACC 0 0 0 0
5 Flue gas 0 0 2 0
6 TG Building 0 0 0 0
7 WEIGHING BRIDGE 0 0 0 0
8 WTP 0 0 0 0
9 PIPE RACK 0 0 0
10 RMC Plant + Misc 0 0 0 0

Tractor & Excavtor


11 operetor / Boom
Pump
12 Fitter
13 Staff on misc works
14 Total 5 0 13 3
Machinery Report on date:-03-05-2019

Transit
Excavtor Tractor trolley Breaker mixer and
Boom pump
Si.no Location
1 All sites 1 5 1 3
Total 1 5 1 3

Total Quantities(Weigh bridge, Tipping floor, MSW pit, Boiler, TG building , ACC, FGC
Quantity

Achieved Achieved
S.no Description of Work Expected Qty As per drg On Date Up to Date
1 P.C.C. 2141 2002 0.2 1648.92
2 R.C.C. 16811 16709 16.992 12860.854
3 Reinforcement work 3000 2906 0.18 2008.06
Reporting on :03-05-2019
Daily Progress Report of JUWMGL
CEEKAY ASSOCIATES PVT LTD @ GUNTUR
Quantity
PCC RCC
As per
As per drg Up to date IN % on date drg Up to date IN % on date

35 34.370 98.200 0.2 350 310.160 88.617 0


290 248.600 85.724 0 1754 1703.650 97.129 0
105 35.160 33.486 0 772 772.000 100.000 0
130 110.300 84.846 0 850 818.160 96.254 13.16
198 187.430 94.662 0 2376 1695.210 71.347 0
649 580.770 89.487 0 6685 4414.474 66.036 3.832
166 158.220 95.313 0 2217 2217.000 100.000 0
391 274.650 70.243 0 1300 784.500 60.346 0
41 19.420 47.366 0 248 145.700 58.750 0
2005 1648.920 82.240 0.2 16552 12860.854 77.700 16.992
-03-05-2019
Mason Un skilled skilled Total Remark
1 5 1 7

1 12 2 22

3 12 1 28
0 0 0 0
4 11 1 18
4 8 2 14
0 0 0 0
1 7 1 9
0 0 0 0
0 8 2 10

4
8
14 63 10 128
:-03-05-2019

Tractor
Leveller Dumper Total Total
Breaker

0 0 0 10
0 0 0 10

ler, TG building , ACC, FGCS and WTP)


ntity
Balance
to be Remark
In % done In % s
82.364 353.08 17.636
76.970 3848.146 23.030
69.100 897.94 30.900
TMT
As per
drg Up to date IN % on date

50 47.500 95.000 0
280 262.240 93.657 0
124 124.000 100.000 0
110 94.100 85.545 0
462 274.430 59.400 0.18
1280 648.040 50.628 0
398 398.000 100.000 0
299 149.030 49.843 0
30 10.720 35.733 0
3033 2008.060 66.207 0.18

Remark