TIME SCHEDULE ( KURVA-S )

PEKERJAAN RENOVASI GEDUNG PERKANTORAN


JURUSAN TEKNIK SIPIL UNIVERSITAS JAYABAYA
WAKTU (HARI)
BOBOT DURASI BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6
URAIAN PEKERJAAN VOL UNIT HARGA TOTAL Progres
(%) ( MINGGU )
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
1 PEKERJAAN PERSIAPAN LS 1.00 Rp 192,000,000.00 4.80 4 1.20 1.20 1.20 1.20
2 PEKERJAAN PONDASI TIANG PANCANG BH 300.00 Rp 312,000,000.00 7.80 6 1.30 1.30 1.30 1.30 1.30 1.30
3 PEKERJAAN STRUKTUR BETON M3 400.00 Rp 1,600,000,000.00 40.00 8 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
4 PEKERJAAN FINISHING LS 1.00 Rp 1,000,000,000.00 25.00 8 3.13 3.13 3.13 3.13 3.13 3.13 3.13 3.13
5 PEKERJAAN MEKANIKAL DAN ELEKTRIKAL LS 1.00 Rp 800,000,000.00 20.00 8 2.50 2.50 2.50 2.50 2.50 2.50 2.50 2.50
6 PEKERJAAN DEMOBILISASI PEMBERSIHAN / AKHIR LS 1.00 Rp 96,000,000.00 2.40 2 1.20 1.20
Rp 4,000,000,000 100.00
PRESTASI PER MINGGU 1.20 1.20 2.50 2.50 6.30 6.30 6.30 6.30 8.13 8.13 8.13 8.13 5.63 5.63 5.63 5.63 2.50 2.50 2.50 2.50 1.20 1.20

PRESTASI KOMULATIF 1.20 2.40 4.90 7.40 13.70 20.00 26.30 32.60 40.73 48.85 56.98 65.10 70.73 76.35 81.98 87.60 90.10 92.60 95.10 97.60 98.80 100.00

Disusun Oleh : Rizky Tantyo


Angkatan : 47
Tugas : Manajemen Konstruksi