Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/324273520

Current Scenario of Electricity Sector in India and Restructuring

Conference Paper · April 2018

CITATIONS READS
0 1,736

1 author:

Ramnaresh Mishra
GLA University
1 PUBLICATION   0 CITATIONS   

SEE PROFILE

All content following this page was uploaded by Ramnaresh Mishra on 07 April 2018.

The user has requested enhancement of the downloaded file.


IEEE Sponsored NSC-2017, Dayalbagh Educational Institute, Dayalbagh, Agra, India 160

Current Scenario of Electricity Sector in India and


Restructuring
Ram Naresh Mishra1, D. K. Chaturvedi2
Department of Electrical Engineering, GLA University, Mathura
1
2
Department of Electrical Engineering, Dayalbagh Educational Institute, Agra

Email: maresh2007@gmail.com, dkc.foe@gmail.com


Abstract— As per the experience of restructuring trend in many NHPC National Hydroelectric Power Corporation
places of the world, the reform and restructuring process in
Indian electricity sector is going on since 1992. To facilitate NMRS Nodal Must Run Share
competition wherever feasible, efforts are being made. This paper NTPC National Thermal Power Corporation
presents current scenario of electricity sector in India and OA Open Access
emphasizes the recent strategies and policies made by PFC Power Finance Corporation
Government of India towards restructuring. With varying degree
of success, various states of India have implemented several key
PGCIL Power Grid Corporation of India Limited
elements of the reform program. The model for UPPCL PMUs Phasor Measurement Units
restructuring is proposed. This model can be adopted at national POSOCO Power System Operation Corporation
level with suitable modifications, if needed. Limited
PSUs Public Sector Undertakings
Index Terms— Electricity Act 2003, Deregulation, Distribution, PX Power Exchange
Generation, Open Access, Power Sector Reforms, Regulatory Co- RE Renewable Energy
mmission, Restructuring, Transmission. REBs Regional Electricity Boards
REMC Renewable Energy Management Centre’s
NOMENCLATURE RLDC Regional Load Dispatch Centre
SC Scheduling Coordinator
ABT Availability Based Tariff SEBs State Electricity Boards
AT&C Aggregate Technical and Commercial SERCs State Electricity Regulatory Commissions
BEE Bureau of Energy Efficiency SLDC State Load Dispatch Centre
CAGR Compound Annual Growth Rate STOA Short Term Open Access
CEA Central Electricity Authority STU State Transmission Utilities
CERC Central Electricity Regulatory Commission Transco Transmission Company
CPGs Captive Power Generations T&D Transmission and Distribution
CTU Central Transmission Utility TSO Transmission System Operator
DDG Decentralized Distributed Generation UI Unscheduled Interchange
Discos Distribution Companies WAMS Wide Area Measurement System
DSM Demand Side Management
ENMRS Expected Nodal Must Run Share I. INTRODUCTION
Gencos Generation Companies
GoI
HHI
Government of India
Herfindahl-Hirschman Index E lectricity has become a part of our existence. Moreover,
development and economic growth of the country
significantly depends on availability of electric energy at
IEA International Energy Agency
IPPs Independent Power Producers economical prices. It is a real time commodity being produced
ISO Independent System Operator and consumed instantly. Due to increasing demand of
LI Lerner Index electricity, power situation in India is not up to the mark yet.
LTOA Long Term Open Access There is a shortage of electricity. In India, the electricity sector
MoP Ministry of Power is mainly governed by the MoP. Electricity sector has three
MRR Must Run Ratio major pillars (generation, transmission, and distribution). The
generation is mainly divided into three sectors like central, state,
MRS Must Run Share and private sector. Central sector or PSUs involved in the
MTOA Medium Term Open Access generation of electricity include NHPC, NTPC, and NPCIL.
NEEPCO North Eastern Electric Power Corporation Various state level corporations (earlier name SEBs) are also
NETA New Electricity Trading Arrangement involved in the generation and intra-state distribution of
electricity. Other than PSUs and state level corporations,
private sector enterprises also play a major role in generation,
IEEE Sponsored NSC-2017, Dayalbagh Educational Institute, Dayalbagh, Agra, India 161

transmission, and distribution. PGCIL is responsible for the act covers major issues involving generation, transmission,
inter-state transmission of electricity and the development of distribution and trading of electricity. Moreover, this act will
national grid. India is a democratic country. Democracy is ensure the competition at wholesale as well as retail level in the
about giving choice to the people. To facilitate competition electricity market.
wherever feasible, efforts are being made. Choice of an 2004 - Open Access Regulations.
appropriate power market model plays an important role in this 2006 - Tariff Policy, Competitive bidding for procurement of
context. With the evolution of markets, well functioning power, Ultra Mega Power Projects.
markets in providing customer choice and good quality service 2007-The Act was amended on 28th May,2007 with greater
through provide competition. For successful power sector emphasis on assessments, fines and legal framework to check
reform, the role of power planning is very important as well as commercial losses due to pilferage and unauthorized use of
economic growth of the country. The main objective of electricity.
deregulation is to encourage competition in electricity market 2007/08-Power exchanges guidelines, and establishment.
to provide reliable and good quality power supply at minimum 2008 - Allotment of Coal Blocks to power generators for
cost. Due to these advantages of deregulation, many countries captive mining.
have already adopted this concept. It has been encouraged by 2010- Formation of POSOCO to handle the power management
the benefits of restructuring in telecommunication, airline functions of PGCIL.
industries etc [1]. 2011 -Competitive bidding for ownership and establishment of
inter-state transmission schemes.
II. OVERVIEW OF ELECTRICITY SECTOR [2-4]: 2013-The commissioning of the 765 kV Raichur- Solapur
P.W. Fleury & Co was conducted first demonstration of an transmission line, thereby establishing the National Grid
electric light on 24th July, 1879 in Calcutta. First generating 2015- Auction of Coal Blocks to power generators for captive
station (hydro-electric) set up near Darjeeling (West Bengal) in mining.
1897 having capacity of 130 KW. Calcutta is the first electrified 2016- Started with steep fall in the international price of energy
city in India (1899).During 1900-1920, various generating commodities such as coal, diesel oil, naphtha, bunker fuel and
station came into existence at different places like Khopoli LNG which are used in electricity generation.
(Maharashtra), Sivasamudram (Mysore), Mettur dam (Madras) 2017- CEA stated that India exported electricity of 5,798 GWh
etc. In1910, the Indian Electricity Act enacted to regulate to neighbouring countries, against a total import of 5,585 GWh.
supply by licensees to consumers. This is happened first time in India [5].
1948 - Electricity (Supply) Act 1948 - Formation of SEBs in
the states and at national level, CEA is responsible for planning A. Structure of Electricity Sector [3-6]:
as well as development of power system.
1964 – Five REBs were formed by the GoI with the consent of India has an installed power generating capacity of 322,881.52
state governments. MW (as on 31 March, 2017) out of which 59.5%
1975 - Creation of central Genco’s for development of super (192,162.88MW) from thermal, 15.1% power stations share is
thermal power stations and large hydro-electric stations leading (48812.28 MW) from hydro,2.1%(6,780 MW) from
to creation of NTPC, NHPC, and NEEPCO. nuclear ,8.9% (28,700.44 MW) from wind power,3.8%
1991 - Electricity (Supply) Act 1948 amended to pave the way (12,288.83 MW) from solar power ,7.8% (25,329.38 MW)
for the formation of private Gencos. CEA empowered to fix the from gas, 2.5% (7,970.08 MW) from biomass, and 0.3%
norms for determining the tariff of all Gencos. The foreign (837.63 MW) from diesel is shown in fig(1). Total installed
investment (100%) in power sector has been allowed by RBI. capacity of generating units region wise is depicted in fig (2). It
1992 - First Gazette notifications on the criteria for fixing the is observed that western region has got highest position among
tariff for sale of electricity by the Gencos to SEBs or any other five regions. The growth of installed capacity as well as
agency. generation is shown in fig (3), and (4). But still there is a gap in
1998 - Electricity Regulatory Commission Act 1998 enacted generation and demand. The annual per capita consumption of
paving the way for the formation of CERC and SERCs. electrical energy (in kWh) is increasing day by day. It was
Regulatory power of the state governments transferred to 1075kWh in 2015-16. As per progress report of village
SERC. Consequently, Tariff regulatory function of CEA electrification as on 31-03-17 CEA, in India, 99.25% of
transferred to CERC. 597,464 villages are electrified and there are74% rural
1998 - Act amended to provide for CTU and STU. house-holds are provided with electricity. Hence, India needs t
1999 - Privatizations of distribution in Odisha. o be establishing more generating units preferably from renew
2000 - Indian Electricity Grid Code (IEGC). able s-ources [11].
2001-Energy Conservation Act, 2001 enacted on 1st Oct The electricity sector of India is organized into five REBs such
2001.This Act ensured energy efficiency in consumption and as NREB, SREB, EREB, WREB, and NEREB. Each REB is
introduction of DSM. Under the provisions of the Act, BEE has consisting of several SEBs. At national level, the CEA advises
been established the MoP for power policy, power planning and regulatory
2002 - Privatization of distribution in Delhi. matters. Where as, at state level SERCs do the same
2002 - ABT. functions. The electricity sector is beset with several problems
2003 –GoI notified Electricity Act 2003 in June 2003. This Act such as large-scale thefts of electricity, fiscal losses at REBs,
repeals the IE Act 1910, ES Act 1948, and ERC Act 1998. This non-payment by consumers at all levels, under investment in
IEEE Sponsored NSC-2017, Dayalbagh Educational Institute, Dayalbagh, Agra, India 162

T&D , increasing power outages due to inadequate


transmission etc. The performance of various state level
corporations (earlier name SEBs) is vastly attributed to
unrealistically low tariffs set by state governments, poor
revenue collections, corruption, and increased costs.
There are five RLDCs in India such as NRLDC, SRLDC,
ERLDC, WRLDC and NERLDC. These RLDCs have been
modernized with modern Energy Management Systems tools.
RLDCs are responsible for scheduling of the central sector
generating units only. But in each state, there is a SRLDC.
SRLDCs carry out the optimum scheduling of the state
generating units. SRLDCs send the requisition to the RLDCs
against their entitlements out of available power from central
sector generation and the RLDCs allocate total available power
to various states in the ration of their entitlements [7].

*Up to May 2017(Provisional), Source: CEA


IEEE Sponsored NSC-2017, Dayalbagh Educational Institute, Dayalbagh, Agra, India 163

distribution. Understanding difficulties faced in the process of


Status of power energy availability, demand and deficit has reforms, the GoI in consultation with the states initiated
given in fig. (5), the shortage of power generation is estimated measures to overcome these difficulties. The unbundling
to be around 2608 MW during 2016-17(Fig.6). Currently, India process has been started few years back. Many SEBs are
has a power deficit of around 1.6%. As per the reports unbundled in Gencos, Transcos, and Discos. All Gencos and
published by Oxford Institute of Energy Studies [12], the GoI Transco’s are controlled by government. In some states, the
should more encourage and facilitate local private investment Discos are controlled by government and in few states such as
in small scale distributed electricity generation capacity ,as part Orissa and Delhi, the Discos are privatized.
of a ‘bottom-up’ solution to electricity sector reform Orisha was the first state which initiated the power sector
rather than ‘top-bottom’ reform. restructuring business in state. Restructuring has been done in
other states also. Milestones of electricity sector reforms are
B. ABT mechanism for frequency regulation: shown in table (1). Most of the state’s only unbundled the SEBs
but did not privatize the distribution business. In India steps has
Let us consider first the cost of electricity which the consumers been taken for deregulation in electricity sector .But it is not yet
pay to Discos. The total cost is the sum of fixed cost, semi fixed fully implemented because there are some issues which need to
cost (depends on maximum KW demand) and variable cost. It be resolved to fruitful implementation of deregulation. There
is mandatory for the consumers to maintain power factor within are many private utilities in some states of India. These are in
prescribed range otherwise penalty is levied on them. ABT is position to face the challenges of competitive electricity market
for the Discos and regulated by CERC. This tariff was [9].For the developing countries, the prospectus and the
introduced in the country from 1st July, 2002. It has three economic growth of electricity sector are in the hands of the
components, viz fixed charges, energy charges, and UI charges. private sectors. There are many private power companies are
UI charges are largely responsible for bringing about the came into existence in India such as Reliance Power Limited,
desired grid discipline. UI charges are payable when a Adani Power , Tata Power Company Limited, Suzlon Energy ,
generator generates more/less than the schedule or a Essar Power, Jindal Power, Torrent Power, AEC Limited,
beneficiary draws more/less than the schedule. The GMR Infrastructure Limited, GVR Power and Infrastructure
incentives/disincentives imposed vary with the grid condition Limited, DLF Power Limited, Birla Power Solutions Limited
at the time of indiscipline. In the real time, the actual dispatch is etc. It is also important to create a healthy competition among
likely to be different from the schedule. If the grid has surplus players who participate in power generation without violating
power at the time of frequency greater than 50.0 Hz, the rate the policies in a deregulated electricity market. At the same
would be lower. If the excess generation takes place at the time time, one should not target the impact of constraints on the
of its shortage (in this case the frequency is below 50.0 Hz), the transmission network in exercising market power by the
payment for extra generation would be at a higher rate. With Gencos. Market power can be measured by using various
effective from 17 September 2012, the permissible range of the indices such as HHI, LI, MRR, MRS, NMRS, and ENMRS
frequency band for Indian’s grid is 49.7-50.2 Hz. The Union [10].
Government regulates grid frequency by requiring states to pay
more when they draw power at low frequencies. The UI price
curve is shown in fig.(7). Now days, the ABT has been
implemented by central
commission almost in all the regional grid of India,which aims
actually at bringing responsibility, accountability in power
generation and also schemes of incentives and disincentives for
consumption by frequency dependent pricing[8].

Fig.
(7)

C. Status of Electricity Sector Reforms: III. IMPACT OF ELECTRICITY SECTOR


RESTRUCTURING:
The electricity sector is facing a plethora of problems in all the
three basic areas like generation, transmission, and distribution. A. Generation Segment:
Several initiatives have been taken by the GoI to invite
participation of private sector in generation, transmission, and
IEEE Sponsored NSC-2017, Dayalbagh Educational Institute, Dayalbagh, Agra, India 164

As per EA2003, GoI introduced certain policy measures to been almost thirteen years passed since enactment of this act.
ensure more private participation in generation and to reduce OA is still distant dream for many stakeholders of this sector.
demand-supply gap. With the arrival of private players in There are various factors such as technical feasibility of open
power generation, its contribution was 43% of generation access in different states and political will create hurdles for its
capacity on 30th April, 2017 (while central has 25% and state implementation. In some states, the cross subsidy surcharge is
has 32% on the same date)[6]. Yet, generation is not enough to very high making the open access unviable.
meet the growing demand of electricity. However, CPGs have Through open access the competition at wholesale (above 1
been growing at a fairly aggressive pace in India. Industrial MW) was introduced in order to decrease the cost of power
sector is one of the largest consumers of electrical energy. It procurement at the consumption level which results in the
consumes about 45.9% of total electricity consumption in the industrial growth of the country. When the buyers and sellers
country. The demand for electricity in India has been entities belong to different states, it is called as interstate open
continuously growing with time. Thus, to sustain and excel in access. In this case CERC regulations are followed. When
the dynamic global environment, it has become imperative for buyers and sellers entities belong to same state, it is called as
the industries to ensure uninterrupted power supply for intrastate open access. In this case SERC regulations are
performance optimization which has subsequently led followed. Inter and Intra state open accesses are further
to the growth in CPGs in India. Technavio's analysts forecast categorized as STOA (for period of less than one month),
the CPG market in India to grow at a CAGR of 4.5 % over the MTOA (for a period of 3 months to 3 years) and LTOA (for a
period 2013-2018. period of 12 years to 25 years). In general the buyer and seller
of electricity can go for bilateral or collective transactions. In
B. Transmission Segment: bilateral transactions a PPA is signed between the buyer and
seller which is generally facilitated by a trader for a little
As per EA 2003, GoI introduced a non-discriminatory open margin. In case of collective transactions the electricity is
access in the segment of transmission. Which enabled the traded through exchanges.
generator to sell electricity for any customer and there is option
to choose the generator by using transmission network. At IV. RECOMMENDATIONS
central level, CTU could provide open access and at state level,
STU could provide open access. As on April 30, 2017, around 1, The present condition of India is not yet suitable for electricity
39,708 km of EHV transmission lines spread over the length restructuring due to the gap between demand and generation.
and breadth of the country. The total transmission capacity of Following steps are recommended to overcome this issue.
the inter-regional links found 75,050 MW [6]. PGCIL is A. Typically, electricity prices in India are less than the cost of
implementing the prestigious and state of the art, REMC for its production thereby it is challenging issues to build and
managing the renewable generation integration and operation operate a new power plant. The poor power factor as well as
which shall include a host of activities from RE forecasting to pilferage of electric power leads to increased T&D losses (22%
energy balancing and generation scheduling. In smart at present) and around 24% AT&C losses, thereby raising the
transmission, PGCIL has been implementing synchrophasor cost of power delivery. However, GoI is targeting to bring
technology in its WAMS project through installation of PMUs down T&D losses in the electricity sector to 15% by 2019 from
at different locations in all regions across the country. Ref.[15] 22 % [5].DDG plays an important role to reduce the T&D
presents a deregulation model for transmission system in India. losses. Since DDG locates closer to consumers utilizing locally
available RE resources [11]. So, power tariffs analysis should
C. Distribution Segment: consider both the structure of tariffs and the costing
methodology for rate making. Moreover, government should
Distribution is an important entity in the chain of electricity decentralize the planning process for an easy entry of
sector and all other entities like generation, transmission generators [13].
dependent on distribution for their revenue realization. Due to B. Open Access restrictions (section 11/108 of Electricity Act
high losses (including pilferage), uneconomical tariff, the 2003) imposed by several state governments/ SLDCs citing
financial position of the Discos in the state, is severely strained. shortages or non availability of transmission infrastructure.
This is the reason behind the inadequate investment by the state Thus, private investment for adding the interstate and intrastate
government in distribution segment. The states also need to transmission capacity should be encouraged in the country [16].
seriously work on regular energy auditing and 100% metering. C. Power sector reformation got the dimension by
It shall be duty of a distribution licensee to develop and politico-administration like free power supply to farmers etc.
maintain an efficient, coordinated and economical distribution The political timeframe causes a mismatch between planning
system in its area, to supply electricity to consumers. Central and the responsibility for its implementation. The direct
government has been extending all possible help to the state control of government should be reduced.
governments in improving the distribution system [9]. D. At present the financial health of electricity distribution
sector is not sound. This is mainly due to unrealistically low
D. Open Access: tariff, high T&D losses, low billing and collection efficiency.
The financial crunch faced by the power industry, compounded
The basic objective of Indian Electricity act 2003 was to by inefficiency and corruption, contributes significantly to the
introduce competition in the electricity sector for improvement crises of distribution sector. The MoP needs to keenly follow
of performance as well as efficiency of electricity market. It has
View publication stats

IEEE Sponsored NSC-2017, Dayalbagh Educational Institute, Dayalbagh, Agra, India 165

the process of privatization of the electricity distribution sector that India exported electricity of 5,798 GWh to neighbouring
in the states. countries, against a total import of 5,585 GWh in the FY
E. Intensive studies and surveys show that huge government 2016-17. So, there is a very limited surplus power available in
committees are set up and the public exchequer put to great the open market. In the country, most of electric power is being
expense to devise paper work for all kinds of new plans and traded in whole sale market either through bilateral or
projects. But its implementation is biggest weakness in India. It multilateral contracts. It seems that the present condition of
would do India good to simply try and implement what is all India is not suitable for retail competition. However, there are
there on papers. many plant of CPGs are exist in the country. They can
participate in the bidding process. In this view, the design of an
V. PROPOSED MODEL FOR UPPCL RESTRUCTURING appropriate electricity market is not easy task for India.
[14]:

This model combines the features of pool as well as REFERENCES


bilateral/multilateral model as shown in fig. (8). The main goal
of a better restructured power system is to open the door for
[1] Lai Loi Lai, “Power System Restructuring and Deregulation, (book),
high degree of competition to all market entities. So that Publisher: John Wiley and Sons, Ltd., New York, 2001.
consumers have option for cheaper and good quality of [2] https://en.wikipedia.org/wiki/Electricity_sector_in_India.
electricity. In this model, sellers and buyers can enter into the [3]Published in Gazette of India, The Electricity Act, 2003, India: Universal
phase of bilateral/multilateral contracts. Moreover, consumers Law Publication Company Pvt. Ltd.
would be able to make electricity purchase agreements directly [4] Alok Kumar, and Sushanta Chatterjee,”Electricity Sector in India Policy
and Regulation”, Oxford University Press, 2012.
with power pool or genco’s or discos or IPPs or retailers as [5]Central Electricity Authority of India Website (http://www.cea.nic.in)
needed. This is costlier approach to set up because of separate [6]Ministry of Power, Government of India Website
entities required for operating the PX and the transmission (http://www.powermin.nic.in.)
system. As for as security of the power system is concerned, [7] S.N. Singh, and S.C. Srivastava, “Electric Power Industry Restructuring in
India: Present Scenario and Future Prospect”, IEEE International Conference
this model has a lot of constraints. Right now, Indian electricity on Electric Utility Deregulation, Restructuring and Power Technologies
sector is not in position to enter in this competitive environment. (DRPT2004) Hong Kong, pp. 20-23, April 2004.
Electricity sector is underway to create surplus generation to [8] Short- term course on “New Trends in Power System Protection and
foster competition among power producers and open the door Control Techniques” organized by Department of Electrical Engineering, IIT,
Roorkee, June 26-30, 2017.
for greater choice for consumers. This model can be adopted at [9]S. A. Khaparde, “Power Sector Reforms and Restructuring in India”, IEEE
national level with suitable modifications, if needed. Xplore 2008.
[10]D.P. Kothari, S. Prabhakar Karthikeyan and I.Jacob,“Market Power- A
Threat to Deregulated Power Systems”, Energetica India (Power Sector
Update)2012.
[11]Kartik Arunachalam, V. S. Pedinti, and Sanket Goel, “Decentralized
Distributed Generation in India: A review”, Journal of Renewable and
Sustainable Energy, vol.8, pp. 1-20, 2016.
[12]Oxford Institute for Energy Studies Website
(http://www.oxfordenergy.org).
[13] A. Srivastava and M. Shahibehpour, “Restructuring choices for the Indian
Power sector”, IEEE Power Review, vol. 22, Issue 11, pp 25-29, Nov. 2002.
[14]Madan Mohan Tripathia, Anil Kumar Pandey, Dinesh Chandra, “Power
system restructuring models in the Indian context”, The Electricity Journal
(Elsevier), vol. 29, pp.22–27, 2016.
[15] PhD Thesis "A Deregulation model for transmission system in India",
Ashish Saini, Faculty of Engineering, DEI, 2006.
[16]Sood Yog Raj, N.P.Pandey, and H.O. Gupta,"Wheeling of power under
Deregulated Environment of power system-A Bibliographical Survey", IEEE
Trans on power system, vol. 17, no. 3, Aug 2002.

Fig.(8)

VI. CONCLUSION

For the developing countries, the prospectus and the economic


growth of electricity sector are in the hands of the private
sectors. India is power deficit country; however CEA stated

You might also like