Rab Gudang Cangkang

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

RENCANA ANGGARAN BIAYA

PROYEK : GUDANG KARET NIAGA RAYA


PEKERJAAN : GUDANG CANGKANG
LOKASI : MEGA TIMUR KUBU RAYA

Harga Satuan Total Harga


No. Uraian Pekerjaan Volume Satuan
(Rp) (Rp)

I PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi / Pengupasan Tanah Setebal 20 cm 1.500,00 m2 15.000,00 22.500.000,00
2 Pengukuran dan Pemasangan Bowplank 116,00 m' 50.000,00 5.800.000,00
JUMLAH I 28.300.000,00

II PEKERJAAN PONDASI
1 Pemancangan Minipile 20x20x24 m 1.872,00 m' 185.000,00 346.320.000,00
2 Bobok/Pecah Kepala Tiang 78,00 Btg 85.000,00 6.630.000,00
3 Galian Tanah Poer 94,00 m3 82.500,00 7.755.000,00
4 Pasir Urug Bawah Poer Tebal 20 cm 18,80 m3 166.900,00 3.137.720,00
5 Cor Beton Lantai Kerja Tebal 5 cm 4,70 m3 1.187.282,14 5.580.226,07
6 Poer Beton Bertulang K225 20,30 m3 2.075.000,00 42.122.500,00
7 Sloof Beton Bertulang Uk. 25x80 cm K225 30,00 m3 2.075.000,00 62.250.000,00
8 Sloof Tee Beam Beton Bertulang Uk. 20x60 cm K225 8,40 m3 2.075.000,00 17.430.000,00
9 Kolom Pondasi Beton Bertulang K225 6,41 m3 2.075.000,00 13.300.750,00
10 Angkur dia. 19 mm x 60 cm 104,00 Pcs 66.000,00 6.864.000,00
JUMLAH II 511.390.196,07

III PEKERJAAN PLAT LANTAI


1 Pasang Cerucuk Bawah Lantai dia. 10/12-4m Jarak 50 cm 5.751,00 Btg 13.500,00 77.638.500,00
2 Urug Pasir Bawah Lantai Tebal 80 cm 1.120,00 m3 166.900,00 186.928.000,00
3 Pasang Lapis Plastik Cor Bawah Lantai 1.400,00 m2 3.500,00 4.900.000,00
4 Tulangan Wiremesh 5 mm Dual Lapis 2.800,00 m2 26.000,00 72.800.000,00
5 Cor Beton Pat Lantai Tebal 12 cm K225 168,00 m3 1.187.282,14 199.463.400,00
JUMLAH III 541.729.900,00

IV PEKERJAAN KONSTRUKSI BAJA


1 Kolom WF. 250 x 125 x 6 x 9 2.841,60 Kg 25.300,00 71.892.480,00
2 Kolom WF 200 x 100 x 5,5 x 8 1.834,38 Kg 22.750,00 41.732.145,00
3 Kap Span WF 250 x 125 x 6 x 9 9.045,76 Kg 7.000,00 63.320.320,00
4 Konsul WF 150 x 7 x 5 x 7 369,60 Kg 18.200,00 6.726.720,00
5 Gording CNP 125 x 50 x 20 x 2,3 8.047,97 Kg 7.515,15 60.481.713,94
6 Plat Landas Tebal 12 mm 280,00 Kg 25.700,00 7.196.000,00
7 Plat Tebal Simpul 10 mm 233,30 Kg 23.100,00 5.389.230,00
8 Plat Tumpuan Gording Tebal 6 mm 840,00 Kg 14.500,00 12.180.000,00
9 Baut Simpul Kuda-Kuda dia. 19 mm x 2" HTB 288,00 Pcs 5.150,00 1.483.200,00
10 Baut Simpul Konsul dia. 16 mm x 2" HTB 96,00 Pcs 4.500,00 432.000,00
11 Baut Gording dia. 12 mm x 1" 1.392,00 Pcs 3.500,00 4.872.000,00
12 Ikat Angin Besi Beton dia. 16 mm + Cincin Tarik dia. 19 mm 32,00 Pcs 415.000,00 13.280.000,00
13 Treak Stank Besi Beton dia. 10 mm x 120 cm 532,00 Pcs 41.000,00 21.812.000,00
14 Pengecatan Baja dengan Cat Anti Karat 234,93 Kg 198.000,00 46.516.140,00
15 Tee Beam Rangka CNP 150 x 50 x 20 x 2,3 + Besi Beton dia 10 mm 14,00 Unit 449.100,00 6.287.400,00
JUMLAH IV 363.601.348,94

V PEKERJAAN ATAP
1 Penutup Atap Zincalum 035 1.638,00 Kg 25.869,57 42.374.347,83
2 Tutup Bubung Zincalum 035 Plat 42,00 m' 67.800,00 2.847.600,00
3 Talang Aluminium 050 Ukuran 1/2 dia. 30 cm 84,00 m' 58.000,00 4.872.000,00
4 Pemasangan Pipa Talang PVC dia. 4" AW 16,00 Unit 149.000,00 2.384.000,00
JUMLAH V 52.477.947,83

VI PEKERJAAN DINDING BATAKO


1 Pasangan Dinding Batako Uk. 20x40x7 cm 1.142,97 m2 156.000,00 178.303.320,00
2 Kolom dan Balok Beton Tulangan Praktis 5,63 m3 2.075.000,00 11.682.250,00
3 Plesteran Dinding Batako Luar Dalam 2.285,50 m2 45.700,00 104.447.350,00
JUMLAH VI 294.432.920,00

VII PEKERJAAN CANOPY DAN PINTU BESI


1 Membuat dan Memasang Pintu Sleding Dua Daun 1,00 Unit 14.750.000,00 14.750.000,00
2 Membuat Canopy di atas Pintu 1,00 Unit 3.500.000,00 3.500.000,00
JUMLAH VII 18.250.000,00

TOTAL I - VII 1.810.182.312,84


PPn 10% 181.018.231,28
GRAND TOTAL 1.991.200.544,12
PEMBULATAN 1.991.200.000,00
Terbilang : Satu Milyar Sembilan Ratus Sembilan Puluh Satu Juta Dua Ratus Ribu Rupiah