Construction Schedule & S-Curve

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

JMG CONSTRUCTION AND GEN. MDSE.

#3248 Block 21 Lot 7 NHA Phase 1, Kauswagan, Cagayan de Oro City

Construction Schedule and S-Curve

Contract: Upgrading and Modernization of School Electrical Distribution System at Impasugong National High School
Location: Impasugong, Bukidnon
Calendar Days: 120 Calendar Days
MONTH 1 MONTH 2 MONTH 3 MONTH 4
ITEM DESCRIPTION
1 2 3 4 1 2 3 4 1 2 3 4 1

A General Requirements
B Distribution Transformer
C Kilowatt Hour Metering System
D Transformer Pole Hardwares
E Primary Lines Extension/Convertion
F Steel Poles & Cross Arms
G Panel Boards
H Cables, copper, stranded, xlpe, tw/thw, thhn
I Conduits, RGS, EMTs, PVC & Flexibles

S-CURVE

Submitted by:

JASPER M. GEMENTIZA
JMG CONSTRUCTION & GEN. MDSE.
MONTH 4
2 3 4 100%

90%

80%

70%

60%

50%

40%

30%

20%

10%

0%