Schedule Pelaksanaan
Schedule Pelaksanaan
Schedule Pelaksanaan
100.0000%
1 PEKERJAAN SIPIL PREPARIN
PEKERJAAN SWITCHYARD
A PREPARATION WORK
1 PEKERJAAN PEMBONGKARAN 0.0628%
2 PEKERJAAN SITE FACILITY 0.3800%
3 AS BUILT DRAWING 0.0261%
B SITE WORK
1 Pekerjaan Tanah 1.6020%
2 Kansteen 0.0246%
3 Pekerjaan Jalan Aspal 0.0000%
4 Fence complete with accessories and foundation 0.2337%
5 Gate complete with pole, accessories and foundation 0.0104%
6 Landscaping ( tanaman termasuk tanah, pupuk, penanaman, perawatan) 0.0835%
7 Hamparan batu pecah 0.1452%
8 Rabat beton 1:3:5; t= 5 cm 0.1888%
11 Bak Kontrol 0.0113%
C PONDASI PERALATAN 150 kV
1 Pondasi Apparatus 1.0805%
2 Foundation for Post Steel Structure 150 kV 0.6017%
3 Foundation for Marshalling Kiosk 0.0227%
D CABLE DUCT 0.9570%
E PENERANGAN JALAN DAN KOMPLEKS 0.1688%
PEKERJAAN SALURAN
C SALURAN TYPE 2 0.1284%
D SALURAN TYPE 2 TERTUTUP 0.0063%
0.000% 0.145% 0.289% 0.444% 0.599% 2.199% 3.799% 5.400% 7.040% 8.874% 10.708% 12.962%
PEKERJAAN PEMBANGUNAN GI 150 kV KENDARI (EXT) DAN GI 150 kV PUUWATU (EXT)
0.200%
0.031% 0.031%
0.169% 0.169%
2.254% 3.376% 3.519% 3.539% 2.737% 2.501% 0.000% 0.000% 2.402% 2.612% 3.888% 3.899%
15.217% 18.593% 22.111% 25.650% 28.387% 30.888% 30.888% 30.888% 33.290% 35.902% 39.790% 43.689%
JU;I AGUSTUS SEPTEMBER
26 27 28 29 30 31 32 33 34 35 36 37
15-21 22-28 29-04 05-11 12-18 19-25 26-01 02-08 09-15 16-22 23-29 30-06
0.817% 0.817%
0.085% 0.085% 0.085% 0.085%
1.457% 1.457% 1.457% 1.457%
0.671% 0.671% 0.671% 0.671%
0.015%
0.008% 0.008%
0.437%
0.159% 0.159% 0.159% 0.159% 0.159% 0.159% 0.159% 0.159%
0.005% 0.005% 0.005% 0.005% 0.005% 0.005%
0.062% 0.062%
0.210%
0.314% 0.314%
1.042% 1.042% 1.042% 1.042%
0.120%
0.379% 0.379%
0.435% 0.435% 0.435% 0.435%
0.094% 0.094%
0.022% 0.022% 0.022% 0.022%
0.119% 0.119% 0.119% 0.119% 0.119% 0.119%
0.057% 0.057% 0.057% 0.057% 0.057% 0.057%
0.112% 0.112% 0.112% 0.112% 0.112% 0.112%
0.034% 0.034% 0.034% 0.034% 0.034% 0.034% 0.034% 0.034%
0.029% 0.029% 0.029% 0.029% 0.029%
0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
0.115% 0.115% 0.115% 0.115% 0.115% 0.115%
0.005% 0.005% 0.005% 0.005% 0.005% 0.005%
5.254% 5.000% 4.908% 8.822% 7.944% 8.311% 6.751% 2.738% 1.304% 1.105% 1.126% 0.818%
48.943% 53.943% 58.851% 67.673% 75.617% 83.928% 90.680% 93.418% 94.722% 95.827% 96.954% 97.772%
OKTOBER NOVEMBER
38 39 40 41 42 43 44 45
07-13 14-20 21-27 28-03 04-10 11-17 18-20
0.032% 0.032%
0.004% 0.004% 0.004% 0.004% 0.004%
0.119%
0.013% 0.013%
0.023% 0.023%
0.039% 0.039% 0.039% 0.039%
0.060%
0.043% 0.043%
0.085%
0.014% 0.014%
0.048% 0.048% 0.048% 0.048%
Dibuat Oleh
PT. Citramasjaya Teknikmandiri
M. HASANUDIN
Project Manager
JANUARI
NO DISCRITION BOBOT SKALA
1
24-27
PEKERJAAN SALURAN
C SALURAN TYPE 2 0.1284%
D SALURAN TYPE 2 TERTUTUP 0.0063%
0.000% 0.217% 0.434% 2.308% 4.182% 5.840% 7.497% 8.839% 10.181% 12.324% 15.123% 18.023%
DARI (EXT) DAN GI 150 kV PUUWATU (EXT)
LE & S CURVE
0.036%
0.047% 0.047% 0.047% 0.047%
0.006%
1.241%
0.122% 0.122% 0.122% 0.122% 0.122% 0.122%
0.005% 0.005% 0.005% 0.005%
0.015% 0.015%
0.008% 0.008%
0.325%
0.655% 0.655% 0.655% 0.655% 0.655% 0.655%
0.317% 0.317% 0.317% 0.317% 0.317% 0.317%
0.007% 0.007% 0.007% 0.007%
0.095%
0.080%
0.041% 0.041% 0.041%
0.060% 0.060% 0.060%
0.084% 0.084% 0.084% 0.084%
0.130% 0.130% 0.130% 0.130%
0.110% 0.110% 0.110% 0.110% 0.110% 0.110%
0.072% 0.072%
0.040% 0.040%
3.217% 2.799% 3.072% 2.811% 4.052% 4.046% 0.000% 0.000% 3.607% 3.805% 4.928% 5.083%
21.240% 24.039% 27.111% 29.922% 33.974% 38.021% 38.021% 38.021% 41.627% 45.432% 50.360% 55.443%
JU;I AGUSTUS SEPTEMBER
26 27 28 29 30 31 32 33 34 35 36
15-21 22-28 29-04 05-11 12-18 19-25 26-01 02-08 09-15 16-22 23-29
0.006%
0.028% 0.028% 0.028% 0.028%
1.457% 1.457%
0.671% 0.671% 0.671% 0.671%
0.015% 0.015%
0.237% 0.237% 0.237% 0.237%
0.044% 0.044% 0.044% 0.044% 0.044%
0.083% 0.083% 0.083% 0.083% 0.083% 0.083%
0.072% 0.072% 0.072% 0.072% 0.072% 0.072%
0.015% 0.015%
0.110% 0.110%
0.072% 0.072% 0.072% 0.072%
0.040% 0.040% 0.040% 0.040%
0.059% 0.059% 0.059% 0.059% 0.059% 0.059%
0.041% 0.041% 0.041% 0.041% 0.041% 0.041%
0.052% 0.052% 0.052% 0.052%
0.053% 0.053% 0.053% 0.053%
0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019% 0.019%
0.028% 0.028%
0.060% 0.060% 0.060% 0.060% 0.060%
0.103% 0.103% 0.103% 0.103% 0.103% 0.103% 0.103% 0.103%
0.024% 0.024% 0.024% 0.024% 0.024% 0.024% 0.024% 0.024%
0.013% 0.013% 0.013% 0.013%
0.028% 0.028%
0.080% 0.080% 0.080%
0.211% 0.211% 0.211% 0.211% 0.211% 0.211%
0.075% 0.075% 0.075% 0.075% 0.075% 0.075% 0.075% 0.075%
0.043% 0.043% 0.043% 0.043% 0.043% 0.043% 0.043% 0.043%
0.022% 0.022%
0.119% 0.119% 0.119%
0.057% 0.057% 0.057% 0.057%
0.112% 0.112% 0.112% 0.112% 0.112% 0.112%
0.046% 0.046% 0.046% 0.046% 0.046% 0.046%
0.029% 0.029% 0.029% 0.029% 0.029%
0.013% 0.013% 0.013% 0.013% 0.013% 0.013%
0.115% 0.115% 0.115% 0.115% 0.115% 0.115%
0.005% 0.005% 0.005% 0.005% 0.005% 0.005%
9.657% 9.839% 8.488% 8.530% 2.213% 2.057% 1.596% 1.471% 0.471% 0.153% 0.000%
65.100% 74.939% 83.427% 91.957% 94.171% 96.227% 97.823% 99.294% 99.765% 99.918% 99.918%
Dibuat Oleh
PT. Citramasjaya Teknikmandiri
M. HASANUDIN
Project Manager