Professional Documents
Culture Documents
Training Experience at The Institute.: 2.1 Office Organization Chart
Training Experience at The Institute.: 2.1 Office Organization Chart
Training Experience at The Institute.: 2.1 Office Organization Chart
Eng.Wijewardhana
(SOE-AP I)
Eng.Dulani
Ms.Priyanka
(Training Draughman)
1
2.2 BILLS OF QUANTITY
2.2.1 INTRODUCTION
The BOQ is a document prepared by the cost consultant that provides project specific measured
quantities of the items of work identified by the drawings. The quantities may be measured in
number , length , area, volume, , weight.
Benefits of a BOQ
Taking off quantities is an essential part of a Quantity Surveyor. He or She must have a good
knowledge and experience on taking off quantities of each and every item of construction work.
During my industrial training period I got chance to preparing measurements of items which
included from foundation up to roof work. That was great opportunity for me.
Basically, measurements were taken by following SLS 573. Before commence the taking off
measurements I thoroughly studied by followings to get use to the drawings and to identify the
items to be measured. Most of the takeoff I have done by using MS Excel software and using
manual drawings. So in my training period I had a chance to familiar with the computer aided
2
methods which basically MS Excel. Most of the Excel Features (functions and formulas) used
to preparation of measurement sheet; it provides more accurate and time saving results.
T D S Description T D S Description
14mm
15mm
9mm 55mm
Dimensions
Dimensions
Squaring
Squaring
Time
Time
Abstract sheet is used to summarize the quantities calculated in the TDS form. It is headed with the
project reference, sheet number and the work section .The item to be entered in the abstract sheet as
same order they will appear in the BOQ. Description are usually spread over two columns with the
relevant detentions in the first column and any deduction in the second column the total quantity of each
item is reduce to metric units such as lm,sqm,cum, ….. The order of item in each work section of the
abstract sheet normally follows The sequence indicated in the first column of SLS- 573.
When similar item occur in different size, the cheapest and normally the smaller item is given first.
3
Abstract Sheet
1. a b
c d
a- Description of item
b- Quantity from TDS
c- Deduction to be made
d- Actual Quantity
3. PREPARATION OF BOQ
The BOQ is the list of various components of a project which gives a detail description of each
component and the quantity of it in metric units as rate of each item, the item quantity
multiplied by unit rate use amount of each item and finally the civil cost of the project.
The Bills of Quantities should be divided generally into the following sections:
a) Preamble
b) Preliminaries
c) Measured Work
d) Provisional Sums
e) Day work schedule
4
Item Description Unit Qty Rate Amount
2.2.3 MEASUREMENTS
Taking off Measurement is one major item for Quantity Surveying duty. In my training period I
got chance to took quantities from the drawings. It was two storied building. Some of items are
described below.
2.2.3.1 FORMWORK
Formwork is a temporary structure. Formworks are generally made from wood or steel. Form
work shall be measured to the contact surface of concrete and formwork. Measurement for
formwork is deemed to include for all necessary boarding, support, erecting frame, cutting
angles, cleaning, wetting and treatments before placing and removal.
5
No deduction shall be made for reinforcements, Structural steel.
2.2.3.3 REINFORCEMENT
2.2.3.3.1 INTRODUCTION
Usually steel is supplied in two basic types.
Tor steel - Tensile strength 410 N/mm2
Mild steel - Tensile strength 250 N/mm2
Most commonly use sizes of steel bars in our sites are as below,
Mild steel -6mm, 10mm
Tor steel -10mm, 12mm, 16mm, 20mm, 25mm, 32mm
5 T 10 - 06 - 150 T
Bar Location
Bar Spacing
Bar Mark
Bar Diameter
Number of Bars
W = D2 /162.162
6
D - Diameter is in- mm
W - Weight is in- kg/m
COLUMN
200
C1 T 16 12 4 48 3825 183.6 950 2250 450
200
C2 T 16 48 4 192 3325 638.4 950 1725 450
50
C1 R 6 12 16 192 1700 326.4
400 400
50
C2 R 6 48 13 624 1700 1060.8
400 400
7
Figure No : 2.2.1 Construction of walls.
Tiling
Tiling is the most common floor finishing way in today. Using Drawings I had to
get measurements for tiling. Commonly tiling is done on the concrete floor and cement ,sand
bend will do before apply tile. Tiles are bond to floor using tile adhesive. Tile grout is use for
filling gaps between tiles. There are different types of tiles and different patterns.
8
2.3 TENDER DOCUMENTS
2.3.1 TENDERING
This is the procedure which is done to select most suitable contractor to particular projects.the
blank BOQ wassent to contractors . sontractors will price the BOQ with their own pricing
stratagies including their profit margins and overheads.
During my training period, I got experiences about Fiiling the tender document.
Bid document issued by ICTAD. There are four type of standard bidding document which can
be use for different capacity of contract.
04. Standers Bidding document for design & build contract.- ICTAD / SBD / 04
Recommended for use on contracts were the contractor is responsible for the design and
construction of the work on specified approvals from the employer.
9
4. Condition of contract
5. Form of bid and qualification information
6. Bidding data and contract data
7. Specifications
8. Bills of quantities
9. Drawings
10. Standard forms for bids
11. Check list for bidders
10
Bid opening and evaluation details
Details relevant to award of contract.
The standard forms that can be use after the award of contract are given in this section.
Letter of acceptance
Agreement
Performance security
Advance payment security
Retention money guarantee
11
2.3.3 PRICING TENDER
The bidder shall fill in rates and prices for all items of the work described in the Bills of
Quantities. Items against which no rate or price is entered by the bidder will not be paid for by
the employer. The vat component shall be entered separately in the space provided in the bills
of quantities.
In our company the blank BOQ was filled by using of NCP rate book (North Central Province)
. Not only that bids were priced with preparing rate brake down in my training period I think it
is correct way for the success of bids. There for we have to be lowest substantially responsible
bidder.
If there is any minor mistake, they were corrected by the authorized officer and singned.If there
any new item which price is not in the NCP rate book they build new rates for them.
When we pricing BOQ according to the SBD / 04 ( Design and built contract ) we prepared
new rates. we added over head and profits for this type of contracts. First the BOQ priced by
the pure rates.When the finel sum achieved , the profit margin will decided.
Pure rate – A
Decided profit margin – X%
Tender Price = A x X% + A
The profit margin decided by, getting the project or not. If we want to get the project
definite we will decrease our profit margin up to minimum level.
12
2.4 CLIENT BILL
2.4.1 INTRODUCTION
Interim Payment Certificate (IPC) which is submitted to client by contractor in monthly or in
specific time period.
These payments assists in the contractor’s cash flow . The amount of these payments is entered
onto an interim payment certificate and the client must honor the certificate within the period
stipulated by the contract.
And the consultant checked that and issued the payment for work done, Measurements of work
done were jointly taken by contractor, so it easy to checked the bill, only need to check the
arithmetic errors. The components of the Client bill,
13
01. Material at site-
In a construction project we should send detains about materials at site monthly, from
contractor to client , because the material at site belongs to the client and want to know
about that by him
Sometime client send us some specifications about materials. Then should
checked those materials before sending the materials at site list , to client .When we
preparing this list we should include every countable materials such as cement, sand,
soil, Pvc pipes, Plywood sheets etc. and about 80%of material quantity should be added
to the client bill.
02.Mobilization Advance
This advance shall be recoverd from the interim valuations on percentage (%) basis.
The advance payment should be fully recoverd when the total payment value reaches
90% of the initial contract price.
14
After the issue of completion certificate by the engineer 50% of retention money shall be
released to the contractor. If the contractor shall submit the retention money security balance
50% of retention shall be paid to the contractor.
Many construction contracts allow the construction period to be extended where there are
delays that are not the contractors fault is described as an extension of time . The contractor
gives written notice to the contract administrator accepts that the delay was caused by a
relevant event, then the grant an extension of time and completion date is adjusted.
2.4.4 Variation
A variation is an aiteration to the scope of wors in the form an addition ,substtitution or
ommision from the original scope of works. Almost all construction projects vary from the
original design, scope and definition. Whether small or lage , construction projects will have
inevitably depart from the original tenter design, specifications and drawings prepared by the
design team.
15
Valuation of variation often based on the rates and prices provided by the contractor their
tender.Rates are decited by quantity serveyor to get good profit using this opportunity.
16
Figure.No:2.2.2.Interim Payment Certificate
17
18
19
PAYMENT CERTIFICATE Invoice No - CB/DGM (EPC-SP/M&V)/D 1316-02/007
CERTIFICATE NO : INTERIM BILL 07 DATE : 2016.11.30
NAME OF THE CONTRACT: PROVINCIAL ROAD CARPETING PROJECT 2011 -ANURADHAPURA
AWUKANA TOWN TO WALASWEWA VILLAGE THROUGH NAAGAMA .
EMPLOYER : MINISTRY OF ECONOMIC DEVELOPMENT
CONTRACTOR : CENTRAL ENGINEERING CONSULTANCY BUREAU
CONSULTANT : ROAD DEVELOPMENT AUTHORITY
INITIAL CONTRACT VALUE
: RS. 92,549,071.44 (WITH OUT TAXES)
ADVANCE PAYMENT : RS. 18,509,814.29 (WITH OUT TAXES)
COMMENCEMENT DATE: 24/06/2011 COMPLETION DATE : Not Clearly stated
VAT REGISTRATION NO : 409000100-7000
1.0 TOTAL VALUE OF WORK EXECUTED UP TO 08-08-2014
Rs - 59,702,904.61
1.1 Day Works Rs -
1.2 Variation Rs - 1,574,886.88
Total Value of Work Done (A) Rs - 61,277,791.49
2.0 ADDITIONS
2.1 Materials at Site 80% Rs -
Total Value of Addition (B) Rs - 0.00
3.0 DEDUCTION
3.1 Retention 5% for Initial Contract Value Rs 4,627,453.57
3.2 Recovery of Advance Payment Rs 13,617,287.00
(90% of Mob.Advance)
3.3 Liquidated Damages Rs
3.4 Less any other Charges (for bitumen) Rs
Total Value of Deduction (C) Rs - 18,244,740.57
4.0 PRICE ESCALATION (D) Rs -
5.0 ANY OTHER CLAIMS (E) Rs -
6.0 CONTRACTOR DUE NET AMOUNT (A+B+C+D+E) Rs - 43,033,050.92
7.0 TOTAL PREVIOUSLY CERTIFIED (Without taxes) Rs - 40,928,086.16
8.0 NET AMOUNT DUE Rs - 2,104,964.76
9.0 ADD VAT
4.9.11Vat On Net Amount Due ( 12% ) Rs 315,744.71
TOTAL AMOUNT INCLUDING V.A.T Rs 2,420,709.48
I recommended that sum of Rupees Two Million Four Hundred Twenty Thousand Seven Hundred Nine and cents Forty
Eight only
20
21