Sl.

No Activity(June-2007)

1 TG Desynchronising & shifting of plant load on GEB

2 TG to be tripped manually & put on baring

3 Boiler to be depressurised by opening vents.


Boiler to kept on slow cooling ( Natural
4 cooling)
5 Boiler to be put on forced cooling
6 TG to run on barring

7 All
All boiler
Boiler duct manhole
manhole bolts
covers to be
to be loosened
removed for removing
to asses the
8 inside temp. for entering IN.
9 Removing of Nozzle chest,Casing & ESV
10 TG , ESV/Chest valves servicing

11 TG Casing fixing & tightening of bolts

12 Entering in the Boiler for cleaning & other jobs

13 Super Heater roof plate to be replaced


13 Hydraulic testing of Boiler
14 Boiler inspection by Boiler Inspector
15 Boiler Box up
16 TG Box up (TG inlet flange gasket replacement)
17 TG to be put on Barring
18 Boiler steam line charging
19 TG rolling & power change over
20 ACC tube bundle cleaning
21 Oil Cooler
Vaccum cleaningproblem (PI-4vcs01) , (PI-4vcs 02) to be
indication
attended , Trip/False alarm to be checked,Rtd of HP end &
22
Pinion NDE to be replaced

23 Vibration switches of all ACC are to be checked & set right,


24 Air for Oil burner, Damper to be roused
Boiler Eva.2 &3 Blow Down line isolation valve to be
25 replaced