Professional Documents
Culture Documents
Industrial Development
Industrial Development
Introduction
The emergency plans described in this section are an outline of the details
that will be included in the detailed emergency plans to be developed
prior to the construction and operating phases of the Project. This
outline is based on Applicant’s experience in operating other similar
wind power projects. For wind power projects, the key element of an
effective emergency and safety plan is the ability to communicate.
During both construction and operation of the Project, all operations and
construction team leaders will be equipped with two-way short-band radios
and cellular phones.
1
operations and maintenance emergency plans will also be developed and
submitted for review by EFSEC and prior to the start of plant operations.
During the Project construction and startup period, the emergency plans
will be updated to conform to manufacturer and vendor safety
information for the specific equipment installed at the Project.
The emergency plans cover a number of events that may occur at or near
the Project site by natural causes, equipment failure or by human
mistake. The following is a list of potential events that will be covered
by the emergency plans and form its base table of contents.
• Personal medical injury;
• Construction emergencies;
• Project evacuation;
• Fire or explosion;
• Floods;
• Extreme Weather Abnormalities;
• Earthquakes;
• Volcanic eruption;
• Facility Blackout;
• Chemical or Oil Spill or Release;
• Blade or Tower Failure;
• Aircraft Impact;
• Vandalism
Emergency planning is an integral and essential part of loss prevention
strategy. The type of emergency primarily considered here is the major
emergency which may be defined as one which has the potential to cause
2
serious danger to persons and or damage to property and which tends to
cause disruption inside and or outside the site and may require the use of
outside resources.
Emergency is a general term implying hazardous both inside and outside
the installations. Thus, emergencies are termed “On-Site” when it
confines itself within the plant even though it may require external help
and “Off-Site” when emergency extends beyond its premises. It is to be
understood here, that if an emergency occurs inside the plant and could
not be controlled, it may lead to an off-site emergency.
3
Assuming all reasonable plant safety design and their improvements have
been considered like design codes, practices alarms, shutdown interlocks
etc., the accidents may occur as the plant operating parameter valves may
exceed or lie out side the normal parameters.
These potential uncontrollable parameters give the plant operators an
indication of consequences in advance of actual occurrence. The
important elements of emergency planning can be broadly classified as
follows.
i. Identifying the disaster potential scenarios and advance
planning to combat and minimise the damage.
Of the above points, the first four are most relevant to the immediate
attention to works management. The areas affected by each accident
scenario can be identified by their consequences like Pool Fire, Flash Fire
and Toxic gas release. It would be appropriate to classify the hazards
around the plant and to provide emergency measures in the area both
onsite or offsite (if the zone extends).
4
ALERT:
It is the duty of any witness of the beginning of an accident or of an
anomaly which might lead to an accident to give the alert and to act with
available means within the limits of his ability.
Alert is the information given to ask for assistance, in principle using
alarms which are inside or outside the establishment.
EMERGENCY FACILITIES:
Communication System
Wind Sock
Emergency Transport Vehicle
First Aid, Fire fighting Equipment located in different areas in the block
and utilities areas.
Eye wash fountains
Personnel Protective Equipment
5
FACILITIES AT EMERGENCY CONTROL CENTRE (ECC):
Emergency Control Center plays a vital role to control emergency of any
magnitude.
Following material is normally kept available in Emergency Control
Center:
6
ASSEMBLY POINTS:
Assembly points are those locations where the persons who are not
connected with emergency operations can await either for further
instructions or for rescue transport and rehabilitation. Presently Time
office is considered as such assembly points. For any reason this
assembly points becomes vulnerable for consequences of fire, the persons
can go out of the factory gate and assemble outside.
Assembly points are manned by Time Office persons and they work
under the control of Emergency Coordinator.
EMERGENCY PROCEDURES:
Whoever notices an emergency identified above or a grave situation
which has potential to develop into an emergency should forthwith raise
an alarm by shouting or approach his plant shift in charge and informs
him the details.
EMERGENCY COMMUNICATION:
Whoever notices an emergency of fire or gas leak, shout as “Fire, Fire,
Fire or gas leak, gas leak, gas leak” in the regional language, as the case
may be. He would rush to the shift in charge.
7
Shift in charger rushes to the scene, assess the situation and inform the
Incident Controller / Site Controller / Security. While doing so, he would
initiate measures to protect himself and to controlling the emergency.
EMERGENCY WARNING:
At present there is no arrangement of siren in the plan. One emergency
siren would be procured and installed so that it is audible to the entire
plant area. Its operating plant would be located in ECC. Security on the
authorization of Site Controller would operate. As there is no
arrangement for normal siren, any siren operation means that there is an
emergency in the plant.
ALL CLEAR:
Site Controller in consultation with Incident Controller and after ensuring
that the emergency situation is overcome would order for all clear signal
indicating that emergency is over come. All clear signal is organised by
Security Officer continuous siren for 3 minutes is the All Clear Siren.
These sirens would be made familiar to all employees. It would be
ensured that in the surrounding industry, there is no similarity in normal
or emergency sirens of this plant.
EMERGENCY ACTIONS:
Who ever notice an emergency will bring it to knowledge of Site
Controller and he verifies about it as quickly as possible.
Once the emergency is confirmed, Site Controller would declare on set of
On Site Emergency and Order security to raise emergency alarm through
out the plant.
Incident Controllers and shift in charge organise to communicate
emergency orally and by hand bells by shift in charges.
8
At the same time, these with emergency responsibilities, key personnel
and essential employees are expected to undertake specified emergency
duties.
9
Diesel Generator Operator would be ready to start the emergency
equipment if required and if generator is not in operation. In the event of
fire accident, electrical operator would switch off power supply in that
block enabling fire fighting operations.
Water pump operator would change the system and make arrangements
for water for fire fighting operations.
1. EMERGENCY LIGHTING:
10
NON ESSENTIAL WORKERS AND OTHERS:
Persons from outside or other workers, contract, casual workers who are
not connected with emergency operations must withdraw from the plant
where emergency occurred, to either assembly point or other safe
location and await instructions.
Incident Controller arranges sending away of non essential employees to
either assembly point or to outside gate.
Road Tankers, Lorries drivers, cleaners with draw the vehicles beyond
the factory to safe location and await at that place for any emergency
instructions like evacuation etc., Security organizes sending away of
waiting trucks to a far off place.
BEYOND NORMAL WORKING HOURS & HOLIDAYS:
Being a process industry the procedure is same at any time either beyond
normal working ours or holidays etc.
FAMILIARISATION:
11
METHODOLOGY
12
PURPOSE OF THE STUDY
METHOD OF STUDY
In order to conduct the research, the researcher has followed the case
study method, historical method. This method are used to make an in
depth analysis of the various measures and their application. Relevant
information was collected through interview with managers officers,
workers, supervisors, and through various documents, magazine. the
survey method was used mainly to understand as to how the employees
and workers perceive the safety practices of the organization.
DATA COLLECTION
The data for the study were collected both from primary and
secondary sources. the primary sources include the executive, no
executives. The secondary sources include the relevant records and files
of various department and magazines, periodicals, etc.
SAMPLING
For the purpose of studding the opinion of both managers and workers
about the safety measures and avert the accidents, the following drawn
13
using simplified random sampling for obtaining information to union
official.
Various limitations which came across during the project work are:-
Due to break of boiler and most of the number were busy so they
can’t give their opinion.
14
Company profile
Jindal Power & Steel Ltd
Jindal Power Limited (JPL), a subsidiary of Jindal Steel & Power Ltd.
(JSPL), has been contributing significantly to the growing needs of power
in the Country.
JPL has set up India’s first mega power project in the private sector at
Raigarh, Chhattisgarh. The Company has invested approximately Rs.
4338 crore for setting up a 1000 MW power plant, the 1st unit of which
commenced commercial operation in December 2007. All four units (250
MW each) were commissioned within a span of nine months.
The fuel supply of the plant is met through its captive coal mines. A 6.9
km conveyor pipeline has been set up for transportation of coal between
the mines and the plant. The Company has constructed a 258 km, 400 KV
Double Circuit transmission line from the plant to the PGCIL sub-station
at Raipur through which power can be sold anywhere in India. For
meeting the plant’s consumptive water requirement, an 18 m high dam
over the Kurket River has been built, 25 km away from the project site.
15
JPL has also signed an MoU with the State Government of Jharkhand to
set up a 2640 MW thermal power plant.
In the Hydro sector, JPL has signed agreements for 6100 MW projects in
Arunachal Pradesh in joint venture with Hydro Power Development
Corporation of Arunachal Pradesh Limited.
Year 2008
16
Year 2009
ISO 9001:2000
ISO 14001:2004
OHSAS 18001:2007
Overview
17
Jindal Power Limited has set up India’s first mega power project in the
private sector – the 1000 MW thermal power plant at Raigarh,
Chhattisgarh. The Company has invested approximately Rs. 4338 crore
for setting up a 1000 MW power plant, the 1st unit of which commenced
commercial operations in December 2007. All four units (250 MW each)
were commissioned within a span of nine months.
The fuel supply of the plant is met through its captive coal mines. A 6.9
km conveyor pipeline has been set up for transportation of coal between
the mines and the plant.
The existing 1000 MW power plant was set up with four turbine
generators of 250 MW each, also supplied by BHEL.
Social responsibility
As part of our corporate social responsibility philosophy, we believe that
overall sustainable community development is essential for the growth of
the power industry. The ‘O P Jindal Samaj Kalyan Samiti’ works with
18
underprivileged communities in our areas of operation to develop
resources in the region, support local professional development and
enhance the quality of life in adopted villages through education,
healthcare and civic amenities.
Jindal Power Limited conforms to the latest regulatory norms and aids in
environmental protection practices through the implementation of state of
the art technologies. Persistent efforts are made to control pollution in and
around the factories to provide clean air and water. The Company has
19
taken the following steps towards achieving a pure and pollution free
environment:
20
environment events and celebrate the World Environment Day, Earth Day
and Ozone Day through different initiatives.
Achievements
21
Letters of appreciation received from Chhattisgarh State Health
Department, Rural Development Department and Women & Child
Development Department.
Certificate of Excellence and First Prize in individual category
(two) in the XIXth Annual Flower Show organised by JUSCO &
Horticulture Society, Jamshedpur, in December 2007.
First prize in stall competition in 16th Horticulture Exhibition-
cum-Flower Show, 2008 organised by Tata Refractories Limited.
Vegetable show, 2008, organised by JSPL, Raigarh
22
RISK ASSESSMENT AND ONSITE EMERGENCY PLAN
Hazard Identification
Identification of causes and types of hazards is the primary task for
planning for risk assessment. Hazard can happen because of the nature of
chemicals handled and also the nature of process involved. So for risk
analysis first step is to identify the hazardous chemicals which are to be
studied for risk analysis.
23
The following Table 1 shows the list of major chemicals which have
been identified as hazardous chemicals in The Manufacture, Storage
and import of Hazardous Chemical Rules, 1989 and which are to be
considered as Major accident hazards (MAH) installations.
Table 1
The chemicals which are stored more than the threshold quantities are
to be considered for major accident hazard. Fuel oil (LDO/HFO), used as
supportive fuel in the boiler, is classified as Highly Flammable liquid
as its flash point remains within 30oC-90oC. Its threshold quantity is
2500 tonnes. Similarly for Chlorine is a toxic gas and its MAH
quantity is 25 tonnes. So Fuel oil and Chlorine will be considered for
further analysis for risk assessment.
Quantity stored for transformer oil very low to be considered for the
study. Sulphuric Acid and Caustic soda are hazardous chemicals but are
not included in Schedule 3 for MAH.
24
.Material Safety Data Sheets (MSDS) for Fuel Oil and Chlorine are
provided at the end of this chapter.
Hazards Scenarios
Major Hazards from oil storage can be fire. Maximum credible accidents
from oil storage tank can be
a) Tank Fire
Tank Fire:
Oil is stored in floating roof tank. Leak in rim seal leading to
25
accumulation of vapour is a source of fire. Lighting can be a source of
ignition and can cause tank fire. Overflow from tank leading to spillage
may cause vapour cloud formation. This can catch fire and it can flash
back to the tank to cause tank fire.
Radiation at various heat flux levels which are critical in risk analysis, are
given in the Table 2.
26
Table 2
Effect of Heat Radiation
The damage and fatality (percentage of the exposed people to be killed) due
to the exposure time is very important in determining the degree of
fatality and corresponding effect distance. It is observed that the exposed
persons normally find shelter or protection from the heat radiation (e.g.
against a wall) within 10 seconds. However, exposure time of 30
seconds is normally assumed for pessimistic calculation which applies
if people do not run away immediately or when no protection is available.
The variation of the effects on humans due to heat flux and duration of
exposure have been developed in the form of a Probit Equation
which gives following values for human fatality levels in Table 3.
Table 3
27
Nature of Hazard from Chlorine Storage
Chlorine is a gas at ambient temperature and pressure. Its boiling
point at 1 atmosphere pressure is -34.1oC. It is a greenish yellow gas with
irritating pungent smell. It is heavier than air and its molecular weight is
70.9. Chlorine poses a major health hazard if human beings are
exposed to higher concentration. Chlorine is non-combustible in air
but most combustible materials will burn in chlorine as they do in oxygen.
Flammable gases and vapours will form explosive mixtures with chlorine.
28
Four specific scenarios can be considered
Table 4
29
Chlorine Mortality in 30 minutes (ppm)
10% 50%
90%
Healthy people outdoor
Up and about 125 250 500
Vigorous Walking 62 125 250
Vulnerable people indoor
Up and about 50 100 200
Vigorous Walking 25 50
100
Consequence Analysis
Methodology
Consequence models estimate the potential hazards of the release of a
chemical. It is done based on the release characteristics of the chemical
concerned. A number of formulae and softwares are used for these
purposes.
For the present study, for Pool fire and Tank fire, steady state burning is
assumed.
Also for large fire wind speed is considered insignificant. Heat
radiations at different distances have been calculated based on equations
of USEPA’s CAMEO model. Dispersion of chlorine has been calculated
using software WHAZAN (World Bank Hazard Analysis) - II, version-
2.1. WHAZAN is a software package, which contains a set of hazard
30
analysis models (called consequence models) together with a physical
properties database of chemicals. The models estimate the effects of
hazardous chemical releases.
Table 5
31
daytime and night time and for winter and summer seasons have been
considered. For winter day temperature of 25oC and night
Table 6 shows the impact distances for chlorine discharge for different
scenarios.
Table 6
32
Risk Assessment
The risk assessment determines whether the risks are tolerable or
if risk mitigation measures are required to reduce the risk to a level
which can be considered to be as low as reasonably practicable
(ALARP). UK standards are generally followed here. Risk assessment
depends on failure frequency of the system and probability of ignition
and explosion. These are assessed below.
Failure frequency
Table 7.
33
Ignition Probability
Ignition probability data is important in quantification of risks. Historical
data on ignition of flammable releases are used as a basis for determining
suitable ignition probabilities. As probability of ignition depends upon
availability of source of ignition, it also depends on the maintenance of
safety level. Table 8 shows the ignition probability for flammable liquids.
Table 8
34
Table 9
The results show that the risk from fire and chlorine dispersion remains
within ALARP region. Tank fire by lightning is of negligible risk.
Limitation of the Risk Assessment Study Any mathematical expression
of physical events has some limitations. The properties of chemicals,
release conditions, meteorological data are all used as ideal data
which can have variation in the actual condition. Therefore the
consequences of hazardous incidents will have varying accuracy. Many
types of hazardous incidents can only be assessed by making a variety
of simplifying assumptions. Many times an ideal simple mode of failure
could not be identified in real disaster event. A number of apparently
independent events can occur at a time because of some simple events.
Failure rates are also statistical averages depending upon the reporting
accuracy. Also all the failure rate data are generated in the western
developed countries which may not be always same for here.
35
On Site Emergency Plan
In recent years public awareness of hazards from industry have
increased considerably. Local people and employees have now better
legal safeguards against industrial disasters. The management today
has more responsibilities in respect of any kind of disaster in its
project. So specific management plan to encounter a disaster situation
is of utmost importance. As disaster types, sources, effects are different, it
needs multidisciplinary and multi-organizational approach to tackle such
situation.
Types of Disaster
Disaster is an event which causes severe disruption to life of number of
people or to the project activities resulting in suffering and loss of life and
property.
Disasters can be
Degrees of Disaster
1. LO - can cause injury, illness and equipments damage but not very
serious
36
Illness property and equipment damage.
3. HIGH - Catastrophic situation, major danger, can cause deaths,
major widespread illness, injuries, loss of major property and
equipments. Immediately uncontrollable.
Stages of Disaster
The duration of disaster's effect can be divided into following stages:
Warning
Impact
Rescue
Relief
Rehabilitation
1) Warning:
The natural calamities which may lead to disasters e.g. flood, cyclone can
often be predicted. There are possibilities of disasters during local trouble,
37
riot and war etc. also. All facilities to encounter the disaster should be kept
ready and employees in full alert.
2) Impact:
This is the time when the disaster actually strikes and very little can be
done to counter the situation. The impact period may be of few seconds
(like explosion or earthquake) or for days (like flood, fire etc.).
3) Rescue:
This is the most important stage which starts before the predicted disaster
of just after the impact. All available resources need to be
immediately engaged in operation.
4) Relief:
This is a longer stage of work depending on the degree of disaster. Work
during this stage will need external help for medical, food, clothing and
shelter.
5) Rehabilitation:
This is an important stage in terms of future planning. It includes
rebuilding of damaged properties, restart of project work, compensation
etc.
On site Emergency Plan is required to meet the emergency condition
during disastrous event in the plant. Its objectives are to:
Rescue and treat casualties
Safeguard other people & Installations Minimize damage
38
Control initially and restore ultimately to normal situation
Arrange rehabilitation of the affective people
A summary of the plan is given below. The plan will be revised and
detailed after the commissioning of the plant, as then all the units will
be in final shape. The exact name and designations of all personnel will
be then provided in the plan.
Site controller will ensure that all members of his/her team have been
informed to collect at Emergency Control centre. He/She will then
proceed to Emergency Control Centre to take charge.
After firsthand assessment of situation he/she will give necessary
instructions to Emergency Control Team. He/She will maintain a Log book
39
of all the activities. He/she will keep in touch with the external
communication Team. He/she will ensure that information is sent to
outside emergency services (Police and Fire Brigade).
He/she will depute people to,
Attend to telephone
40
b) Send one guard to start the fire pump.
Communication Officer
Controller
Personnel Manager
41
Will keep a record of attendance of workers, staff, contractor’s
personnel, and visitors at the Gate which will act as Assembly Point.
Safety Officer
Will assist the Incident Controller with his special knowledge on the
safety aspects in the factory. He will help to identify the hazardous
chemicals,
hazard zones and zone of probable impact in different accident scenarios
Will select people with special training in safety matters to assist in the
control activities
Announce through PAS about the incident zone and any other
immediate
Medical Officer
Assembly Point
Will take up the full responsibility of providing medical assistance
duringemergency
42
Telephone Operator
Contractor’s Employees
Contractor's employees will be instructed in the Emergency Procedures
before commencing work on this site. They will report to the emergency
assembly point on this site. Personnel Manager will guide them in case
a major decision like evacuation from the factory is taken.
Visitors
Infrequent visitors are registered on each visit. They will be given a
Visitors pass which includes an emergency action statement. The
responsibility for visitors in emergency situation rests with the person being
visited.
43
He/she will act as Site controller for the time being. As soon as becomes
aware of the emergency and its location, he will proceed to the scene.
He will assess the scale of the incident and direct operations within the
affected areas. He/she will contact and inform the Site Controller
and Incident Controller immediately. Till their arrival he will continue
to perform their duties. He/she will contact the departmental head to act as
incident controller and guide Safety Officer and Security Officers for
containing the damage. He/she will call the Medical Officer to the plant if
necessary. Other staff with designated responsibilities will act as instructed.
Infrastructure
Fire Fighting Facilities: The plant will have adequate fire fighting aids
including fire hydrants close to the required locations. There will
be Portable Fire Extinguishers of different types and sizes are installed in
specific places.
The factory siren will be used for raising the alarm and also for ALL
CLEAR
signal
Emergency Control Centre is the point from which the Site Controller
directs the movements of Personnel and Equipment during an Emergency.
Contents of Emergency Control Centre:
44
Table 10
g) Emergency lighting.
45
Assembly Point is a place containing an internal telephone and paging
system, where people can wait in a group during emergency to receive
instructions from the Emergency Controller.
Fire Brigade
District Hospital
OPCB
Factory Inspector
Local Media
District Magistrate
46
Emergency Response Diagram
47
Material Safety Data Sheets (MSDS) for Fuel Oil and Chlorine
Diesel
Explosivity Moderate
Auto Ignition Temp. C 256.6
Explosive Limits % 0.7-5
Flash Point, C,CC/ OC 32 to 96
48
HAZARDS SPECIFICATION
NFPA RATING
Health 0
Stability 0
Flammability 2
Material Factor 10
CHLORINE
General
Synonyms: bertholite, molecular chlorine Molecular formula: Cl2
Physical data
Appearance: light greenish-yellow gas with an irritating odour Melting
point: -101 C
Flash point:
Explosion limits:
49
Stability
Toxicology
Toxic by inhalation, ingestion and through skin contact. Inhalation
can cause serious lung damage and may be fatal. 1000ppm (0.1%) is
likely to be fatal after a few deep breaths, and half that concentration
fatal after a few minutes. May irritate or burn skin. OEL (8hr TWA) 1
ppm.
Toxicity data
IHL-HMN LCLO 2530 mg/m3/30m
IHL-HMN LCLO 500 ppm/5m
IHL-RAT LC50 293 ppm/1h
IHL-MUS LC50 137 ppm/1h
Transport information
Environmental information
Personal protection
50
JOB SAFETY ANALYSIS
HAZOP
Job Safety Analysis (JSA) & HAZOP are procedure or a technique
adopted to make a detailed study of a particular operation to identify the
hazardous condition and methods of works and to suggest/develop a
solution to overcome the hazard involvement. Hirakud Power has planned
this activity in their safety action plan.
JSA Programme: -
1. Each section should have their own JSA team.
2. The team should not consist more than 4/5 members out of which two
should be from middle management and two from Wages Roll.
3. A prescribed format shall be used for JSA & HAZOP.
4. To start with, operations, which involve more hazards, should be
analysed.
5. After the analysis of JSA & HAZOP format with any additional note
if required should be submitted to the Department Head for approval.
Once the JSA & HAZOP are approved it becomes responsibility of
the Department to implement the recommendations made by the JSA
& HAZOP team the section should ensure that all the employees
involved in the operation accept the practice the recommended safe
operating procedure.
6. The concerned Departmental Head should ensure that the JSA &
HAZOP team of the Departmental function and carry out analysis as
per schedule.
7. The Safety Officer should act as an Advisor to JSA & HAZOP team
and provide guidance for proper analysis.
8. All the records should be maintained in the Department.
51
9. Whenever it is possible to make a spare copy, the same should be sent
to safety of.
HAZARDS & OPERABILITY STUDY (HAZOP)
WHAT: -Hazards & operability study is a tool to assess, the various type
of hazard potential of mal-operation or mal-function of individual
equipmentor system as a whole involved in the existing or new process
operation, caused because of deviation from the design intentions and
their consequential effects as a whole
The type of hazard could be
1. To the people
2. To the equipment.
3. To the product quality
4. To the environment/general public.
OBJECTIVE: -
To improve the
a) Safety of the people involved in the process.
b) Safe operation of the equipment involved in the operation.
c) Quality of the product.
d) Adverse effect on the environment, if any.
e) By identifying the potential hazards and implementing it’s
remedial action.
52
AID Program
In case of any emergency situation following near by factory
management may be called for help.
53
MEDICAL & HOSPITALSATION FACILITIES AVAILABLE NEAR
SITE
MEDICAL FACILITIES AVAILABLE NEAR SITE
54
Conclusion
Management alone can’t prevent accidents. It can only help in the
process of making the plants safe. Much will depend on the attitude of the
workers also. Preventation of accidents is an essential part of good
workmanship. every worker must learn & understand the danger points of
his work or process & precaution should be taken to prevent accidents.
Essential information on accident must be passed on by the worker to
follow workers, so that potential dangers method of safe guarding against
them is understood by all. It is also the duties of the workers to utilize all
the safety appliances & facilities provided by management. the workers
can contribute much to the promotion of safety by giving their own
advice & constructive suggestion based on their own experience. They
can also contribute in developing employee’s behaviour.
Safety is not a separate entity but it is interwoven with all aspects of
national life & growth corporate planning at the national level will be a
great success if safety management is emphasized at all stages national
development. What we must try to do is prevent accidents as far as
possible & encourage education in industrial safety. What exactly
required is will, determination, effort & dedication to see this country
prosper & PROGRESS.
55