Status of Critical activities 2019-20 (Mine wise) - Talcher CF as on 07/05/2019

TALCHER COALFIELD
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility Present Status
1 Jagannath OCP a) Shifting of 15 Nos. hutments on Govt. Land of village Rakas & shifting of 31-Jul-19 District Admn No development till now. Demanding job in Private
EC: 7.5 MTY Road Security.
b) Completion of development work at Baulpur R&R site 31-Jul-19 GM, Jagannath Dola Mandap, WBM Road, Peripheral Boundary wall
and main drain completed. Estimate for Overhead
tank for water supply prepared. Work for
construction of Anganwari,Pressure Filter and
Bus Stop will be tendered before 10.05.2019.
c) Obtaining EC after obtaining recommendation of EAC (Violation). 30-Sep-19 GM (E&F) EMP has been uploaded on 30.04.2019. Now
the case is to be put up before EAC violation
committee for deliberation and approval.

d) Shifting of Rakas village to Baulpur R&R site – to avoid frequent 30-Nov-19 GM, Jagannath Shifting will be done after completion of Development
disturbances work.
e) Shifting of HEMM from Bharatpur OCP 20-Apr-19 GM, Jagannath Excavator will be provided from Ananta OCP after
obtaining alternate site approval for
Contractual agency
2 Bhubaneswari OCP a) Shifting of remaining PAFs of Tala Sahi - Balanda Site 31-May-19 District Admn PAFs are demanding complete development of R&R
EC: 28 MTY Site, where boundary wall has been constructed &
Land Reqd: 60 Ha only 100 meter is left and 19 encroachers are to be
OB: 17 M.Cum, vacated.
CPD: 46 to 55 K b) Shifting of remaining PAFs of Narharipur-Rehabilitation 31-May-19 GM, Jagannath 22 PAFs are demanding employment in subsequent
acquisition.
c) Shifting of remaining PAFs of Sahar Sahi-Gurjang Site 31-May-19 GM, Jagannath Shifting will be done after completion of Pond and
Crematorium at Gurjang R&R Site.Tender for the
same is to be opened on 08.05.2019

d) Amendment of FC letter for inclusion of the remaining 20.384 ha. Forest land 31-Dec-19 GM, Jagannath Area has to process for amendment of FC for
for which original application was made. EC will also be required to amended inclusion of 20.384 Ha.
after amendment of FC
e) Off-take: Arrangement of feeding of 25 MT Coal in L&T Pipe Conveyor 15-Apr-19 FDs To be decided in FDs Meet.
System-Decision & course of Action
f) Arrangement for evacuation of 15 MT Coal from L&T Pipe Conveyor System- 30-Apr-19 GM (E&M) Scheme is awaited from CMPDI.
Scheme by CMPDI to be expedited – synchronization reqd.
g) 20% expansion in EC capacity 30-Oct-19 GM (E&F)/ GM, Area has to prepare Form-I for further enhancement
JA of 20% of EC.
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility Present Status
3 Ananta OCP a) Finalization of Compensation payment & Employment issues of Allahadnagar 31-May-19 GM (L&R) Two families (1. Biswal family 4.5 Acre) (2. Samal
EC: 20 MTY village. family 4.0 Acre). Land compensation has been
granted and will be disbursed after completion
of Code of Conduct period for General Election.
(After 23.05.2019). Both the families are
demanding one employment from each family.
b) Finalization of Compensation payment & Employment issues of 31-May-19 GM (L&R) Structure measurement is under process.
Brundabanpur village.
c) Tree felling of already diverted forest land to be completed. 30-Jun-19 GM, Jagannath Tree falling for 700 Nos. completed.
d) Preparation of Operational Plan by CMPDI due to down throw fault 31-May-19 GM (P&P) Field work is going on, two holes failed, three holes
completed successfully, fourth hole drilling is
going on.
4 Lingaraj OCP a) Shifting of left out PAFs of Langijoda & Madanmohanpur 30-Nov-19 GM, Lingaraj Demanding additional compensation at par with
EC: 20 MTY compensation paid to PAF who handed over the land
at later stage. Villagers also filed writ petition at
Hon'ble High Court of Odisha.

b) Commissioning of L&T CHP/SILO 31-Jul-19 GM, Lingaraj 99% work completed, only grouting of Railway track
50 meters on both sides of the SILO is to be done.

c) Rail connectivity from Deulbera Siding to Lingaraj MGR Sdg. 31-Jul-19 GM, Lingaraj RITES Part - About 56% track laying completed and
one ROB is under construction will be completed up
to 30th June19 . Railway Part - About 63% work
completed. PH-I, Out of 3 ROB and 1 Culvert, 1
ROB has been constructed, rest construction is
under process in PH-II Out of 3 R0B, EARTH
WORK COMPLETED for the 1st and for 2nd -
earth work has been started.

d) Activities for shifting of coal corridor road 15-May-19 GM, Lingaraj Estimate is under preparation stage at the Area
and will be submitted to MCL HQ upto 15th
May.
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility Present Status
5 Kaniha OCP a) Compensation payment and balance employment issues of Kansamunda 31-May-19 GM (L&R) 177 cases have been finalisd by Tribunal. Out of
EC: 14 MTY village for proper mine operation. these, 35 persons have received compensation.
Remaining cases pending for want of Death
Certificates, Legal Heir etc.

b) Resettlement of village Jarada 30-Nov-19 District Admn Resettlement is pending for want of finalisation of
R&R site. Villagers of Patharmunda are not allowing
any development work and demanding employment
beyond norms.

c) Identification and alienation of Govt. land for Resettlement Site 30-Apr-19 GM, Kaniha Once again R&R site at village Takua need to be
considered for development in consultation with State
Administration. Further, two places within 15 Kms
have been identified by the Area and Tahsildar has
been requested to submit his views.
d) Boundary adjustment of Coal Block of Chhelia for progress of R&R 31-May-19 GM (P&P) CMPDI has been referred for making boundary
adjustment.
e) Application for EC/FC for Integrated Project with Gopalji 31-May-19 GM, Kaniha Land schedule under preparation
f) Shifting of 220KV HT Power line. 31-Dec-19 GM, Kaniha Rs.76 Crores deposited to OPTCL.
6 Bharatpur OCP a) Resolving remaining Employment issues of Nakeipasi for physical 31-May-19 GM, Bharatpur Action is being taken up for resolving the issues of
EC: 20 MTY possession of land remaining 3 perons.
b) Physical possession of Dashrathipur village land for mining operation – order 31-May-19 GM, Bharatpur Next date of hearing fixed on 03.05.19
by Tribunal regarding family dispute
c) Physical possession of Danara village land – issue of employment pending 31-Jul-19 GM (Legal) Pending at Supreme Court
at SC to be resolved.
d) Amendment of 20 MTY EC – submitted to MoEF on 22.01.2019 31-May-19 GM (E&F) Agenda not decided. Likely to be decided in next
EAC Meeting.
e) New OB contract @ 44,000 Cum./day after August 2019 15-Aug-19 GM (CMC)/ CMPDI has vetted the proposal and will be
GM, Bharatpur submited to MCL HQ CMC deptt. on
f) Requirement of 02 numbers Pay Loader for Road Sale loading 15-May-19 GM (Excv.) 07.05.2019
Supply Order for 11 Pay Loaders have been placed.
Likely to start supply after 15th May'19.

g) Start of activities for EC/FC for expansion area (26 MTY) 1-Apr-19 GM, Bharatpur Land schedule has been prepared and will be
submitted to Tahsidar for vetting on 10.05.2019
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility Present Status
7 Hingula OCP a) Starting of mining at forest patch – resolving VSS obstruction issue 31-May-19 GM, Hingula Mining started in Forest patch - OB being
EC: 15 MTY dumped in old quarry. For external OB dump 30
Target: 10 MT Ha forest land tree counting completed and
Land: 21 Ha estimate has been submitted to DFO for
OB: 5 M.Cum (14 to 16 approval.
K/day)
b) Shifting of Bhalugadia – start of Resettlement Site work at Kochianali – 31-Jul-19 District Admn Employment issues of Danara villagers is pending at
resolve Danara issue Supreme Court. Development work at Kochianali site
will start after resolving the issue of Danara villagers.
c) Finalization of Resettlement (C.C) issues relating to Patna Sahi of 31-Jul-19 GM (L&R) Issue related to Patna Sahi Cash Compensation for
Gopalprasad village. 386 families is at MCL HQ level for approval.
d) Construction of road over bridge/underpass on Panchayat Road leading to 31-Jul-19 GM, Hingula Estimate is under preparation stage at the Area.
Bhalugadia Basti.
e) Hingula Dispatch - EC amendment issue 15-Apr-19 GM (E&F) Application has been done for EC amendment.
Decision will be taken in next EAC meeting.
8 Balram OCP a) Diversion of road for progress of Solada quarry. 31-May-19 GM, Hingula Road diverted on 4th May 2019 night.
EC: 8 MTY b) Obtaining EC/FC for the extension area. 31-Dec-19 GM, Hingula Land schedule under preparation.
Target: 4.5 MTY c) Shifting of Puruna Sahi of Kalamchhuin village – completion of Jamunali 31-Dec-19 GM, Hingula Development work at Jamunali is under progress.
Land: 13 Ha R&R Site. Retendering will be done for outer compound wall.
OB: 10 M.Cum (27 to 33 d) Completion of Coal Corridor Road – Phase I & II 31-Jul-19 District Admn Work will be taken up with the help of District
K/day) Administration again after election.
e Shifting of Hingula High School, Hingula College, Public Health Center & 30-Nov-19 District Admn Shifting will be done after completion of Jamunali
Police Outpost R&R site.
TALCHER COALFIELD
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility
1 Jagannath OCP a) Shifting of 15 Nos. hutments on Govt. Land of village Rakas & shifting of 31-Jul-19 District Admn
EC: 7.5 MTY Road
b) Completion of development work at Baulpur R&R site 31-Jul-19 GM, Jagannath

c) Obtaining EC after obtaining recommendation of EAC (Violation). 30-Sep-19 GM (E&F)

d) Shifting of Rakas village to Baulpur R&R site – to avoid frequent 30-Nov-19 GM, Jagannath
disturbances

e) Shifting of HEMM from Bharatpur OCP 20-Apr-19 GM, Jagannath

2 Bhubaneswari OCP a) Shifting of remaining PAFs of Tala Sahi - Balanda Site 31-May-19 District Admn
EC: 28 MTY
Land Reqd: 60 Ha
OB: 17 M.Cum,
CPD: 46 to 55 K
b) Shifting of remaining PAFs of Narharipur-Rehabilitation 31-May-19 GM, Jagannath

c) Shifting of remaining PAFs of Sahar Sahi-Gurjang Site 31-May-19 GM, Jagannath

d) Amendment of FC letter for inclusion of the remaining 20.384 ha. Forest 31-Dec-19 GM, Jagannath
land for which original application was made. EC will also be required to
amended after amendment of FC

e) Off-take: Arrangement of feeding of 25 MT Coal in L&T Pipe Conveyor 15-Apr-19 FDs


System-Decision & course of Action
f) Arrangement for evacuation of 15 MT Coal from L&T Pipe Conveyor 30-Apr-19 GM (E&M)
System-Scheme by CMPDI to be expedited – synchronization reqd.
g) 20% expansion in EC capacity 30-Oct-19 GM (E&F)/ GM,
JA
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility
3 Ananta OCP a) Finalization of Compensation payment & Employment issues of 31-May-19 GM (L&R)
EC: 20 MTY Allahadnagar village.

b) Finalization of Compensation payment & Employment issues of 31-May-19 GM (L&R)


Brundabanpur village.
c) Tree felling of already diverted forest land to be completed. 30-Jun-19 GM, Jagannath
d) Preparation of Operational Plan by CMPDI due to down throw fault 31-May-19 GM (P&P)
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility
4 Lingaraj OCP a) Shifting of left out PAFs of Langijoda & Madanmohanpur 30-Nov-19 GM, Lingaraj
EC: 20 MTY

b) Commissioning of L&T CHP/SILO 31-Jul-19 GM, Lingaraj

c) Rail connectivity from Deulbera Siding to Lingaraj MGR Sdg. 31-Jul-19 GM, Lingaraj

d) Activities for shifting of coal corridor road 15-May-19 GM, Lingaraj

5 Kaniha OCP a) Compensation payment and balance employment issues of Kansamunda 31-May-19 GM (L&R)
EC: 14 MTY village for proper mine operation.

b) Resettlement of village Jarada 30-Nov-19 District Admn

c) Identification and alienation of Govt. land for Resettlement Site 30-Apr-19 GM, Kaniha

d) Boundary adjustment of Coal Block of Chhelia for progress of R&R 31-May-19 GM (P&P)

e) Application for EC/FC for Integrated Project with Gopalji 31-May-19 GM, Kaniha
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility
f) Shifting of 220KV HT Power line. 31-Dec-19 GM, Kaniha
Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility
6 Bharatpur OCP a) Resolving remaining Employment issues of Nakeipasi for physical 31-May-19 GM, Bharatpur
EC: 20 MTY possession of land

b) Physical possession of Dashrathipur village land for mining operation – 31-May-19 GM, Bharatpur
order by Tribunal regarding family dispute
c) Physical possession of Danara village land – issue of employment pending 31-Jul-19 GM (Legal)
at SC to be resolved.
d) Amendment of 20 MTY EC – submitted to MoEF on 22.01.2019 31-May-19 GM (E&F)

e) New OB contract @ 44,000 Cum./day after August 2019 15-Aug-19 GM (CMC)/


GM, Bharatpur

f) Requirement of 02 numbers Pay Loader for Road Sale loading 15-May-19 GM (Excv.)

g) Start of activities for EC/FC for expansion area (26 MTY) 1-Apr-19 GM, Bharatpur

7 Hingula OCP a) Starting of mining at forest patch – resolving VSS obstruction issue 31-May-19 GM, Hingula
EC: 15 MTY
Target: 10 MT
Land: 21 Ha
OB: 5 M.Cum (14 to 16
K/day)
b) Shifting of Bhalugadia – start of Resettlement Site work at Kochianali – 31-Jul-19 District Admn
resolve Danara issue

c) Finalization of Resettlement (C.C) issues relating to Patna Sahi of 31-Jul-19 GM (L&R)


Gopalprasad village.
d) Construction of road over bridge/underpass on Panchayat Road leading to 31-Jul-19 GM, Hingula
Bhalugadia Basti.
e) Hingula Dispatch - EC amendment issue 15-Apr-19 GM (E&F)

8 Balram OCP a) Diversion of road for progress of Solada quarry. 31-May-19 GM, Hingula
EC: 8 MTY
Target: 4.5 MTY b) Obtaining EC/FC for the extension area. 31-Dec-19 GM, Hingula
Land: 13 Ha c) Shifting of Puruna Sahi of Kalamchhuin village – completion of Jamunali 31-Dec-19 GM, Hingula
OB: 10 M.Cum (27 to 33 R&R Site.
K/day)

d) Completion of Coal Corridor Road – Phase I & II 31-Jul-19 District Admn


Sl. Mine Critical Activities for achieving production target during 2019-20 Finish by date Responsibility
e Shifting of Hingula High School, Hingula College, Public Health Center & 30-Nov-19 District Admn
Police Outpost
Present Status
No development till now. Demanding job in Private
Security.
Dola Mandap, WBM Road, Peripheral Boundary wall
and main drain completed. Estimate for Overhead
tank for water supply prepared. Work for
construction of Anganwari,Pressure Filter and Bus
Stop will be tendered before 10.05.2019.

EMP has been uploaded on 30.04.2019. Now the


case is to be put up before EAC violation
committee for deliberation and approval.

Shifting will be done after completion of


Development work.

Excavator will be provided from Ananta OCP after


obtaining alternate site approval for Contractual
agency

PAFs are demanding complete development of R&R


Site, where boundary wall has been constructed &
only 100 meter is left and 19 encroachers are to be
vacated.

22 PAFs are demanding employment in subsequent


acquisition.

Shifting will be done after completion of Pond and


Crematorium at Gurjang R&R Site.Tender for the
same is to be opened on 08.05.2019

Area has to process for amendment of FC for


inclusion of 20.384 Ha.

To be decided in FDs Meet.

Scheme is awaited from CMPDI.

Area has to prepare Form-I for further


enhancement of 20% of EC.
Present Status
Two families (1. Biswal family 4.5 Acre) (2. Samal
family 4.0 Acre). Land compensation has been
granted and will be disbursed after completion of
Code of Conduct period for General Election. (After
23.05.2019). Both the families are demanding one
employment from each family.

Structure measurement is under process.

Tree falling for 700 Nos. completed.


Field work is going on, two holes failed, three holes
completed successfully, fourth hole drilling is going
on.
Present Status
Demanding additional compensation at par with
compensation paid to PAF who handed over the
land at later stage. Villagers also filed writ petition
at Hon'ble High Court of Odisha.

99% work completed, only grouting of Railway track


50 meters on both sides of the SILO is to be done.

RITES Part - About 56% track laying completed and


one ROB is under construction will be completed up
to 30th June19 . Railway Part - About 63% work
completed. PH-I, Out of 3 ROB and 1 Culvert, 1
ROB has been constructed, rest construction is
under process in PH-II Out of 3 R0B, EARTH WORK
COMPLETED for the 1st and for 2nd - earth work
has been started.

Estimate is under preparation stage at the Area


and will be submitted to MCL HQ upto 15th May.

177 cases have been finalisd by Tribunal. Out of


these, 35 persons have received compensation.
Remaining cases pending for want of Death
Certificates, Legal Heir etc.

Resettlement is pending for want of finalisation of


R&R site. Villagers of Patharmunda are not allowing
any development work and demanding
employment beyond norms.

Once again R&R site at village Takua need to be


considered for development in consultation with
State Administration. Further, two places within 15
Kms have been identified by the Area and Tahsildar
has been requested to submit his views.

CMPDI has been referred for making boundary


adjustment.
Land schedule under preparation
Present Status
Rs.76 Crores deposited to OPTCL.
Present Status
Action is being taken up for resolving the issues of
remaining 3 perons.

Next date of hearing fixed on 03.05.19

Pending at Supreme Court

Agenda not decided. Likely to be decided in next


EAC Meeting.
CMPDI has vetted the proposal and will be
submited to MCL HQ CMC deptt. on 07.05.2019

Supply Order for 11 Pay Loaders have been placed.


Likely to start supply after 15th May'19.

Land schedule has been prepared and will be


submitted to Tahsidar for vetting on 10.05.2019
Mining started in Forest patch - OB being dumped
in old quarry. For external OB dump 30 Ha forest
land tree counting completed and estimate has
been submitted to DFO for approval.

Employment issues of Danara villagers is pending at


Supreme Court. Development work at Kochianali
site will start after resolving the issue of Danara
villagers.

Issue related to Patna Sahi Cash Compensation for


386 families is at MCL HQ level for approval.
Estimate is under preparation stage at the Area.

Application has been done for EC amendment.


Decision will be taken in next EAC meeting.
Road diverted on 4th May 2019 night.
Land schedule under preparation.
Development work at Jamunali is under progress.
Retendering will be done for outer compound wall.

Work will be taken up with the help of District


Administration again after election.
Present Status
Shifting will be done after completion of Jamunali
R&R site.