Professional Documents
Culture Documents
17H00040 Status Report 3 25 19
17H00040 Status Report 3 25 19
17H00040 Status Report 3 25 19
PROJECT UPDATE:
On-going.
ation of Drainage (910mm & 1220mm dia RCPCs, Class IV) with a net
walk, Concrete Curb and Gutter, Manholes and restoration of the existing
n.
Cargo Truck-1
Backhoe - 1
1. Constant Reminder to the Contractor through meetings and
101(2) Removal of Actual Structures and Obstruction each 294,311.61 0.38% 0.00% 0.00% 80
101(4a) Removal of Actual Structures and Obstruction (RCPC) l.m. 588,564.10 0.77% 0.00% 0.00%
70
Removal of Actual Structures and Obstruction (Curb
101(4h) l.m. 735,658.00 0.96% 0.00% 0.00%
and Gutter)
Removal of Actual Structures and Obstruction,
101(6) m3 441,444.92 0.58% 0.00% 0.00%
Concrete
103(1)a Structure Excavation, Common Soil m3 882,796.48 1.15% 0.00% 0.00%
103(6)a Pipe Culverts and Drain Excavation (Common Soil) m3
2,443,739.12 3.19% 0.01% 0.00% 0.01%
60
104(1)b1 Embankment from Borrow (Common Soil) m3 2,969,377.28 3.87% 0.00% 0.00%
105(1)a Subgrade Preparation (Common Materials) m2 989,038.05 1.29% 0.00% 0.00%
200(1) Aggregate Subbase Course m3 683,824.44 0.89% 0.00% 0.00%
201(1) Aggregate Base Course m3 628,989.30 0.82% 0.00% 0.00%
50
301(1)b Bituminous Prime Coat-RC-Cut-Back Asphalt, Grade 70 m2 531,540.24 0.69% 0.00% 0.00%
302(1)a Bituminous Tack Coat-RC-Cut-Back Asphalt, Grade 70 m2 527,341.92 0.69% 0.00% 0.00%
502(2)c Inlets, type, 910 mm dia. each 3,705,555.20 4.83% 0.00% 0.00%
502(2)e Inlets, type, 1220 mm dia. each 1,430,985.00 1.87% 0.00% 0.00%
502(4)c Concrete Covers 910 mm dia. each 490,622.12 0.64% 0.00% 0.00% 20
600(1)a Concrete Curb, Cast in place l.m. 5,762,551.20 7.52% 0.00% 0.00%
10
600(2) Concrete Gutter, Cast in place l.m. 5,762,551.20 7.52% 0.00% 0.00%
Prepared by:
RACHEL L. LUMAPAS
Project Engineer
Upgrading/Rehabilitation of Drainage along National Roads-Secondary Roads, Mandaue Causeway (Ouano Ave).
100
90
80
70
60
50
40
30
20
10
0
0 APRIL MAY JUN JUL AUG SEP OCT
2017
APRIL MAY JUN JUL AUG SEP OCT NOV DEC
2.53 4.620 8.26 12.63 22.660 35.2 14.1
2.69 4.39 13.92 4
2.53 7.150 15.410 28.040 50.700 85.900 100.00
2.69 7.08 21 25 58.10 97.66 100
0.16 -0.07 5.590 -3.040 7.400 11.76 0.00
Submitted by:
JOSELITO P. SAYSON
OIC, Construction Division
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE VII
South Road Properties (SRP), Cebu City
PROJECT UPDATE:
Project is Ongoing
Road-Right-of-Way Problem On going acquisition of Road Right of Way by our Legal Division.
REMARKS:
A.1.1 (16) Operation and Maintenance of Field Office for the Engineer mo. 27.00
PART C EARTHWORKS
103(6)a Pipe Culvert and Drain Excavation, Common Soil) cu.m. 13,526.00
400(17)a24.1 Concrete Piles Cast in Drilled Holes (600mm dia.) l.m. 10,360.00
400(17)a24.2 Concrete Secant Pile Cast in Drilled Holes (600mm Dia.) l.m. 8,764.00
400(17)a3.1 Concrete Piles Cast in Drilled Holes (1000mm dia.) l.m. 2,736.00
400(17)a3.2 Concrete Secant Pile Cast in Drilled Holes (1000mm Dia.) l.m. 760.00
400(17)a5 Concrete Piles Cast in Drilled Holes (1200mm dia.) l.m. 1,008.00
500(1)b3 Pipe Culverts, 910mm dia, Class IV, RCPC l.m. 2,700.00
500(1)b5 Pipe Culverts, 1220mm dia, Class IV, RCPC l.m. 501.00
TOTAL
ork Development - New Construction of Flyovers/Interchanges/Underpasses
ructure at Intersection of U.N. Avenue and Plaridel Road, Mandaue City
711,815,378.35 100.00%
ACTUAL AMOUNT WTD%
1,058,908.03 0.149%
169,344.00 0.024%
900,275.41 0.126%
16,462.66 0.002%
1,040,376.96 0.146%
2,301,626.88 0.323%
2,809,938.78 0.395%
2,904,709.25 0.408%
- 0.000%
- 0.000% 105(1)a
- 0.000% sqm 3102.75
- 0.000%
- 0.000%
- 0.000%
- 0.000%
66,460.91 0.009%
- 0.000% 1+020.000
311(1)f1
- 0.000%
- 0.000% 311(1)f1
- 0.000% 1+204.500
- 0.000% 311(1)f1
- 0.000%
- 0.000% 1+290.000
- 0.000% 311(1)f1
- 0.000%
- 0.000% 1+340.500
- 0.000% 311(1)f1
- 0.000%
- 0.000% 1+200.000
- 0.000% 311(1)f1
- 0.000%
- 0.000%
1,480,231.48 0.208%
- 0.000%
696,127.39 0.098%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
- 0.000%
20,732,489.95 2.913%
0.126% 0.000%
0.000%
0.002% 0.000%
0.146% 0.000%
0.323% 0.000%
0.395% 0.000%
0.408% 0.000%
0.000%
0.000%
0.000% 0.000%
0.000%
0.000% 0.000%
1+375.500 85.5 0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000%
0.000% 0.000%
0.041% 0.167%
0.000% 0.000%
0.046% 0.052%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000% 0.000%
0.000%
2.913% 0.000%
6.187% 0.219%
Right side
(salvador ang
Left Side
open lot)
103(6)a Pipe Culvert and Drain Excavation, Common Soil) 3,816,529.03 0.536% 0.000% 0.000% 0.000%
104(2)a3 Embankment from Selected Fill (Engineered Fill) 12,592,093.25 1.769% 0.000% 0.000% 0.000%
105(1)a Subgrade Preparation, Commom Materials 863,188.48 0.121% 0.000% 0.009% 0.009%
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 13,584,941.89 1.908% 0.000% 0.158% 0.158%
207(1)a Portland Cement Treated Plant Mix Base Course, New Soil Aggregate 6,675,159.68 0.938% 0.000% 0.000% 0.000%
PART E SURFACE COURSE 60
60
311(1)a Portland Cement Concrete Pavement (Unreinforced), 0.15m thick, 14 days 1,966,748.45 0.276% 0.000% 0.000% 0.000%
311(1)f1 Portland Cement Concrete Pavement (Unreinforced), 0.30m thick, 14 days 55,265,467.04 7.764% 0.000% 0.484% 0.484%
311(2)f1 Portland Cement Concrete Pavement (Reinforced) - 0.30m thick, 14 days 23,888,899.69 3.356% 0.000% 0.000% 0.000%
PART F UNDERPASS CONSTRUCTION
400(17)a24.
Concrete Piles Cast in Drilled Holes (600mm dia.) 167,295,916.97 23.503% 0.000% 0.000% 0.000%
1 SUSPENDE
400(17)a24. D DUE TO
2
Concrete Secant Pile Cast in Drilled Holes (600mm Dia.) 70,447,134.82 9.897% 0.000% 0.000% 0.000% 50 DESIGN STAGE
50
RROW
400(17)a3.1 Concrete Piles Cast in Drilled Holes (1000mm dia.) 52,896,158.87 7.431% 0.000% 0.000% 0.000%
PROBLEMS
400(17)a3.2 Concrete Secant Pile Cast in Drilled Holes (1000mm Dia.) 12,081,432.29 1.697% 0.000% 0.000% 0.000%
400(17)a5 Concrete Piles Cast in Drilled Holes (1200mm dia.) 23,746,609.35 3.336% 0.000% 0.000% 0.000%
400(26)b Pile Integrity Testing (Low Strain) 6,664,896.00 0.936% 0.000% 0.000% 0.000%
400(27) High Strain Dynamic Testing (P.D.A.) 1,234,240.00 0.173% 0.000% 0.000% 0.000%
401(2)c Concrete Railing (Parapet) 6,812,777.44 0.957% 0.000% 0.000% 0.000%
404(1)b.3 Reinforcing Steel, Grade 60 61,366,077.91 8.621% 0.000% 0.000% 0.000% 40
40
405(1)b3.7 Structural Concrete, Class A, 28 Mpa, 28 days 19,765,374.91 2.777% 0.000% 0.000% 0.000%
502(1)a3.1 Curb, Inlet, Manhole for 910mmØ RCPC 1,760,792.77 0.247% 0.052% 0.046% 0.098%
502(1)a3.2 Grate Inlet Manhole for 910mmØ RCPC 1,824,687.42 0.256% 0.000% 0.000% 0.000%
502(1)a5 Curb, Inlet, Manhole for 1220mmØ RCPC 724,492.38 0.102% 0.000% 0.000% 0.000%
502(2)a7 Drain Drop Inlet Type 1 5,500,559.46 0.773% 0.000% 0.000% 0.000%
502(2)a8 Inlets, Curb Inlet Catch Basin 1,799,632.35 0.253% 0.000% 0.000% 0.000% 20
20
510(2)a Concrete Slope Protection, Shotcrete 6,113,463.55 0.859% 0.000% 0.000% 0.000%
517(2)d Drain Pipe (150mmØ PVC Pipe) 154,614.54 0.022% 0.000% 0.000% 0.000%
PART H MISCELLANEOUS STRUCTRES
600(1)a Concrete Curb (Cast in Place) 1,236,149.82 0.174% 0.000% 0.000% 0.000%
600(7) Curb and Gutter (Cast in Place) 2,118,118.24 0.298% 0.000% 0.000% 0.000%
601(1) Sidewalk (Concrete) 5,215,865.76 0.733% 0.000% 0.000% 0.000%
603(3)a1 Metal Guardrail (Metal Beam) including Post, Single, W-Beam 2,002,481.64 0.281% 0.000% 0.000% 0.000% 10
603(4)b1 Metal Beam End Piece 13,190.13 0.002% 0.000% 0.000% 0.000% 10
605 Regulatory and Warning Signs 1,444,093.28 0.203% 0.000% 0.000% 0.000%
612(1) Reflectorized Thermoplastic Pavement Markings - White 1,977,310.94 0.278% 0.000% 0.000% 0.000%
612(2) Reflectorized Thermoplastic Pavement Markings - Yellow
6.406
114,232.16 0.016% 0.000% 0.000% 0.000% 5.500
5.879 5.927 6.187
5.247 5.348
624(10) Roadway Lighting 10,763,612.16 1.512% 0.000% 0.000% 0.000% 4.800
1201(1) Water Pumping System including Pump House and Sump Pit 2,163,557.76 0.304% 0.000% 0.000% 0.000% 2.764 2.884
3.316
2.314
1 1.829
1102(16)a1 Generator Set including Power House 3,906,207.20 0.549% 0.000% 0.000% 0.000% 0 0.874
1.327
1 0.372
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33
PART L DETAILED ENGINEERING DESIGN 20,732,489.95 2.913% 0.000% 2.913% 2.913%
MONTH ### DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JULY AUG
ORIGINAL SCHEDULE ### 0.372 0.502 0.453 0.502 0.485 0.502 0.776 0.453 0.439 0.425 0.439 0.425 1.371 6.209 5.608 5.515 4.408 4.555 7.949 9.335 8.730 7.156 7.019 6.216 6.424 3.407 2.902 3.448 2.345 1.492 0.141
MONTHLY PROGRESS
REVISED SCHEDULE (CTE1) 0.388 0.502 0.453 0.502 0.485 0.502 0.788 0.439 0.439 0.425 0.439 0.425 0.332 0.000 0.683 4.854 4.698 4.98 4.949 5.15 8.156 8.727 9.211 9.02 8.109 6.638 6.21 4.148 3.09 2.107 1.714 1.352 0.085
ACTUAL ### 0.372 0.502 0.453 0.502 0.485 0.450 0.120 0.432 1.484 0.447 0.10 0.152 0.379 0.048 0.260 0.219
ORIGINAL SCHEDULE ### 0.372 0.874 1.327 1.829 2.314 2.816 3.592 4.045 4.484 4.909 5.348 5.773 7.144 13.353 18.961 24.476 28.884 33.439 41.388 50.723 59.453 66.609 73.628 79.844 86.268 89.675 92.577 96.025 98.37 99.862 100
REVISED SCHEDULE (CTE1) 0.388 0.89 1.343 1.845 2.33 2.832 3.62 4.059 4.498 4.923 5.362 5.787 6.119 6.119 6.802 11.656 16.354 21.334 26.283 31.433 39.589 48.316 57.527 66.547 74.656 81.294 87.504 91.652 94.742 96.849 98.563 99.915 100.00
CUMULATIVE PROGRESS
ACTUAL ### 0.372 0.874 1.327 1.829 2.314 2.764 2.884 3.316 4.800 5.247 5.348 5.500 5.879 5.927 6.187 6.406
SLIPPAGE 0 0 0 0 0 -0.052 -0.708 -0.729 0.316 0.338 0.000 -0.273 -1.266 -7.427 -12.775 -5.251
711,815,488.35
-
Prepared by: Submitted by:
A.1.1(8) Provision of Field Office for the Engineer(Rental ) mos. 8.03 8.00 11,912.46 95,299.68
B.7 Occupational Safety and Health Program mos. 8.03 8.00 29,886.81 239,094.48
101(1) Removal of Structures and Obstruction L.S. 1.00 0.60 588,575.91 353,145.55
101(2) Removal of Actual Structures and Obstruction each 241.00 114.00 1,221.21 139,217.94
104(1)b1 Embankment from Borrow (Common Soil) m3 7,424.00 2,636.09 399.97 1,054,356.12
500(1)b3 Pipe Culverts(910 mm dia.) Class IV RCPC l.m. 3,752.00 1,538.00 3,095.17 4,760,371.46
500(1)b5 Pipe Culverts, 1220 mm dia., Class IV RCPC l.m. 876.00 876.00 4,745.39 4,156,961.64
502(2)c Inlets, type, 910 mm dia. each 194.00 70.00 19,100.80 1,337,056.00
502(2)e Inlets, type, 1220 mm dia. each 50.00 42.00 28,619.70 1,202,027.40
502(4)c Concrete Covers 910 mm dia. each 194.00 70.00 2,528.98 177,028.60
502(4)e Concrete Covers 1220 mm dia. each 50.00 42.00 3,582.75 150,475.50
600(1)a Concrete Curb, Cast in place l.m. 4,760.00 2,480.00 1,210.62 3,002,337.60
600(2) Concrete Gutter, Cast in place l.m. 4,760.00 2,480.00 1,210.62 3,002,337.60
TOTAL 34,582,440.11
VALUE OF WORK ITEM ACTUAL ACCOMPLISHMENT
AMOUNT WTD% THIS MO. PREVIOUS TOTAL total ind. Perc