Professional Documents
Culture Documents
Corrib Onshore Pipeline:: Enhancing Safety
Corrib Onshore Pipeline:: Enhancing Safety
Corrib Onshore Pipeline:: Enhancing Safety
ENHANCING SAFETY
PIPELINE SAFETY
To ensure the safety and long-term 1. Design
integrity of a pipeline the following The pipeline must be designed for the key operating parameters of pressure,
flow rate and fluid to be transported.
key elements must be managed
effectively • Pressure
The normal operating pressure of the onshore pipeline will be 90 to 100 bar.
1. Design The maximum pressure in the pipeline onshore will be limited by the Landfall
Valve Facility to 144 bar. The pressure to which the onshore pipeline will be
2. Construction hydro-tested (strength tested using water as the test medium) is in excess of
3. Operation and Maintenance 500 bar. This provides a very significant margin of safety. As gas is produced
from the Corrib field and the gas reservoir is depleted, the operating
pressure will decrease and is predicted to fall to 60 bar after 4 years, further
The Corrib pipeline project is enhancing the margin of safety.
applying best industry practice to
• Flow rate
all of these aspects, with safety as The pipeline has been designed to transport 10 million cubic metres per day
its first priority. at a velocity of 6 metres per second equivalent to 22 kilometres per hour.
• Fluid
The onshore pipeline will contain natural gas, hydrocarbon liquids, water and
inhibitors that are injected at the wells. The inhibitors are used to protect the
internal wall of the pipeline against corrosion, and to prevent the formation
of gas hydrates, which can lead to pipeline or valve blockages.
The application of knowledge and experience gained over many years through
operating pipeline systems similar to Corrib will ensure the safe and stable
operation of the pipeline.
The design must also take into account the terrain to be traversed, soil 2. Construction
conditions such as stability and corrosivity and social factors such as land
use and housing. The construction of pipelines on land, whether in farm lands or bog, is
a routine activity for the construction industry. The way any pipeline is
In areas of deep peat proven construction techniques similar to those used constructed depends to a large extent on soil conditions and terrain.
by Bord Gáis Eireann for the Mayo Galway pipeline will be used to make sure The geophysical and geotechnical characteristics of the route will be
the pipeline is stable. investigated and assessed before construction takes place. The construction
methodologies proposed for the onshore pipeline will be described in the
The pipeline will be routed in compliance with separation distances specified Environmental Impact Statement (EIS) submitted with the upcoming pipeline
in the relevant Irish and international pipeline design codes. A quantified risk consent applications, which will be the subject of public consultation during
assessment of the onshore pipeline carried out by Advantica on behalf of the the application process.
then Minister for Communications, Marine and Natural Resources in 2005,
confirmed that the risks associated with the Corrib onshore pipeline are
acceptable according to international norms.
3. Operation and Maintenance
The onshore pipeline will have an outside diameter of 508mm / 20” and
wall thickness of 27.1mm. To put this in context, the pipeline linking the ring The offshore and onshore sections of the pipeline will be protected against
main in Galway to the terminal at Bellanaboy has an outside diameter of internal and external corrosion throughout the lifetime of the operation. In
660mm / 26” and is 9mm thick. The Corrib pipeline has been fabricated order to prevent internal corrosion, inhibitor chemicals will be continuously
from high-grade carbon steel and will be capable of safely transporting the injected into the pipeline at the offshore gas wells. The inhibitor will be
gas from the gas field to the terminal. pumped out to the wells via a small pipeline, which is incorporated into a
group of service pipes and cables referred to as an umbilical, and is linked
to the terminal.
The outside of the pipeline will be protected by a polypropylene
thermoplastic coating, as well as an impressed voltage system. Monitoring
tools and techniques will be used to gather data to allow regular assessment
of the internal and external condition of the pipe and to ensure its integrity
throughout the lifetime of the operations. Pipeline inspection tools that travel
through the pipeline will be used to inspect the condition of the pipeline.
The Advantica Independent
Safety Review
In August 2005, the Minister for The Corrib Gas Partners’
Communications, Marine and Natural response to the Safety Review’s
Resources commissioned a consultant recommendations
company, Advantica, to carry out an
Independent Safety Review to address
Pipeline Pressure:
concerns expressed by local residents
Advantica recommended a system to ensure that the onshore pipeline
regarding the safety of the onshore pressure could not exceed 144 bar, suggesting this to be a practical and
section of the Corrib gas pipeline. effective measure to reduce risk in light of societal concerns that had
been expressed.
The findings of this review were published in early May 2006 and In response to this recommendation The Corrib Gas Partners have designed
concluded that: “proper consideration was given to safety issues in the a Landfall Valve Facility, which automatically shuts off the pressure from
selection process for the preferred design option and the locations of the offshore in the very unlikely event that the pressure in the onshore pipeline
landfall, pipeline route and terminal”. should rise towards 144 bar.
sea bed -
approx 350m below sea level PIPELINE
2 manifold
wellhead wellhead
wellhead
Normal Operator Control: Routine control adjustments from the control room.
Non-routine Operator Control: Alarm indicates to Operator that pressure is rising above the normal range and will go to automatic
closure if corrective control is not initiated.
FIG 1.0
(NOT TO SCALE)
Controlling the pressure onshore:
the Landfall Valve Facility
Background How it works
The original pipeline design for the Corrib project included an onshore The Landfall Valve Facility will function as follows (See Fig 2.0):
isolation valve located at the landfall. This was intended to allow the
onshore section of the pipeline to be isolated manually from the offshore • Three pressure sensors/transmitters, located at the landfall valve
section – for instance if maintenance was needed. In response to facility, continuously measure the pressure in the pipeline.
Advantica’s recommendations, the Corrib Gas Partners have undertaken
• If the sensors detect the gas pressure increasing above a certain
to install an automatic Landfall Valve Facility where the Corrib pipeline
level, they send a series of ‘trip’ signals to a ‘control unit’.
comes ashore.
• The control unit in turn commands the two shutdown valves to close.
The Landfall Valve Facility in brief • The flow in the pipeline stops, ensuring that the pressure on the
onshore side does not rise any further.
The Landfall Valve Facility is a system that will shut off the flow of gas
automatically in the very unlikely event that the pressure in the pipeline This function is automatic and requires no human intervention. In the
rises towards 144 bar at the landfall. When activated, the shut-off valves case of a control system malfunction or a loss of signal, the valves will
close, resulting in complete isolation of the onshore section from the also close automatically.
offshore section of the pipeline. The pressure in the onshore pipeline The pressure in the production system from the wells to the terminal will
cannot rise above 144 bar. be controlled such that this safeguarding system should never have to
The Landfall Valve Facility will be located at the landfall in Glengad, (See operate. The system will be tested on a regular basis, typically with a full
Fig 1.0) about 50 metres from the edge of the cliff. It will consist of a test once a year and partial tests of different components several times
number of valves in the pipeline system, located below ground, together a year.
with some supporting equipment that will be placed above ground. To
minimise visual impact the ground level of the installation will be lowered
into the landscape in this area ensuring that very little of the facility will ProgressING the Landfall Valve Facility
be visible from the public road.
The Landfall Valve Facility will form a part of the modified onshore
pipeline system, which requires consent from An Bord Pleanála under the
Strategic Infrastructure Act, and from the Minister for Communications,
Energy and Natural Resources under the Gas Act.
control unit
v3 v4
shutdown valves
v2
Maintenance
isolation valve
v5
Maintenance
isolation valve
v1
mainline PT
isolation valve
PT
PT
PT V1 V2 & V5
Pressure sensors. Measure the pressure Mainline isolation valve. Closed during Maintenance Isolation Valves. Open
in the pipeline normal operation during normal operation, closed when
maintenance of the shutdown valves is
Control Unit V3 & V4 required.
THE Control Unit sends signals to Shutdown valves. Will close automatically
shutdown valves to close them when when pressure approaches 144 bar
pressure approaches 144 bar
FIG 2.0
(NOT TO SCALE)
Landfall Valve Facility:
Questions & Answers
Some of the most frequently asked What back up plans are in place if the valves fail
questions on the Landfall Valve Facility to limit the pressure?
are outlined below. The valve itself is a backup system, which will only come into operation
in very exceptional circumstances, for example if the terminal has to be
shut down for any reason, in combination with the valves in the Corrib
Field failing to operate as they should. The valve system will be designed
with several layers of redundancy (safety), to make sure that the onshore
pipeline system never experiences pressures above 144 bar.
It should be noted that the onshore pipeline was originally designed to
withstand the highest occurring wellhead pressure, and that it will be
tested to over 500 bar before the system is taken into operation. Thus, in
the extremely unlikely event that all the above systems fail, the pipeline
will contain the pressure and no gas will escape. The new design will
have the pipeline rated at 144 bar, with a design factor of 0.3 which is
the factor used for suburban areas.