Concurrent delays does not bar extension of time, but it does bar monetary
compensation for daily fixed overhead costs
of the type claimed because such cost would be incurred on account of the concurrent delays even if Engineer/PM/Client responsible delay had not occured.
We would not have been able to carry out the works anyway because of own default, notwithstanding with failure to obtain fencing permit and shoring design approval/permit.