CTP 11 - Status of Minor Bridges 17-03-2019
CTP 11 - Status of Minor Bridges 17-03-2019
Minor
101 87A 33+430 1 x 6.1 PSC Slab Construction Methodology required NOO
Bridge
Minor
130 121A 52+190.35 1 x 1.5 x 2 RCC Box Construction Methodology required NOO
Bridge
Minor
131 121B 52+746.45 2 x 1.5 x 2 RCC Box Construction Methodology required NOO
Bridge
Minor
132 121C 52+942.55 1 x 1.5 x 2 RCC Box Construction Methodology required NOO
Bridge
Minor
135 124A 55+747.26 1 x 5 x 3 RCC Box Construction Methodology required NOO
Bridge
Minor
136 124 55+912.24 1 x 5 x 3 RCC Box Construction Methodology required NOO
Bridge
Minor
137 125A 56+054.61 1 x 1.2 x 1.2 RCC Box Construction Methodology required NOO UR
Bridge
Minor
140 125 56+461.14 1 x 3 x 1.5 RCC Box Construction Methodology required NOO
Bridge
Minor
141 126A 56+564.93 1 x 1.2 x 1.2 RCC Box Construction Methodology required NOO GFC
Bridge
Minor
146 127D 59+678.02 1 x 3 x 2 RCC Box Construction Methodology required NOO
Bridge
Minor
147 128A 59+713.4 1 x 3 x 1.5 RCC Box Construction Methodology required NOO
Bridge
Minor
149 128C 59+923.85 1 x 1.2 x 1.2 RCC Box Construction Methodology required NOO UR
Bridge
Minor
151 129 60+570.11 1 x 2 x 2 RCC Box Construction Methodology required NOO GFC
Bridge
CTP 11 - STATUS OF MINOR BRIDGES 17-03-2019
DFC Proposed Span
Bridge Structure Type of
Chainage arrangement Status GAD Design
S.No No Config. Bridge
(kM)
No Size (m) Present status Present Status
Minor
152 130A 60+951.4 1 x 3 x 2 RCC Box No GFR NOO
Bridge
Minor
153 130 61+139.08 1 x 3 x 2 RCC Box No GFR NOO
Bridge
Minor
154 131 61+437.64 1 x 1.2 x 1.2 RCC Box No GFR NOO NOO/UR(GFC)
Bridge
Minor
156 132B 62+021.76 1 x 5 x 3 RCC Box No GFR NOO
Bridge
Minor
157 133A 62+526.42 1 x 3.5 x 1.2 RCC Box No GFR NOO NONOC(UR)GFC
Bridge
Minor
158 133B 62+627.55 1 x 1.2 x 1.2 RCC Box No GFR NOO UR
Bridge
Minor
162 134A 64+364.72 1 x 3 x 1.5 RCC Box Construction Methodology required NOO
Bridge
Minor
163 134B 64+505.1 1 x 3 x 1.5 RCC Box Construction Methodology required NOO
Bridge
Minor
164 135A 65+650.18 1 x 3 x 1.5 RCC Box Construction Methodology required NOO
Bridge
Minor
166 137A 66+670.16 2 x 3.2 x 3 RCC Box Construction Methodology required NOO
Bridge
Minor
167 137B 66+928.08 1 x 1.2 x 1.2 RCC Box Construction Methodology required NOO GFC
Bridge
Minor
173 140B 70+907.72 1 x 5 x 4 RCC Box Construction Methodology required NOO UR
Bridge
Minor
176 141C 72+240.69 1 X 1.2 x 1.2 RCC Box Construction Methodology required NOO UR
Bridge
Minor
178 143A 74+500 1 x 3.2 x 1.2 RCC Box Construction Methodology required NOO
Bridge
Minor
179 144 74+963.07 2 x 3.5 x 1.5 RCC Box Construction Methodology required NOO
Bridge
Minor
183 146C 77+411.99 1 x 3 x 4 RCC Box Construction Methodology required NOO
Bridge
Minor
184 146D 78+058.56 1 x 1.2 x 1.2 RCC Box Construction Methodology required NOO UR
Bridge
Minor
185 147A 78+457.12 1 x 3 x 1.2 RCC Box Construction Methodology required NOO
Bridge