Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

1/16/2019 21 Primavera Tips and Shortcuts

21 PRIMAVERA TIPS AND


SHORTCUTS

1.    SPOT OPEN ENDS IN THE ACTIVITY NETWORK

An important health check to perform before issuing a schedule is to remove open ends in the activity network. A good
starting point is to look for the list of activities without predecessors/ successors in the Scheduling/Leveling Report, which
can be accessed from the Schedule window (F9 or Tools >Schedule>View Log). A sample of this section of the report is
shown below:

Figure 1.1 – Scheduling/Leveling Report


Note that open ends are also generated by activities whose i) only predecessor relationship is a finish-to-finish link or ii)
only successor relationship is a start-to-start link. This check can be performed manually within P6 by looking at
relationship lines on the Gantt chart or looking at predecessors/ successors in the Activity Details window; or through the
Schedule Check utility available in Primavera Risk Analysis, or other schedule analysis software with similar capabilities.

2.    PROJECT-LEVEL SETTINGS: USING THE DEFAULTS TAB

The Defaults tab under project settings can save you a lot of time if you need to add multiple activities with the same
calendar, duration type, percent complete type, activity type, cost account and/or even a given ID structure. In other
words, there is a way you can pre-assign a given value to each of these settings for all new activities you insert to the
schedule, eliminating the need to edit them on a per-activity basis, after you’ve added the new tasks.
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 1/20
1/16/2019
In order to do this, go to the Projects window, select the21project
Primavera Tips and
you’re Shortcutson and then locate the Defaults tab at the
working
bottom of the screen, where the Project Details are displayed. If the Defaults tab is not visible, make sure you right-click
anywhere in the Project Details area, choose “Customize Project Details” from the drop-down menu and move Defaults
to the Displayed Tabs list on the right. Once you access this tab, you’ll be able to select pre-determined values for all the
parameters mentioned above.

3.    RENUMBER ACTIVITY IDS

Although P6 is more flexible than P3 when it comes to changing activity IDs, making edits for multiple activities can be
cumbersome- especially if you’re dealing with, say, more than 10 activities or even worse: renumbering an entire
schedule. In order to re-number multiple activities, all you need to do is highlight the line items whose IDs you need to
update, right-click and select “Renumber Activity IDs”. You will then be prompted to i) define an increment value, ii) define
prefix/suffix or iii) replace characters in the current numbering structure of the selected activities.

For example, let’s assume you have a group of activities belonging to 2 different phases of your project and whose IDs
are entirely numeric. If you needed to update their IDs to reflect the phase each line item belongs to through an
alphanumeric ID, you’d do the following:

a) Highlight all activities occurring during phase 1 of the project, as shown in Figure 3.1 below.

Figure 3.1 – Select Activities


b) Right-click, choose “Renumber Activity IDs” and check the “Auto-number” option.

c) Pick a prefix such as “PH1-”, a suffix “1000” and an increment value of 10. Click Ok to see the updated codes for your
activities (ie: PH1-1000, PH1-1010, PH1-1020, etc), as shown in Figure 3.2 and Figure 3.3 below.
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 2/20
1/16/2019 21 Primavera Tips and Shortcuts

Figure 3.2 – Renumber Activity IDs Parameters

Figure 3.3 – Updated Activity IDs for Selected Activities


d) Proceed in the same way for phase 2 activities, using “PH2-” as prefix to denote they belong to phase 2.

4.    FILL DOWN INFORMATION

You can use this command to quickly copy WBS and Activity Code values (as well as almost any parameter that can be
displayed as a column in the Activity Table) from one activity into other activities in the schedule. For instance, if you’d
like to change the calendar for multiple activities, you need to:

a) Display the Calendar column in the Activity Table, as shown in image 4.1 below.
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 3/20
1/16/2019 21 Primavera Tips and Shortcuts

Figure 4.1 – Display Calendar Column in Activity Table


b) Change the calendar ID of the first activity in the range to the desired calendar.

c) Highlight all the activities that you need to update calendars for. Note that the activities you select don’t need to be
listed consecutively in the Activity Table (ie: gaps in the range are allowed as well). Also, ensure that the cell containing
the desired calendar ID (ie: the value that will be copied onto the rest of the activities in the highlighted range) is the first
item in that selection, as shown in image 4.2 below.

Figure 4.2 – Activity Selection

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 4/20
1/16/2019
d) 21 Primavera
Click Edit>Fill Down, press Ctrl+E, or right-click on the range and Tipsselect
and Shortcuts
Fill Down. The calendar for all activities in the
highlighted range will be updated to match that of the first cell in the range, as shown in Figure 4.3 below.

5 DISABLE AUTO-REORGANIZATION

If you’re using a layout that groups activities by a certain parameter (eg: WBS, calendar or a particular activity code),
editing the value of this parameter for multiple activities can become a cumbersome task. Why? Because every time you
update this information for one activity it automatically gets moved to its new “location” in the schedule, forcing you to
make edits on a per-activity basis.

This problem can be easily avoided by disabling the auto-reorganization option, which you can access through the
corresponding button in the “Tools” toolbar, or the Shift+F12 hotkey. This way, you can work on editing the values of a
particular parameter at the activity table level without any of your activities moving around until you’re done making
changes. This can be particularly helpful if you’re using the Fill Down tool to copy information from one activity into
multiple activities.

6 UPDATE PARAMETER VALUES FOR ALL ACTIVITIES IN THE


SCHEDULE

There are several data fields and activity settings than can be edited at once for all the activities in your schedule through
P6’s Global Change tool. In order to access this feature, click the Tools menu, and select Global Change. You will be
prompted to create or modify an existing rule.

For instance, let’s assume you’d like to change the percent complete type for all activities in the schedule from Duration
to Physical. After adding a new Global Change, you’d need to select “Activities” in the subject area (note that you can
also implement global changes on resource assignments and project expenses), and then create a rule for P6 to apply
across the schedule, as shown in Image 6.1. This rule is set up as follows:
-Box #1: If Parameter “Percent Complete Type” equals “Duration”.
-Box #2: Then Parameter “Percent Complete Type” equals “Physical”

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 5/20
1/16/2019 21 Primavera Tips and Shortcuts

Figure 6.1 – Modify Global Change


Next, click the Ok button and select “Apply Change”. You will see a log with all the proposed changes, as shown in
Figure 6.2 below. Finally, click “Commit Changes” to update all parameter values to the new values.

Figure 6.2 – Global Change Report


Note that you can add multiple rules and use two logic operators (ie: apply changes if “any” or “all” of the rules created
apply) to customize the Global Change you’re trying to implement. In this case of this tip, we only used a single rule; but
the tool can clearly be utilized to implement more intricate and complex changes to the schedule.

7 CHANGE TIME UNITS & DATES FORMAT


https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 6/20
1/16/2019
In order to control the way in which these values are 21 Primavera
shown Tips system,
in the and Shortcuts
you may click Edit>User Preferences, and
navigate between the Time Units (Figure 7.1) and Dates (Figure 7.2) tabs on the left-hand side of the User Preferences
window. For instance, this comes in handy when engaging in higher-precision scheduling efforts, which could require
tracking activities down to the hour. Conversely, you could set units to weeks, months or even years if you’re working on
less-detailed, higher-level schedules.

Figure 7.1 – User Preferences, Time Units Tab


Figure 7.2 – User Preferences, Dates Tab

As you adjust the settings on the Units Format window, you can see the resulting format on the right-hand side of the
window, within the “Example” boxes. Similarly, changes made to the date format can be visualized at the bottom of the
“Dates” window, in the “Sample” box.

8 EXPORT TO EXCEL

Unlike P3, Primavera P6 allows you to export information directly into a spreadsheet by copying and pasting the desired
information, just like you would do on any other program. To export the entire Primavera Schedule, press Ctrl+A to select
all the information displayed on the Activity Table; then press Ctrl+C to copy and Ctrl+V to paste directly to spreadsheet.
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 7/20
1/16/2019
Alternatively, 21 Primavera
you can always stick to the traditional method Tips and Shortcuts
by i) right-clicking on your selection and choosing “Export to
Excel” or by ii) clicking File>Export, and choosing the Spreadsheet (xls) option.

9 COMPARE SCHEDULES WITH CLAIM DIGGER

Have you ever lost track of the changes made from one schedule revision to another, or needed to put together a
comprehensive variance report? In these cases, the Claim Digger utility that comes with Primavera P6 can be particularly
useful.

In order to run the Claim Digger utility, all you need to do is go to the Tools menu, and click “Claim Digger.” You will then
be prompted to pick 2 files: one for the original project (or baseline) and another containing the revised project, as shown
in Image 9.1 below. Click compare and you’ll get a comprehensive report of all the differences between both schedules
from durations, float and logic to activity additions/deletions and WBS changes.

Image 9.1 – Select Revised Project and Baseline

10 BULK IMPORT FROM EXCEL

Have you ever done a significant amount of work in Excel as part of the initial planning process for your project (eg:
define WBS, activities, activity codes, etc.), and needed to find a way to incorporate all the information without having to
create activities one by one? This is where the Import function comes in handy. All you need to do is go to File> Import>
Spreadsheet – (xls), and choose the file containing the information you’d like to import.

It’s very important to make sure your spreadsheet follows a specific format that Primavera P6 can read and import.
Therefore, it’s a good practice to create a template first, which you’ll then dump your data on and import. In order to do
so, simply go to File> Export and check the Activities box in the Export Type window. You will be prompted to select the
fields (ie: columns) that you’d like your Excel template to display. This can include activity ID, name, durations, WBS
activity codes and even other information such as predecessors/ successors, resources, etc., as shown in Figure 10.1.
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 8/20
1/16/2019
Once 21 Primavera
you’ve picked your columns, you can export the template Tipssave
and and Shortcuts
to a known location. You can now open the file
and dump your data into the columns you selected. Save the updated template, and proceed to import as instructed
above.

Figure 10.1 – Modify Template

11 OPEN MULTIPLE SCHEDULES SIMULTANEOUSLY

When deciding on the granularity and level of detail of your schedules, remember that P6 allows you to work on several
projects at the same time and created logic ties between them. This feature gives you the flexibility to split the work into
multiple, smaller schedules, without compromising the articulation between them.

For instance, given the magnitude of a particular project, you may decide that it’s better to create multiple sub-schedules
that feed into a master schedule by establishing ties between the former’s more granular items, and the latter’s higher-
level, summary milestones and activities. Cross-project ties can be created by opening multiple schedules at a time, and
proceeding to assign links as though you were working on a typical, larger schedule. To open multiple projects
simultaneously, simply go to the EPS, hold the Ctrl key to add the desired projects to your selection, and press Ctrl+O.

12 SCALE TO SINGLE-PAGE WIDTH

This simple, yet useful tip will spare you the (quite recurrent) pain of seeing your schedules printed on more than 1 page
wide (ie: “horizontally” split in 2 or more parts). To scale your project so it doesn’t exceed a width of 1 page, click Print
Preview>Page Setup. Make sure you do this from the Activity List view (not EPS). Then, select “Fit Timescale To” and
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 9/20
1/16/2019
make 21 Primavera
sure “1” is selected, as shown in Figure 12.1. Similarly, youTipsmay
and Shortcuts
choose the “Fit To” option and enter the same
value. In this case, however, you’ll also be prompted to fit the schedule to a given number of pages tall.

Figure 12.1 – Page Setup

13 CREATING LOGIC TIES IN THE ACTIVITY NETWORK

When developing the logic for your schedule, remember links can be created in three ways, which you can use to
expedite your workflow:
1) Visually: by clicking and dragging your cursor from one bar to another in the Gantt chart.
2) At the Activity Details level: by going to the predecessors and successors tabs in the activity details window and
adding activities to each list.
3) At the Activity Table level: by highlighting the activities you need to connect, right-clicking on the selection, and
choosing the “Link Activities” option.

14 QUICKLY SEQUENCE ACTIVITIES IN ANY ORDER

Linking activities at the Activity Table level is a very powerful tool for creating logic ties (more so than the visual or activity
detail methods). A very useful tip when creating chains of activities is to highlight as many activities as needed in the
order in which they are to be sequenced. After doing so, just right-click the selection and choose “Link Activities” from the
drop-down menu. After running the schedule, you’ll see that they follow the order in which they were highlighted when
creating the links, as opposed to the order in which they were originally listed in the activity table (ie: by activity ID,
alphabetically, by WBS or any other criterion). Images 14.1 through 14.3 illustrate these steps:

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 10/20
1/16/2019 21 Primavera Tips and Shortcuts

Image 14.1 – Activity Set Without Logic Ties

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 11/20
1/16/2019 21 Primavera Tips and Shortcuts

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 12/20
1/16/2019 21 Primavera Tips and Shortcuts

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 13/20
1/16/2019 21 Primavera Tips and Shortcuts

Image 14.2 – Activity Selection in Desired Order

Image 14.3 – Final Activity Sequence

15 IMPORT A NEWER XER FILE INTO AN OLDER VERSION OF P6

Primavera returns an error message when trying to import a XER file created in a newer version of P6 (for example,
when trying to open a P6 15.0 file from P6 8.3). In order to solve this problem, simply follow these steps:

a) Open the XER file you’re trying to import using Notepad.

b) Locate the second string of characters (or “word”) on the very first line (or “sentence”) of the document, as shown in
Image 15.1 below. This is where the file version is specified.

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 14/20
1/16/2019 21 Primavera Tips and Shortcuts

c) Edit this number to match your version of P6. In this example, you’d replace “15.0” by “8.3”.

d) Save the file. Make sure the extension remains as .XER and is not changed to .TXT.

e) Import the updated XER file.

16 REPORTING PROJECT VARIANCE

Maintaining and Assigning baselines is a very useful P6 feature that allows you, amongst other things, to easily report
variances across different schedules. All you need to do is to add the project against which you’d like to compare your
current schedule to, and then add variance columns to the activity table displaying the desired changes in the schedule.

First, pick your baseline(s) by going to Project>Maintain Baselines (see Image 16.1). Here you’ll be able to choose from
your other projects in the EPS, or save a copy of the currently open file to serve as one. Each baseline can be named
and assigned a baseline type (ie: initial planning baseline, customer sign-off baseline, etc.). Once you have a list of
potential baselines (or target/ reference projects to compare your current schedule to), you can go to Project>Assign
Baselines (see Image 16.2). A window will pop up and you’ll be asked to select a project baseline, as well as up to three
user baselines (primary, secondary and tertiary).

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 15/20
1/16/2019 21 Primavera Tips and Shortcuts

Image 16.1 – Maintain Baselines

Image 16.2 – Assign Baselines


The last step is to have P6 display the calculated variances for you. To do this, simply add columns to the activity table
(right-click> columns) and pick the variance-related fields that best suit your reporting needs. Options include columns
like “Variance – BL Project Duration” and “Variance – BL Project Labor Cost”.

17 CREATING CUSTOM UNITS OF MEASURE

By default, Primavera has only a few options to choose from when it comes to defining and assigning Units Of Measure
(UoM) for material resources in the schedule. This is a very common issue that you might encounter in virtually every
project you work on, as materials (and therefore their units) can widely vary depending on project type, cost-
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 16/20
1/16/2019
management 21 Primavera Tips and Shortcuts
requirements, measuring conventions, etc.

For example, when looking through a construction budget you might see that timber matting is measured by square foot;
while on a similar project its UoM can be square yards– a unit that might not be available by default in P6. Similarly,
activities such as seeding and stabilization might require an area UoM other than the traditional square foot, such as
acres.

In order to create custom UoMs, go to Admin>Admin Categories. On the Admin Categories window, go to the Units of
Measure tab. Select “Add” and assign your custom unit an abbreviation and name. The new UoM will be listed in the
dropdown menu when creating or modifying material resources, as show in Image 17.1 below.

Image 17.1 – Admin Categories, Units of Measure

18 RULE OF THUMB: LONGEST PATH VS TOTAL FLOAT <= 0

You may have noticed that P6 offers two criteria for determining the critical path in your schedule (F9 hotkey>Schedule
Options): i) Total Float Less Than Or Equal To (typically zero) and ii) longest path. While both can yield the same results
under certain conditions, most times critical paths can differ dramatically when calculated under one criterion over the
other. Below are a few notes that will help you decide which of the 2 to use.

The intent of the Critical Path Method (CPM) is to allow you to obtain total project duration by finding the longest
sequence (ie: “path”) of activities from project start through completion. If we’re working on a schedule baseline, then
both methods will lead to the same result. In other words, activities in the longest path will also be those with zero total
float (TF). This continues to hold even when we add constraints to our baseline to account for intermediate and final
project deadlines (eg: building dried-in, substantial completion and final completion milestones); as by definition, a
baseline shows no delays and hence no negative float.
https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 17/20
1/16/2019
Now, 21 Primavera
let’s assume we update the schedule and find that there is Tips and Shortcuts
a delay relative to the original completion deadline, as
well as some of the intermediate milestones we incorporated earlier into the baseline. As you may expect, these
unsatisfied constraints generate negative TF values. Evidently, each of the 2 critical path calculation criteria will yield
completely different results this time around. The Total Float Less Than Or Equal To (zero) method will include any
activity with a negative TF value; while the Longest Path method will continue to show the longest progression of
activities leading to project completion.

This means that, if a 100-activity schedule is delayed and 80% of its activities have negative TF values, then the critical
path determined through the first method will be comprised of 80 line items, and will not necessarily let us distinguish
which activities have an impact on the current project completion forecast. The Longest Path option, on the other hand,
will continue to show only the activities that drive our current completion date and keep the list of activities considered
“critical” to a minimum.

In conclusion, the Total Float Less Than Or Equal To rule is valid for calculating total project duration (ie: the longest
sequence of activities leading to your project completion milestone) as long as you don’t have unsatisfied constraints
generating negative TF values. However, chances are you’ll be in the latter scenario most of the time, as you’ll for sure
need to add constraints to your schedule; let alone update it on a regular basis and probably even show delays on more
than one occasion. In these cases, the Longest Path option would be the recommended setting for calculating total and
remaining project duration.

19 IMPORT & EXPORT LAYOUTS

Setting up layouts can be a cumbersome task, especially if you have to replicate someone else’s layout to make sure
you’re looking at the same report and data, or just to be consistent with reporting formats. You can save you and your
team a lot of time by setting up a layout (ie: report) once, exporting it and having the people involved in the project import
it without having to re-create it on their own every time you send them a schedule.

To do this, go to View>Layout>Open and select the layout that you’ve previously set up for your project. Once you select
“Export,” you’ll be prompted to specify a location for the .plf file (Primavera Layout File) that was just created. That is the
file that you should send to anyone who needs to see the schedule under the specific format (ie: layout) that you’ve
created.

Similarly, when the recipients of the .plf file have already opened the schedule, all they need to do is go to the same
menu and select “Import” this time (View>Layout>Open; Import). Once they’ve imported it, it will be listed on the Open
Layout list for them to use.

20 EXPORT FILTERS

Similar to Layouts, Filters can be exported for the same reason: making sure everyone involved in the project is able to
see the same data, and save time to set up complex and sophisticated filters. P6, however, doesn’t have an option to
directly export a filter as an isolated element. Instead, you’ll need to incorporate it to a layout and export it as part of the
layout.

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 18/20
1/16/2019
Once 21 Primavera
you’ve created a layout and a filter, open the Filters window. Tips and can
This Shortcuts
be accessed by right-clicking on the activity
table and selecting Filters, pressing the funnel icon on the toolbar or by clicking View>Filter By>Customize. Once there,
select the desired (ie: previously created) filter from the list and press the Copy As Layout button, as shown in Image
20.1 below.Now the filter will be listed under “Layout Filters”, and will be exported together with the current layout (ie: the
layout that you previously created and which you wish to send to your project team).

Image 20.1 – Filters, Copy As Layout

21 A D D I N G G R A N U L A R I T Y T O YOUR SCHEDULE WITHOUT


BUMPING UP ACTIVITY COUNT

One of the advantages of adding more detail to a schedule is that it allows for finer progress tracking. In other words,
reporting status on a deliverable that is represented by more than 1 activity in the schedule can be a more structured,
traceable and overall reliable process than for a single-line-item one.

For instance, think of the effort associated to preparing as-built drawings during the closeout phase of a project. This can
be either incorporated to the schedule as a single item representing all work from final as-built survey through record
drawing set approval; or it can be broken down into the smaller tasks (or “steps”) implied by this effort. At the same time,
however, the latter can result in an unnecessary number of new activities which can make your schedule unmanageable
and very cumbersome to update.

If you’ve been faced with this dilemma, fortunately you can get the best of both worlds by using the Activity Steps feature.
This option allows you to create sub-tasks (namely, “steps”) for the activities you need to track more closely without the
need to break them down into separate, smaller activities. In order to do this, select the activity you need to create steps

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 19/20
1/16/2019
for. 21 Primavera
Then, go to the Steps tab located in the Activity Details windowTipsand
and Shortcuts
define the sub-tasks required for this activity as
shown in Figure 21.1.

Image 21.1 – Activity Details (Steps Tab)


As shown above, you can record progress under each Activity Step, and even assign weights to drive overall activity
progress calculation. If the latter is the case and you’d like P6 to do this automatically for you, make sure to activate the
“Activity Percent Complete Based on Activity Steps” setting. This option can be found under the Calculations tab at the
project-level settings, as shown in Figure 21.2 below:

Image 21.2 – Project-Level Settings


(Calculations Tab)

Chicago (http://www.viatechnik.com/chicago-office)
New York (http://www.viatechnik.com/new-york-office)
Philadelphia (http://www.viatechnik.com/philadelphia-office)
Phoenix (http://www.viatechnik.com/phoenix-office)
San Francisco (http://www.viatechnik.com/san-francisco-office)
Asia (http://www.viatechnik.com/asia-pacific-office)


Site map (http://www.viatechnik.com/Sitemap/)

(https://www.linkedin.com/company/2705791)

© 2016 VIATechnik LLC All Rights


Reserved

https://www.viatechnik.com/resources/21-primavera-tips-shortcuts/ 20/20

You might also like