Professional Documents
Culture Documents
Lecture 12-14 2014
Lecture 12-14 2014
• Development started in
Probabilistic production cost the late 1960:th
simulation of electricity • Analytical calculations
markets – L12 • A fast method but
limitations concerning
Lennart Söder
Professor in Electric Power Systems
possibilities to include
market details.
1 2
3 4
Calculation of system index Calculation of system index
- Basic idea - Basic idea
LOLP = LDC(600) = 876 h/year = 10%
5 6
7 8
Load model Load model – Alternative 2
• How to determine the load duration curve? • Definition 6.11. The load curve, D(k),
• It can not be calculated but it has to be states the mean load per hour during a
estimated from historical data and specified time period: k = 1, …, T.
forecasts. D(k) = load hour k [MWh/h]
9 10
day day
The expected value of the load corresponds to the area below the curve The area below the real LDC is as large as the area below the load curve
11 12
Load model – Alternative 2 Load model – Alternative 2
13 14
The area is now changed since the y-axes is divided with T. To get the
correct expected value, the area has to be multiplied with T.
15 16
Load model – Practical aspect Thermal power station model
The model of the thermal power stations
include:
• Installed capacity,
• Production cost,
This means that we assume that the
incremental production cost is independent
of the production level, i.e., constant
efficiency.
• Availability,
17 18
19 20
Thermal power station model Thermal power station model
- Estimation of availability - Estimation of availability
Definition 6.14. The Mean Time To Failure Definition 6.15. The Mean Time To Repair
is calculated by is calculated by
21 22
23 24
Thermal power station model Thermal power station model
- Estimation of availability - Estimation of availability
Definition 6.18. The availability is the Definition 6.19. The unavailability is the
probability that a power plant is available. probability that a power plant is
This probability can be estimated as the unavailable, which can be estimated by
part of a longer period that the unit is
available:
25 26
27 28
Power Generation Operation Probabilistic production cost
and Planning, EG2200 simulation (PPC)
1 2
3 4
Calculation of system index Calculation of system index
- Basic idea - Basic idea
LOLP = LDC(600) = 876 h/year = 10%
5 6
h/year LDC
The area is now changed since the y-axes is divided with T. To get the
correct expected value, the area has to be multiplied with T.
7 8
Thermal power station model Equivalent load
• We have seen that it is simple to calculate
the system indices in a system where all
power plants are 100 % available
• How is this performed when this is not the
case?
• PPC-method: Concider outages in power
stations as load increase instead of reduced
• The availability of a thermal power station available production capacity.
can not be calculated, but has to be
estimated from historical data and
forecasts of the future.
9 10
Definition 6.10. The equivalent load is A capacity deficit problem (LOLO) occurs when:
given by
Available capacity < demand
Installed capacity – outages < demand
where
Installed capacity < demand + outages
Eg = equivalent load for the power plant
next to be dispatched after unit g,
D = actual load, Installed capacity < equivalent load
Ok = outage in unit k.
11 12
Equivalent load - example Calculation of system indices
• From the equivalent load duration curve,
it is possible to calculate the system indices
• Total available capacity:
• Total outage:
13 14
15 16
Calculation of system indices Calculation of system indices
• Expected energy production in power • Expected production cost. If energy
plants, EG: Assume that we do not have production in each unit is available, then it
unit g. Then the expected unserved energy is eacy to calculate the production cost.
is . When unit g is then installed
the expected unserved energy decreases to
The difference is expected energy
production in the unit. • It is also possible to include the cost of
disconnected consumers
17 18
21 22
23 24
Example 6.6
Example 6.6
25 26
Example 6.6
27
Power Generation Operation PPC model
and Planning, EG2200
Assume
• Perfect competition
Probabilistic production cost • Perfect information
simulation of electricity • Load is not price sensitive
markets – lecture 14 • Neglect grid losses and
limitations
Lennart Söder
• All scenario parameters can be
Professor in Electric Power Systems
treated as independent
1 2
3 4
Calculation of system index
Load model – Alternative 2
- Basic idea
Example 6.8:
h/year LDC
The area is now changed since the y-axes is divided with T. To get the
correct expected value, the area has to be multiplied with T.
5 6
where
• The availability of a thermal power station
Eg = equivalent load for the power plant
can not be calculated, but has to be next to be dispatched after unit g,
estimated from historical data and D = actual load,
forecasts of the future. Ok = outage in unit k.
7 8
Calculation of system indeces Calculation of system indeces
• Risk of capacity deficit = Loss of load • Expected Energy Not Served, EENS: This
probability. Capacity deficit occurs when means energy that cannot be delivered
the deman exceeds available production depending on capacity deficit, i.e.,
capacity, i.e. equivalent load > installed capacity
9 10
13 14
15 16
Model of many wind turbines
Model of a wind turbine • The production in several wind power plants
can not be treated as independent variables,
Wind power probability function Thermal power probability function since high wind in one place normally means
high winds in neighbouring regions
fp(x)
0
0 C
[MW]
17 18
0
0 C
[MW] 19 20
Model of wind power PPC model
• Thermal power is treated with two states:
Installed capacity or zero. Assume
• Total wind power is treated with a multi- • Perfect competition
state unit: • Perfect information
• ELDC Convolution with thermal power: • Load is not price sensitive
• Neglect grid losses and
limitations
• All scenario parameters can be
treated as independent
• Wind power:
Some of these assumption can be
treated with some specific methods.
21 22
23 24
Example 6.13 Example 6.13
25 26
27 28
Wind power capacity credit - 1 Wind power capacity credit - 2
29 30
31 32