CV.

DELTA CIPTA MANDIRI


GENERAL KONTRAKTOR &
SUPPLIER

CreateTimeline Schedule
an infographic timeline by entering important milestones and activities in this worksheet.The title of this worksheet is in cell B1. Information about how to use this worksheet, includi
Project Location : Name of Project :
PT. Beiersdorf Indonesia Malang 1. Supply Filter Humidity
Preparation By Mirza Zain m 2. Project Ducting AHU Mixing
3. Project Ducting Coating

Headings for theDuration


table Chart Data is in cells B3 through
Milestone
D3. Title Description or Activity
1. Pengumpulan Data
Enter a milestone dates
First Dayin cells B4 through B8. Enter milestone
Survey title in cells C4 through C8.Enter milestone description or activity in cells D4 through D8.This is the last instruction in this wo
2. Contract (PO)
Pemenuhan Kebutuhan Project.
1. Filter Humidity Indent 10 Hari
1 - 2 Week Preperation
2. PU dll
3. SS304
Fabrikasi Masing2 Project
2 week Fabrikasi 1. AHU 1 minggu
2. Mixing 1 minggu
1. Coating
3 Day Instal 2. Mixing
3. Etc
1. Prefilter Coating
3 Day Repainting 2. Prefilter Mixing
3. Etc
2 Day Finishing Test and Commissioning
Total Duration : 5 - 6 Week After PO

Timeline Graphic

Pemenuhan Kebutuhan
1-2 Project.
First 1. Pengumpulan Data Week 1. Filter Humidity Indent
Day 2. Contract (PO) 10 Hari Fabrikasi Masing2 Project
2. PU dll 2 week 1. AHU 1 minggu
3. SS304 2. Mixing 1 minggu

3 Day

2 Day
Test and Commissioning

1. Coating 3 Day
2. Mixing
3. Etc

1. Prefilter Coating
2. Prefilter Mixing
3. Etc

Note : Customer
1. 1.
2. 2.
3. Star Safira Regency Cluster Nabilla Blok B2 No. 29
District : Sukodono - Sidoarjo City – East Java
Phone : +6231 8558 7417